BUILLDING WORK

CELING CONSTRUCRION
REKAPITULASI

No Breakdown NODE Unit Amount

METAL PLANT TILES CC1 Sq. M 31.85


EXPOSED SLAB SOFFIT CC2 Sq. M 463.92
PLASTER BOARD CC3 Sq. M 9.52
PATERNED PLASTER BOARD CC4 Sq. M 89.25
MINERAL FIBER BOARD CC5 Sq. M 1,026.53
CALCIUM SILICATE BOARD TILES CC6 Sq. M 129.97
BUILLDING WORK
CELING FINISHES
REKAPITULASI

No Breakdown NODE Unit Amount

FACTORY FINISH CF1 Sq. M 1,058.38


ANTI FUNGUS PAINT CF3 Sq. M 692.66
BUILLDING WORK

Dimension (m)
Number
Major Number No ROOM OF BUILLDING ADMIN CCR Breakdown Node Breakdown Node TOTAL AMOUNT Note
(pcs)/side
Wide Long

MANAGER
I 1 PURCHASING MANAGER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 4.450 3.500 1.00 15.58
2 ENGINEER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 4.500 3.500 1.00 15.75
3 MANAGER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 5.200 3.500 1.00 18.20
4 WAITING AREA MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 6.000 1.00 36.00
5 FEMALE LOCKER & SHOWER ROOM PATERNED PLASTER BOARD CC4 ANTI FUNGUS PAINT CF3 9.175 6.000 1.00 55.05
6 LOCKER ROOM CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 4.975 6.000 1.00 29.85
7 WAREHOUSE CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 8.550 3.850 1.00 32.92
8 HR SECRETARY/ CLERK ETC EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 9.180 6.000 1.00 55.08
9 HR SECRETARY/ CLERK ETC MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 3.850 3.320 1.00 12.78
10 HR SECRETARY/ CLERK ETC MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 5.850 15.000 1.00 87.75
11 HR SECRETARY/ CLERK ETC MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 8.000 8.850 1.00 70.80
12 CONFERENCE ROOM MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.260 9.600 1.00 21.70
13 MEETING ROOM MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 6.480 1.00 38.88
14 IT OFFICER & SECRETARY MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 3.530 1.00 21.18
15 PLANT/ OPERATIONS MANAGER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 7.900 1.00 47.40
16 QA ARCHIVE ROOM MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 6.000 1.00 36.00
17 (RAISED FLOOR) MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 3.300 1.00 19.80
18 LABORATORY EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 6.000 6.500 1.00 39.00
19 LABORATORY METAL PLANT TILES CC1 FACTORY FINISH CF1 6.000 4.850 1.00 29.10
20 LAB GAS BOTTLE STORAGE METAL PLANT TILES CC1 FACTORY FINISH CF1 2.500 1.100 1.00 2.75
21 BIN CENTRE EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 3.500 1.100 1.00 3.85
22 STORAGE-1 EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 3.750 3.260 1.00 12.23
23 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.400 3.750 1.00 9.00
24 OPEN OFFICE AREA
RECEPTION MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.250 19.000 1.00 42.75
25 PATERNED PLASTER BOARD CC4 ANTI FUNGUS PAINT CF3 6.000 4.250 1.00 25.50
26 INTERVIEW AREA/TRAINING ROOM PATERNED PLASTER BOARD CC4 ANTI FUNGUS PAINT CF3 2.900 3.000 1.00 8.70
27 STORAGE-2 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 3.300 4.250 1.00 14.03
28 CLEANERS MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.100 2.900 1.00 6.09
29 HALLWAY-2 CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 2.500 2.900 1.00 7.25
30 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 1.750 10.000 1.00 17.50
31 HALLWAY-2
HALLWAY-1 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 14.000 2.300 1.00 32.20
32 HALLWAY-1 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 6.000 2.500 1.00 15.00
33 FEMALE TOILET MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.260 12.000 1.00 27.12
34 TOILET CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 3.000 5.000 1.00 15.00
35 PRAYER ROOM (FEMALE) CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 3.400 5.000 1.00 17.00
36 PRAYER ROOM (MALE) CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 3.400 4.000 1.00 13.60
37 DOCUMENT CONTROL OFFICER CALCIUM SILICATE BOARD TILES CC6 ANTI FUNGUS PAINT CF3 3.500 4.100 1.00 14.35
38 DRAFTSMAN MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 4.000 5.400 1.00 21.60
39 ENG & MAINTENANCE ENGINEER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 1.925 5.400 1.00 10.40
40 ENG & MAINTENANCE MANAGER MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 3.100 7.200 1.00 22.32
41 DOCUMENT ARCHIVE ROOM MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 3.200 4.300 1.00 13.76
42 AIRLOCK MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 3.100 2.820 1.00 8.74
43 WH&LOGISTICS OFFICE/STORE KEEPER PLASTER BOARD CC3 ANTI FUNGUS PAINT CF3 2.800 3.400 1.00 9.52
44 ELECTRICAL ROOM MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.830 2.830 1.00 8.01
45 TELECOM ROOM EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 3.680 3.570 1.00 13.14
46 M&E BUILDING SUPPORT SERVICES & ACMV ROOM EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 2.320 3.570 1.00 8.28
47 M&E BUILDING SUPPORT SERVICES & ACMV ROOM EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 8.500 12.000 1.00 102.00
48 (RAISED FLOOR) EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 5.700 3.570 1.00 20.35
49 (RAISED FLOOR) EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 12.000 8.000 1.00 96.00
50 COVERED WALKWAY EXPOSED SLAB SOFFIT CC2 ANTI FUNGUS PAINT CF3 12.000 9.500 1.00 114.00
51 COVERED WALKWAY MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.450 17.000 1.00 41.65
52 COVERED WALKWAY MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.450 53.500 1.00 131.08
53 COVERED WALKWAY MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.450 33.050 1.00 80.97
54 COVERED WALKWAY MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 2.450 27.300 1.00 66.89
55 MINERAL FIBER BOARD CC5 FACTORY FINISH CF1 1.250 12.500 1.00 15.63

SUB JUMLAH

TOTAL JUMLAH
BUILLDING WORK

Dimension (m)
Number
Major Number No Breakdown Node Sketsa Amount Sq.m Note
(pcs)/side
Wide High Thicknes

I SIDE FRONT 48.000 1.400 1.00 67.20


SIDE BACK 48.000 1.400 1.00 67.20
SIDE RIGHT 30.000 1.400 1.00 42.00
SIDE LEFT 30.000 1.400 1.00 42.00

SUB JUMLAH 218.40

TOTAL JUMLAH 218.40