Course: Electrical Power Generation & Utilization Semester: 6th
Deadline: 03rd July 2020 Total Marks: 20
Note: Please use blank A4 size pages.
Assignments submitted after the deadline will not be considered. Answer briefly, don’t write unnecessary details. _________________________________________________________________________________
Q: The following data relates to a 10 MW thermal power station.
Cost of plant Rs. 12,000/kW
Interest, etc 5% per annum Depreciation 5% per annum Cost of primary distribution system Rs. 4,000,000 Interest etc 5% per annum Cost of coal Rs. 400 per metric ton Operational costs Rs. 4,000,000 per annum Maintenance cost Fixed Rs. 200,000 per annum Variable Rs. 300,000 per annum