You are on page 1of 10

968 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 35, NO.

4, JULY/AUGUST 1999

Transient Motor Reacceleration Study in


an Integrated Petrochemical Facility
Gursharan Singh Grewal, Member, IEEE, Stephen Pocsai, Member, IEEE,
and Makhlouf M. Hakim, Senior Member, IEEE

Abstract— The reliability of the power supply can be signifi- TABLE I


cantly improved by modifying the electric motors’ reacceleration EXISTING REACCELERATION STEPS
scheme. It will mitigate the effect of lengthy and simultaneous
acceleration by staggering the high inrush current demand. Tran-
sient simulations were performed at an integrated petrochemical
facility to verify the effectiveness of the existing reacceleration
scheme. The results indicated that the existing scheme will per-
form better with some changes, as discussed further.
Index Terms— Reacceleration, transfer, transient, undervolt-
age.

I. INTRODUCTION *-Motors reaccelerate, as soon as the bus is reenergized.

R EENERGIZATION of electric drives, after a short out-


age, is an important design feature in process facilities for
minimizing production losses. It is common at most industrial
facilities to respond to critical motors’ dropout by transferring
those buses feeding critical motors onto healthy sources and
restarting the motors, automatically. These critical motors need
to be reenergized in a certain order to avoid prolonged voltage
drop at the motor terminals which can reduce the accelerating
torque substantially. Reduced torque can lead to a long starting
time, which triggers overheating problems or, in some cases,
the motor may fail to accelerate altogether. Severe or extended
voltage drop also affects the healthy bus onto which the critical (a)
motors have been transferred and, in extreme cases, may lead
to undervoltage tripping on the healthy bus. Reacceleration
analysis is necessary for predicting voltage and current profiles
and acceleration times of the motors. Among other benefits,
the analysis verifies the viability of the restarting sequence
and provides a guide for setting undervoltage and overcurrent
relays on the load buses.
Traditional voltage drop calculations, using static circuit
analysis, cannot account for the sequenced starting effect, that
is, motors being started while others are still accelerating and
at various values of locked-rotor current (LRC). To capture
this interaction of reaccelerating motors, dynamic stability (b)
simulations were chosen. This paper presents the results of Fig. 1. (a) Motor equivalent circuit. XC is computed internally to assure
reactive power initial conditions. (b) Motor transient model.
Paper ICPSD 97–17, presented at the 1997 IEEE/IAS Industrial and
Commercial Power Systems Technical Conference, Philadelphia, PA, May
12–15, and approved for publication in the IEEE TRANSACTIONS ON INDUSTRY dynamic analysis at a plant where about 350 motors are
APPLICATIONS by the Power Systems Engineering Committee of the IEEE assigned to automatic reacceleration.
Industry Applications Society. Manuscript released for publication March 30,
1998.
It is noted that the scheme discussed in this paper is not
G. S. Grewal and S. Pocsai are with Syncrude Canada Ltd., Fort McMurray, a high-speed bus transfer scheme, where motors’ residual
AB T9H 3L1 Canada (e-mail: grewal.gursharan@syncrude.com). voltage is a primary concern. Instead, the system involves
M. M. Hakim is with Sinai Engineering Corporation, Edmonton, AB T6E
5E5 Canada. massive restarting of motors on a power system that is already
Publisher Item Identifier S 0093-9994(99)05377-3. weakened by at least one contingency and without the benefit
0093–9994/99$10.00  1999 IEEE
GREWAL et al.: TRANSIENT MOTOR REACCELERATION STUDY IN AN INTEGRATED PETROCHEMICAL FACILITY 969

Fig. 2. Load torque—slip characteristics.

