Post Post Project Post Project

Task description Project Week 1 Project Week 2 Project Week 3 Project Week 4 Project Week 5 Project Week 6 Project Week 7 Project Week 8 Project Week 9 Project Week 10 Project Week 11 Project Week 12 Construction Week3 Week4
Define basic client requirements
Basic site appraisal
Identify project risk
Create rough project budget – cost estimate
Project Brief developed with the client
Define project outcomes and spatial requirements
Define procurement strategy
Agree basic project budget with client
Obtain site information
Conduct site surveys
Arrive at architectural concept approved by client in response to brief
Design programme development
Develop cost plan
Design reviews
Design studies
Develop Pre Tender Estimate
Call for tender for contractor with client
Engineering analysis
Cost exercises
Decide Building Systems and Material sourcing
Develop technical drawings
Appoint contractor
Develop construction programme
Handover with Plan for Use Strategy
Project performance review
Implement facilities management
Undertake post occupancy evaluation