Professional Documents
Culture Documents
PRESUPUESTOS
NOMBRE DEL ESTUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR
PROYECTO: DIRECCIÓN:
Percepcion Prima
SALARIO REAL INTEGRADO
Total
Cargo Salario Base Total Vacacional Gratificacion Devengado Cuota IMSS I.S.R.P. Guarderia INFONAVIT
Almacenista $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Aluminero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Aux. de Topografo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Ayudante A $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Ayudante B $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Azulejero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Barretero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bombero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cabo de oficiales $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cabo de peones $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cadenero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Carpintero de Banco $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Carpintero Obra Negra $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Checador de materiales $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Chofer de Camion $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Electricista $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fierrero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Herrero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Jefe de Almacen $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Maestro $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Maniobrista $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mecánico $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Mecanico montador de equipo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Montador de equipo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Oficial Albañil $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Oficial electrico "C" $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Oficial Especializado $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Oficial Plomero "C" $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Operador $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Operador de Equipo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Operador de Maquinaria "A" $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Operador de Maquinaria "B" $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Peon $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Pintor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Plomero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Poblador $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Rastrillero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Sobreestante de terraceria $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Sobrestante de tuberia soldada $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Soldador $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Soldador Calificado $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Tomador de Tiempo $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Tornillero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Tubero de primera $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Tubero de segunda $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Velador $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Vidriero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Yesero $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
PAN
I -2019
Cuadrilla No.13 (Of. Alb+2 peon) Cuadrilla No.18 (Of.Alb+ Ayud "B")
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Peon Jor. 2 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Ofical albañil Jor. 1 $0.00 $0.00 Oficial Albañil Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Peones Jor. 0.15000 $0.00 $0.00 Cabo de Peones Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 22(Carp Banco+ Ayud "A") Cuadrilla No.27 (Herrero+ Ayud"B")
