ID Task Task Name Duration Start Finish Predecessors 04 May

11'20
May18'20
May25'20
May01'20
Jun08
'20
Jun15'20
Jun22'20
Jun29
'20
Jun06'20
Jul13
'20Jul20
'20Jul27
'20Jul03
'20Aug
10'20
Aug17'20
Aug24'20
Aug31'20
Aug07'20
Sep14'20
Sep21'20
Sep '20
Mode SWS T FMT SWS T F MT SWS T FMT SWS T FMT SWS T FMT SWS T F MT SWS
1 Proiect REMAT SA Calarasi 87 days Mon 18/05/20 Tue 15/09/20
2 Elaborarea proiectului de rezistenta si arhitectura 28 days Mon 18/05/20 Wed 24/06/20
3 Executia elementelor prefabricate in fabrica 35 days Wed 01/07/20 Tue 18/08/20 2FS+4 days
4 Executia fundatiilor 25 days Mon 01/06/20 Fri 03/07/20
5 Montajul paharelor de beton prefabricate 17 days Mon 15/06/20 Tue 07/07/20 4FS-15 days
6 Montajul stalpilor prefabricati 12 days Wed 08/07/20 Thu 23/07/20 5
7 Montajul grinzilor prefabricate de BA 15 days Tue 28/07/20 Mon 17/08/20 6FS+2 days
8 Montaj pane acoperis 12 days Tue 11/08/20 Wed 26/08/20 7FS-5 days
9 Montaj contravantuiri in plan acoperis 8 days Fri 21/08/20 Tue 01/09/20 8FS-4 days
10 Montaj tabla acoperis 10 days Wed 26/08/20 Tue 08/09/20 9FS-5 days
11 Montaj luminatoare si atic 4 days Wed 09/09/20 Mon 14/09/20 10
12 Receptia cu beneficiarul la terminarea lucrarilor 1 day Tue 15/09/20 Tue 15/09/20 11

Task Project Summary Manual Task Start-only Deadline


Project: REMAT SA Calarasi
Split Inactive Task Duration-only Finish-only Progress
Date: 18.05.2020
Elaborat: ing. Pascariu Oana Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone