TWI
Um
‘THE WELDING INSTITUTE,
CODES AND STANDARDS
CLASS OF WORK
There are many types of work which require engineering materials to be joined
by welding, for example:
pressure vessels
bridges
oil rigs
earth moving equipment
aero—engines
ventilation systems
storage tanks
heavy vehicle chassis
car bodies
food processing plant
The quality requirements of the joints in these fabrications depend on their
fitness-for-purpose and differ significantly from one application to the next.
Pressure vessels require welds which can withstand the stresses and high
temperatures experienced in operation.
Bridges must take into account the effect of differing vehicle loads and wind
loading.
Oil rigs are designed to withstand the effect of wave formation and wind loads.
Earth moving equipment has to accommodate differences in terrain and earth
conditions and is subject to fatigue loading.
Welds in food processing plants must withstand corrosion by hot acidic liquors.
On the next page some typical Codes of practice and Standards which cover
various types of constructions being fabricated by welding are listed.
Note: Throughout this text, the term Code is used to cover Code of Practice,
Standard and Specification.
WELDING TECHNOLOGY
Issue 0191 3.4TWI
a
3.2
‘THE WELDING INSTITUTE
Code Class of Work
BS 5500 Unfired fusion welded pressure vessels
ASME Vill American boiler and pressure vessel code
BS 2633 Class 1 Arc welding of ferritic steel pipework for carrying
fluids
BS 4515 Process of welding steel pipelines on land and offshore
BS 5950 Structural use in steelwork in building
AWS 01.1 Structural welding code (American)
BS 5400 Steel concrete and composite bridges
BS 6235 Code of Practice for fixed offshore structure
API 1104 ‘Standard for welding pipelines and related facilities
These documents can also provide a useful source of data for applications
where Codes do not exist. It should be remembered, however, that the
principal criterion in the Codes listed is the quality of the joint in relation to the
service conditions, There are other applications where success is judged by
different criteria, such as dimensional accuracy.
Another important consideration is controlling the cost of welding. Variations in
weld times and quantities of consumables can readily result if the method of
making a weld is left to the welder to decide.
‘The continuous and satisfactory performance of weldments made to various
Codes requires that specific guidelines are laid down to cover materials, design
of joints, welding processes, welding consumables, acceptance criteria and
inspection techniques.
‘These guidelines are usually grouped under the general heading of a Weld
Procedure,
WELDING TECHNOLOGY
Issue 0191TWI
iM
‘THE WELDING INSTITUTE
SENIOR WELDING INSPECTOR
"SIGNING OFF A PRODUCT"
In many fields of fabrication it is a requirement that on completion of a product a
review is made of all documentation to ensure conformity to the specification,
code and drawing requirements. Usually until this review is completed and
perhaps a Release Note or Shipping Note is signed, the product is not complete
with possible late payments and penalties on delivery being incurred.
It could be part of the Senior Welding Inspector's duties to carry out this task,
The requirements for such a check would normally be stated in the client's
specification although some standards, e.g. BS5500, lay down what documents
must be available and checked. Some, if not all, of these documents may have
to be incorporated into a Data Book on completion of the contract.
In order to perform this task, a check list of all documents used on the product
must be prepared. The task is made easier if Quality Plans or at least
Inspection Check lists are in use on the job. The numbers and types of
documents will obviously depend upon the complexity and quality standard of
the product, but among the documents to be reviewed could be:
Quality Plan All stages complete and signed off
Inspection Check List All stages complete and signed off
Materials All certificates checked. In some cases this may
include tests carried out by the consumable(s)
supplier.
Procedures for: Cutting
Welding
Repair
NOT All have to be approved
PWHT
Testing
Coating
Qualification of: Welders
NDT Personnel _Alll have to be approved and
Inspectors are up to date
WELDING TECHNOLOGY
Issue 0191 3.3TWI
im
3.4
Inspection Reports for:
Calibration Certificates:
PWHT Charts:
Hydro Test:
As Built Drawings:
Materials & Weld Map:
Nameplate Rubbings:
‘THE WELDING INSTITUTE
Visual Ensure they cover all
NOT appropriate joints and
Dimensional structures:
for those items of equipment deemed necessary,
e.g. pressure gauges for Hydro Test
Ensure all necessary information is on records,
e.g, job descriptions, chartspeeds
Reports are complete
All are completed
All are completed
When applicable
Concessions/Deviations/Site Query sheets
Permits to work/Degas certificates applicable
Coating Reports
WELDING TECHNOLOGY
Issue 0191QUESTIONS
Qi.
a2
a3.
aa.
Qs.
CODES AND STANDARDS
List the typical items to be found in a Code of Practice
Explain the meanings of the terms:
a) ‘Shall
b) ‘Should’
What is meant by the term ‘concession’?
Does a Code of Practice contain all relevant information?
State the three (8) parties generally mentioned in Codes or Standards
aQs3QUESTIONS
Qi
Q2.
Q3.
a4.
Qs.
SENIOR WELDING INSPECTOR
CODES AND STANDARDS
List the contents of a typical Code of Practice.
Are the requirements legally binding
‘At what point of production should the inspector ensure the correct use of
consumables.
Can a non-approved welder be employed on production work.
Long question (300 words)
Write in an essay format a "signing off of product" to your respective code.
Qs3A