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Ayudante "A" Jor. 1 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Carpintero de Banco Jor. 1 $0.00 $0.00 Herrero Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Peones Jor. 0.10000 $0.00 $0.00 $0.00
Maestro Jor. 0.03333 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 35(Plomero+ ayud "A") Cuadrilla No.40 (Op. Equipo+ peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Ayudante "A" Jor. 1 $0.00 $0.00 Operador de Equipo Jor. 1 $0.00 $0.00
Plomero Jor. 1 $0.00 $0.00 Peon Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.10000 $0.00 $0.00 Cabo de Oficiales Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 41(Op. Equipo+2peones) Cuadrilla No.46 (Chofer Camio+peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Operador de Equipo Jor. 1 $0.00 $0.00 Peon Jor. 1 $0.00 $0.00
Peon Jor. 2 $0.00 $0.00 Chofer de Camion Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.15000 $0.00 $0.00 Sobrestante de Terraceria Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 42(Op. Equ + 3 peon) Cuadrilla No.47 (Chofer Camion+ Ayud"B")
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Operador de Equipo Jor. 1 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Peon Jor. 3 $0.00 $0.00 Chofer de Camion Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.20000 $0.00 $0.00 Sobrestante de Terraceria Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.06667 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 52(2 Oficial Albañil + 10 peon) Cuadrilla No.57 (Poblador + Ayud"A")
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 2 $0.00 $0.00 Ayudante "A" Jor. 1 $0.00 $0.00
Peon Jor. 10 $0.00 $0.00 Poblador Jor. 1 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.60000 $0.00 $0.00 Cabo de Oficiales Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.20000 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No.53 (Plomero + Ayudante "B"+ Peon) Cuadrilla No.58(Oficial Albañil+ 1Ayud"B"+ 7 Peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Plomero Jor. 1 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Peon Jor. 1 $0.00 $0.00 Oficial Albañil Jor. 1 $0.00 $0.00
Ayudante "B" Jor. 1 $0.00 $0.00 Peon Jor. 7 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.15000 $0.00 $0.00 Cabo de Oficiales Jor. 0.45000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00 Maestro Jor. 0.15000 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 54(Oficial Electrico "C"+Ayud"B" + Peon) Cuadrilla No.59 (Oficial Albañil+ 1Ayud"B"+ 3 Peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Ayudante "B" Jor. 1 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Oficial Electrico "C" Jor. 1 $0.00 $0.00 Oficial Albañil Jor. 1 $0.00 $0.00
Peon Jor. 1 $0.00 $0.00 Peon Jor. 3 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.15000 $0.00 $0.00 Cabo de Oficiales Jor. 0.25000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00 Maestro Jor. 0.08333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 55(10 Peon) Cuadrilla No.60 (Oficial Albañil+ Ayudante "A" + peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Peon Jor. 10 $0.00 $0.00 Oficial. Albañil Jor. 1 $0.00 $0.00
$0.00 Peon Jor. 1 $0.00 $0.00
$0.00 Ayudante "A" Jor. 1 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Peones Jor. 0.50000 $0.00 $0.00 Cabo de Oficiales Jor. 0.15000 $0.00 $0.00
Maestro Jor. 0.16667 $0.00 $0.00 Maestro Jor. 0.05000 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 61(Oficial Albañil +Tubero 2da.+2peones) Cuadrilla No.66 (Tubero 1ra+ 2Tubero 2da + 4 peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 1 $0.00 $0.00 Peon Jor. 4 $0.00 $0.00
Peon Jor. 2 $0.00 $0.00 Tubero de segunda Jor. 2 $0.00 $0.00
Tubero de segunda Jor. 1 $0.00 $0.00 Tubero de primera Jor. 1 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.20000 $0.00 $0.00 Cabo de Oficiales Jor. 0.35000 $0.00 $0.00
