Q. Should I complete this course and enter the 35 hours to even fill my PMP
application?
A. This course is a PMI REP and you will have earned 35 contact hours for
your PMP application after you complete the course. Contact hours include
all elements of the course: assignments and activities.
Q. Can we leave initiating blank while filling up experience in the project for
project management hours?
A. The key here is that you should convince the PMI that you have experience
in all five process groups across all your project management experience
submitted on the application. However, on a single project, you do not need
to have experience in all five process groups.
Q. At which stage does a typical project have its maximum and minimum
cost?(Initial stage, middle stage, final stage etc.?
A. The resources and cost usage is maximum in the middle stage and minimum
in the initiation stage.