Professional Documents
Culture Documents
TENDER - BRO Himachal Pradesh Rs.87 CR PDF
TENDER - BRO Himachal Pradesh Rs.87 CR PDF
CE (P)RTNL/03/2020-21
June 2020
Note
*These documents can also be seen in the office of the CE Project Rohtang Tunnel
Border Roads, C/O 56 APO, during working Hours.
M/s………………………………...
……………………………………..
……………………………………..
……………………………………..
1. A set of tender documents for the above work is forwarded herewith. Please note that tender
will be received through on line only by the Chief Engineer (P) Rohtang Tunnel, C/o 56 APO
up to 1500 Hrs on 24th of July 2020. ‘T’-bid will be opened as per date / time as mentioned in the
tender critical date sheet. After online opening of T-Bid the results of their qualification as well Q-Bid
opening will be intimated later.
2. Tenderers or their duly authorized representative who have submitted their tenders and who
wish to be present at the time of opening of tenders may visit the office of Chief Engineer (P)
Rohtang Tunnel, C/o 56 APO at the above-mentioned time. However, they can view online tender
opening process at their premises.
3. Tender documents may also be downloaded from Central Public Procurement Portal (CPPP)
website https://eprocure.gov.in/eprocure/app. Scanned copies of all the documents, duly
authenticated, as per requirement of tender conditions be uploaded with the online submitted bid.
The hard copy original instruments in respect of Earnest Money, integrity pact duly singed on each
page by the bidder(s) and under taking given at page No____ of tender must be delivered to The
Chief Engineer Project within 05 days from the bid submission end date. If scanned copy of earnest
money and integrity pact is not uploaded along with the T-bid, same shall be rejected by the
accepting officer. Scanned and original copies should be same and no difference is acceptable.
4. Tendering procedure shall be single stage two bid system and tender documents are prepared in
two parts as under: -
4.1 (a) The tender to be submitted (online) by the bidder will be comprised of the following
documents: -
(i) BLANK.
(ii) Scanned copy of earnest money deposit by un-enlisted contractor and enlisted
contractors who have not submitted standing security deposit.
(iii) Scanned and signed copy of all the eligibility /qualification documents required as per
tender conditions given at page No. to page No. of tender documents along with
Material Technical Performance Requirements and Experience of key construction activities
as given in particular specifications.
(iv) Scanned and signed copy of Integrity Pact.
(v) Scanned and signed copy of under taking by tenderer given at Serial Page No.____
of tender.
(b) Following documents will be deemed to be part of the contract during the time of
acceptance of contract: -
5.2.1 If contractor is not enlisted with BRO or enlisted with BRO but has not submitted
Standing Security Deposit, he should have submitted Earnest Money.
5.2.2 All the pages of T-bid should have been signed by the bidder / authorized rep having
valid Power of Attorney.
6. Eligibility Criteria: - Tenderers shall meet the following eligibility criteria for qualifying in
Technical bid.
(a) The tenderer should have working capital and /or credit facilities of at least 10% of the
estimated cost of the work (Applicable only for non-enlisted Contractors)
6.1 Experience:-
Tenderers should have successfully completed or substantially completed with any Govt
agencies/PSU/Municipal Corporation/local Govt. bodies/BRO
Three similar works costing not less than the amount equal to 40% of estimated cost of
work or two similar works costing not less than the amount equal to 50% of estimated cost of
work or one similar work costing not less than the amount to equal to 80% of estimated cost
of work in last seven & current financial years.
Design, supply and installation of major slope stabilization work using steel wire grid/mesh
Geo-composite along with deep surface anchoring on steep vertical rock slopes on Major
State Highway / National Highway / Border Roads project in India” in last seven years and
current financial year.
(Certificate from the officer not below the rank of executive engineer of the respective
Government organization for whom the work is executed must be furnished for above along
with the bid.)
Notes: -
1. Substantially completed works means those works which are 90% completed
on the date of submission (i.e. gross value of work done up to the last date of
submission is 90% or more of the original contract price) and continuing
satisfactorily.
2. Tenderer shall submit list of work executed in the past 7 years in their letter
head duly signed by the proprietor /partner/ director of the firm in the
proformacontained in clause 8.10.
6.2.1 ABC as per formula given here under should be more than estimated cost work given in
NIT. Tenderers shall calculate ABC and submit details duly signed on letter head.
Available Bid Capacity = 2.5 x A x N- B
A - Maximum value of all civil Engg. works in any one year during the last 5 financial
years (updated to the current price level with enhancement factor as given below)
supported with duly certified Balance Sheets/ Certificates form Chartered Accountant.
N- Number of years prescribed for completion of work for which the current bid is invited
B- Value of the balance ongoing works to be executed in period N
6.2.2 The tenderers shall indicate actual figures of completion cost of work and value of A
without any enhancement as stated above.
6.2.3 The tenderer may be accorded an opportunity to clarify or modify his qualification
documents, if necessary, with respect to any rectifiable defects through option of short fall in
tender documents to be uploaded by the bidder. The tenderer will respond in not more than
07 days of uploading of the clarification letter through shortfall option failing which his tender
is liable to be rejected.
Note: Tenderer should provide undertaking of arranging VEP as per specific requirement of
this specialized nature of work as required for successful and timely completion of
work.
6.4 Performance and other requirements:-
(a) There is not poor/slow progress in running work. (If yes, he will submit details
and reasons of delay to check that these are not attributable to him or are beyond his
control).
(b) There are not serious defect observed in works which stand un-rectified (If yes
he will submit details and reasons).
(c) There are not cancelled / abandoned contracts in which Govt. unrealized
recoveries exist (If yes, he will submit details and reasons).
(d) He / They have not been blacklisted by any Govt. Deptt (If yes, he will submit
details and reasons).
(e) There are not any Govt. dues outstanding against the firm (If yes, he will
submit details and reasons).
(f) The proprietor/Partners/Directors of the firm are not habitual litigant i.e. having
more than 3 unsuccessful arbitration/court cases during last 5 years in which his
views / claims substantially rejected.
(g) Proprietor / partners / directors of firm are not involved in antinational / social
activities and have neither been convicted nor any proceedings are pending in court
for such activities during last 5 years (If yes, he will submit details).
6.5 Disqualification: -Even though the tenderer meet the above criteria, they are
liable to be disqualified if they have made misleading or false information in bidding
documents submitted.
Experience of key Construction activity in India for Materials to be used:
(i) Surface Anchoring works using double corrosion-protected multi strand prestressed
cable anchors and / or steel anchors on steep slopes which includes Drilling, grouting,
providing and fixing anchors at locations in India for Government Organizations – 18750
Running Meter Approximate @ 40% quantity of BOQ (minimum)
(ii) Supply and installation of three-dimensional reinforced erosion control mat and / or
steel wire mesh / grid Geo-composite at locations in India for Government
Organizations – 11000 Sqm Meter Approximate @ 40% quantity of BOQ (minimum)
(iii) Experience in Avalanche / Rock fall protection barrier structures in India for
Government Organizations
Note: In case of JV, experience of the key construction activities can be met individually
or jointly, but each partner should have the experience of executing above items of key
construction activities.
(Certificate from the officer not below the rank of executive engineer of the
respective Government organization for whom the work is executed must be
furnished for (i), (ii) & (iii) above along with the bid.)
7. JOINT VENTURE –JV is allowed for this work as cost of work is above 50.00
Crores. (Only Indian companies JV is allowed)
7.1 Two firms are permitted to bid for the tender based on Joint Venture agreement between
them. Joint Venture (JV) shall not comprise more than two firms (called parties of JV). The
format of agreement at Annexure ‘I’. The JV shall be considered as un-enlisted contractor. The
JV shall submit earnest Money Deposit for all tenders and individual Security deposit as per
instructions, if contract is awarded.
7.3 No JV shall be allowed for furniture works. No JV shall be allowed to participate if either
or both the parties are banned/adversely remarked in WLR of BRO or debarred from tendering
by any authority.
7.4 Foreign Companies shall not be permitted to participate in JV except in case of tunnel
project. Security clearance of Foreign Companies having foreign citizenship Directors shall dealt
with as prescribed under subsequent para.
7.5 (a) Indian Companies having Director (s) of foreign origin and Indian Companies
having Director (s) of Indian origin but residing abroad / having foreign citizenship shall be
permitted to participate in JV. However, security clearance in such cases shall be obtained by
following procedure laid down by Ministry of Home Affairs vide their letter No. II/20034/2013-IS II
dt 30 Jun 2015 and amendment there if vide OM No II/20034/2013-II dt 09 Dec 2015. These
letters, being classified, are not being shared. The case for security clearance shall be
processed to HQ DGBR for taking up matter with concerned authorities.
(b) Case for security clearance shall be processed to HQ DGBR on PRIORITY after opening
‘T’bid (Cover-1). Further processing of tender to open Finance Bid (Cover-2) shall not be held up
awaiting receipt of security clearance. However, if the JV requiring security clearance of Director
(s) becomes L1, the tender shall be accepted only on receipt of security clearance. For this, the
Accepting officer will pursue the security clearance vigorously.
(c ) For runway tenders, all other policies issued vide E-in-C’s Branch letter No.
A/37696/OSDPL/POL/E2 W (PPC) dt 15 May 2015 as amended vide their letter even No dt 14
Mar 2017 pertaining to experience, nature of works executed, requirement of tools, plants and
machinery, financial turnover, Available Bid Capacity etc shall be followed.
7. 6 A valid agreement shall exist between the parties of JV defining clearly the role,
responsibility and scope of work of each party, percentage share of each party along with
nomination of leader (lead Party) for the purpose of this work and a confirmation that the parties
of the JV are jointly and severally responsible.
7. 7 JV as a single unit or each party of the JV shall have Permanent Account Number (PAN)
and GSTIN. However, if the contract is awarded to the JV, then PAN & GST shall be obtained by
the JV as single unit.
7.8 The JV shall have two parties. The lead party of the JV shall meet minimum 60% or the
percentage of share in the JV (whichever is higher) of the qualifying criteria pertaining to (a) past
experience of completed works, (b) Average Annual Turnover, (c) Bank Solvency/ Financially
Sound for engagement and (d) Working Capital. Both the parties combined shall meet minimum
120% of the above qualifying criteria. The party other than the lead party shall meet minimum
30% of the above qualifying criteria.
7. 9 Both the Parties of JV shall jointly possess the required T&P, machinery and
engineering/ supervisory staff. T&P can be either on ownership basis or lease hold as stipulated
in NIT/ tender documents and documentary proof of the same shall be submitted. Other
qualification criteria shall be meet fully/ jointly by both the parties of JV or as a single unit of JV.
7. 10 In the Residual Bid Capacity ( in the formula 2.5 xAxN-B, where A= Maximum turnover in
last five financial years, N= Period of completion of contracted (tendered) work ( in years
calculated till two decimal places) and B= Value of balance work in all Govt & Private works), in
respect of a JV, values of A and B shall be the sum total of the respective figures of both the
parties.