Maestro Jor. 0.06667 $0.00 $0.00 Maestro Jor. 0.11667 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 62(Oficial Albañil +Tubero 1ra.+2peones) Cuadrilla No.67 (Tubero 1ra+ 2Tubero 2da + 6 peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 1 $0.00 $0.00 Peon Jor. 6 $0.00 $0.00
Peon Jor. 2 $0.00 $0.00 Tubero de segunda Jor. 2 $0.00 $0.00
Tubero de primera Jor. 1 $0.00 $0.00 Tubero de primera Jor. 1 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.20000 $0.00 $0.00 Cabo de Oficiales Jor. 0.45000 $0.00 $0.00
Maestro Jor. 0.06667 $0.00 $0.00 Maestro Jor. 0.15000 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No.63 (Oficial Albañil +Tubero 1ra.+4peones) Cuadrilla No.68(Tornillero + 4 Rastrillero+ 5 Peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 1 $0.00 $0.00 Tornillero Jor. 1 $0.00 $0.00
Peon Jor. 4 $0.00 $0.00 Rastrillero Jor. 4 $0.00 $0.00
Tubero de primera Jor. 1 $0.00 $0.00 Peon Jor. 5 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.30000 $0.00 $0.00 Cabo de Oficiales Jor. 0.50000 $0.00 $0.00
Maestro Jor. 0.10000 $0.00 $0.00 Maestro Jor. 0.16667 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 64(Oficial Albañil +Tubero 1ra.+7peones) Cuadrilla No.69 (4Oficial Albañil+ 4Ayud"B")
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 1 $0.00 $0.00 Ayudante "B" Jor. 4 $0.00 $0.00
Peon Jor. 7 $0.00 $0.00 Oficial Albañil Jor. 4 $0.00 $0.00
Tubero de primera Jor. 1 $0.00 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Oficiales Jor. 0.45000 $0.00 $0.00 Cabo de Oficiales Jor. 0.40000 $0.00 $0.00
Maestro Jor. 0.15000 $0.00 $0.00 Maestro Jor. 0.13333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 65(Oficial Albañil +Tubero 1ra.+9peones) Cuadrilla No.70 (Montador de Equipo + Ayudante "B" )
Mano de obra Unidad Cantidad Salario Real Imp. Total Mano de obra Unidad Cantidad Salario Real Imp. Total
Oficial. Albañil Jor. 1 $0.00 $0.00 Montador de Equipo Jor. 1 $0.00 $0.00
Peon Jor. 9 $0.00 $0.00 Ayudante "B" Jor. 1 $0.00 $0.00
Tubero de primera Jor. 1 $0.00 $0.00 $0.00
$0.00 $0.00
Mando Intermedios Mando Intermedios
Cabo de Peones Jor. 0.55000 $0.00 $0.00 Cabo de Oficiales Jor. 0.10000 $0.00 $0.00
Maestro Jor. 0.18333 $0.00 $0.00 Maestro Jor. 0.03333 $0.00 $0.00
Sub-Total $0.00 Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00 Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00 Total $0.00
Cuadrilla No. 71(Montador de Equipo + Ayudante "B"+ Peon)
Mano de obra Unidad Cantidad Salario Real Imp. Total
Montador de Equipo Jor. 1 $0.00 $0.00
Ayudante "B" Jor. 1 $0.00 $0.00
Peon Jor. 1 $0.00 $0.00
$0.00
Mando Intermedios
Cabo de Oficiales Jor. 0.15000 $0.00 $0.00
Maestro Jor. 0.05000 $0.00 $0.00
Sub-Total $0.00
Dep. Herramienta Menor % 4% $0.00 $0.00
Total $0.00
Costo de
Material Unidad proveedor Costo del flete
Cemento gris Ton $0.00 $0.00
cemento Blaco Ton $0.00 $0.00
Cemento Crest Ton $0.00 $0.00
Yeso Ton $0.00 $0.00
Grano de Marmol (marmolina) Ton $0.00 $0.00
SIKALITE kg $0.00 $0.00
Arena #5 M3 $0.00 $0.00
Arena #4 M3 $0.00 $0.00
Agua M3 $0.00 $0.00
Grava 3/4 M3 $0.00 $0.00
O CON
200
0.00358
0.00%
0.01
0.8
0.5
68.43
0.00
2.60
54.75
125.78
0.00
0.000
7.67
7.67
41.63
175.07
50
0.00307
0.00%
0.01
0.9
0.75
0.31
0.00
0.09
0.28
0.68
0.00
0.000
0.00
0.00
19.72
20.40
SOLINA KOHLER
50
0.00307
0.00%
0.01
0.9
0.75
0.22
0.00
0.06
0.20
0.49
0.00
0.000
0.00
0.00
20.44
20.93
DAD
50
0.00307
0.00%
0.01
0.8
0.75
0.14
0.00
0.04
0.12
0.30
0.00
0.000
0.00
0.00
17.26
17.55
A
0.00307
0.00%
0.01
0.75
0.66
0.00
0.02
0.66
1.34
0.00
0.000
0.00
0.00
18.85
20.19
PACIDAD
200
0.00358
0.00%
0.01
0.8
0.5
44.35
0.00
1.68
35.48
81.52
0.00
0.000
7.67
7.67
38.83
128.01
E DE
200
0.00358
0.00%
0.01
0.8
0.5
42.54
0.00
1.62
34.03
78.19
0.00
0.000
7.67
7.67
38.83
124.68
IDOR
200
0.00358
0.00%
0.01
0.8
0.75
107.72
0.00
3.72
86.18
197.61
0.00
0.000
135.00
135.00
36.16
368.78
14
200
0.00307
0.00%
0.01
0.8
0.75
51.50
0.00
1.93
41.20
94.62
0.00
0.000
0.00
0.00
36.16
130.79
,78 HP.
