You are on page 1of 1

CURVA S 4118 - 4119 - REV.

09 Página 1

ANALISIS DE LA CURVA S
DISEÑO, CONSTRUCCIÓN, INSPECCIÓN, PRUEBA Y SUMINISTRO DE UN (2) SEPARADOR
PROYECTO
TRIFASICOS - OT 4118-4119
CLIENTE HOCOL S.A.
SEMANA S-19 S-20 S-21 S-22 S-23 S-24 S-25 S-26 S-27 S-28 S-29 S-30
4118-4119 PESO
FECHA 14/02/2020 21/02/2020 28/02/2020 6/03/2020 13/03/2020 20/03/2020 27/03/2020 3/04/2020 10/04/2020 17/04/2020 24/04/2020 30/04/2020
PROGRAMA 82% 87% 92% 98% 100% 100% 100% 100% 100% 100% 100% 100%
INGENIERIA 28%
AVANCE 82% 87% 92% 98%
GESTION DE PROGRAMA 65% 65% 68% 71% 76% 80% 87% 92% 92% 92% 100% 100%
20%
COMPRAS AVANCE 65% 65% 68% 71%
PROGRAMA 39% 45% 52% 59% 72% 86% 96% 99% 100% 100% 100% 100%
FABRICACIÓN 48%
AVANCE 39% 45% 52% 59%
PROGRAMA 30% 69% 77% 82% 100%
PRUEBAS 3%
AVANCE
PROGRAMA 100%
TRANSPORTE 1%
AVANCE
PROGRAMA 55% 59% 64% 70% 78% 85% 91% 95% 96% 97% 98% 100%
100%
TOTAL PROYECTO EJECUTADO 55% 59% 64% 70% 0% 0% 0% 0% 0% 0% 0% 0%
PROYECTADO

ATRASO 0% 0% 0% 0% 78% 85% 91% 95% 96% 97% 98% 100%

120%

100%

80%

60%

40%

20%

0%
S-19 S-20 S-21 S-22 S-23 S-24 S-25 S-26 S-27 S-28 S-29 S-30
PROGRAMA 55% 59% 64% 70% 78% 85% 91% 95% 96% 97% 98% 100%
EJECUTADO 55% 59% 64% 70% 0% 0% 0% 0% 0% 0% 0% 0%
PROYECTADO

You might also like