BAHAN U/MEKANIKAL

1. WF. 250 X 125 X MTR = 10 BTG+3+14 = 28 BTG


2. WF 200 X 100 X MTR = 11 = 11 BTG
3. CNP 125 X 6 MTR = 96 = 96 BTG
4. MS PLATE 4 X 8 X 15 MM = U/TAPAK = 1 LBR
5. MS PLATE 4 X 8 X 12 MM = U/ RAFTER = 1 LBR
6. MS PLATE 4 X 8 X 8 MM = U/ STRIPNER = 1 LBR
7. MS PLATE 4 X 8 X 6 MM = U/TUPAI-TUPAI = 1 LBR
8. MS PLATE 4 X 8 X 2 MM = U/PINTU = 14 LBR
9. BESI SIKU 50 X 50 X 6 MTR = U/TULANG PINTU = 20 BTG
10. UNP 150 X 75 X 6 MTR = U.REL PINTU ATAS = 2 BTG
11. BESI SIKU 75 X 75 X 6 MTR = U/REL PINTU BAWA = 2 BTG
12. BESI BETON 16 MM X 12 MM = U/TALI ANGIN = 20 BTG
13. BESI BETON 12 MM X 12 MTR = U/SAG ROTE = 10 BTG
14. BAUT ¾ X 2 ½ = U/RAFTER = 250 BH
15. BAUT ½ X 1 ½ = U/SAG ROTE / TUPAI-TUPAI = 560 BH
16. BAUT 5/8 X 2 ½ = U/T BEAM / KANOPI = 50 BH
17. BAUT 7/8 X 500 MM = U/BAUT ANGKOR = 48 BH
18. TREKER 12 INCI = 16 BH
19. SENG EXPANDEX 0,75 X 0,4 MM X 5.300 MM = 124 LBR
20. RABUNG 0,4 MM X 3 MTR = 8 LBR
21. CAT MENI = 100 KG
22. CAT WARNA = 100 KG
23. THINER 100 KG
24. KUAS ROL/LENGKAP = 10 BH
25. KUAS 4 “ = 5 BH
26. KAWAT RB 26 3,2 MM = 100 KG
27. BATU GERENDA 4” = 5 LSN
28. BAUT SENG SKRUP =4 KTK

UPAH PABLIKASI/EREKSI DAN SIPIL UNTUK PEKERJAAN 100 %


= Rp. 160.000.000
UNTUK PEKERJAAN SIPIL

1. BESI BETON 12 MM U/PONDASI DAN SLOP 80 BATANG

2. BESO BETON 6 MM U/RING (CINCIN) 75 BATANG

3. BESI BRC 6 MM U/LANTAI 40 LEMBAR

4. KAYU 1 X 2 INC U/GOPLANG 40 BATANG

5. KAYU 2X3 INC U/PERANCA 25 BATANG

6. PAPAN U/PERANCA DAN MAL 50 BATANG

7. BATU BATA 40.000 BH

8. SEMEN 500 SAK

9. KAWAT BETON 40 KG

10. PAKU 3 INC 10 KG

11. PAKU 2 ½ INC 10 KG

12. PAKU2 INC 10 KG

13. BATU SPLIT 10 M3

14. REDIMIX K 250 U/COR LANTAI 50 M3

15. PASIR 30 M3

16. CAT DASAR U /DINDING 110 KG

17. CAT TERMBOK YANG KEDUA/PINISING 125 KG

18. KUAS ROL 8 BH

19. KUAS 5 INC 8 BH