200
0.00307
0.00%
0.01
0.8
0.75
170.98
0.00
5.13
136.79
312.90
0.00
0.000
0.00
0.00
48.22
361.12
ERKINS
200
0.00307
0.00%
0.01
0.8
0.75
29.78
0.00
1.60
23.82
55.20
0.00
0.000
27.80
27.80
34.27
117.27
0
0.00307
0.00%
0.01
0.8
0.9
0.47
0.00
0.04
0.38
0.89
0.00
0.000
0.00
0.00
110.58
111.47
0
0.00307
0.00%
0.01
0.8
0.9
1.02
0.00
0.08
0.81
1.91
0.00
0.000
0.00
0.00
110.58
112.48
ACIDAD ,
0.00307
0.3972
0.01
0.75
1.03
0.20
0.01
1.03
2.27
0.00
0.000
0.52
0.52
13.14
13.14
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
SUB-TOTAL SUB-TOTAL
TOTAL $0.00 TOTAL $0.00
Pasta cemento gris-agua
Mano de obra Unid. Cant. P.U. Importe
Cemento gris(2.008+5%) Ton. 2.10840 $0.00 $0.00
Agua (0.953+20%) m3 1.1436 $0.00 $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
SUB-TOTAL
TOTAL $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
SUB-TOTAL
TOTAL $0.00
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALP
PRESUPUESTOS
NOMBRE DEL ESTUDIANTE:
GRUPO: SEMESTRE:
PROYECTO: DIRECCIÓN:
Concreto f´c=100 kg/cm2, con resistencia normal Concreto f´c=200 kg/cm2, con resistencia normal
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx. 3/4", fabricado en obra c/revolvedora 1 saco
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.267+5%) Ton. 0.28 $0.00 $0.00 Cemento gris (0.359+5%) Ton 0.38 $0.00
Arena #4 (0.509+10%) m3 0.56 $0.00 $0.00 Arena #4 (0.498+10%) m3 0.55 $0.00
Grava #3/4 (0.616+10%) m3 0.68 $0.00 $0.00 Grava 3/4" (0.603+10%) m3 0.66 $0.00
Agua (0.217+20%) m3 0.26 $0.00 $0.00 Agua (0.202+20%) m3 0.24 $0.00
Concreto f´c=125 kg/cm2, con resistencia normal Concreto f´c=225 kg/cm2, con resistencia normal
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.293+5%) Ton 0.31 $0.00 $0.00 Cemento gris (0.380+5%) Ton 0.40 $0.00
Arena #4 (0.506+10%) m3 0.56 $0.00 $0.00 Arena #4 (0.500+10%) m3 0.55 $0.00
Grava #3/4 (0.613+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.600+10%) m3 0.66 $0.00
Agua (0.214+20%) m3 0.26 $0.00 $0.00 Agua (0.198+20%) m3 0.24 $0.00
Concreto f´c=150 kg/cm2, con resistencia normal Concreto f´c=250 kg/cm2, con resistencia normal
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.318+5%) Ton 0.33 $0.00 $0.00 Cemento gris (0.401+5%) Ton 0.42 $0.00
Arena #4 (0.503+10%) m3 0.55 $0.00 $0.00 Arena #4 (0.502+10%) m3 0.55 $0.00
Grava #3/4 (0.610+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.598+10%) m3 0.66 $0.00
Agua (0.211+20%) m3 0.25 $0.00 $0.00 Agua (0.195+20%) m3 0.23 $0.00
Concreto f´c=175 kg/cm2, con resistencia normal Concreto f´c=275 kg/cm2, con resistencia normal
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.338+5%) Ton 0.35 $0.00 $0.00 Cemento gris (0.416+5%) Ton 0.44 $0.00
Arena #4 (0.500+10%) m3 0.55 $0.00 $0.00 Arena #4 (0.504+10%) m3 0.55 $0.00
Grava #3/4 (0.606+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.606+10%) m3 0.67 $0.00
Agua (0.206+20%) m3 0.25 $0.00 $0.00 Agua (0.195+20%) m3 0.23 $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor. 0.07692 $0.00 $0.00
Revolvedora (8/13) Hr. 0.61538 $20.40 $12.55
SUB-TOTAL $12.55
TOTAL $12.55
MÉXICO CAMPUS TLALPAN
UESTOS
CICLO ESCOLAR I -2019
mal
aco
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
mal
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
mal
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
mal
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
Concreto f´c=100 kg/cm2, con Imp. integral agr. Concreto f´c=200 kg/cm2, con Imp. integral, agr.