7.11 Similarly when a Firm/ Contractor working in JV applies for tender (s) in his own capacity
(i.e. independently), the part value of A and B of his JV work (s) in proportion to his percentage
share in JV shall also be considered against the tender applied in his own capacity and hence
these details shall be submitted by the Firm/ Contractor in his ‘T’ bid.
7.12 JV concluded upto the date of bid submission are permitted to apply. Copy of JV should
be uploaded. The Department reserves the right to verify the particulars furnished by the
applicant independently. If any information furnished by the applicant JV is found incorrect and /
or misleading and/or false representation and/or deliberately suppressed information, at a later
stage, the JV and both the parties shall be liable to be debarred from tendering / taking up of any
work in BRO.
7.13 Party / parties will not be allowed to bid for the same tender in their independent capacity
as well as under JV. Also no party will be allowed to bid for the same tender under multiple JVs.
In case of violation (party/parties bidding independently as well as under JV for the same tender,
party/parties bidding for the same tender under multiple JVs), the bid of the party/parties
concerned as well as the bid(s) of the related JV(s) shall not be opened (ie shall not be qualified
in ‘T’ bid Cover ‘1’).
7.14 The lead party shall attend all progress review meetings and shall be answerable to all
issues relating to the project.
7.15 For any of the defaults as under of the JV, administrative action shall be taken against
both the parties of JV: -
In case of non –submission of physical original documents of cost of tender, EMD-Barring from
bidding for six months.
7.16 Any unrealized recovery from JV shall be recovered proportionately from the parties in
proportion to their percentage share in the JV. If it is not possible to recover proportionate share
(partly/fully) form one party, it shall be recovered from other party.
8. List & format of eligibility documents to be attached along with Part-I oftender
documents to prove eligibility: -
List of works completed/substantially completed in last seven and current financial years and
ongoing works in following format: -
Name Brief Name & Accepted Dateof Original Extended Actual date Cost of Remarks
of Scope address Contract Commen date of date of ofcompletion completed explaining
work of of Amount cement complete completion / Present work reasons of
&CA Work employer of work ion Progress delay if
No. / client any
Note: Works proving criteria of experience shall be highlighted and performance certificate from
client in respect of these works shall be submitted.
For – A: - Balance sheets/Certificates from Chartered Accountant indicating annual turnover of civil
Engg works constructed in last 5 years.
For – B: - Contractors shall submit details of ongoing works as per format stated in clause 8.1 of
above.
Tenderers shall calculate ABC and submit details duly signed
8.3 Equipments, Plants and Vehicles:
(a) Tenderer shall indicate source of requisite Equipment’s, Plants and Vehicles with vintage
required for execution of work in following format: -
S/ No. Item Year of Manufacture Source from where to be Location Based on known
arranged (Owned / lease presently commitments,
etc.) deployed whether will be
available for use in
the proposed
contract.
(a) There is no poor/slow progress in running works. (If yes, he will submit details and reasons of
delay to check that these are not attributable to him or are beyond his control).
(b) There are no serious defects observed in works which stand un-rectified (If yes, he will submit
details and reasons).
(c) There are no cancelled/abandoned contracts in which Govt unrealized recoveries exist (If yes,
he will submit details and reasons).
(d) He/They have not been blacklisted by any Govt. Deptt. (Ifyes, he will submit details and
reasons).
(e) There are no Govt dues outstanding against the firm (If yes, he will submit details and
reasons).
(f) Proprietor/partners/directors of firm are not involved in anti-national/ anti-social activities and
have neither been convicted nor are any proceedings pending in court for such activities (If yes, he
will submit details).
8.5.2 Tenderer shall submit information of all arbitration/court cases decided during last five
and current financial years and also presently in progress as per following format: -
(a) Name & Address of employer
(b) Cause of dispute
(c) Amounts involved
(d) Brief of Court Judgment/arbitration award (if published) otherwise present progress
8.6 Constitution of firm along with copy of partnership deed (in case of partnership
firms)
and memorandum of articles and association (in case of limited companies).
8.7 In case of un-enlisted firms, Copies of Passport of proprietor/partners/directors (if
available). Present address& photograph for verification of character and antecedents of
proprietor/partners/directors from police authorities.
8.8 Copies of PAN Card of proprietor/partners/directors.
8.9 Lowest bidder if un-enlisted firm in BRO (if his offer is decided for acceptance)
will be required to fill enlistment form for provisional enlistment.
Notes: -
1. Documents as listed at clause 8.6 to 8.8 above are exempted for tenderers
enlisted with BRO in any class.
2 Affidavits shall be submitted on Non-Judicial stamp papers of appropriate values
duly attested by the Magistrate/Notary Public.
3. Photocopies of documents shall be attested by Gazetted officer/Public notary and
also
self-attested.
4. The bidder should meet all the technical evaluation criteria indicated in the bid
documents in order that the bid is considered to be technically responsive and the bidder
qualifying to have its Financial Bid opened.
9. Part-II (‘Price/Commercial- ‘Q’ Bid)
10 Q-bid evaluation
(i) Arithmetical corrections shall be made as per General Condition of Contracts 6
(A)(A) of IAFW-2249.
(ii) Commercial Bids will be reviewed to ensure that the figures indicated therein
are consistent with the details of the corresponding Technical bids.
(iii) For the purpose of evaluation “cost” shall be inclusive of all taxes and duties.
(iv) Bidder who has quoted lowest total cost in Schedule A (L-1) shall be
considered successful bidder and all other bidders shall be considered unsuccessful.
Offer of successful bidder (L-1) shall only be considered for acceptance. If L-1 backs
out, retendering shall be resorted in a fair and transparent manner. (iii) Completion
Period as indicated in Tender Document have been accepted.
10.1 The Chief Engineer Project Rohtang Tunnel will be Accepting Officer here-in-
after referred to as such for the purpose of this contract.
10.2 If tenderers desire that any condition or stipulation given in the tender
documents is to be modified or deleted, they may submit their comments/suggestions
before last working date of clarification as shown in critical date details in subject
tender ID for consideration by the Deptt. for issue of corrigendum/amendments to
tender documents. If deptt. considers comments/ suggestions suitable,
corrigendum/amendments to tender documents shall be issued and also uploaded on
E- tendering Portal. If deptt. does not consider comments/suggestion suitable,
corrigendum/amendments to tender documents shall not be issued/uploaded on E-
tendering Portal and tenderers shall quote strictly complying with the various
provisions given in the tender documents. Any tender who stipulates any alterations to
any of the conditions/provisions laid down in tender documents (including
corrigendum/amendments) or which proposes any other conditions of any description
whatsoever is liable to be rejected.
10.3 The tenderers are advised to visit the work site to acquaint themselves of
working and site conditions, before submitting their tender. The submission of tender
by a person implies that he has read this tender forwarding letter, the conditions of
contract and has made himself aware of the scope and specifications of the work to be
done and of the conditions and other factors, site conditions, taxes and levies
prevailing etc. which may affect the quotation and execution of the work.
10.4. Tenderer must be very careful to deliver a Bona fide tender; failing which the
tenders are liable to be rejected. Tenderers are, therefore, advised to ensure that their
tender must satisfy each and every condition laid down in tender documents.
10.5. Your attention is drawn to the Indian Official Secret Act-1923 (XIX of 1923) as
amended up to date particularly section 5 thereof.
11 Earnest Money: -
(a) Earnest money is not required to be submitted by the enlisted contractor with BRO
(term “enlisted contractor” used in tender documents means “enlisted contractor with
BRO”) who have submitted standing security but same is required from enlisted
contractor with BRO, who have not submitted standing security deposit.
(b) Un-enlisted contractors with BRO/Enlisted contractors with BRO, who have not
submitted standing security deposit will submit the tender accompanied with Earnest
Money amounting to Rs. 47,00,000/-(Rupees Forty-Seven Lakhs Only) in the shape
of call Receipt/Term Deposit Receipt/Special Term Deposit Receipt in favour of Chief
Engineer Project Rohtang Tunnel, C/o 56 APO by nationalized/scheduled Bank
payable at SBI, Manali Distt Kullu Himachal Pradesh. Technical Bid not accompanied
with earnest money will not be considered for opening of financial Bid. The amount of
this receipt should be basic amount and not their maturity value. Any deposit lying with
the department in any form against any other tender and/or contract shall not be
considered for adjustment as the earnest money against the tender. Any tender not
accompanied with the earnest money in the form as indicated here-in-before or
accompanied with any letter/communication containing any request for adjustment of
any other deposit as earnest money shall be treated as non bona fide tender.
(c) Earnest money shall be returned to unsuccessful bidder (other than L-1) after
opening of Financial Bids and to successful (L-1) bidder after receipt of security
deposit.
12 Performance Security: -
12.1 Within 28 days of the letter of acceptance, the successful bidder (L-1) shall
deliver to the Accepting Officer a Performance Security for an amount equivalent to
5% of the Contract sum as laid down under condition 19 of IAFW -2249 / Condition 14
A of IAFW -1815 Z (General Conditions of Contract).
12.2 Failure of the successful contractor to comply with the requirement of sub
clause 12.1 shall constitute sufficient grounds for cancellation of award of work and
forfeiture of the Earnest Money. In case of BRO enlisted contractor amount equal to
the Earnest Money stipulated in the Notice Inviting Tender, shall be notified to the
tenderer for depositing the amount through MRO, issue of tender to such tenderers
shall remain suspended till the aforesaid amount equal to the earnest Money is
deposited in Government Treasury.
12.3 In the event of contract being cancelled, under Condition 52, 53, & 54 of IAFW-
2249 or under conditions 26, 27 & 28 of IAFW-1815Z General Conditions of Contracts
the Performance Security & retention money as per last RAR shall be forfeited. ALL
T&P and material of contractor lying at site shall be confiscated by the Government
and shall be absolutely at the disposal of the President of India and no compensation
whatsoever shall be allowed by department.
12.4 Form for Bank Guarantee Bond against Performance Security Deposit shall be
as per Annx- III.
12.5 The period of validity of the Bank Guarantee Bond against Performance
Security shall be upto and including the scheduled date of expiry of Defects Liability
Period.
13. The Accepting Officer reserves the right to accept a tender submitted by a Public
Undertaking, giving a purchase preference over other tender(s) as are admissible
under the Government Policy. No claim for any compensation or otherwise shall be
admissible to such tenders whose tenders may be rejected on account of the said
policy.
14. The tender shall remain open for acceptance for a period of 120 days from bid
submission end date.
15. On acceptance of tender, the name of authorized representative (s) of the
contractors who would be responsible for taking instructions from Engineer-in-Charge
or its authorized representative shall be intimated by the contractor within 7 days of
issue of Acceptance letters.
16.
