Professional Documents
Culture Documents
Scheduling
Scheduling
16-2
16-2
Five year market plan identifies new and existing
segments that need to be serviced
Further refined to a three year plan.
Specific departure and arrival times arrived at.
Crew availability to be matched to flight
schedules
Crew means both pilots and attendants
16-3
16-3
Pilots cannot be scheduled for more than 35 hours
in a 7 day week
No more than 100 hours in a 28 day cycle.
They must have a 36 hour break every seven days
and 30 days off in an 84 day cycle
Each pilot’s tour of duty begins and ends at a crew
base, and consists of alternate duty and rest
periods
Duty periods may have one or more flights
16-4
16-4
Sophisticated optimization models are used to
design generic minimum cost schedules that
recognize all the constraints.
The tours of duty are posted and crew members
bid on them within a specified period of time.
Actual crew rosters are constructed from the bids
received.
Roster must ensure that…
16-5
16-5
…each flight has a qualified crew
…and that each crew member has a feasible
schedule over the roster period.
Crew requests and preferences may be there.
Daily disruptions may happen. Weather,
emergencies, mechanical snags
Customers expect these to be resolved quickly
and companies look for low cost solution.
16-6
16-6
Establishing the timing of the use of
equipment, facilities and human activities in
an organization
Allocating resources over time to accomplish
specific tasks.
Scheduling Encompasses allocating workloads
to specific work centers and determining the
sequence in which operations are to be done.
16-7
16-7
Eg: Manufacturers must schedule production,
which means developing schedules for
workers, equipment, purchases, maintenance,
etc..
Eg: Hospitals must schedule admissions,
surgery, nursing assignments, and support
services such as meal preparations, security,
maintenance and cleaning.
16-8
16-8
Eg: Educational institutions must schedule
classrooms, instruction, and students.
16-9
16-9
Location of police stations, capacity of men
and patrol cars are other decisions.
Forecasting of requirements
16-10
16-10
Scheduling is a process that must answer
questions such as:
Is it low cost?
16-11
16-11
Demand Scheduling (involves assigning
customers to a definite time for order
fulfillment):
Workforce scheduling (involves determining
when employees will work)
Operations Scheduling (involves assigning
jobs to workstations or employees to jobs for
specified time periods).
16-12
16-12
Operations Scheduling and Valentine week?
16-13
16-13
Low-volume
Intermediate-
volume
High-volume
Service operation
16-15
Characterized by standardized equipment and
activities that provide identical or highly
similar operations on customers or
jobs/products as they pass through the system.
The goal is to obtain a smooth rate of flow of
goods and services through the system in
order to get a high utilization of labor and
equipment.
16-16
16-16
Flow system: High-volume system with
Standardized equipment and activities
Flow-shop scheduling: Scheduling for high-
volume flow system
Continuous flow
shop
Assembly line 16-17
Line Balancing..
16-18
16-18
Systems are highly repetitive in nature
16-19
16-19
Use of specialized material handling
equipment..
Division of labor..
16-20
16-20
Few flow systems are entirely dedicated to a single
product or service
Each product change requires
Slightly different inputs of parts
Slightly different materials
Slightly different processing requirements that must be
scheduled into the line
Need to avoid excessive inventory buildup
Disruptions may result in less-than-desired output
The following factors often dictate the success of high-
volume systems:
• Process and product design
• Preventive maintenance
• Rapid repair when breakdowns occur
• Optimal product mixes
• Minimization of quality problems
• Reliability and timing of supplies
Outputs fall between the standardized type of output
of high-volume systems and the make-to-order output
of job shops
Output rates are insufficient to warrant continuous
production
Rather, it is more economical
to produce intermittently
Work centers periodically
shift from one product to
another
Three basic issues:
Run size of jobs
The timing of jobs
The sequence in which jobs will be produced
2 DS p
QO
H p u
Volumes are larger when compared to job
shops.