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx. 3/4", fabricado en obra c/revolvedora 1 saco
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.267+5%) Ton 0.28 $0.00 $0.00 Cemento gris (0.359+5%) Ton 0.38 $0.00
Arena #4 (0.509+10%) m3 0.56 $0.00 $0.00 Arena #4 (0.498+10%) m3 0.55 $0.00
Grava #3/4 (0.616+10%) m3 0.68 $0.00 $0.00 Grava 3/4" (0.603+10%) m3 0.66 $0.00
Agua (0.217+20%) m3 0.26 $0.00 $0.00 Agua (0.202+20%) m3 0.24 $0.00
Sikalite (3.204+5%) kg 3.36 $0.00 $0.00 Sikalite (4.308+5%) kg 4.52 $0.00
SUB-TOTAL $0.00 SUB-TOTAL
Mano de obra y equipo Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00 $0.00 Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00
Revolvedora (8/13) Hr 0.61538 $20.40 $12.55 Revolvedora (8/13) Hr 0.61538 $20.40
SUB-TOTAL $12.55 SUB-TOTAL
TOTAL $12.55 TOTAL
Concreto f´c=125 kg/cm2, con Imp. Integral, agr. Concreto f´c=225 kg/cm2, con Imp. Integral, agr.
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.293+5%) Ton 0.31 $0.00 $0.00 Cemento gris (0.380+5%) Ton 0.40 $0.00
Arena #4 (0.506+10%) m3 0.56 $0.00 $0.00 Arena #4 (0.500+10%) m3 0.55 $0.00
Grava #3/4 (0.613+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.600+10%) m3 0.66 $0.00
Agua (0.214+20%) m3 0.26 $0.00 $0.00 Agua (0.198+20%) m3 0.24 $0.00
Sikalite (3.516+5%) kg 3.69 $0.00 $0.00 Sikalite (4.560+5%) kg 4.79 $0.00
SUB-TOTAL $0.00 SUB-TOTAL
Mano de obra y equipo Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00 $0.00 Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00
Revolvedora (8/13) Hr 0.61538 $20.40 $12.55 Revolvedora (8/13) Hr 0.61538 $20.40
SUB-TOTAL $12.55 SUB-TOTAL
TOTAL $12.55 TOTAL
Concreto f´c=150 kg/cm2, con Imp. Integral, agr. Concreto f´c=250 kg/cm2, con Imp. Integral, agr.
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.318+5%) Ton 0.33 $0.00 $0.00 Cemento gris (0.401+5%) Ton 0.42 $0.00
Arena #4 (0.503+10%) m3 0.55 $0.00 $0.00 Arena #4 (0.502+10%) m3 0.55 $0.00
Grava #3/4 (0.610+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.598+10%) m3 0.66 $0.00
Agua (0.211+20%) m3 0.25 $0.00 $0.00 Agua (0.195+20%) m3 0.23 $0.00
Sikalite (3.816+5%) kg 4.01 $0.00 $0.00 Sikalite (4.812+5%) kg 5.05 $0.00
SUB-TOTAL $0.00 SUB-TOTAL
Mano de obra y equipo Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00 $0.00 Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00
Revolvedora (8/13) Hr 0.61538 $20.40 $12.55 Revolvedora (8/13) Hr 0.61538 $20.40
SUB-TOTAL $12.55 SUB-TOTAL
TOTAL $12.55 TOTAL
Concreto f´c=175 kg/cm2, con Imp. Integral, agr. Concreto f´c=275 kg/cm2, con Imp. Integral, agr.
máx.3/4", fabricado en obra c/revolvedora 1 saco. máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Cemento gris (0.338+5%) Ton 0.35 $0.00 $0.00 Cemento gris (0.416+5%) Ton 0.44 $0.00
Arena #4 (0.500+10%) m3 0.55 $0.00 $0.00 Arena #4 (0.504+10%) m3 0.55 $0.00
Grava #3/4 (0.606+10%) m3 0.67 $0.00 $0.00 Grava #3/4 (0.606+10%) m3 0.67 $0.00
Agua (0.206+20%) m3 0.25 $0.00 $0.00 Agua (0.195+20%) m3 0.23 $0.00
Sikalite (4.056+5%) kg 4.26 $0.00 $0.00 Sikalite (4.992+5%) kg 5.24 $0.00
SUB-TOTAL $0.00 SUB-TOTAL
Mano de obra y equipo Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00 $0.00 Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00
Revolvedora (8/13) Hr 0.61538 $20.40 $12.55 Revolvedora (8/13) Hr 0.61538 $20.40
SUB-TOTAL $12.55 SUB-TOTAL
TOTAL $12.55 TOTAL
Concreto f´c=300 kg/cm2, con Imp. Integral, agr.
máx.3/4", fabricado en obra c/revolvedora 1 saco.
