ENGINEERING PRACTICE REPORTCareer Episode
MCIBSE
Competence
Objective
‘Queen Elizabeth Hospital, Birmingham
International Translational Medicine Building
Client: Briggs & Forrester
Main Contractor: Vinci Construction
Sector: Healthcare
Role: Project Director
December 2013 February 2014
aa
ae
[a - —
In the early spring of 2014 Vinci Construction were contracted to
deliver the refurbishment of the 80 year old Queen Elizabeth Hospital
and provide a new state of the art, international Translational
Medicine facility. Briggs and Forester were awarded the M&E
installation on a design and build basis
During the tender process | worked with Briggs and Forester’s bid
team to assist them in looking at best value design options.
| put together a small design team and we looked at options to
provide solutions to the very stringent client briefing requirements.
I chaired brainstorming sessions where the brief was disseminated
and each area was assessed and various engineering options
evaluated to enable each of the project disciplines to be costed to the
best advantage of the project.
A2, B1, 82,
ca
International Translational Medicine Building
April 2014 ~ May 2014
Following a successful tender submission and negotiation, Briggs and
Forrester were awarded the design and build contract to deliver the
‘mechanical and electrical engineering systems to serve the
refurbished hospital and | began negotiation with the contracts and
project delivery directors of B&F to secure the detailed design work
on behalf of RPS to support them in accordance with their design
programme. My role was to agree the level of the design and the
deliverables needed to ensure the project programme milestones
could be met. This involved contract negotiation meetings and the
setting up and putting in place of the appointments and agreeing
warranties and fee schedules.
82, C1, D1,
D3International Translational Medicine Building
May 2014~ September 2014
Upon satisfactory agreements being reached between myself and
BR's project directors in connection with the project duties and
responsibilities we commenced the detailed design of the M&E
systems on behalf of B&F and my role then consisted of leading the
design teams and acting as a conduit between my teams and our
client’s delivery team
Whilst setting up the teams and carrying out the initial thermal
analysis it was noted that the hospitals design team were not in full
accord in connection with the facade treatments. At this stage I
needed to call a series of technical meetings with my client (B&F) and
the hospitals design team to carefully draw attention to this fact and
try to agree a way forward in which we could prove compliance with
the parameters set whilst protecting our client from the provision of
any costly additions to the scheme which were not originally costed
for within their tender submission,
c1c2
83, C3
International Translational Medicine Building
September 2014 - November 2014
Toversaw and quality checked the mechanical design calculations and
drawings produced by our senior engineering staff and liaised with
B&F on a constant basis to assist the timely flow of information.
During the design stage | worked with B&F to ensure our teams
efforts were being concentrated in the correct direction for the needs
of the project. | also agreed and assisted B&F in the clarification of
extra duties based upon client team variations. Throughout the
project | was responsible for the full financial aspect of the work and
was responsible for agreeing costs for all valid and instructed duties
required to deliver the designs to the appropriate levels.
B1, C1, C2,
D3Career Episode
MCIBSE
Competence
Objective
(PSBP) Derby Batch
Client: Education Funding Authority (Bowmer & Kirkland)
Sector: Education
Role: Lead Engineer
January 2014 - Ongoing
The Priority Schools Building Programme is the Governments current
education funding mechanism which has been set in place to provide
over 200 new Primary and Secondary education schools within the
UK.
‘The funding is based upon compliance with the EFA’s template school
and stringent design parameters as set out within their facilities
output specification.
Based upon my considerable experience with regards to delivering
education projects over the previous 5 years, | approached Bowmer &
kirkland Construction and set up a partnering deal with them where
RPS Group would support all of their bids in connection with any of
‘the PSBP project batches they decided to bid, where | would be
responsible for the provision of mechanical, electrical, acoustic and
fire engineering support to assist them in the competitive bid process.
A2,B1
Ttook on the role of Lead Engineer and provided Bowmer & Kirkland
with complete technical and commercial supporting information in
connection with the scope of services | was able to offer within my
role as Building Services Director of RPS's Birmingham and Milton
Keynes offices. | provided detailed information as required in
connection with my staff, experience and technical understanding of
the Education Funding Authorities requirements to assist Bowmer &
Kirkland in the first stage of the pre-qualification process.