16 Revision/Modification of quotedPrice
(a) In case the tenderer has to revise /modify /withdraw his quoted rates / offer after it
is uploaded in e-tendering portal he may do so on before bid submission end date &
time in e-tendering portal only. Any revision/ modification in offer / withdrawal of offer
in the form of an open letter after bid submission end date & time and the same shall
be considered as revocation of offer and shall not be taken into account, while
considering his originally quoted offer.
17 Revocation of offer
In the event of lowest tenderer revokes his offer or revise his rates upward (which will
be treated as revocation of offer), after bid submission end date and before expiry of
original validity period stipulated in tender documents, the earnest money deposited by
him shall be forfeited. In case of BRO enlisted contractors, the amount equal to the
earnest money stipulated in the Notice Tender, shall be notified to the tenderer for
depositing the amount through MRO, failing which the amount shall be recovered from
any payment due to such contractor or shall be adjusted from the Standing Security
Deposit. In addition, L-1 tenderer revoking offer and his related firms shall not be
issued the tender in second or subsequent calls of subject work.
Yours Faithfully
Signature of Contractor For
Accepting Officer Dated :………………..
Enclosures: Tender Documents
18 Integrity Pact (IP): - Integrity Pact (Applicable for tender with estimated cost of Rs. 5.00
Crore and above for all works contracts and in tender for procurement of services, stores
equipments & plants with estimated cost of Rs. 1.00 Crore and above)
IP duly signed by Accepting Officer/ authorized officer has been uploaded along with this tender
as Annx-I Same shall be signed by bidder(s) on each page and scanned copy shall be uploaded
as part of Technical bid (Cover-1) and original IP duly signed on each page shall be
forwarded by post along with Tender fee and EMD (if applicable). IP will be an integral part of
the Contract and both parties are bound by provision.
20. Security Deposit: - In case of a enlisted contractor, who has submitted the Standing Security
deposit, but the tendered cost of the work exceeds the upper tendering limit of the contractor and the
Accepting Officer decides to accept his tender, as notified by the Accepting Officer in the prescribed
form within 30 days of the receipt by him of
notificationofacceptanceofthetender,failingwhichthissumshallberecoveredfromthefirst RAR payment,
and if the date of first RAR is prior to the period mentioned above, the same shall be recovered from
such payment.
(a) In case of un-enlisted contractor / enlisted contractor who has not deposited the standing
Security deposit, and the Accepting Officer decides to accept his tender, then contractor has to lodge
Security Deposit as notified by the Accepting Officer in the prescribed form within 30 days of the
receipt by him of notification of acceptance of the tender, failing which the sum shall be recovered
from the first RAR payment, and if the date of first RAR is prior to the period mentioned above, the
same shall be recovered from such payment. The Security Deposit amount will be communicated as
per departmental norms but no case the same shall be more than Rs. 18,75,000/- (Rupees Eighteen
Lacs Seventy-Five Thousand). Departmental norms of security deposit may be seen in any officer of
BRO.
c) The contractor may at his discretion furnish in lieu of Security Deposit a bank Guarantee Bond
executed by any nationalized / Schedule Bank for the said amount. The form of Bank Guarantee Bond
may be seen in any office of BRO.
(b) The Accepting Officer reserves the right to accept a tender submitted by a Public
undertaking, giving a purchase preference over other tender(s) as are admissible under the
government Policy. No claim for any compensation or otherwise shall be admissible to such
tenders whose tenders may be rejected on account of the said policy.
21 BLANK
22. The tender shall remain open for acceptance for a period of One hundred twenty (120)
days from the date of opening of the Q bid of the tender (excluding the date of opening).
23. BLANK
(a) On acceptance of tender, the name of authorized representative (s) of the contractors who
would be responsible for taking instructions from Engineer-in-Charge or its authorized
representative shall be intimated by the contractor within 7 days of issue of Accepting
letters.
(a) The tenderer shall quote his rates in figures only in the provided column in schedule
‘A’ given in Excel sheet only. In case the tenderer has to revise / modify the rates quoted in
the schedule ‘A’ before tender submission end date as mentioned in critical data sheet,
resubmission bid shall be allowed.
(b) In case the tenderer has to revise/ modify /withdraw his quoted rates / offer after it is
submitted, he may do so on his on line before the latest date & time fixed for submission of
tenders. Any revision / modification in offer / withdrawal of offer in the form of an open shall
not be taken into account, while considering in his originally offer.
(c) The tenderers shall not be permitted to revise / modify / withdraw priced bid
unopened after closure of the time fixed for receipt of tender.
ANNEXURE-I
To be signed by the bidder and same signatory competent/authorized to sign
the relevant Contract on behalf of BRO
INTEGRITY AGREEMENT
BETWEEN
AND WHEREAS the Principal)/ Owner values full compliance with all relevant laws
of the land, rules, regulations, Economic use of resources and of
fairness/transparency in its relation with its Bidder(s) and Contractor(s)
AND WHEREAS to meet the purpose aforesaid both the parties have agreed to
enter into this integrity agreement (hereinafter referred to as “Integrity Pact” or
“Pact”), the terms and conditions of which shall also be read as integral part and
parcel of the tender/bid documents and contract between the parties.
NOW, THEREFORE, in consideration of mutual covenants contained in this
Pact, the parties hereby agree as follows and this Pact witnesses as under: -
1. Commitment of the Principal/Owner
(a) The Principal/Owner commits itself to take all measures necessary to prevent
corruption and to observe the following principles.
(i) No employee of the Principal/Owner personally or through any of his/her family
members, will in connection with the Tender, or the execution of the Contract, demand,
take a promise for or accept, for self of third person, any material or immaterial benefit
which the person is not legally entitled to.
(ii) The Principal/Owner will during the Tender process, treat all Bidders with
equity and reason The Principal/Owner will, in particular, before and during the
Tender process, provide to all Bidder(s)the same information and will not provide to
any Bidder(s) confidential/additional Information through which the Bidders could
obtain an advantage in relation to the Tender process or the Contract execution
(iii) The Principal/Owner shall endeavor to exclude from the Tender process
any person, whose conduct in the past has been of biased nature.
(i) The Bidder(s)/Contractor(s) will not directly or through any other person or
firm, offer promise or give to any of the Principal/Owner’s employees involved in
the Tender process or execution of the Contract or to any third person any material
or other benefit which he/she is not legally entitled to in order to obtain in exchange
any advantage of any kind whatsoever during the Tender process or during the
execution of the Contract.
(ii) The Bidders(s)/Contractor(s) will not enter with other Bidder(s) into any
undisclosed agreement or understanding, whether formal or informal. This applies
in particular to prices, specifications, certifications, subsidiary contracts, submission
or non-submission of bids or any other actions to restrict competitiveness or to
cartelize in the bidding process.
(iii) The Bidder(s)/Contractors(s) will not commit any offence under the
relevant IPC/PC Act. Further the Bidder(s) /Contractor(s) will not use improperly,
(for the purpose of competition or personal gain) or pass on to other, any
information or documents provided by the Principal/Owner as part of the business
relationship, regarding plans, technical proposals and business details, including
information contained or transmitted electronically.
(d) The Bidder(s)/Contractor(s) will not, directly or through any other person of firm
indulge in fraudulent practice means a willful misrepresentation or omission of facts
or submission of fake/forged documents in order to induce public official to act in
reliance thereof, with the purpose of obtaining unjust advantage by or causing
damage to justified interest of other and/ or to influence the procurement process to
the detriment of the Government interests.
(e) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm
use Coercive Practice (means the act of obtaining something, compelling an action
or influencing a decision through intimidation, that or the use of force directly or
indirectly, where potential or actual injury may befall upon a person his/her
reputation or property to influence their participation in the tendering process)
3 Consequences of Breach
(a) The bidder declares that no previous transgressions occurred in the last 5 years
with any other company in any country confirming to the anticorruption approach or
with central Government or state government or any other central/state public
sector enterprises in India that could justify his exclusion from the tender process.
(b) If the Bidder makes incorrect statement on this subject, he can be disqualified
from the tender process or action can be taken for banning of business
dealing/holiday listing of the Bidder(s)/Contractor(s) as deemed fit by the
Principal/Owner.
(b) The Principal/Owner will enter into pact on identical terms as this one with all
bidders and contractors.
(c) The Principal/Owner will disqualify bidders, who do not submit, the any signed
pact between the Principal/Owner and the bidder, along with the tender or violate
its provisions at any stage of the Tender process from the tender process.
This pact begins when both the parties have legally signed it, it expires for
the contractor/vendor after the final payment under the contract had been
made or till the continuation of defect liability period, whichever is more and
for all other bidders, till the contract has been awarded. If any claim is
made/lodged during the time, the same shall be binding and continue to be
valid despite the lapse of the pacts as specified above, unless it is
discharged/determined by the competent authority, BRO.
7. Other provisions
(a) This pact is subject to Indian Law, place of performance and jurisdiction is the
Headquarters of the formation of the Principal/Owner, who has floated the tender.
(b) Changes and supplements need to be made in writing. Side agreements have
not been made. If the contractor is a partnership or a consortium, this pact must be
signed by all the partners or by one or more partner holding power of attorney
signed by all partners and consortium members. In case of a company, the pact
must be signed by a representative duly authorized by board resolution
(c) Should one or several provisions of this pact turn out to be invalid; the
remainder of the pact remains valid. In this case, the parties will strive to come to
an agreement to their original intensions.
(d) It is agreed terms and condition that any dispute of difference arising between
the parties with regard to the terms of this Integrity Agreement / Pact, any action
taken by the Owner/Principal in accordance with this Integrity Agreement/Pact or
interpretation thereof shall not be subject to arbitration.
All rights and remedies of the parties hereto shall be in addition to all the other
legal rights and remedies belonging to such parties under the contract and/or law
and the same shall be deemed to be cumulative and not alternative to such legal
rights and remedies aforesaid. For the sake of brevity, both the parties agree that
this Integrity pact will have precedence over the Tender/contact documents with
regard any of the provisions covered under this Integrity Pact.
9. Independent Monitors
(a) That the MoD has appointed following Independent Monitors for this Pact
(b) The task of the monitor is to review independently and objectively, any
complaint received with regard to violation of Integrity pact and offer comments or
carry out enquiry as deemed fit.
(c) That the monitor is not subject to any instructions by the representatives of the
parties and would perform his functions neutrally and independently.
(d) That Bidder(s)/Contractor(s) accepts that if the monitor needs to access any
records then the monitor shall have the right to access without restriction to all
project documentation of the Principal/Owner including that provided by the
bidder/contractor. The Bidder/Contractor will also grant the Monitor, upon his
request and demonstration of a valid interest, unrestricted and unconditional
access to his project documentation including minutes of meeting. The same is
applicable to Sub-Contractors and Associates. The monitor is under obligation to
treat the information and documents of the Principal/Owner and
bidder/contractor/sub-contractors/Associates with confidentiality.