Material Unid. Cant. P.U. Importe
Cemento gris (0.431+5%) Ton 0.45 $0.00 $0.00
Arena #4 (0.507+10%) m3 0.56 $0.00 $0.00
Grava #3/4 (0.614+10%) m3 0.68 $0.00 $0.00
Agua (0.196+20%) m3 0.24 $0.00 $0.00
Sikalite (5.172+5%) kg 5.43 $0.00 $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
Cuadrilla No. 4 (1/13) Jor 0.07692 $0.00 $0.00
Revolvedora (8/13) Hr 0.61538 $20.40 $12.55
SUB-TOTAL $12.55
TOTAL $12.55
I -2019
gr.
aco
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
gr.
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
gr.
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
gr.
aco.
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$12.55
$12.55
$12.55
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
ESTUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
COLADO DE COLADO DE
Concreto f´c=100 kg/cm2, con resistencia normal con agr. Concreto f´c=200 kg/cm2, con resistencia normal con agr.
máx.3/4", vaciado con carretillas y botes en elems. de cim. máx.3/4", vaciado con carretillas y botes en elems. de cim.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=100kg/ (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=200k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=125 kg/cm2, con resistencia normal con agr. Concreto f´c=225 kg/cm2, con resistencia normal con agr.
máx.3/4", vaciado con carretillas y botes en elems. de cim. máx.3/4", vaciado con carretillas y botes en elems. de cim.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=125kg/ (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=225k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=150 kg/cm2, con resistencia normal con agr. Concreto f´c=250 kg/cm2, con resistencia normal con agr.
máx.3/4", vaciado con carretillas y botes en elems. de cim. máx.3/4", vaciado con carretillas y botes en elems. de cim.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=150kg/ (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=250k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=175 kg/cm2, con resistencia normal con agr. Concreto f´c=275 kg/cm2, con resistencia normal con agr.
máx.3/4", vaciado con carretillas y botes en elems. de cim. máx.3/4", vaciado con carretillas y botes en elems. de cim.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=175kg/ (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=275k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
SUB-TOTAL $13.18
Mano de obra y equipo
Cuadrilla No. 49 (1/8) Jor. 0.12500 $0.00 $0.00
Cuadrilla No. 1(0.0235*10) Jor. 0.23500 $0.00 $0.00
Vibrador (4/8) Hr. 0.50000 $20.93 $10.47
SUB-TOTAL $10.47
TOTAL $23.64
I -2019
on agr.
de cim.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
on agr.
de cim.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
on agr.
de cim.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
on agr.