Canned foods, baked goods, paint and
cosmetics.
Run size of jobs, timing of jobs and the
sequence in which jobs should be processed
are the issues
16-25
16-25
Important considerations
Setup cost
Usage is not always as smooth as assumed in the
economic lot size model
Alternative scheduling approach
Base production on a master schedule developed from
customer orders and forecasted demand
MRP more important for assembled goods
For companies producing processed goods (beverages,
canned products, paints, magazines), time-phasing may
not be that important.
Job shop scheduling
Scheduling for low-volume systems with many
variations in requirements
Make-to-order products
Processing requirements keep varying
Material requirements vary across batches
Processing time varies across batches
Processing sequence and setups varies
A complex scheduling environment
It is impossible to establish firm schedules until actual job
orders are received
Loading refers to the assignment of specific
jobs to work centers and to various machines in
the work centers.
16-28
16-28
Loading
the assignment of jobs to processing centers
Gantt chart
Used as a visual aid for loading and scheduling purposes
Purpose of the Gantt chart is to organize and visually display the
actual or intended use of resources in a time framework
Managers may use the charts for trial-and-error schedule
development to get an idea of what different arrangements
would involve
Load chart
A Gantt chart that shows the loading and idle times for a
group of machines or list of departments
Infinite loading
Jobs are assigned to workstations without regard to the capacity of the work
center (may result in imbalance and subsequent steps to correct the same)
Finite loading
Jobs are assigned to work centers taking into account the work center
capacity and job processing times
Infinite loading
1 2 3 4 5 6
Finite loading
Capacity
1 2 3 4 5 6
Forward scheduling
Scheduling ahead from some point in time.
Used when the question is:
“How long will it take to complete this job?
Backward scheduling
Scheduling backwards from some due date
Used when the question is:
“When is the latest this job can be started and still be
completed on time?”
used as a visual aid for scheduling
The job or activity progress chart
The workstation chart
Current date
Job 4/17 4/18 4/19 4/20 4/21 4/22 4/23 4/24 4/25 4/26
Start activity
Dr. Jon
Operating Adams Dr. Aubrey Brothers Dr. Alaina Bright
Room A
Dr. Jeff
Operating Dr. Gary Case Dow Dr. Madeline Easton
Room B
16-34
Schedule chart
A Gantt chart that shows the orders or jobs in progress
and whether they are on schedule
Assignment model
A linear programming model for optimal assignment of
tasks and resources
Hungarian method
Method of assigning jobs by a one-for-one matching to
identify the lowest cost solution
1. Row reduction: subtract the smallest number in each row from
every number in the row
a. Enter the result in a new table
2. Column reduction: subtract the smallest number in each
column from every number in the column
a. Enter the result in a new table
3. Test whether an optimum assignment can be made
a. Determine the minimum number of lines needed to cross out all zeros
b. If the number of lines equals the number of rows, an optimum assignment is
possible. Go to step 6
c. Else, go to step 4
4. If the number of lines is less than the number of rows, modify
the table:
a. Subtract the smallest number from every uncovered number in the table
b. Add the smallest uncovered number to the numbers at intersections of cross-out
lines
c. Numbers crossed out but not at intersections of cross-out lines carry over
unchanged to the next table
5. Repeat steps 3 and 4 until an optimal table is obtained
6. Make the assignments
a. Begin with rows or columns with only one zero
b. Match items that have zeros, using only one match for each row and each column
c. Eliminate both the row and the column after the match
Determine the optimum assignment of jobs to
workers for the following data:
