Calculation of Quantities of Toe Wall

Unit 10 m
Particulars of item nos Length Breadth H/D Quantity Unit Rate Amount
1 Excavation of earthwork in foundations
Below base slab 1 10 1.2 0.3 3.6 cum
Sides of shear key 2 10 0.3 0.3 0.9 cum
Total= 4.5 cum 374.97 1687.37
2 Lean Concrete M15
Below base slab 1 10 1.2 0.075 0.9 cum
Sides of shear key 2 10 0.3 0.05 0.15 cum
Total= 1.05 cum 4,300.10 4515.11
3 RCC M25 Concrete
Base slab 1 10 1.1 0.15 1.65 cum
Stem wall  1 10 0.175 1.05
(200 mm to 150 mm thick) 1.84 cum
Shear key 1 10 0.3 0.3 0.9 cum
Concrete delineator block 2 0.15 0.15 0.75 0.02 cum
Total= 4.41 cum 4,979.91 21961.41
4 HYSD steel reinforcement bars Fe 500
Main steel in base slab 10 mm 
@ 150 mm c/c 68 1.1 74.8 0.62 46.38 kg
Main steel in Stem Wall 10 
mm @ 150 mm c/c 68 1.4 95.2 0.62 59.02 kg
Distribution steel 8 mm dia in 
base salb 5 9.9 49.5 0.39 19.31 kg
Distribution steel 8 mm 
diaStem wall 6 9.9 59.4 0.39 23.17 kg
8 mm dia ring in shear key 51 1.2 61.2 0.39 23.87 kg
Steel bars in shear key 4 9.9 39.6 0.39 15.44 kg
Concrete delineator block 8 1 8 0.39 3.12 kg
Tie reinforcement 8 0.3 2.4 0.39 0.94 kg
Total= 0.19 MT 58,102.35 11039.45
Total cost per 10 m= 37515.97
Rate per metre= 3752