TABLE II area is supplied by dual 13.8-kV feeders originating at two


MOTOR PARAMETERS different 13.8-kV buses in the utility plant. A secondary
selective scheme is used to feed the loads, via step-down
transformers at service voltages of 4.16 kV and 600 V. Under
normal conditions, the tie breaker at the service level is open.
All feeder and transformers are sized to continuously carry the
essential loads of both buses when the tie breaker is closed. If
a service bus is deenergized by other than a protection lockout,
the tie breaker closes automatically. Provided that voltage on
the deenergized bus is restored within 5 s (with power from the
alternate bus), all critical motors on the bus are automatically
restarted. Bus transfer is initiated by undervoltage condition
on either of the twin service buses. Two types of transfer
schemes are used on site, depending on the permissible delay
of restarting. Critical utilities motors at the powerhouse are
of off-loading the motors, i.e., all motors are restarted under restarted instantaneously after bus transfer. For those, the un-
full load. dervoltage initiation is set at 30%, to ensure sufficient decay of
motors’ residual voltage before transfer and restarting. For the
II. SYSTEM DESCRIPTION remaining sites, motor restarting is delayed by several seconds
Syncrude Canada Ltd. (SCL), located in Alberta, Canada, and undervoltage initiation is typically set around 75%.
is one of the largest integrated mining and petrochemical There are few large synchronous motors on site. These
complexes in the world, producing 12% of Canada’s crude oil motors are not reaccelerated due to prestart permissive and
requirements. Plant load, which averages 220 MW, is supplied other system constraints.
mainly by on-site generation. An interconnection with the local
utility [Alberta Power Ltd. (APL)] is also provided, through III. CRITICAL VERSUS NONCRITICAL MOTORS
two 72-kV short transmission lines. A brief description of the Critical motors are defined as those which are required to
distribution system under consideration is as follows: maintain operations in a safe and orderly manner. These can
• 8 72/13.8-kV transformers, 34 MVA; be divided into the following three main categories:
• 20 13.8-kV feeders; • drives that, if lost, could cause damage to the process
• 66 transformers (1–15-MVA range). equipment, such as furnace charge pumps, the loss of
This does not include the distribution in the mine, because which could cause overheating or coking of the furnace
no motor is required to reaccelerate in that area. Every process tubes;
970 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 35, NO. 4, JULY/AUGUST 1999

Fig. 3. Sample 13.8-kV distribution system.

• drives that, if lost, could lead to relieving conditions, e.g., drive, the motor is equipped with reacceleration, to cover the
tower feed pumps, reflux pumps, etc.; period of time when the turbine drive is out of service and
• drives which, if lost for any length of time, would cause only the electric drive is being used.
operations upset or shutdown, such as powerhouse boiler
feedwater drives.
Noncritical motors are those which would not result in any IV. CHARACTERISTICS OF REACCELERATION SCHEME
process upset if they fail for an extended period of time. In The allowable window for motor drive reacceleration is5 s.
cases where an electric drive is spared with a steam turbine If voltage is not restored to the motors source within 5 s, the
GREWAL et al.: TRANSIENT MOTOR REACCELERATION STUDY IN AN INTEGRATED PETROCHEMICAL FACILITY 971

TABLE III
MOTOR DATA

affected system will shut down. If, on the other hand, voltage 50 motors or more get restarted automatically. By design,
is detected within the 5-s window, individual timers, one for all these motors end up on one single 13.8-kV alternate
each motor, begin timing and eventually restart the motors in feeder over and above its own original load. To simulate
the preset sequence. Any motor not operating initially is not the effect, typical motor starting calculations fall short
restarted. in simulating the true dynamic effect of this massive
Since the motors slow down before being transferred and and extended sequence of repeated starts. It was felt that
reenergized, they may draw currents in the locked-rotor range a transient stability program with sufficient capacity is
when reenergized. Any attempt to restart all motors simulta- the most suitable tool. Among other obvious dynamic
neously could cause a plant-wide power failure. To prevent accuracies, these programs have the capacity to simulate
this, critical motors are grouped in steps based on the process several starts in one run, with monitoring of a large
categories discussed previously. Seven reacceleration steps are number of parameters, and, thus, facilitate assessing the
used, as shown in Table I. The timing for the various steps full impact of successive large-scale motor restarts. The
has been set to provide a minimum interval of 8 s between specific program used has the capacity to simulate 400
successive steps. induction motors in one run. Generators, governors, and
Three factors affect the time it takes to reenergize a motor. excitation systems were modeled in detail. The models
First is the operating time of the undervoltage relay, which used had already been developed and verified in previous
trips the incoming breaker. Second, there is intentional time analysis of transient stability issues at the plant.
delay imposed on the closure of the bus tie breaker. Finally, • The electrical distribution system database was used
after the bus tie is closed, the prearranged starting sequence for system modeling. One-line drawings, datasheets, test
mentioned above adds to the total time for reenergization. The reports, nameplate data, and schedules were referred to,
only variable in the total time is the operating time of the and intensive field inspections were done to gather the
undervoltage relay. Because the relays used are of the inverse- relevant information. The provincial grid was represented
time type, the dropout time depends on the magnitude of the by a three-bus equivalent at the ends of the 240-kV
voltage drop. transmission lines.
• The induction motors model selected from the software
V. STUDY METHODOLOGY AND TOOLS
library was based on the equivalent circuit shown in
There are 335 motors that may be reaccelerated upon Fig. 1(a). The model itself is shown in Fig. 1(b).
load bus transfers, ranging in size from a few to 3500 hp. • The simplified model is based on equivalent Thevenin’s
In order to obtain a realistic assessment of the response air-gap voltage behind an equivalent impedance. The
of the reacceleration scheme, the following approach was motors were classified into three groups based on the
established. horsepower rating. The parameters for each group were
• Referring to the single-line diagram, it is clear that an selected based on the typical LRC, locked-rotor, and
outage of one 13.8-kV feeder, say due to a fault on breakdown torque characteristics for the size range, as
the cable and subsequent isolation of the feeder, will shown in Table II. Generally, LRC at the high end and
trigger undervoltage transfer on all the 4.16-kV and 600- torque at the low end of the range were assumed to be
V service buses supplied by that feeder. In some cases, conservative. An exponential torque–speed relationship,
972 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 35, NO. 4, JULY/AUGUST 1999