Worker
A B C D
1 8 6 2 4
2 6 7 11 10
Job
3 3 5 7 6
4 5 10 12 9
Worker Row
A B C D minimum
1 8 6 2 4 2 Subtract the smallest
2 6 7 11 10 6 number in each row from
Job every number in the row
3 3 5 7 6 3
4 5 10 12 9 5
Worker
A B C D
1 6 4 0 2
2 0 1 5 4
Job
3 0 2 4 3
4 0 5 7 4
Worker
A B C D
1 6 4 0 2 Subtract the smallest
2 0 1 5 4 number in each column
Job from every number in the
3 0 2 4 3 column
4 0 5 7 4
Column min. 0 1 0 2
Worker
A B C D
1 6 3 0 0
2 0 0 5 2
Job
3 0 1 4 1
4 0 4 7 2
Worker
A B C D
Determine the minimum
1 6 3 0 0
number of lines needed to
2 0 0 5 2 cross out all zeros. (Try to
Job cross out as many zeros as
3 0 1 4 1
possible when drawing lines
4 0 4 7 2
Worker
A B C D
1 7 3 0 0
2 1 0 5 2
Job
3 0 0 3 0
4 0 3 6 1
Worker
A B C D
1 7 3 0 0 Determine the minimum
number of lines needed to
2 1 0 5 2 cross out all zeros. (Try to
Job
3 0 0 3 0 cross out as many zeros as
possible when drawing lines
4 0 3 6 1
Since four lines are needed to cross out all zeros and
the table has four rows, this an optimal assignment
can be made
Worker
A B C D
1 7 3 0 0 Make assignments: Start
with rows and columns with
2 1 0 5 2 only one zero. Match jobs
Job
3 0 0 3 0 with workers that have a
zero
4 0 3 6 1
Assignment Cost
2-B $7
4-A $5
1-C $2
3-D $6
Total $20
Sequencing: Determine the order in which jobs
at a work center will be processed.
16-46
16-46
Sequencing
Determine the order in which jobs at a work center will be
processed
Priority rules
Simple heuristics used to select the order in which jobs will be
processed
The rules generally assume that job setup cost and time are
independent of processing sequence
Job time
Time needed for setup and processing of a job
FCFS - first come, first served
CR - critical ratio
Rush - emergency
The set of jobs is known; no new orders arrive after
processing begins and no jobs are canceled
Setup time is independent of processing sequence
16-58
A(25) B(16) D(10) C(14) E(12) FCFS
0 25 41 51 65 77
0 16 41 51 65 77
0 10 22 36 52 77
16-59
Time Since
Processing Time remaining
Job Order Arrived Due Date CR
Time (days) till due date
(days ago)
A 15 25 29 29 1.16
B 12 16 27 27 1.69
C 5 14 68 68 4.86
D 10 10 48 48 4.80
E 0 12 80 80 6.67
A(25) CR
0 25
Now, assume Time 25 and repeat the procedure till all jobs are sequenced
16-60
Customer Start Processing Finish Due Days Days Ago Flow
Sequence Time Time (days) Time Date Past Since Order Time
(days) (days) Due Arrived (days)
A 0 + 25 = 25 29 0 15 40
B 25 + 16 = 41 27 14 12 53
D 41 + 10 = 51 48 3 10 61
C 51 + 14 = 65 68 0 5 70
E 65 + 12 = 77 80 0 0 77
0 + 14 + 3 + 0 + 0
Average days past due = = 3.4 days
5
/Tardiness
40 + 53 + 61 + 70 + 77
Average flow time = = 60.2 days
5
16-61
Customer Start Processing Finish Due Days Days Ago Flow
Sequence Time Time (days) Time Date Past Since Order Time
(days) (days) Due Arrived (days)
D 0 + 10 = 10 48 0 10 20
E 10 + 12 = 22 80 0 0 22
C 22 + 14 = 36 68 0 5 41
B 36 + 16 = 52 27 25 12 64
A 52 + 25 = 77 29 48 15 92
0 + 0 + 0 + 25 + 48
Average days past due = = 14.6 days
5
/Tardiness
20 + 22 + 41 + 64 + 92
Average flow time = = 47.8 days
5
16-62
Customer Start Processing Finish Due Days Days Ago Flow
Sequence Time Time (days) Time Date Past Since Order Time
(days) (days) Due Arrived (days)
B 0 + 16 = 16 27 0 12 28
A 16 + 25 = 41 29 12 15 56
D 41 + 10 = 51 48 3 10 61
C 51 + 14 = 65 68 0 5 70
E 65 + 12 = 77 80 0 0 77
0 + 12 + 3 + 0 + 0
Average days past due = = 3.0 days
5
/Tardiness
28 + 56 + 61 + 70 + 71
Average flow time = = 58.4 days
5
16-63
Sequence FCFC SPT EDD
Average days
past due
3.4 14.6 3
/Tardiness
# of Tardi Jobs 2 2 2
16-64
Variability in
Setup times
Processing times
Interruptions
Unforeseen and sudden changes in the set of jobs
No method for identifying optimal schedule
Scheduling is not an exact science
Ongoing task for a manager
16-65
Set realistic due dates
16-66
Johnson’s Rule
Technique for minimizing makespan for a group of jobs
to be processed on two machines or at two work centers.