Al, B2,
The first batch that Bowmer & Kirkland decided to qualify for was the
PSBP Derby Batch (Batch 39), and from a pre-qualification of 6 maincontractors Bowmer & Kirkland were selected as one of two
preferential bidders and thus were required to embark upon a 6 week
intensive bid process which consisted of the complete concept and
outline design of a template school within the Derby batch,
A2,C1
‘As part of this process my role was to attend weekly engagement
‘meetings with the Education Funding Authority technical teams and
the schools representatives. Where along with the project architect
and structural engineers we outlined our design process and tabled
our solutions which were constantly assessed and discussed with the
Client team, My role within this was to ensure that the EFA’s technical
assessors were fully aware of our complete grasp of the requirements
of the outline specification documentation and that our solutions
were in accordance with these requirements including the
requirement for climate based daylight modelling and over-heating
assessments using the CIBSE TMS2 method to show compliance with
the requirements for adaptive cooling
B2, 83, C1,
2, 3, £1,
53
‘Week by week | prepared schematics and outline design information
covering the main ME headline requirements, including overheating
strategies, daylighting solutions, low energy heating and hot water
service distribution solutions, daylight linking and acoustic
considerations.
C1, 02, €3
Following the completion of the six week engagement process which
was run in direct competition between the two preferred bidders we
provided our submission documents, and following a period of review
and deliberation our team were informed that we had been
successful and were to go forward as the preferred bidder and were
asked to provide the delivery and construction of 7 new schools as
part of the PSBP Derby batch.
D1, £2
‘At this point my role continued to be as Lead Engineer. However my
day to day involvement on a direct level diminished as my role now is‘to ensure that my mechanical, electrical, acoustic and fire engineering
teams have been fully briefed to enable them to provide designs at a
detailed or performance level in accordance with the requirements
set by the Education Funding Authority. | meet on a weekly basis with
my project delivery teams to ensure all aspects of the design and
construction of the schools are delivered in accordance with our
duties and responsibilities. Whenever any of my engineers have to
attend site for meetings or inspections ensure that that are fully
briefed as to their role and that they are aware of all health and
safety requirements, have the correct personal equipment, and
where necessary carry the correct qualifications to safely carry out
their duties.
1,3, D1,
2, D3, E2,
3
Currently 4 of the 7 schools are on site and well underway with
regards to construction and my role is to ensure that each of these
schools is delivered in accordance with the requirements of the
building services brief and specification whilst ensuring that each
project is kept within the commercial constraints as dictated by the
budgets and Bowmer & kirkland’s commercial teams.
3, C4, D3,
2Career Episode
MCIBSE
‘Competence
Objective
‘Aston University, Birmingham
Four Year Framework Bid
Client: Aston University
Sector: Education
Role: Framework Director
During the early part of 2014 | learned that Aston University were
renewing their external Consultants Framework from 2015 ~ 2019
and made the decision to pursue the opportunity to become part of
their consultants team. | instructed my bid team to express an
interest in tendering this opportunity and we then embarked upon
the process of bidding to join the framework.
My role was to lead the bid and | prepared all of the technical and
operational responses as part of the initial Pre-Qualification process
(Pag).
BL
We submitted our PAQin accordance with the guidelines set by the
university and were informed during June 2014 that out of a total of
26 applications we were successful and had been invited to tender
along with five other successful practises for the opportunity to be
considered as a University framework partner.
Az
{At this point we were tasked with the completion of a tendering
document which consisted of a series of project, delivery and fee
based questions. My role was to prepare, co-ordinate and check the
responses, provide operational information and set the level of fees
to be utilised for the following four years.
81, 82, C1
We were also tasked with preparing a full presentation as part of a
formal interview with the University’s Estates and Engineering
directors and management. The formal interview was to consist of a
forty minute presentation with a twenty minute Q&A session
immediately afterwards. | selected two key members of my staff to
accompany me and to assist me in the presentation and interview. |
then looked at the specific requirements of the document and
prepared a powerpoint presentation which addressed each of the
questions and afforded me the opportunity to answer and expand
upon the required responses during the interview process.
3, C4, D3
Following the interview | was informed that RPS had been selected to
join Aston Universities consultant framework and I am currently
engaging in a process to get to know the estates teams and am
working with two of my associate level engineers in connection with
setting up a dedicated team to serve the framework.