(a)

(b)
Fig. 4. Voltage profiles on (a) bus 9327 and (b) bus 9330, feeder “B” lost.

as shown in Fig. 2, was assumed to represent the me- VII. CRITERIA FOR ACCEPTABLE PERFORMANCE
chanical load torque on the motor. Note that the assumed OF REACCELERATION
torque at synchronous speed is 0.8 per unit of motor 1) Supply load bus voltage >85% of the motor’s nameplate
nameplate. voltage during reacceleration. Based on the motor name-
VI. PREDISTURBANCE OPERATING ASSUMPTIONS plate rating of 575 V and 4.0 kV, the 85% threshold is
actually 81.5% and 81.7% of 600 V and 4.16 kV supply
The following assumptions were made regarding system voltages, respectively.
conditions prior to the disturbance. 2) Successful acceleration is deemed to occur when the
• The generator on the upstream bus feeding the alternate motor reaches full speed in less than 6 s under the load
13.8-kV feeder is down for maintenance. torque conditions described previously.
• Motors come to full stop before the reacceleration begins.
• The running load on the healthy service bus is 35% of the
oil natural, air natural (ONAN) kVA rating of its source VIII. SIMULATIONS
transformer, at 0.8 lagging power factor. This value was Performance of the reacceleration scheme was examined
based on typical running load conditions. through the voltage–time plots at the load buses. The motors
• Undervoltage relay dropout time is taken at 0 V. were started in the simulations as per the expected starting
GREWAL et al.: TRANSIENT MOTOR REACCELERATION STUDY IN AN INTEGRATED PETROCHEMICAL FACILITY 973

(c)

(d)
Fig. 4. (Continued.) Voltage profiles on (c) bus 9334 and (d) bus 9337, feeder “B” lost.

time, which consists of the undervoltage relay time, intentional Motors shown in the figure are those which reaccelerate upon
time delay in tie-breaker closure, and the reaccelerating timer. bus transfer. Following loss of feeder “B,” the tie breakers
The following parameters were monitored in the simulation: on the transformers, fed via feeder “A,” close and global
• voltage dip on the healthy load bus, onto which the motors reacceleration takes place at the load bus levels. Motors are
are reaccelerated and at the terminals of each motor; simulated to start as per the “total time” shown in Table III.
• voltage dip at the 13.8-kV supply feeder; Fig. 4 shows the voltage–time plots at different load buses.
• current flow at the load bus; These plots have to be analyzed together to see the voltage dip
• current flow in 13.8-kV supply feeder; on a particular bus due to motors starting on it, as well as on
• acceleration time of the motors. other buses. A sharp voltage drop indicates motor starting on
the subject bus and other, less severe, dips are due to startups
IX. RESULTS on other buses, as marked on the bus 9327 voltage profile.
A small portion of the 13.8-kV distribution system, shown Similar voltage profiles on the other buses, 9330, 9334, and
in Fig. 3, is selected as a sample for discussion. The system 9337, give the complete reacceleration effect on transformers
supplies power to the load via 13.8/4.16-kV transformers. supplied by feeder “A” due to opening of the “B” source.
974 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 35, NO. 4, JULY/AUGUST 1999

(a)

(b)
Fig. 5. Voltage profiles on (a) bus 9047 and (b) bus 9054, feeder “A” lost.

Fig. 5 shows the voltage profiles on the alternate load buses the starting sequence, the voltage profile is improved, both in
9047, 9054, 9056, and 9060, when feeder “A” is lost. magnitude and duration of the depression, as shown on Fig. 7.

