CURVA S 4118 - 4119 - REV.

13 Página 1

ANALISIS DE LA CURVA S
DISEÑO, CONSTRUCCIÓN, INSPECCIÓN, PRUEBA Y SUMINISTRO DE UN (2) SEPARADOR
PROYECTO
TRIFASICOS - OT 4118-4119
CLIENTE HOCOL S.A.
SEMANA S-19 S-20 S-21 S-22 S-23 S-24 S-25 S-26 S-27 S-26 S-27 S-28 S-29 S-30 S-30 S-30 S-30
4118-4119 FECHA 14/02/2020 21/02/2020 28/02/2020 6/03/2020 13/03/2020 20/03/2020 27/03/2020 3/04/2020 10/04/2020 17/04/2020 24/04/2020 1/05/2020 8/05/2020 15/05/2020 22/05/2020 29/05/2020 3/06/2020
PESO

PROGRAMA 82% 87% 92% 98% 100% 100% 100% 100% 100% 100% 100% 100%
INGENIERIA 27%
AVANCE 82% 87% 92% 98% 100% 100% 100% 100% 100% 100% 100%
GESTION DE PROGRAMA 65% 65% 68% 71% 89% 90% 93% 98% 98% 98% 100% 100%
16%
COMPRAS AVANCE 65% 65% 68% 71% 89% 91% 91% 91% 91% 91% 91%
PROGRAMA 39% 45% 52% 59% 77% 88% 94% 99% 100% 100% 100% 100%
FABRICACIÓN 53%
AVANCE 39% 45% 52% 59% 77% 87% 88% 88% 88% 88% 88%
PROGRAMA 5% 42% 78% 87% 100%
PRUEBAS 3%
AVANCE
PROGRAMA 100%
TRANSPORTE 1%
AVANCE
PROGRAMA 53% 58% 63% 69% 82% 88% 92% 95% 97% 98% 99% 100%
100%
TOTAL PROYECTO EJECUTADO 53% 58% 63% 69% 82% 88% 88% 88% 88% 88% 88%
PROYECTADO 88% 90% 92% 95% 97% 98% 100%

ATRASO 3% 7% 9% 10% 10% 10% 8% 5% 3% 2% 0%


120%

100%

80%

60%

40%

20%

0%
S-19 S-20 S-21 S-22 S-23 S-24 S-25 S-26 S-27 S-26 S-27 S-28 S-29 S-30 S-30 S-30 S-30
PROGRAMA 53% 58% 63% 69% 82% 88% 92% 95% 97% 98% 99% 100%
EJECUTADO 53% 58% 63% 69% 82% 88% 88% 88% 88% 88% 88%
PROYECTADO 88% 90% 92% 95% 97% 98% 100%