D1, 02, £2Career Episode
MCIBSE
Competence
Objective
Telereal Trillium/British Telecom
Five Year Framework
Client: British Telecom
Sector: Commercial/industrial
Role: Framework Manager
From 2006 ~ 2011 R W Gregory then subsequently RPS Group were
employed as the framework consultants for British Telecom covering
their entire portfolio within their Midlands, Wales & West region. My
role was that of the framework manager and | was responsible for the
full delivery of the life cycle replacement and capex works throughout
the region on an annual basis.
81, 82, C1
Prior to the beginning of each financial year | was involved in the
submission of a business case document which included my
recommendations as to the condition of the existing plant and
equipment within BT's portfolio and highlighted the need and
urgency for either replacement or upgrading works to be considered
as part of the following years budget.
A2, C1, C2,
D1
‘My role included liaising with the Telereal Trilium project and delivery
teams on a weekly basis to report on the status, financially,
technically and in accordance with programme of each project from
inception to completion.
| was responsible for a team of six mechanical and electrical
engineers and acted as project delivery manager ensuring each
project was designed, tendered and delivered on time and within the
agreed cost framework
A2, B2, B3,
1, €3, Ca
‘On a monthly basis | was responsible for issuing a full report on the
status of each project which highlighted the financial and
programming position of each job and also indicated and potential
issues which had or were likely to occur. The report was then used as
an agenda for a monthly meeting with my client’s project delivery
teams,
C4, D1, D2,
D3
(On an annual basis my team delivered between twenty to thirty
projects from as little as £20,000.00 through to as much as
£1,000,000.00 and consisted of projects such as boiler plant and
chiller replacements through to wholesale building rationalisation
programmes,
Al, C1, C2,
3
‘At the beginning of each financial year | attended a programme
meeting with the directors and senior project managers of BT andTelereal, where the coming years initial batch of projects were
decided and agreed. Following agreement of the projects to be
delivered | was responsible for grouping individual projects together
by either type or location and produced a business case as to how |
considered it best to tender each grouping to gain best commercial
advantage from the marketplace.
82, D1, D2,
D3
I then briefed my internal teams and each project was surveyed and
designed by myself and my engineers and then each batch was
tendered in accordance with the requirements of the client. | was
responsible for the opening and review of each tender to validate and
interrogate each submission prior to presenting a fully detailed
tender report to the client with my recommendations as to how to
best procure and deliver each batch of projects.
A2, B2, C1,
2,3
| was responsible for the design, supply and delivery of the first two
biomass heating plants within BT's property portfolio (2008). Both
projects were in North Wales (Porthmadog and Llandegai), to take
advantage of combined pellet delivery costs and logistics whilst
helping to reduce BT’s carbon commitment as part of their carbon
reduction programme.
82, C1, C4,
53Career Episode
MCIBSE
Competence
Objective
Workers institute Building
Client: The Black Country Living Museum
Sector: Museums/Public Buildings
Role: _Mechanical Design Engineer
December 2005 - November 2007
{In 2005 the Black Country Living Museum decided to embark upon
the wholesale brick by brick deconstruction of the Chain Makers
Institute Building which was located in Cradley Heath High Street
within the Black Country, and to ensure its faithful reconstruction
onto the site of the Black Country Living Museum in Dudley, West
Midlands.
Initially | attended Client briefing sessions where the curator and
Museum Director provided the historical and logistical background as
to the specific requirements of the project and my role was to design
‘a mechanical services solution which consisted of heating, ventilation,
domestic water services and above ground drainage installations in a
way that complimented the age and style of the building, whilst being
sympathetic to the energy needs and current requirements in
connection with Building Regulations and energy guidelines.
Al, A2, 81,
82, 83
Tt was an absolute requirement that any of the buildings services
plant or equipment on show would be totally in accordance with the
age and style of the building, therefore | prepared designs which were
visually and aesthetically in line and in accordance with the type, style
and age of the building, Through a process of discussion and design
collaboration with the Project Architect and Structural Engineer |
designed a heating system which consisted of underfloor heating to
all areas where it could be installed unobtrusively and appropriately.
ALCL
However due to the limitations imposed upon the design parametersdue to the level of insulation that could be provided to the thermal
envelope whilst still maintaining an accurate reconstruction the
output of the underfloor heating system was not high enough to
meet the needs of the losses from the total thermal envelope.