That if the monitor has reported to the Principal/Owner a substantiated suspicion of
an offence under relevant Anti-corruption Laws of India and the Principal/Owner
has not, within reasonable time, taken visible action to proceed against such
offence or reported it to the Vigilance Department, the Monitor may also transmit
this information directly to the Central Vigilance commissioner, Govt of India.
Name of Nodal Officer of BRO: Shri S K Deota,IDCMS
Director(Contracts)
E-mail ID santoshkd22868-cgo.nic.in
Mobile No 9409307524
WITNESSES
1….
address) 2…..
Dated:
INTEGRITY PACT
To,
M/s
_
_
Yours faithfully
To,
I/We agree that the Notice Inviting Tender (NIT) is an invitation to offer
made on the condition that I/We will sign the enclosed Integrity Agreement,
which is an integral part of tender documents, falling which, I/We will stand
disqualified from the tendering process. I/We acknowledge that THE
MAKINGOFTHEBIDSHALLBEREGARDEDASANUNCONDITIONALAND
ABSOLUTE ACCEPTANCE of this condition of the NIT
I/We acknowledge that in the event of my/our failure to sign and accept the
Integrity Agreement, while submitting the tender/bid, BRO shall have
unqualified absolute and unfettered right to disqualify the tender/bidder and
reject the tender/bid in accordance with terms and condition of the
tender/bid.
Yours faithfully
1. Online bids are invited on single stage two bid system for “SLOPE STABILIZATION AND
AVALANCHE PROTECTION AT KM 14.700 ON APPROACH ROAD TO SOUTH PORTAL
(ARSP) UNDER PROJECT ROHTANG TUNNEL
The title of above heading on CPPP site https://eprocure.gov.in/eprocure/appis “SLOPE
STABILIZATION AND AVALANCHE PROTECTION AT KM 14.700 ON APPROACH ROAD TO
SOUTH PORTAL (ARSP) UNDER PROJECT ROHTANG TUNNEL”
2. Tender documents may be downloaded from BRO websitewww.bro.gov.in (for reference
only) and CPPP sitehttps://eprocure.gov.in/eprocure/app as per the schedule as given in CRITICAL
DATE SHEET as under.
4. The work is estimated to cost Rs 8750.00 Lacs (Rupees Eighty Seven Crores Fifty Lakhs
only) approximately or as subsequently amended in tender documents or uploaded in BRO website
www.bro.gov.in and CPPP website https://eprocure.gov.in/eprocure/app This estimate, however, is
not a guarantee and is merely given as a rough guide and if works cost more or less, the tenderer
shall have no claim on that account of what so ever nature.
5. The tender shall be based on specifications and General conditions of contracts IAFW - 2249
(GCC) and item rate Contract form based on IAFW-1779A/lump sum contract based on IAFW-2159
with Schedule-A (listed of works) to be priced by the tenderers.
6. Not more than one tender shall be submitted by one contactor or contractors having
business relationship. Under no circumstance will father and his son(s) or other close relations who
have business relationship with one another (i.e. when one or more partner(s)/director(s) are
common) be allowed to tender for the same contract as separate competitors. A breach of this
condition will render the tenders of both parties liable to rejection.
8. The Chief Engineer, Project Rohtang Tunnel, C/O 56 APO will be the Accepting Officer,
here in after, referred to as such for the purpose of this contract.
9. Intending tenderers are advised to visit again BRO website www.bro.gov.in (for reference
only) and CPPP website https://eprocure.gov.in/eprocure/app 03 (three) days prior to date of
submission of tender for any corrigendum / addendum/amendment.
10. Earnest money is not required to be attached with tender by the valid enlisted contractors
with BRO who have submitted standing security deposit and MSME registered firms as per Rule
170 (i) of GFR 2017 but it is required from other contractors and to be attached (Scanned copy) with
Technical Bid for Rs. 47,00,000/-(Rupees Forty Seven Lakhs Only) in the shape of Call Deposit
Receipt/Term Deposit Receipt/Special Term Deposit Receipt in favour of Chief Engineer Project
Rohtang Tunnel, C/O 56 APO obtained from any Nationalized/ Scheduled Bank and having
maturity/validity period 90 days more than validity period of his offer payable at SBI, Manali Distt.
Kullu, (Himachal Pradesh).
11. Successful Bidder (L-1) shall deliver to Accepting Officer a Performance Security for an
amount of 5% of contract sum in the shape of Bank Guarantee or FDR within 28 days of issue of
LoA.
12. Copies of drawings (if applicable) and other documents pertaining to the work (signed for the
purpose of identification by the Accepting Officer or his accredited representative) will be opened for
inspection at the following locations: -
13. Tenderers are advised to visit the work site by making prior appointment with Chief Engineer
(P) Rohtang Tunnel (GREF), C/O 56 APO. Any query related to the tender condition may be
clarified at following telephone No. 9436223000, SW Rohtang Tunnel. All the work site are located
along the Approach Road to South Portal of Rohtang Tunnel (Now Atal Tunnel), in the State of
Himachal Pradesh.
14. A tenderer shall be deemed to have full knowledge of all relevant documents, site etc. whether
he had inspected them or not.
15. Any qualification documents/ tender which stipulates any alternative to any of the conditions
laid down or which proposes any other conditions of any description whatsoever is liable to be
rejected.
16. The Accepting Officer reserves his right to accept a tender submitted by a Public Undertaking,
giving a purchase preference over other tender(s) which may be lower, as are admissible under the
Govt policy. No claim for any compensation or otherwise shall be admissible from such tenderers
whose tenders may be rejected on account of the said policy.
17. The submission of a tender by a tenderer implies that he had read this notice and conditions of
contract and has made himself aware of the scope and specifications of the work to be done and of
the conditions and rates at which stores, tools and plants etc. will be issued to him, local conditions
and other factors bearing on the execution of the work.
18. The Pre-Contract Integrity Pact (Applicable for tender with estimated cost of Rs. 5.00 Crore
and above for all works contracts and in tender for procurement of services, stores equipments &
plants with estimated cost of Rs. 1.00 Crore and above) has been signed by Accepting Officer or by
the Officer specifically designated by him and scanned copy uploaded as part of NIT along with
tender documents. Scanned copy of Integrity Pact duly signed on each pages by the bidder(s) shall
be uploaded as part of technical bid (Cover-I) and original Integrity Pact duly signed on each pages
shall be forwarded by post along with EMD and DD towards cost of tender.
19. The scanned copy of original instruments in respect of earnest money, Integrity Pact duly
signed on each page by the bidder(s), and under taking regarding acceptance of tender conditions,
Enlistment letter if firm is enlisted in BRO, EPFO, Registration letter, GST Registration, eligibility
documents, Similar work experience, material technical performance requirements and experience
of key construction activity and any other documents required to be submitted with respect to
various conditions mentioned in the tender documents must be uploaded along with the technical
bid. The Hard copies of all the documents should reach the tender Inviting Authority in the sealed
envelope within 05 days of bid submission end date.
20. BLANK.
21. BLANK.
22. In case of applications/bids from un-enlisted contractors if required as per tender conditions,
where scanned copies of requisite DD/ Bankers cheque towards cost of tender has been uploaded
but physical copies are not received by the stipulated date, finance bids will not be opened. Name
of such contractors along with complete address shall be circulated for not opening of their bids for
a period of six months commencing from the date of opening of finance bid.
24. In case of rejection of technical bid , contractor may appeal to next higher Engineering
Authority i.eHQADGBR on email bro-adgnw@nic.in against rejection whose decision shall be final
and binding , However , contractor/ bidder shall not be entitled for any compensation whatsoever
on account of rejection of technical bid.
25. For any further particulars, you may refer BRO website http:/www.bro.gov.in and CPPP website
https://eprocure.gov.in/eprocure/app.
26. BRO appointed Independent Monitors for Integrity Pact in BRO contracts in consultation with
Central Vigilance Commission. Name and Address of the monitors as amended from time to time,
can be referred to on the MoD website at www.mod.nic.in. Following are the independent monitors
for thiswork:-
28. Important- Above particulars may change due to administrative or any other reason and
shall be available in BRO web site www.bro.gov.in and CPPP website
https://eprocure.gov.in/eprocure/app. Therefore bidders/ contractors are requested to visit
BRO web site www.bro.gov.in and CPPP website https://eprocure.gov.in/eprocure/app
frequently and at least once again 03 (three) days prior to bid submission date as per critical
date sheet, for any changes in above particulars.
EE (Civ.)
SW
For Accepting Officer
Headquarters
Chief Engineer
Project Rohtang Tunnel
C/O 56 APO
PIN-931720
3. Wherever the phrases Commander Works Engineer (CWE) and Garrison Engineer (GE)
have been used in the General Conditions of Contract (IAFW -2249) the same are considered as
Task Force Commander (TFC) and OC Contract respectively as applicable in Border Roads
Organization.
* AS APPLICABLE
1. DEFINITIONS ETC: (a) The “Contract” means the documents forming the tender and
acceptance thereof, together with the documents referred to therein including these conditions,
Schedules, ‘A’, ‘B’. ‘C’, ‘D’ and/or General summary attached to the form of tender, their B.R.O.
schedule, the specifications and the drawings, and all these documents, as applicable-taken
together shall be deemed to form one contract and shall be complementary to one another.
(b) The “Tender documents” means the form of tender, the applicable Schedules ‘A’,
‘B’, ‘C’, ‘D’ and/or General summary, these Conditions, and the specifications and/or
Drawings as loaned to Contractors for the purpose of preparing their tenders.
(c) The “Works” means the works described in the tender documents, or in the case of
Term Contracts, in individual Works Orders and/or accompanying Drawings and
Specifications as may be issued from time to time to the Contractor by the OC CONTRACT
or Engineer in Charge within the powers conferred upon them, including all modified extra or
additional works and obligations to be carried out either on the site or at any factory or
workshop or other place for subsequent incorporation, as required for the performance of
the Contract.
(d) The “Site” means the lands and/or other places on, in into or through which work is
to be executed under the Contract or any adjacent land, path or street which may be allotted
or used for the purpose of carrying out the Contract.
(e) The “Contractor” means the individual or firm or company, whether incorporated or
not, undertaking the works and shall include the legal personal representatives of such
individual or the persons composing such firm or company, or the successors of such
individual or firm or company and the permitted assigns of such individual or firm or
company.
(f) “Government” means the President of India, his successors in office and assigns
and the ”Accepting Officer” means the duly authorized officer who signs the contract on
behalf of the President.
Chief Engineer and Additional Chief Engineer (if specially authorized by the Chief Engineer)
shall exercise the same powers in respect of Contracts concluded by either of them on
behalf of President and subject as otherwise provided in this contract, all notices to be given
and all actions to be taken on behalf of Government in respect of such contracts may be
given or the Additional Chief Engineer.
(g) The letters “Commander Contract” mean “Task Force Commander” who, in the
case of Measurement and Lump Sum Contracts directs the contract and the letters “OC
CONTRACT” mean OC, RCC or BCC who administers and in the case of Term Contracts
directs the Contract.