de cim.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
Colado de Concreto con Impermeabilizacion Integral en elementos de Cimentacion
Colado de Concreto f´c=100 kg/cm2, con Imp. integral en elem. De Cimentacion Colado de Concreto f´c=200 kg/cm2, con Imp. integral en elem. De Cimentacion
Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=100k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=200k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
Colado de Concreto f´c=125 kg/cm2, con Imp. integral en elem. De Cimentacion Colado de Concreto f´c=225 kg/cm2, con Imp. integral en elem. De Cimentacion
Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=125k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=225k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
Colado de Concreto f´c=150 kg/cm2, con Imp. integral en elem. De Cimentacion Colado de Concreto f´c=250 kg/cm2, con Imp. integral en elem. De Cimentacion
Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=150k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=250k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
Colado de Concreto f´c=175 kg/cm2, con Imp. integral en elem. De Cimentacion Colado de Concreto f´c=275 kg/cm2, con Imp. integral en elem. De Cimentacion
Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado Agregado máx.3/4", vaciado con carretillas y botes. Incluye vibrado y curado
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=175k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=275k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
SUB-TOTAL $13.18
Mano de obra y equipo
Cuadrilla No. 49 (1/8) Jor. 0.12500 $0.00 $0.00
Cuadrilla No. 1(0.0235*10) Jor. 0.23500 $0.00 $0.00
Vibrador (4/8) Hr. 0.50000 $20.93 $10.47
SUB-TOTAL $10.47
TOTAL $23.64
I -2019
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
$13.18
$0.00
$0.00
$10.47
$10.47
$23.64
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
COLADO DE COLADO DE
Concreto f´c=100 kg/cm2, con Resistencia normal, agr. Concreto f´c=200 kg/cm2, con Resistencia normal, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=100k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=200k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=125 kg/cm2, con Resistencia normal, agr. Concreto f´c=225 kg/cm2, con Resistencia normal, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=125k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=225k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=150 kg/cm2, con Resistencia normal, agr. Concreto f´c=250 kg/cm2, con Resistencia normal, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=150k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=250k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=175 kg/cm2, con Resistencia normal, agr. Concreto f´c=275 kg/cm2, con Resistencia normal, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=175k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=275k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
SUB-TOTAL $13.18
Mano de obra y equipo
Cuadrilla No. 50 (1/5) Jor. 0.2000 $0.00 $0.00
Cuadrilla No. 1(0.0235*10) Jor. 0.2350 $0.00 $0.00
Vibrador (4/5) Hr. 0.8000 $20.93 $16.74
SUB-TOTAL $16.74
TOTAL $29.92
I -2019
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
COLADO DE COLADO DE
Concreto f´c=100 kg/cm2, con Impermea. Integral, agr. Concreto f´c=200 kg/cm2, con Impermea. Integral, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=100k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=200k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=125 kg/cm2, con Impermea. Integral, agr. Concreto f´c=225 kg/cm2, con Impermea. Integral, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=125k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=225k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=150 kg/cm2, con Impermea. Integral, agr. Concreto f´c=250 kg/cm2, con Impermea. Integral, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=150k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=250k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
COLADO DE COLADO DE
Concreto f´c=175 kg/cm2, con Impermea. Integral, agr. Concreto f´c=275 kg/cm2, con Impermea. Integral, agr.
máx.3/4", vaciado con carretillas y botes en elems. estructural. máx.3/4", vaciado con carretillas y botes en elems. estructural.
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Conc.f´c=175k (1.00+5%) m3 1.05 $12.55 $13.18 Conc.f´c=275k (1.00+5%) m3 1.05 $12.55
Agua (0.800+20%) m3 0.96 $0.00 $0.00 Agua (0.800+20%) m3 0.96 $0.00
SUB-TOTAL $13.18
Mano de obra y equipo
Cuadrilla No. 50 (1/5) Jor. 0.2000 $0.00 $0.00
Cuadrilla No. 1(0.0235*10) Jor. 0.2350 $0.00 $0.00
Vibrador (4/5) Hr. 0.8000 $20.93 $16.74
SUB-TOTAL $16.74
TOTAL $29.92
I -2019
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
agr.
estructural.