XI. CONCLUSIONS
X. OPTIMIZATION When large-scale motor reacceleration is planned, it is
In the system under consideration, few improvements in the essential to examine the dynamic response of the distribution
“timer” settings were required to improve the voltage profile system to the reacceleration. Although static calculations may
during disturbance. show sufficient voltage during starting, successive starts, even
In Fig. 4, the voltage on bus 9330 is depressed to >85% for at different buses, may cause starting difficulties. Motors may
approximately 7–8 s. The prolonged depression is caused by fail to reaccelerate or the ensuing voltage drop may trigger
starting of two 450-hp motors followed by one 2150-hp motor, tripping of a healthy source, leading to a chain reaction. With
3.5 s later. To avoid prolonged LRC in the 450-hp motors, the transient stability programs available on desktop computers,
sequence of the motor starting is changed. As shown on Fig. 6, it is found justifiable to use them in this analysis, which
both the magnitude and the duration of the voltage depression has traditionally been done with simplified methods. A study
are improved significantly. should preferably be done as part of the initial plant system
Similarly, in Fig. 4, for bus 9056, a significant voltage drop design. Frequency of subsequent studies will depend on the
starts at about 44 s and lasts for about 9 s. By rearranging number and size of new motor additions.
GREWAL et al.: TRANSIENT MOTOR REACCELERATION STUDY IN AN INTEGRATED PETROCHEMICAL FACILITY 975

(c)

(d)
Fig. 5. (Continued.) Voltage profiles on (c) bus 9056 and (d) 9060, feeder “A” lost.

The benefits of the study are realized in improvement of duration of the drop threatens to trigger undervoltage
the electrical system performance under single contingency tripping on the healthy bus and extends the starting time
conditions. In the specific facility studied, the motors requiring of the motors so that heat damage is a concern. Some of
changes were on the cooling water system, which is critical to the motors required reacceleration “timer” setting change
the survival of the plant during upsets. to ensure safe reacceleration.
The theoretical analysis in itself does not guarantee the • A general criterion was established to avoid having to
satisfactory performance of the reacceleration scheme in the repeat similar global reacceleration studies frequently.
field. Correctness of the relay/timer settings, maintenance Based on the observations of motor response, and taking
practices, etc., will undoubtedly influence the success of into account typical impedance and operating parameters
reacceleration attempts. at the plant, this criterion was established for future ex-
pansion of the reacceleration scheme. Additional motors
XII. LEARNINGS may be included in the reacceleration scheme provided
• Excessive voltage drop was observed at some locations the total hprsepower of the motors starting within a
due to not only local motor starting, but to the combined window of 8 s does not exceed 50% of the transformer
effect of starts at other locations. The magnitude and ONAN kVA rating.
976 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 35, NO. 4, JULY/AUGUST 1999

Fig. 6. Bus 9330 voltage profile with the optimized relay settings on feeder “A.”

Fig. 7. Bus 9056 voltage profile with the optimized relay settings on feeder “B.”

• The existing scheme can be improved by reducing the tive load buses. This will simplify coordination of the
time delays to speed up the restoration of the critical restarting sequence.
drives. The results of the study show significant margin
in the system’s ability to withstand full-scale restarting. REFERENCES
• As part of the data gathering of the existing timer and
relay settings, it was found that there were inconsistencies [1] CYMSTAB/UDM User’s Guide and Reference Manual, CYME Interna-
in the relay and the timer settings as compared to the tional Inc., St-Bruno, P.Q., Canada, Nov. 1991.
[2] C. L. Becnel, “Maintaining process continuity during voltage dips,”
setting sheets. IEEE Trans. Ind. Applicat., vol. IA-18, July/Aug. 1982.
[3] IEEE Recommended Practice for Electric Power Distribution for Indus-
trial Plants, ANSI/IEEE Std. 141-1986.
[4] American National Standard for Polyphase Induction Motors for Power
Generating Stations, ANSI C50.41-1982.
XIII. NEXT STEPS [5] G. W. Bottrell, “Fast bus-transfer techniques for maintaining full plant
• One of the next steps is to ensure undervoltage relay production,” presented at the 1989 IEEE Petroleum and Chemical
Industry Technical Conf., Paper PCIC-89-08.
settings to be higher than the expected voltage drop. New
criterion for this was to ride through an 80% voltage dip
lasting up to 8 s.
• Undervoltage relays and the bus closing timers’ settings Gursharan Singh Grewal (S’90–M’90), for a photograph and biography,
are to be made identical on all the secondary selec- see this issue, p. 967.
GREWAL et al.: TRANSIENT MOTOR REACCELERATION STUDY IN AN INTEGRATED PETROCHEMICAL FACILITY 977

Stephen Pocsai (M’93) received the BSc. degree Makhlouf (Mak) M. Hakim (M’75–SM’86), for a photograph and biography,
in electrical engineering from the University of see this issue, p. 967.
Calgary, Calgary, AB, Canada, in 1990.
He is with the Utilities Department, Syncrude
Canada Ltd., Fort McMurray, AB, Canada. His
experience includes detail engineering and system
engineering support. He is currently involved in
evaluating the long-term impact on the utilities’
operation due to various large projects coming on-
line in the near future.

You might also like