(h) The “Engineer-in-Charge” means the Assistant Executive Engineer or the Assistant
Engineer (A.E) or the Superintendent Grade-I appointed by the OC CONTRACT to
supervise the Works or part of the Works.
(i) “Approved” and “Directed” means the approval or direction of the Director
CONTRACT or OC CONTRACT or person deputed by him for the particular purpose.
(j) “M.D.” means the “Government of India (Ministry of Defence)”.
(k) “M.E.S” means the “Military Engineer Services”.
(l) “I.S.” means ‘Indian Standards’ as issued by the Bureau of Indian Standards.
(i) In the case of Lump Sum Contracts (I.A.F.W.-2159) the sum for which the
tender is accepted.
(iii) In the case of Item Rate Contracts for Works by Measurement (I.A.F.W.-
1779-A) the total cost of the work arrived at after extension of the quantities shown in
Schedule ‘A’ by the item rates quoted by the tender for the various items.
(o) The “Final Sum” means the amount payable under the contract by Government to
the Contractor, for the full and entire execution and completion of the Works, or in the case
of Term Contracts, of individual Works Orders.
(p) “Accepted Risks” mean the risks on the Site accepted by the Accepting Officer or
the COMMANDER CONTRACT in case of Contracts accepted by OC CONTRACTs., of
riots (otherwise than among Contractor’s employees), war, invasion, act of foreign enemies,
hostilities, civil war, rebellion, revolution, insurrection, military or usurped power, damage
from air craft and acts of God such as earthquake, lightening, unprecedented floods and
tornado.
(q) The “Date for Completion” is the date or dates for completion of the whole or any
part of the works, set out or ascertained in accordance with the individual Works Orders or
the tender documents, or any subsequent amendment thereto as provided in the condition 9
and 11 hereinafter.
(r) A “Week” means seven days without regard to the number of hours
worked or not worked in any day in that week.
(s) A “Day” means a day of 24 hours irrespective of the number of hours
worked or not worked or not worked in that day.
(t) A “Working Day” means any day other than that prescribed by the
Negotiable Instruments Acts as being a holiday and consists of the number of
hours of labour as commonly recognized by good employers in the trade in
the district where the work is carried out.
(u) “Emergency Works” mean any urgent measures which, in the
opinion of the Engineer-in-Charge, become necessary during the progress of
the works to obviate any risk of accident or failure or which becomes
necessary during the progress of the Works to obviate any risk of accident or
which becomes necessary for security, or rectifications to essential services
like water supply and electrification during the maintenance period of the
contract.
(v) “Prime Cost” and “Prime Cost Sums” and the letters “P.C.” or a
combination of the same mean the amount actually paid by the Contractor for
any article, commodity or special work and include all proper charges for
packing, carriage and delivery to the site, after deduction of all trade
discounts, rebates and allowances and all discounts obtainable for cash in so
far as such discounts exceed 2.5 percent.
(y) “Day work” means items of labour and/or materials which, in the
opinion of the Engineer-in-Charge, are not capable of being evaluated by the
accepted methods of measurement or assessment.
(z) Blank.
2ASecrecy:-The Contractor shall take all steps necessary to ensure that all
persons employed on any work in connection with the Contract have notice
that the Indian Official Secrets Act, 1923 (XIX of 1923) applies to them and will
continue so to apply even after the execution of such works under the
Contract.
All documents, copies thereof and extracts there from furnished to the Contractor
shall be returned to the OC CONTRACT on the completion of the Works or the earlier
determination of the Contract.
The Contractor shall be deemed to have satisfied himself as to the nature of the Site,
local facilities of access and all matters affecting the execution and completion of the
Works. No extra charges consequent on misunderstanding or otherwise will be
allowed.
4A. Works to be carried out (Applicable only to Term Contracts) - The Contracts
shall except as provided under Schedule ‘B’ and Condition 10 thereof, include all
labour, materials tools, plant, equipment and transport which may be required in
preparation for, and for and in the full and entire execution and completion of any new
work or works, reconstruction or repairs within the Contract Area, which Contractor may
be called upon to carry out and which can be priced under the B.R.O. Schedule and for
which the total estimate at Contract Rates of any single work, job or service as defined
below shall not exceed Rs. 60,000 subject to the following reservations, viz:-
(a) Periodical Services, viz, painting, lime or colour washing any tint and
distempering (except in connection with or arising out of the works mentioned
above, and, in addition any order, placed during he period of the Contract, the
gross total value of which orders, does not exceed Rs. 5,000) shall be excluded
from theContract.
(b) The Construction of field defences and shelters within the Contract Area
on and during mobilization may be excluded from the contract.
(c) All roads, paths, parade grounds, runways, taxi tracks, aprons, landing
grounds, (except any order for periodical painting of lines circles or other markings
on runways, taxi tracks, aprons and landing grounds placed during the period of
the contract, the gross value of which does not exceed Rs. 2,500) tree planting,
gardening and the renewal of mud floors shall be excluded from the contract.
(d) All electrical and water supply work and steam or hot-water installations,
estimated to cost over Rs. 10,000 shall be excluded from the Contract and at the
discretion of the OC CONTRACT any such work estimated to cost Rs. 10,000 or
under may also be excluded.
(e) The OC CONTRACT may employ on work otherwise included within the scope
of Contract:
(i) any number of serving soldiers, the regular civilian staff of the B.R.O., store
men, and transport (the property of Government, or hired locally);
(ii) in addition, a limited number of civilian work people. Except in the event of the
Contractor’s default, the number so employed shall not exceed the average specified in
the tender documents. (Those employed on work reserved in the sub-clauses (a) to (e)
above not included)
(f) An item of work which is part of a Major Work costing over Rs. 60,000
shall be excluded from the Contract.
The estimates referred to above shall be based on the Contract Rates and shall include
contingencies, but exclude the surplus B.R.O stores referred to in Condition 10 hereof
and any stores to be obtained under special contract; the shall be the sole judge as to
what constitutes a single work, job or service or to treat the Contract Area as a whole
for the purpose of grouping work as may be convenient, and his decision in these
matters shall be final and binding.
The Contractor will be deemed to have satisfied himself as to the nature of the Works
likely to be ordered upon him, local facilities for the supply of labour and materials
within the Contract Area and of access to the Site or Sites and all other matters
affecting the execution and completion of the Works. No extra charges consequent on
misunderstanding or otherwise will be allowed.
5. Prime Cost Sums: -All prime cost sums shall be reserved for the supply of
materials or the execution of work by persons to be nominated by the Accepting Officer
or selected in such a way as he may direct.
The full amount of the prime cost sums inserted in the tender documents and the value
of the percentage addition thereto quoted by the Contractor to cover all overheads and
profit will be deducted from the Contract Sum. The Contractor shall be paid the actual
prime cost (as defined), plus the percentage addition quoted by him to cover all
overheads and profit. He shall produce to the OC CONTRACT such quotations,
invoices and receipted bills as may be necessary to show the actual details of the sums
paid by him.
The OC CONTRACT shall also be at liberty to order and pay for all or any portion of
such items direct and issue them to the Contractor for fixing only, in which case the
Contractor shall not be paid anything to cover all overheads and profit in respect of
such items.
He shall be paid for fixing, where applicable, in accordance with the conditions of
Contract; the payment for fixing shall cover unloading, getting in, unpacking and return
of empties and other incidental expenses.
6. Provisional Items: - The full amount of provisional lump sums and the value
annexed to each provisional item inserted in the tender documents shall be deducted
from the Contract Sum and the value of work ordered and executed there under shall
be ascertained by measurement or valuation as for deviations. No work under these
items is to be begun without instructions in writing from the Engineer-in-Charge.
The extent of quantities or items described as “Provisional” shall not be varied beyond
the limits laid down in Condition 7.
In the case of discrepancy between Schedule ‘A’, the Bills of Quantities, the
Specifications and/or the Drawings the following order of precedence shall be
observed: -
If there are varying or conflicting provisions made in any one document forming part of
the Contract the Accepting Officer shall be the sole deciding authority with regard to the
intention of the document and his decision in this respect shall be final and binding.
Any error in description, quantity or rate in Schedule ‘A’ and Bills of Quantities, or any
omission there from shall not vitiate the Contract or release the Contractor from the
execution of the Whole or any part of the Works comprised therein according to the
Drawings and Specifications or from any of his obligations under the Contract. Any
error in quantity, rate or amount in Schedule ‘A’/Bills of quantities and general summary
shall be adjusted in accordance with the following rules:
(C) Lump Sum Contracts based on Schedule ‘A’ with supporting Bills of
Quantities
- There shall be no rectification of any errors, omissions or wrong estimates
in the prices inserted by the Contractor in the Bills of Quantities.
Provided further, if the cumulative effect of all the errors in quantities (not
shown as provisional) or any omissions of items, exceeds the limits stipulated
hereinbefore, rectification of the errors and increase/decrease of the Contract Sum
shall be restricted only to the extent beyond the said limits. The Contract Sum so
altered shall, for all purposes of this ‘Contract’ be substituted for the sum originally
accepted as if the contract had been accepted at the altered price instead of the
original price and such alteration shall not be considered as a deviation.
No work that radically changes the original nature and scope of the Contract
shall be ordered as a Deviation and in the event of disagreement between the
Contractor and the Accepting Officer, the decision, of the next higher authority (or of
the Chief Engineer in Case of contracts accepted by him) shall be final and binding
on the Contractor.
(a) The Deviation Limit referred to above is the net effect (algebraically
sum) of all additions and deductions ordered.
(d) The value of additions of items of any individual trade not already
included in the Contract shall not exceed 10% of the Deviation Limit.
Note: -Individual trade means the trade sections into which a Bill of
Quantities or Schedule ‘A’ has been divided or, in the absence of any such
division, the individual sections of
B.R.O. Standard Schedule of Rates such as Excavation and Earthwork,
Concrete, Wood Works and Joinery, etc.
All additions and deductions will be priced as per Condition 62 hereof and
added to or deduced from the Contract Sum. Whenever the Accepting Officer intends
to exercise such right his intention shall be communicated to the contractor by the
OC CONTRACT whose order in writing shall specify the deviations which are to be
made, the lump sum assessment or the proposed basis of payment, the change if
any, in the date or completion of the relevant phase and/or the entire contract. Any
objection by the Contractor to any matter concerning the Deviation Order, shall be
notified by him in writing to the OC CONTRACT within fifteen days from the date of
receipt of such order, but under no circumstances shall be progress of the Works be
stopped (unless so ordered by the OC CONTRACT) owing the differences or
controversy that may arise from such objection. In default of such notification the
Contractor will be deemed to have accepted the order and
the conditions stated therein without in any way affecting the right of the parties to
rectify any mistake on the basis of payment only to the extent it differs from condition
62. in the event of the Contractor failing to agree with the OC CONTRACT regarding
the proposed alteration of time the objection shall be referred to the Accepting Officer
or, in the case of Contracts (other than Term Contracts) accepted by the OC
CONTRACT to the Chief Engineer, whose decision shall be final and binding.