In order to meet the shortfall in the requirements for heating of the
large open spaces | designed a low level pipe coil system and cast iron
column type radiators within smaller office and circulation areas on a
one pipe system which were all sized to cater for the shortfall in the
buildings thermal requirements.
A2
In order to gain maximum benefit from the low grade heat
requirement of the underfloor heating | prepared two options which
were to be tendered in connection with the low pressure hot water
heating systems. The first option consisted of a ground source heat
pump solution (bore hole) which was sized to serve both the
underfloor heating and the pipe coils and radiator circuits albeit at a
very low surface temperature with the heat emitters sized
accordingly.
‘The second option consisted of a gas fired condensing boiler
arrangement in lieu of the ground source heat pump where a new gas
supply was to be taken from the existing site infrastructure to serve
the boiler arrangement with the heating flow and return
temperatures kept to a low heat output as required by the underfloor
heating to provide maximum efficiency from the boiler arrangement
albeit with a higher delta T. The ventilation solution was generally a
natural solution with toilets mechanically ventilated by induct twin
fans positioned away from public view.
A2, 81, B2,
83, C1
82, C1
The domestic water service installations generally consisted of
hidden distribution pipework with any pipework on show generally
provided at one size larger than actually required with all fittings of
the end feed variety with all pipework being painted out following
installation to give the effect of larger malleable/lead pipe
connections.
Following the completion of designs and full tender packages the
project was tendered and eventually let with the gas fired boiler
option being the preferred method of heating by the Client and the
systems were installed with the gas fired boiler option as opposed to
the ground source heat pump solution.
c2
The flue arrangement form the gas fired boiler was taken via a
proprietary liner installation within an existing chimney with an
approved terminal device which was shielded visually from publicview via an oversized chimney pot outlet.
During the installation period of the building my role was to attend
site on a bi weekly basis to ensure that the quality and integrity of the
building services installations was in line with the needs and
requirements of the Black Country Living Museum with special focus
being taken on the actual installation methods and insurance that no
corners were cut by the installation teams in connection with the
visual impact of the services systems.
4, D1, D2
Upon completion of the installations, | was responsible for witnessing
the commissioning and testing of flow rates and temperatures for
compliance with the requirements of my specifications and drawings.
03, E2Career Episode
MCIBSE
‘Competence
Objective
Brighton Waterfront Marina Project
Client: Parkridge Developments
Sector: Retail/Commercial
Role: _ Mechanical Design Engineer
February 2001 - October 2003
During 2001 Parkridge Developments embarked on the complete
redevelopment of Brighton Marina area with the provision of a brand
new 4 storey hotel with a retail outlet development, restaurants and
leisure facilities attached to the ground floor of the hotel.
(On behalf of Jonathan Hart Associates my role was as the lead
mechanical services design consultant, working with a lead electrical
design consultant and public health engineer. | was responsible for
the complete design of the mechanical services systems to the new
hotel, the new retail units and overall site infrastructure including gas
and water supplies.
A2, B2, B3,
ct
Twas involved in the design team process between the developer,
architect, structural engineer and marine planners. | was responsible
for designing the heating, ventilation, domestic water services,
variable refrigerant volume systems (VRV) and retail unit
infrastructure supply.
Due to the location of the site some of the key design challenges
incorporated making sure that any external plant was suitable for a
coastal installation and due to the positioning of the plant area a flue
dilution system was the chosen method of removing the products of
combustion from the plant area which created an acoustic challenge.
01, 03, E1,
£2
prepared a full technical specification and drawings for all of the
mechanical services installations and these documents formed the
basis of the mechanical services tender process.
aFollowing the tender submissions | was asked to attend review
meetings where the full services tender submissions were analysed
and tender review reports prepared to assist the Client in the
selection of the preferred installation contractors.
2
Following commencement of a site start my role was to attend site on
‘a monthly basis to ensure installation quality, technical compliance
and overall workmanship standards were of the highest order.
3, C4, E2
‘At the completion of the project my role was to witness all on site
tests, comment on operation and maintenance manuals, check
commissioning figures against the design requirements, and ensure
the handover of the installations were done in an acceptable and
professional manner.