Importe
$13.18
$0.00
$13.18
$0.00
$0.00
$16.74
$16.74
$29.92
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
cimentacion alambron 1/4" (2) fy =3000 kg/cm2 cimentacion varilla 1/2" (4) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Alambron 1/4"n (1.00+4%) m3 1.04 $0.00 $0.00 varilla 1/2"no.4 (1.00+6%) m3 1.06 $0.00
alambre recocido (43+7%) m3 46.01 $0.00 $0.00 alambre recoci (18+7%) m3 19.26 $0.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
cimentacion varilla 5/16" (2.5) fy =4200 kg/cm2 cimentacion varilla 5/8" (5) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varilla 5/16"no. (1.00+5%) m3 1.05 $0.00 $0.00 varilla 5/8"no.5 (1.00+6%) m3 1.06 $0.00
alambre recoci (28kg+7%) m3 29.96 $0.00 $0.00 alambre recoci (16+7%) m3 17.12 $0.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
cimentacion varilla 3/8" (3) fy =4200 kg/cm2 cimentacion varilla 3/4" (6) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varilla 3/8"no.3 (1.00+6%) m3 1.06 $0.00 $0.00 varilla 3/4"no.6 (1.00+6%) m3 1.06 $0.00
alambre recoci (22+7%) m3 23.54 $0.00 $0.00 alambre recoci (10+7%) m3 10.70 $0.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
cimentacion varilla 1" (8) fy =4200 kg/cm2 cimentacion varilla 1 1/2" (12) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varlla 1"no.8 (1.00+7%) m3 1.07 $0.00 $0.00 varlla 1 1/2 "no (1.00+7%) m3 1.07 $0.00
alambre recoci (15+7%) m3 16.05 $0.00 $0.00 alambre recoci (14+7%) m3 14.98 $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
Cuadrilla No 24 (1/0.28) Jor. 3.57143 $332.82 $1,188.64
SUB-TOTAL $1,188.64
TOTAL $1,188.64
I -2019
ntos de
Importe
$0.00
$0.00
$0.00
$1,664.10
$1,664.10
$1,664.10
ntos de
Importe
$0.00
$0.00
$0.00
$1,512.82
$1,512.82
$1,512.82
ntos de
Importe
$0.00
$0.00
$0.00
$1,386.75
$1,386.75
$1,386.75
ntos de
Importe
$0.00
$0.00
$0.00
$1,109.40
$1,109.40
$1,109.40
UNIVERSIDAD DEL VALLE DE MÉXICO CAMPUS TLALPAN
PRESUPUESTOS
STUDIANTE:
GRUPO: SEMESTRE: CICLO ESCOLAR I -2019
PROYECTO: DIRECCIÓN:
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
estructurales alambron 1/4" (2) fy =3000 kg/cm2 estructurales varilla 1/2" (4) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
Alambron 1/4"n (1.00+4%) m3 1.04 $0.00 $0.00 varilla 1/2"no.4 (1.00+6%) m3 1.06 $0.00
alambre recoci (43+7%) m3 46.01 $0.00 $0.00 alambre recoci (18+7%) m3 19.26 $0.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
estructurales varilla 5/16" (2.5) fy =4200 kg/cm2 estructurales varilla 5/8" (5) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varilla 5/16"no. (1.00+5%) m3 1.05 $0.00 $0.00 varilla 5/8"no.5 (1.00+6%) m3 1.06 $0.00
alambre recoci (28kg+7%) m3 29.96 $0.00 $0.00 alambre recoci (16+7%) m3 17.12 $8.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
estructurales varilla 3/8" (3) fy =4200 kg/cm2 estructurales varilla 3/4" (6) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varilla 3/8"no.3 (1.00+6%) m3 1.06 $0.00 $0.00 varilla 3/4"no.6 (1.00+6%) m3 1.06 $0.00
alambre recoci (22+7%) m3 23.54 $0.00 $0.00 alambre recoci (10+7%) m3 10.70 $0.00
Habilitado y armado de acero de refuerzo en elementos de Habilitado y armado de acero de refuerzo en elementos de
estructurales varilla 1" (8) fy =4200 kg/cm2 estructurales varilla 1 1/2" (12) fy =4200 kg/cm2
Material Unid. Cant. P.U. Importe Material Unid. Cant. P.U.
varlla 1"no.8 (1.00+7%) m3 1.07 $0.00 $0.00 varlla 1 1/2 "no (1.00+7%) m3 1.07 $0.00
alambre recoci (15+7%) m3 16.05 $0.00 $0.00 alambre recoci (14+7%) m3 14.98 $0.00
SUB-TOTAL $0.00
Mano de obra y equipo
Cuadrilla No 24 (1/0.26) Jor. 3.84615 $0.00 $0.00
SUB-TOTAL $0.00
TOTAL $0.00
I -2019
ntos de
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
ntos de
Importe
$0.00
$136.96
$136.96
$0.00
$0.00
$136.96
ntos de
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
ntos de
Importe
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00