9. Suspension of Works-
The Contractor shall, during such suspension, properly protect and secure
the Works to the extent necessary and carry out the instructions given in that behalf
by the OC Contract.
(b) If the suspension is ordered for reasons (ii) and (iii) in Sub-para(a)above.
(i) the contractor shall be entitled to an extension of time equal to
the period of every such suspension plus 25% for completion of the
item or group of items of work for which a separate period of
completion is specified in the Contract and of which the suspended
work forms a part, and
10. Materials:-
(a) Materials to be provided by the Contractor-
The Contractor shall, at his own cost and expense, provide all materials
required for the Works other than those listed in Schedule ‘B’ which are to be
supplied by Government.
The Contractor shall at his own cost and expense and without delay supply to
the Engineer- in-Charge samples of materials proposed to be used in the Works. The
Engineer-in-Charge shall within seven days of supply of samples or within such
further period as he may require and intimate to the Contractor in writing inform the
Contractor whether samples are approved by him or not. If samples are not approved
the Contractor shall forthwith arrange to supply to the Engineer-in- Charge for his
approval fresh samples complying with the specification laid down in the contract.
The Engineer-in-Charge shall have full powers to require removal of any or all
of the materials brought to Site by the Contractor which are not new and in
accordance with the Contract specifications or do not conform in character or quality
to samples approved by him. In case of default on the part of the Contractor in
removing rejected materials the Engineer-in-Charge shall be at liberty to have them
removed by other means at the Contractor’s expense and risk. The Engineer-in-
Charge shall have full powers to require other proper materials to be substituted for
rejected materials and in the event of the Contractor refusing to comply, he may
cause the same to be supplied by other means. All costs/charges and expenses
which may attend upon such substitution shall be borne by the Contractor.
Contractor shall immediately be notified thereof. Provided that such indemnity shall
not apply when such infringement has taken place in complying with the specific
directions issued by Government but the Contractor shall pay any royalties or other
charges payable in respect of any such use the amount so paid being reimbursed to
the Contractor only if the use was the result of any drawing and/or specifications
issued after submission of the tender.
(i) the Contractor will be paid for “fixing only” in respect of materials
savaged from and refixed in the same building or another building situated within a
radius of 200 metres whether such
Government officials concerned with the Contract shall be entitled at any time
to inspect and examine any materials intended to be used in or on the Works, either
on the Site or at factory or workshop or other place(s) where such materials are
assembled, fabricated or manufactured or at any place(s) where these are laying or
from which these are being obtained and the contractor shall give such facilities as
may be required for such inspection and examination.
All materials brought to the Site shall become and remain the property of
Government and shall not be removed off the Site without the prior written approval
of the Engineer-in-Charge. But whenever the Works are finally completed and
advance, if any, in respect of any such materials is fully recovered, the Contractor
shall at his own expense forthwith remove from the Site all surplus materials
originally supplied by him and upon such removal the same shall retest in and
become the property of the Contractor.
then, in any such case the Officer hereinafter mentioned may make
fair and reasonable extension in the completion dates of individual items or groups of
items of Works for which separate periods of completion are mentioned in the
Contract documents or Works Order, as applicable.
Upon the happening of any such event causing delay, the Contractor shall
immediately, but not later than 30 days of the happening of the event, give notice
thereof in writing to the OC CONTRACT but shall nevertheless use constantly his
best endeavor to prevent or make good the delay and shall do all that may
reasonable be required to the satisfaction of OC CONTRACT to proceed with the
works. Extension of time shall be granted as under: -
(a) Byreasonofnon-availabilityorbreakdownofGovt.ToolsandPlantlistedinSchedule‘C’.,
then, in any such event, notwithstanding the provisions hereinbefore contained, the
Accepting Officer may in his discretion grant such extension of time as may appeal
reasonable to him and the same shall be communicated to the Contractor by the OC
CONTRACT in writing. The decision so communicated shall be final and binding and
the Contractor shall be bound to complete the works within such extended time.
12. Blank.
13. Blank.
14. Royalties - No royalty will be recovered for materials, which the Contractor
may be allowed to remove
15. Plant and Equipment- Subject to the provision made hereinafter, the
Contractor shall at his own cost and expense, supply all tools, plants and
equipment’s (hereinafter referred to as T&P) required for the execution of work. In
case, the Contractor so requires, some or all items of T&P listed in Schedule ‘C’ will
be given to him on hire by Government at the rates shown in the Schedule provided
that he has indicated his requirement while submitting his tender. The Contractor
shall, however, have no option but to hire from the Govt. particular items of T&P
listed in Schedule ‘C’ for which specific provision has been made in tender document
to indicate that hiring by contractor is compulsory. In respect of, the other items of
Schedule ‘C’ (hiring of which has not been indicated as compulsory), such of those
item(s) as has/have not been indicated (while submitting tender) to be hired by
contractor shall be automatically deemed to have been deleted from Schedule ‘C’.
Soon after acceptance, of tender, the Contractor shall agree, in writing with the OC
CONTRACT on a phased programme of his requirement with regard to the issue of
such of the Govt. T&P which are to be hired by him from the Govt., and in respect
whereof the contractor shall give the Engineer-in- Charge a notice in writing at least a
week in advance of the date of his requirement as per the aforesaid phased
programme. Government T&P hired to the Contractor shall be conveyed by him at
his expense from the place of issue to the site and back.
The period T&P remains in Contractor’s charge shall be termed the “HIRE
PERIOD” and would reckon from the commencement of the day of issue up to the
end of the day of return irrespective of the actual hours of issue and return. The Hire
Period for purposes of this contract shall consist of “Working Days” and “Off-
days”. For purposes of levy of the Hire Charges, the whole of the Hire Period shall
be deemed as consisting of Working Days except for the Off-days, viz., Sundays,
Maintenance Days, and other authorized holidays closed for work (as per prior
written order of the OCCONTRACT).
For purposes of this Condition, the day will be deemed to start from 0800 hours in the
morning (or any other hour-hereinafter referred to as ‘D’ hour-fixed by the OC
CONTRACT in writing at the commencement of the Hire Period) up to the
corresponding hour next day.
The Contractor shall pay to the Government Hire Charges and Standby
Charges as per rates shown in Schedule ‘C’ for the Working days and off-days
respectively.
The Hire Charges cover Depreciation, Interest, Maintenance, Running
Expenses and expenses for “on cost” (with crew as listed in Schedule ‘C’ and fuel
and lubricants).
During the Hire period if the T.&P. is rendered unworkable either due
to mechanical breakdown or other minor repairs provided always that they are not, in
the absolute discretion of the OC CONTRACT attributable to the Contractor’s (or his
workmen’s) neglect, the period the T.& P. remained inoperative will be termed the
Breakdown Period and the Contractor will be charged for half a working day if any
item of Government T&P has stopped working on account of breakdown before it has
worked for four hours in a day. If the item of Government T. & P. has stopped
working after it has worked for more than four hours but less than eight hours, the
Contractor will be charged for a full working day. Off-days immediately preceding or
succeeding the Breakdown period will not count towards the Breakdown Period but
only be treated as Off-days and be charged as Standby Charges. The Contractor will
also be exempted from levy of any charges for the number of days he is called upon
in writing by the OC CONTRACT to suspend the execution of the Works, provided
the T. & P. in question has in fact remained idle with the Contractor because of the
suspension.
The Contractor shall be wholly responsible for the care and custody of T. & P
during the whole of the Hire Period and any damage to it (except accepted risks,
provided always the Contractor has taken precaution necessary to protect it from
such risk) which in the absolute discretion of the OC CONTRACT is attributable to
neglect on the part of the Contractor, his agent, or his workmen, shall be made good
at contractor’s cost, charges and expense to the entire satisfaction of the OC
CONTRACT
In the event of the Contractor not requiring any of the T. & P. at any time after
commencement of the Hire period he may return it to the OC CONTRACT
immediately after a two clear days’ prior notice, or at any time without notice if he
agrees to pay the Standby Charges for two additional days without in any way
affecting the rights of the OC CONTRACT to use the T. & P. during this period as he
likes including Hiring out to a third party. The Hire Charges during the notice period
will be charged for as “Working Days” and “Off-days” as they actually occur.
The Working Day for levy of the Hire Charges shall reckon as under: -
(a) The first eight hours (excluding a break of one hour) commencing 1 Working day
from the ‘D’ hour.
(b) Any period exceeding eight hours (excluding a break of 1-1/4 1-1/4 Working days
hours) upto and including 10 hours from the ‘D’ hours.
(c) Any period exceeding 10 hours (excluding a break 1-1/2 hours) 1-1/2 Working days
upto and including 12 hours from the ‘D’ hour).
(d) Any period exceeding 12 hours (excluding a break of 2 hours) upto 2 Working days
and including 16 hours from the ‘D’ hours)
The Hire rates for Government transport shall be inclusive of all running
costs, driver, petrol, oil and lubricants.
The Contractor shall be responsible for the loading and unloading of vehicles
and shall comply with such restrictions regarding weight carrying capacities, nature of
materials to be transported and routes to be followed as may be notified to him by the
Engineer-in-Charge from time to time during the period of hire, as well as to observe
reasonable precautions at all times to prevent damage to and undue wear and tear of
the vehicles.
Government transport shall remain under the control of Government while on
hire to the Contractor but Government accept no liability for any loss or damage to
goods conveyed therein, arising out of or in any way connected with the operation of
the said vehicles. The Contractor shall indemnify Government against any loss or
damage to the person or property of Government, or any agent, servant, or employee
of Government, or to any third party due to any neglect or default of the Contractor,
his agents, servants, or work-people, connected with the use by him of the transport.
17. Assignment or Transfer of Contract - The Contractor shall not without the
prior written approval of the Accepting Officer assign or transfer the Contract, or any
part thereof or any share, or interest therein. No sum of money to become payable
under the Contract shall be payable to any person other than the Contractor unless
the prior written approval of the Accepting Officer to the assignment or transfer of
such money is given.
18. Sub-contracts - The Contractor shall not sub-let any portion of the Contract
without the prior written approval of the Accepting Officer. The Accepting Officer may
invite offers for performance by sub-contractors of any work in satisfaction of prime
cost sumsincluded in the tender documents. In the exercise of this option, offers will
be made returnable to the Accepting Officer who shall select the firm to do the Work
and inform the Contractor, who will be required to conclude a contract with the
nominated sub-contractor for the execution of the work as specified by the Accepting
Officer to the sub-contractor. The Accepting Officer shall not nominate any sub-
contractor against whom the contractor shall make reasonable objection.