01, €1, £2
‘Once the project was handed over to the satisfaction of the complete
design team | was tasked with agreeing the final accounts in
connection with the mechanical services installations.
D1Career Episode MCIBSE
Competence
Objective
limor Engineering Brigsworth
New Restaurant Facility
Client: Iimore Engineering Ltd
Main Contractor: Anglo Holt Construction
Sector: Commercial
Role: Senior Mechanical Engineer _
‘March 1996 — February 1998
Whilst working as a Projects Manager for a mechanical services
design and build contracting company we were asked by Anglo Holt
Construction to provide a tender submission for the design, supply
and delivery of a mechanical services installation to serve anew
restaurant for Ilmor Engineering Northamptonshire,
My role was initially to provide outline designs based upon a Client
briefing document and provide a costed tender for the installation of | A2, B2
the required mechanical services works.
This process required me in carry out full heat loss and heat gain
calculations, preliminary heating, chilled water and hot water service | 83
pipe sizings, preliminary air volume calculations and ductwork sizing
along with plant load and estimation exercises.
This enabled me to provide a price for the supply and installation of
the works required.
We were subsequently informed that our tender had been successfull
and that we were contracted to install the mechanical services
installations to the new restaurant facility.
My role was to then take the outline design concept drawings
through to a construction stage which included the full detailing of | Ai, A2, B1
the plant arrangements to serve the restaurant and amenity areas as
well as full sizing of all heating, chilled water, ventilation and
domestic water services installations.
‘A client stipulation was that the installations were be as energy
efficient as possible and with the aim of a chiller manufacturer we
provided the air cooled chiller with an extra closed circuit to be used
as a pre-heat for the domestic hot water service requirements.
83, C1
Throughout this process I was in close discussions with the Client and
the contracting team to ensure that the overall design and installationof the mechanical systems was in line with the commercial budgets | C1
and in accordance with the expectations of the end users.
The restaurant was a pyramidal shape with large areas of glazing to
the north and east elevations.
Throughout the construction period my role was to liaise with the site
installation foreman and ensure that the designs were installed in €3, 01, 3
accordance with my requirements, and in accordance with the site
parameters.
‘At the end of the project | was responsible for ensuring that all of the
heating and chilled water circuits were correctly balanced and that all | E1
pumps were running efficiently and to the correct volumes.Career Episode
MCIBSE
Competence
Objective
CIBSE West Midiands Regional Committee
January 2002 — April 2003,
joined the CIBSE West Midlands Regional Committee in 2002 as a co-
opted committee member to provide support to the Regions Social
Secretary and assist in the organising and delivery of the Regions
Annual Dinner and May Ball.
‘September 2003 - April 2008
From this period | took over the role of Social Secretary serving the
West Midlands where | organised, on an annual basis, the May Ball
and Annual Dinner of the CIBSE West Midlands Region, along with
golf days and attendance at occupational road shows and seminars
on behalf of the region.
ca,
‘September 2008 - April 2009
During this period | acted as Social Secretary as well as the Regions
Vice Chairman where | again organised and delivered the various
social functions along with supporting the Regional Chair with
attendance at social functions on behalf of the Region in the
Chairman's absence when he could not attend.
4, D1, 02,
D3, £1, £4
‘September 2009 - April 2012
During this period | was proud to be the CIBSE West Midlands
Regional Chair and as chairman | attended the Regional Liaison
Committee at Batham on behalf of the region, fostered strong links
with other CIBSE regions and attended various events, dinners,
conferences and technical meetings also on behalf of the region.
4, D1, D2,
3, £1, £4
‘September 2012 - April 2013
After three years | stepped down from the chair to act as CIBSE West
Midlands Vice Chair supporting the incoming Chairman and assisting
her with preparation of minutes, attendance at regional meetings and
attending social functions and careers roadshows.
C4, 01, 02,
D3, £1, £4
‘September 2013 - Current
Lam currently acting as CIBSE West Midlands Publicity Officer andsupport all of my fellow members with regards to guidance,
mentoring and assisting any of my fellow committee members to
provide the benefit, where required, of the experience | have had
over the last 12 years as a CIBSE Committee Member.
During July 2014 | was given the great honour of being presented
with the CIBSE Bronze Medal for services to the West Midlands
Region.
4, D1, 02,
D3, £1, £4