Minimizes total idle time
Several conditions must be satisfied
Job time must be known and constant for each job at the
work center
Job times must be independent of sequence
Jobs must follow same two-step sequence
All jobs must be completed at the first work center before
moving to second work center
1. List the jobs and their times at each work center
2. Select the job with the shortest time
a. If the shortest time is at the first work center, schedule that job first
b. If the shortest time is at the second work center, schedule the job last.
c. Break ties arbitrarily
3. Eliminate the job from further consideration
4. Repeat steps 2 and 3, working toward the center of the sequence, until
all jobs have been scheduled
Theory of constraints
Production planning approach that emphasizes balancing
flow throughout a system, and pursues a perpetual five-step
improvement process centered around the system’s currently
most restrictive constraint.
Bottleneck operations limit system output
Therefore, schedule bottleneck operations in a way that minimizes
their idle times
Drum-buffer-rope
Drum = the schedule
Buffer = potentially constraining resources outside of the bottleneck
Rope = represents synchronizing the sequence of operations to
ensure effective use of the bottleneck operations
Varying batch sizes to achieve greatest output of bottleneck
operations
Process batch
The economical quantity to produce upon the activation of a given
operation
Transfer batch
The quantity to be transported from one operation to another, assumed
to be smaller than the first operation’s process batch
Improving bottleneck operations:
1. Determine what is constraining the operation
2. Exploit the constraint (i.e., make sure the constraining resource is
used to its maximum)
3. Subordinate everything to the constraint (i.e., focus on the
constraint)
4. Determine how to overcome (eliminate) the constraint
5. Repeat the process for the next highest constraint
Three important theory of constraints metrics:
Throughput
The rate at which the system generates money through sales
Inventory
Inventory represents money tied up in goods and materials used
in a process
Operating expense
All the money the system spends to convert inventory into
throughput: this includes utilities, scrap, depreciation, and so on
Service scheduling often presents challenges not found
in manufacturing
These are primarily related to:
1. The inability to store or inventory services
2. The random nature of service requests
16-79
Steps in developing a workforce schedule
Step 1: Find all the pairs of consecutive days
Step 2: If a tie occurs, choose one of the tied pairs,
consistent with the provisions written into the
labor agreement
Step 3: Assign the employees for the selected pair of
days off
Step 4: Repeat steps 1 – 3 until all of the requirements
have been satisfied
16-80
EXAMPLE
The Amalgamated Parcel Service is open seven days a week. The
schedule of requirements is
Day M T W Th F S Su
Required number of employees 6 4 8 9 10 3 2
16-81
SOLUTION
Friday contains the maximum requirements, and the pair S – Su
has the lowest total requirements. Therefore, Employee 1 is
scheduled to work Monday through Friday.