In case of a Contractor who has executed the standing Security Bond but
where the tendered cost of the work exceeds the financial limit of the Contractor, and
the Accepting Officer decides to accept his tender, the Contractor shall lodge with the
Accepting Officer concerned additional Security Deposit as notified by the Accepting
Officer within thirty days of the receipt by him of notification of acceptance of his
tender, failing which this sum will be recovered from the first RAR payment or from
the first final Bill. In the case of Term (Running) Contracts, if the amount from the first
final bill is not adequate, the remaining sum shall be recovered from the subsequent
bill(s) of the contractor in full. However, in cases where any payment under this
Contract is made to the contractor within thirty days of the receipt by him of
notification of acceptance of tender the amount of additional Security Deposit shall be
recovered from such payment.
In case of a Contractor who is not enlisted for the area in which the work lies,
but whose name is in the BRO approved list of any BRO formation and has
deposited standing security and executed standing security bond and the Accepting
Officer decides to accept his tender the Contractor shall lodge with the Controller of
Defence Accounts concerned before acceptance of tender, the sum as notified by the
Accepting Officer as Security Deposit in the prescribed form.
Such sum shall be deposited in securities of the market value of such sum in
accordance with the Regulations for the Military Engineer Services for the time being
in force and any securities so deposited shall be endorsed in accordance with the
Government Securities Manual for the time being in force and, if the securities are in
the name of the Contractor, they shall be transferred to the Controller of Defence
Account concerned in such a way that they can be realized by him without reference
to the Contractor.
Government shall not be responsible for any loss of securities or for any depreciation
in the value of securities while in their charge nor for loss of interest thereon.
23. Orders under the Contract - All orders, notices etc., to be given under the
Contract shall be in writing, typescript or printed and if sent by registered post to the
last known place of abode or business of the Contractor shall be deemed to have
been served on the date when in the ordinary course of post it would have been
delivered to him.
The Contractor shall carry out without delay all orders given to him.
24. Admission to Site - The Contractor will not be permitted to enter on (other
than for inspection purposes) or take possession of the Site until instructed to do so
by the OC CONTRACT The portions of the Site to be occupied by the Contractor will
be clearly defined and/or marked on the Site plan, and the Contractor will on no
account be allowed to extend his operations beyond these areas. In the event of the
areas of land so allotted for the purposes of Accommodation of Labour, erection of
Temporary Workshops, stores, etc. Storage of Materials and the like being other than
Class A-1 land (which fact shall be ascertained by the Contractor from the OC
CONTRACT), the Contractor shall pay a nominal rent of Re-1 per year, or part of a
year, in respect of each and every separate area of land allotted to him.
No such approval shall however exempt the Contractor from complying with
any statutory provisions in regard to the taking and publication of such photographs.
Any B.R.O. Officials connected with the Contract shall have right of entry to the Site
at all times.
The Engineer-in-Charge shall have the power to exclude from the site any labour
whose admission thereto may in his opinion be undesirable for any reason
whatsoever. The OC CONTRACT shall have the power to exclude from the site any
person whose admission thereto may in his opinion be undesirable for any reason
whatsoever. The Contractor shall not be allowed any compensation on account of the
foregoing.
25. Contractor’s Supervision: The Contractor shall either himself supervise the
execution of the Contract or shall appoint a competent Agent approved by the OC
CONTRACT to act in his stead.
Where the Contractor is not a qualified Engineer or even if he is so qualified,
he cannot in the opinion of the OC CONTRACT, give his full personal attention to the
works, he shall at his own expense, employ a person/persons possessing the
following qualifications and/or experience as his accredited Agent (s) to supervise the
Works and to receive instructions from the Engineer-in- Charge.
(a) For works costing over Two Degree holders in Engineering from a Government
Rs. 300 Lakhs other recognized Institution or equivalent/final or direct final pass of
than those covered in sub-division II of the Institution of Surveyors (India)) with at least 5
(g) below. years practical experience of Works.
AND
Adequate numbers of Diploma holders in Engineering from a
(Note-The above provision shall be applicable irrespective of the fact whether contractor
himself is a qualified Engineer or not).
(b) For Works costing A Degree holder in Engineering from a Government recognized
between Rs. 100 lakhs Institution or equivalent/final or direct final pass of sub-division II
and Rs. 300 lakhs other of the Institution of Surveyors (India) with at least 4 years practical
than those covered in experience of works.
(g) below OR
Two Diploma holders in Engineering from a Government
recognized Institution with at least 6 years practical experience of
works.
(c) For Works costing A Degree holder in Engineering from a Government recognized
between Rs. 60 lakhs Institution or equivalent/final or direct final pass of sub-division II
and Rs. 100 lakhs other of the Institution of Surveyors (India) with at least 3 years practical
than those covered in experience of works.
(g) below OR
A Diploma holder in Engineering from a Government recognized
Institution with at least 5 years practical experience of works.
(d) For Works costing A Degree holder in Engineering from a Government recognized
between Rs. 7.5 lakhs Institution or equivalent/final or direct final pass of sub-division II
and Rs. 60 lakhs other of the Institution of Surveyors (India with at least 2 years practical
than those covered in experience of works.
(g) below OR
A Diploma holder in Engineering from a Government recognized
Institution with at least 4 years practical experience of works.
(e) For works costing A Degree or Diploma holder in Engineering from a Government
between Rs. 2 lakhs recognized Institution/final or direct final pass of sub-division II of
and Rs. 7.5 lakhs other the Institution of Surveyors (India) with adequate practical
than those covered in experience of Works.
(g) below
(f) For Works costing A competent person with adequate practical experience of works.
uptoRs. 2 lakhs other
than those covered in
(g)
below.
(g) For works of any value A competent person with adequate practical experience of works.
for repairs to buildings
and roads, periodical
services to buildings,
term contracts, grass
cutting and fencing.
The employment of Agent (s) as aforesaid shall be to the approval of the OC
CONTRACT who may verify his/their qualifications and experience by referring to
original degree/diploma/testimonials which shall be made available to him by the
Contractor or by the individual employed or proposed to be employed.
If the Contractor fails to appoint a suitable Agent on being ordered to do so,
the OC CONTRACT shall have full powers to suspend the execution of the Works
until such date as a suitable Agent is appointed and the Contractor shall be held
responsible for the delay so caused to the Works.
Orders given to the Contractor’s Agent shall be considered to have the same
force as if they had been given to the Contractor himself.
The Contractor or his Agent shall be in attendance at the Site during all
working hours and shall superintend the execution of the Works with such additional
assistance in each trade as the OC CONTRACT may consider necessary.
The Contractor or his accredited Agent shall attend, when required and
without making any charge for doing so, either at the office of the Engineer-in-Charge
or on the Works to receive instructions.
The OC CONTRACT shall have full powers, and without giving any reason, to
require the Contractor immediately to cease to employ in connection with this
contract any Agent, servant or employee whose continued employment is in his
opinion undesirable. The Contractor shall not be allowed any compensation on this
account.
26. Labour - The Contractor shall employ labour in sufficient number to maintain
the required rate of progress and of quality to ensure workmanship of the degree
required by the Specifications and to the satisfaction of the Engineer-in-Charge.
The Contractor shall remain liable for the payment of all wages or other
moneys to his work people or employees under the payment of Wages Act, 1936,
Minimum Wages Act, 1948, Employer’s Liability Act, 1938, Workmen’s
Compensation Act, 1923 or any other Actor enactments relating thereto and rules
framed there under from time to time. The Contractor shall work only on and during
the hours of a working day unless he obtains the prior written approval of the
Engineer- in-Charge to do otherwise. If such approval is given no liability in respect of
any excess cost arising there from shall be incurred by Government.
The Contractor shall furnish to the Engineer-in-Charge every morning a
distribution return of the number and description by trades of his work-people
employed on the Works.
The Contractor shall during the progress of the Works comply at his own
expense with all the rules and provisions contained in the B.R.O Model Rules for the
protection of health and sanitary arrangements for workers employed by contractors
(appended hereto as Annexure “C” to these Conditions) and shall at his own
expense provide for all facilities on his failure to do so, the OC Contract shall be
entitled to provide the same and recover the cost thereof from the contractor.
The Contractor shall not employ in connection with the Works any
person who has not completed his fifteenth year of age.
The Contractor shall at his own expense arrange for all the safety provisions as per
the B.R.O Safety Code (appended to these Conditions as an Annexure ‘B’) and shall
at his own expense provide for all facilities in connection therewith to the satisfaction
of the Engineer-in-Charge and on his failure to do so, the OC CONTRACT shall be
entitled to provide the same and recover the cost incurred in that behalf from the
Contractor. Provided further that in case of failure to arrange for the safety provisions
as above the Contractor should in addition be liable to pay a penalty of Rs. 50 for
each default.
27. Training of Apprentices - The Contractor shall comply with the provisions of
the Apprentices Act, 1961 and the rules and orders issued there under from time to
time. If he fails to do so, his failure will be a breach of contract and the Accepting
Officer may, in his discretion, cancelthe contract. The contractor shall also be liable
for any pecuniary liability arising on account of any violation by him of the provisions
of the Act.
(a) Leave: -
(i) In case of delivery: - Maternity leave not exceeding 8 weeks,
4 weeks up to and including the day of delivery and 4 weeks
following that day.
In the event of a provision existing in the tender documents for B.R.O. Supply
of water on payment and the contractor desiring to buy it from B.R.O., he will be
permitted to draw it from
B.R.O. Water supply system or other B.R.O. sources at such point or points as may
be decided by the OC Contract on his sole discretion and the Contractor shall make
necessary arrangements at his own cost for lifting, pumping, carrying or conveying
water to the site of works as required.
Normally in all cases of water supplied from B.R.O. piped system, the supply
shall be metered and paid for by Contractor at the ‘All India flat rate per 1,000 gallons
which includes hire charges for meter to be provided by B.R.O. In exceptional cases
where metering is not feasible, i.e., water from B.R.O. wells or static tanks, or in the
case of Term Contracts where the Contractor draws water not from any ONE
sources, the Contractor shall pay Rs. 3.75 per every Rs. 1,000 worth of work done
priced at Contract rates. In the event of breakdown of B.R.O. Supply of water or in
the event of the said supply of B.R.O. water becoming intermittent, the Contractor
shall have no claim whatsoever on this account.
The water used for any or all requirements shall be subject to the prior written
approval of the Engineer-in-Charge.
32. Temporary Workshops, Stores, etc. - The Contractor shall during the
progress of the Works provide, erect and maintain at his own expense all necessary
temporary workshops, stores, offices, etc., as are required for the proper and efficient
execution of the Works. The planning, siting and erection of these buildings shall be
to the approval of the Engineer-in-Charge and they shall at all times be kept tidy and
in a clean and sanitary condition to the entire satisfaction of the Engineer- in-Charge
and at the Contractor’s expense.
