Concurrent Delay and Pacing
Delay in Construction Project
Day
15
lelay
What is Concurrent Delay?
The term “concurrent delay” is commonly used to describe circumstances where
owner-caused delays and contractor-caused delays occur at the same time.
In true concurrency, the owner and contractor delay events (the cause of delay)
both occur at the same time and the delay caused by the delay events start and
finish at the same time. True concurrency is unlikely to occur and this narrow
definition is too limited for practical application. Conversely, Keating (Keating on
Construction Contracts 10th ed, Sweet & Maxwell, 2016) considers delays as
concurrent when:
* each delay event, in the absence of any competing event, has caused delay;
* each delay event is on the critical path; and
* the delays caused by the owner and the contractor overlap.
Typical scenarios of concurrent delay and
how to resolve them
In situations of concurrent delay, the Contracts between the parties must first be
examined to determine whether they provide an answer to how the allocation of
liability for any concurrent delay should be considered without sophisticated
analysis.
The contract between the parties may provide no direct guidance as to the
treatment of concurrent delay. Then the most common principle applied in the
international construction industry which addressed below is utilized.
1. True Concurrency
1]2]3[4[5]6|7]8| 9 [10[11]12[13[14]1s
eee
If the owner-caused and contractor-caused delays are concurrent and of equal
duration, and if they equally affected the critical path to project completion, the
contractor would not be entitled to compensable delay damages and the owner
‘would not be entitled to its actual delay or liquidated damages.
The Contractor is still entitled to a full Extension of Time (5 days).
2. Partial Concurrency
Day
Contractor-caused Delay
AACE International's Recommended Practice No. 29R-03 for forensic schedule
delay analysis states the following:
* That is, the contractor is barred from recovering delay damages to the extent that
concurrent contractor-caused delays offset owner-caused delays, and the owner is
barred from recovery liquidated or actual delay damages to the extent that
concurrent owner-caused delays offset contractor- caused delays.”
The Society of Construction Law Delay and Disruption Protocol states the
following
“if a contractor incurs additional costs that are caused by both owner delay and
concurrent contractor delay, then the contractor should only recover compensation
to the extent it is able to separately identify the additional costs that were only
caused by the owner delay. If it would have incurred the additional costs in any
event as a result of concurrent contractor- caused delays, the contractor will not be
entitled to recover those additional costs unless provided otherwise in the contract.”
In this example, the Contractor's compensable duration is 2 days. It can not
receive 3 days of compensation for its own delay.
The Contractor is still entitled to a full Extension of Time (5 days).
In a complicated project, the Collapsed As-Built / As-Built But For Delay Analysis
method is deployed to quantify the Contractor's entitlement to receive
compensation. The method is addressed in the following article: How to perform
Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6
3. Functional Concurrency
Contractor-caused Delay
Functional concurrency occurs when the separate network paths, on which the
delays reside, concurrently impact the Project Completion date.
AACE International Kecommended Practice No. 2YRUS Forensic Schedule
Analysis (Section 4.2.0.1, p. 105.) affirms that the functional theory is “closely
attuned to delay methodologies that use modeled CPM schedules as their basis
and utilize some form of time period analysis. Since these analyses measure delay
at the end of time periods [typically the status updates] it makes sense to measure
concurrency under this methodology at the same points, rather than trying to
develop a separate concurrency analysis. Accordingly, the functional application of
concurrent delay theory does not necessarily require the delay events to occur at
the same time. In addition, the functional theory allows that CPM schedules, even if
properly maintained, are not perfect, and near critical delays may in fact be
concurrent.”
In this example, there would be no compensable delay for the Contractor and the
Owner.
The Contractor is still entitled to a full Extension of Time (5 days).
Summary Table of Concurrent Delay
Scenarios and Net Effect
The various permutations of concurrent delay are summarized by AACE
International in Table below (Recommended Practice No. 29R-03 Figure 12-Net
Effect Matrix-Concurrent Delay, p. 100.):
Concurrent Delay Scenarios and Net Effect
‘Delay Event ‘Concurrent With ‘Net Effect
Owner Delay Another Owner ‘Compensable to Contractor,
Delay or Nothing Non-excusable to Owner
Contractor Delay Another Contractor Non-Excusable to Contractor,
Delay or Nothing Compensable to Owner
Force Majeure Another Force Majeure | Excusable but Not
Delay Delay or Nothing Compensable to Either Party
Owner Delay Contractor Delay Excusable but Not
Compensable to Either Party
Owner Delay Force Majeure Delay Excusable but Not
Compensable to Either Party
Contractor Delay Force Majeure Delay Excusable but Not
Compensable to Either Party
What is Pacing Delay?
Pacing delay occurs when the delay in one activity occurs, and a conscious and
contemporaneous decision is made by the contractor to pace progress in 2
second and independent activity. Thus, the contractor deliberately slowed down
its work in an effort to "keep pace with the owner's delay’. The thinking typically
expressed by contractors is "Why should | hurry up and wait?” because the owner-
caused delay was driving the project completion.
It is common for construction contracts to not address or define concurrent
delays let alone “pacing” Most construction contracts contain specific language
such as, “time is of the essence” or “a contractor shall diligently perform the work"
which requires a contractor to expedite the completion of the work. Consequently,
most construction contracts do not inherently sanction a contractor to “pace” its
work when delayed by an owner-caused impact to the critical path.
However, nearly all construction contracts include an implied warranty that
Tequires the contracting parties not to delay, hinder, or interfere with the
performance of the other party. A contractor is allowed to enjoy a least cost
performance based on implied warranty. When an owner delays the critical path,
‘the contractor is permitted to mitigate costs to the benefit of the contractor
thereby providing a basis for “pacing”
Pacing is typically presented in two scenarios.
1. Direct Pacing - This situation occurs when the duration of a successor
schedule activity is extended due to a delay in a predecessor activity on which the
progress of the successor activity is directly dependent. An example would be that
the duration of wire pulling is delayed because conduit installation is taking longer
than anticipated due to the lack of conduit materials on the site. This is pacing
delay, not concurrent delay because the cause of one delay is the result of the
other delay.
2. Indirect Pacing ~ In this situation, the paced activity has no dependency on the
other activity. For example, a contractor deliberately slows down piping
installation in one area of the project due to an owner-caused delay in another
area of the project. The owner-caused delay creates float while the contactor's
decision to slow down piping installation consumes this float.
In its evaluation of potential concurrent delay vs. a pacing delay, the following
generally accepted international construction industry guidelines appl
importance, as follows:
1. A predecessor dependent parent delay must precede a pacing delay;
2. The contractor needs to demonstrate that it could resume progress at an un-
paced rate; and
3. The contractor needs to provide evidence that a conscious and deliberate
decision was made at the time to pace the work as a result of the other delay.
If no documentation is made available to justify a pacing delay, then consistent
with the AACE International recommended practice, concurrent delays by the
contractor should not be regarded as pacing delays, and instead are delays for
which the contractor is responsible.
References:
Analysis of Concurrent Delay on Construction Claims ~ Richard J. Long