A firmware for VDE-AR-N 4105
and BDEW Richtlinien
Sw version 1.2.0
1 General information 2
2 Changes in the version 1.2.0 3
3 Changes in the version 1.1 10
4 Related information 12
5 Notes 13
IMPORTANT: It is necessary to use gen-set controllers (IGS-NT) in AUT mode and power
management enabled for correct function of IM-NT-VDE firmware. If gen-set controllers are not in
AUT mode or they are not available for power management IM-NT does not register them correctly
and curves CapabilityQ L and CapabilityQ C need to be removed from the configuration to allow
the controller to work correctly (when the curves are removed they are replace with constant PF
boundaries 0.6L and 0.8C and the function PforQ is not available).
IMPORTANT: This type of paragraph highlights a procedure, adjustment etc., which can cause a
damage or unproper function of the equipment if not performed correctly and may not be clear at
first sight.
Example: This type of paragraph contains information that is used to illustrate how a specific function
works.
2.2 Repairs
Mains ret del setpoint now works correctly in combination with MainsSyncTlong and MainsSyncTshort
The setpoint Mains ret del is now available in the configuration
Load Demand Swap function now works correctly
Master assignment problem resolved
Problem with 0s power band change delays resolved
Updated to the last standard IM-NT-3.4.0
Problem with communication with IGS-PTM module when the controller and IGS-PTM started at the
same time resolved
Problem with CANNegotiation function when synchronized setpoint is changed resolved
Problem with Inteli IO8/8 communication resolved
It is now possible to send IB-EML-SMS via IG-IB
PLC Delay block problem with 100ms shorter delays resolved
Trivial error in calculation of AIN value based on User sensors resolved
All LBOs now considered as configured when used in PLC
It is possible to measure more than 32,000 RPM via InteliAIN8 RPM input
Unwanted activation of Timer resolved
LBO:HORN FLASHING is no longer delayed against LBO HORN
The controller will no longer cycle through states when another controller indicates closed GCB on the
bus but IM-NT measures wrong voltage on the bus
3.2 Repairs
The behavior of functions Overheat protection and MinPwr PtM fixed
Control diagram in InteliMonitor is now shown properly for all controllers
Test on Load fail calculation repaired when power management is set to ABS(kVA)
When the system is not in parallel to Mains operation the Mains fail now always causes the function
SyncNotAllowed to used alway MainsSysTlong delay
Archives (*.ant)
For InteliMainsNT/C BaseBox For InteliSysNT/C BaseBox
IM-BB-VDE-MGCB-1.2.0.6.ant IM-IS-VDE-MGCB-1.2.0.6.ant
5.2 Disclaimer
The certification is only valid with the correct actual settings that can be obtained at the time of commissioning
in official documents.
Local load has to be counted in while commissioning and setting setpoints like Samax, NominMainsImport
etc. Considerable and/or fluctuating local load may violate the VDE compliance since the load will consume
power that may be requested to be exported to the grid.