Note that Friday still has the maximum requirements and that
the requirements for the S – Su pair are carried forward because
these are Employee 1’s days off. These updated requirements are
the ones the scheduler uses for the next employee.
The day-off assignments for the employees are shown in the
following table.
16-82
Scheduling Days Off
M T W Th F S Su Employee Comments
6 4 8 9 10 3 2 1 The S–Su pair has the lowest total requirements. Assign
Employee 1 to a M-F schedule.
5 3 7 8 9 3 2 2 The S–Su pair has the lowest total requirements. Assign
Employee 2 to a M-F schedule.
4 2 6 7 8 3 2 3 The S–Su pair has the lowest total requirements. Assign
Employee 3 to a M-F schedule.
3 1 5 6 7 3 2 4 The M–T pair has the lowest total requirements. Assign
Employee 4 to a W-Su schedule.
3 1 4 5 6 2 1 5 The S–Su pair has the lowest total requirements. Assign
Employee 5 to a M-F schedule.
2 0 3 4 5 2 1 6 The M–T pair has the lowest total requirements. Assign
Employee 6 to a W-Su schedule.
2 0 2 3 4 1 0 7 The S–Su pair has the lowest total requirements. Assign
Employee 7 to a M-F schedule.
1 0 1 2 3 1 0 8 Four pairs have the minimum requirement and the
lowest total. Choose the S–Su pair according to the tie-
breaking rule. Assign Employee 8 to a M-F schedule.
0 0 0 1 2 1 0 9 Arbitrarily choose the Su–M pair to break ties because
the S–Su pair does not have the lowest total
requirements. Assign Employee 9 to a T-S schedule.
0 0 0 0 1 0 0 10 Choose the S–Su pair according to the tie-breaking rule.
Assign Employee 10 to a M-F schedule.
16-83
Scheduling Days Off
M T W Th F S Su Employee Comments
6 4 8 9 10 3 2 1 The S–Su pair has the lowest total requirements. Assign
Employee 1 to a M-F schedule.
5 3 7 8 9 3 2 2 The S–Su pair has the lowest total requirements. Assign
Employee 2 to a M-F schedule.
4 2 6 7 8 3 2 3 The S–Su pair has the lowest total requirements. Assign
Employee 3 to a M-F schedule.
3 1 5 6 7 3 2 4 The M–T pair has the lowest total requirements. Assign
Employee 4 to a W-Su schedule.
3 1 4 5 6 2 1 5 The S–Su pair has the lowest total requirements. Assign
Employee 5 to a M-F schedule.
2 0 3 4 5 2 1 6 The M–T pair has the lowest total requirements. Assign
Employee 6 to a W-Su schedule.
2 0 2 3 4 1 0 7 The S–Su pair has the lowest total requirements. Assign
Employee 7 to a M-F schedule.
1 0 1 2 3 1 0 8 Four pairs have the minimum requirement and the
lowest total. Choose the S–Su pair according to the tie-
breaking rule. Assign Employee 8 to a M-F schedule.
0 0 0 1 2 1 0 9 Arbitrarily choose the Su–M pair to break ties because
the S–Su pair does not have the lowest total
requirements. Assign Employee 9 to a T-S schedule.
0 0 0 0 1 0 0 10 Choose the S–Su pair according to the tie-breaking rule.
Assign Employee 10 to a M-F schedule.
16-84
In this example, Friday always has the maximum requirements
and should be avoided as a day off. The final schedule for the
employees is shown in the following table.
Final Schedule
Employee M T W Th F S Su Total
1 X X X X X off off
2 X X X X X off off
3 X X X X X off off
4 off off X X X X X
5 X X X X X off off
6 off off X X X X X
7 X X X X X off off
8 X X X X X off off
9 off X X X X X off
10 X X X X X off off
Capacity, C 7 8 10 10 10 3 2 50
Requirements, R 6 4 8 9 10 3 2 42
Slack, C – R 1 4 2 1 0 0 0 8
16-85