33. Blank.
34. Tools and Plant on Site - All tools, plant and equipment brought to the Site
shall become the property of Government and shall not be removed off the Site
without the prior written approval of the OC CONTRACT But whenever the Works are
finally completed or the Contract is determined for reasons other than the default of
the Contractor, the Contractor shall forthwith remove from the Site all tools, plant and
equipment (other than such as may have been provided by Government) and upon
such removal, the same shall revest in, and become the property of the Contractor.
36. Precautions against Risks. - The Contractor shall be responsible at his own
expense, for precautions to prevent loss or damage from any and all risks other than
for Accepted Risks and to minimize the amount of any such loss or damage and for
the provision of all protective works, casing, coverings, etc., required for the purpose,
until the Works have been handed over complete to the Engineer-in-Charge.
All Government buildings rented to the Contractor for workshops or stores shall be
insured by the Contractor in favour of Government to their full value against risk of
loss or damage from whatsoever cause arising other than the accepted risk, and the
policy of insurance and receipts for premiums shall be produced when required by
the OC CONTRACT; provided always that where part only of a building is rented to
the Contractor he will be required to insure the building only if used by him for the
purpose of storing or using materials of a combustible nature, as to which the
decision of the OC CONTRACT shall be final and binding.
The Contractor shall provide all watchmen necessary for the protection of the
Site, the Works and of materials and plant and all things on the Site during the
progress of the Works, and shall solely be responsible for and shall take all
reasonable and proper steps for protecting, securing, lighting and watching all places
on or about the Works and the Site which may be dangerous to any person whom so
ever.
37. Notices and Fees - The Contractor shall give all notices required by any
statutory provisions or by the regulations and/or bye-laws of any local authority
and/or of any public service, company of authority affected by the Works or with
whose systems the same are or will be connected and he shall pay and indemnify
Government against any fees, or charges demandable by law under such acts,
regulations and/or bye-laws in respect of the Works and shall make and supply all
drawings and shall make and supply all drawings and plans required in connection
with any such notices.
38. Setting out the Works - The OC CONTRACT or Engineer-in-Charge, shall
supply dimensioned drawings, levels and other information necessary to enable the
Contractor to set out the Works. The Contractor shall set out the Works and shall
provide and fix all settings out apparatus required and solely be responsible for the
correctness and maintenance of the setting out. No Work shall commence till the
setting out is approved by the Engineer-in-Charge.
39. Site Drainage - All water that may accumulate on the Site during the
progress of the Works, or in trenches and excavations, from other than the accepted
risks, shall be removed from the Site to the entire satisfaction of the Engineer-in-
Charge and at the Contractor’s expense.
40. Excavation - Materials of any kind obtained from excavation on the Site shall
remain the property of Government and shall be disposed off as Engineer-in-Charge
directs.
41. Foundations - The Contractor shall not lay any foundations until the
excavations for the same have been examined and approved in writing by the EIC.
42. Covering in Work - The Contractor shall give reasonable notice in writing to
the Engineer- in-Charge whenever any work is to be permanently covered or
concealed, whether by earth or other means and in default of so doing shall, if
required by the Engineer-in-Charge uncover such work at his own expense.
Extra soil required for filling, etc. shall be obtained only from those places for
which prior written approval has been given by the Engineer-in-Charge.
43. Approval of Works by Stages - All work embracing more than one process
shall be subject to examination and approval at each stage thereof and the
Contractor shall give due notice in writing to the Engineer-in-Charge when each
stage is ready. In default of such notice being received, the Engineer-in-Charge shall
be entitled to appraise the quality and extent thereof and in the event of any dispute
the decision of the OC CONTRACT thereon shall be final and binding.
In additions, in case of Major Works exceeding rupees one lakhs and Special
Repairs exceeding rupees five lakhs, the Engineer-in-Charge will maintain a Works
Dairy (IAFW-2347) incorporating daily record of all important events in the execution
of work and the Contractor or his accredited agent will sign it daily in the office of the
Engineer-in-Charge.
An invoice in duplicate signed by the Contractor or his Agent shall be sent with each
delivery of materials for day-work and the Contractor will be furnished with a receipt,
signed by the Engineer- in-Charge, specifying the description, quantities, weight or
measurement (as the case may be) of the articles approved; reference will be made
to this receipt in the return aforesaid and the receipt itself is to be produced in
support of the Contractor’s bill.
In the case of Lump Sum Contracts, the rates to be charged and the percentage
addition for profit and establishment charges, etc., will be agreed upon between the
COMMANDER CONTRACT and the Contractor prior to the execution of the work.
46. Inspection of the Work. -B.R.O Officers concerned with the Contract shall
have power at any time to inspect and examine any part of the Works and the
contractor shall give such facilities as may be required to be given for such
inspections and examination.
47. Responsibility for Buildings: - In the event of any building or part, of a building
being handed over to the Contractor for the execution of Works thereto under the
provisions of the Contract, he shall give a written receipt for all fixtures, glass, etc.,
and he shall be required to make good at his own expense all damage resulting from
any cause whatsoever, accepted risks and fire excepted (unless such fire shall have
been caused through the negligence of the Contractor or any of his agents, servants
or employees) while in his charge and to deliver up the said building or part thereof to
the Engineer –in-Charge in a clean state complete in every particular, on the
completion of the Works.
48. Damage and Loss. – (a) All plant, temporary building, equipment, and things on
the site provided by or on behalf of the Contractor for the construction of, but not for
incorporation in the Works shall stand at the risk and be in the sole charge of the
Contractor and the Contractor shall be responsible for, and with all possible speed
make good, any loss or damage thereto arising from any cause whatsoever,
including the accepted risk.
(b) Save as above, the Works and all materials and things whatsoever
including such as may have been provided by Government on the site in connection
with and for the purpose of the contract shall stand at the risk and be in the sole
charge of the Contractor and the Contractor shall be responsible for, and with all
possible speed make good, any loss or damage thereto arising from any cause
whatsoever, other than the accepted risks and shall deliver up all the Works to the
Engineer – in-Charge in a clean state, complete in every particular.
In the event of any loss or damage to works and materials on the Site from
any of the accepted risks, or loss or damage from accepted risk and fire to
Government buildings handed over to contractor for execution of works referred to in
condition 47, the following provisions shall have effect: -
(i) The contractor shall, as maybe directed in writing by the Engineer – in –
Charge, remove from the site any debris and so much of the Works as shall
have been damaged, taking to the OC Contract store such articles and/or
materials as may be directed;
(ii) The Contractor shall, as may be directed in writing by the Engineer- in-
Charge, proceed with the erection and completion of the works under and in
accordance with the provisions and conditions of the contract; and
(iii) There shall be added to the Contract Sum the net amount due,
ascertained in the same manner as for deviations, or as prescribed for
payment, in respect of re-execution of the works lost or damaged, the
replacement of any materials and things lost or damaged but not
incorporated in the works at the date when the loss or damage occurred, and
the removal by the contractor as provided above the debris and damaged
work referred to therein.
Provided always that the contractor shall not be entitled to payment under this
condition in respect of so much loss or damage as has been occasioned by any
failure on his part to perform his obligations under the contract.
(c) Save as provided above, the contractor shall at his own expense reinstate
and make good to the satisfaction of the OC Contract or make compensation for any
injury, loss or damage occasioned to any property or right whatever including
property and rights of Government (or agents, servants, or employees of
Government) being injury, loss or damage arising out of or in any way in connection
with the execution or purported execution of the contract and further, the contractor
shall indemnify Government against all claims enforceable against Government (or
any agent, servant or employee of Government) or which would be so enforceable
against Government were Government, a private person, in respect of such injury
(including injury resulting in death), loss or damage to any person whomsoever or
property, including all claims which may arise under the workmen’s compensation
Act or otherwise.
49. Completion. - The Works shall be completed to the entire satisfaction of the OC
Contract and in accordance with the Contractor’s forecast of time, and progress
where operative. All unused stores and materials tools, plant, equipment, scaffolding,
temporary buildings, huts and things belonging to the Contractor (other than such
items as are required for rectification of defects) shall be removed and the Site of
Works cleared of rubbish and all waste materials by the Contractor, at his own
expense and delivered up clean and tidy to the satisfaction of the Engineer –in-
Charge on or before the date for completion.
All unused or surplus stores and materials and other items out of those
provided by the Government shall be returned by the contractor, at his own expense,
within such period as may be notified by the Engineer – in- Charge, to the place of
issue against written receipts from the Engineer –in- Charge.
Soon after the rectification of defects, any stores and materials and other
items mentioned above, retained for rectification of defects shall also be removed
and site and works cleared as above and delivered to the Engineer – in – Charge in a
neat state.
The OC Contract shall also certify to the Contractor the state of items or
groups of items of the Works at the end of the defect’s liability period.
50. Compensation for Delay. -If the Contractor fails to complete the works and
clear the site on or before the date (s) fixed for completion, he shall, without prejudice
to any other right or remedy of Government on account of such breach, be liable to
pay compensation as under: -
(a) In the case of Term contracts, one per cent of the estimated value of
the Requisition or the Works order for every week that the whole of the
work remains uncompleted;
(b) In the case of other Contracts, one per cent of the Contract value of
the item or group of items of Work (excluding the Contract value of such individual
items as are completed and taken over by OC Contract on or before the date(s) fixed
for completion, in terms of condition 49 hereof) for which as separate period of
completion is given in the Contract, for every week that the whole of the work in
respect of the item or group of items of work concerned remains uncompleted, even
though the Contract as a whole be completed by the latest date specified in the
Contract for any item or group of items ofworks.
For the purpose of this condition the ‘Contract Value’ shall be the value at contract
rates of the work as actually ordered including all deviation orders on the Contractor.
When the delay is not a full week or in multiples of a week but involves a fraction of a
week the compensation payable for the fraction shall be proportional to the number
of days involved.
Provided always that the total amount of compensation to be paid under this
condition shall not exceed as mentioned below: -
(a) In the case of Term Contracts, ten percent of the estimated value of the
Requisition or works order as a whole;
(b) In the case of other contracts: -
(i) Where the Contract sum does not Ten percent of the Contract value of the item of group of
exceed Rs 10 Lakhs. items of works for which a separate period of completion
is given.
(ii) Where the Contract sum exceeds Ten percent of the Contract value of the item or group of
Rs 10 Lakhs but does not exceed items of works for which a separate period of completion
Rs 20 lakhs. is given or Rupees one and a half lakhs whichever is
less.
(iii) Where the Contract sum exceeds Seven and half percent of the contract value of the item
Rs 20 Lakhs but does not exceed or group of items of work for which a separate period of
Rs 150 lakhs. completion is given, or Rupees seven and a half lakhs
whichever is less.
(iv) Where the Contract sum exceeds Five percent of the contract value of the item or group of
Rs 150 Lakhs but does not exceed items of work for which a separate period of completion is
Rs 300 lakhs. given or Rupees twelve and a half lakh whichever is less.
(v) Where the Contract sum exceeds Four percent of the Contract value of the item or group of
Rs 300 lakhs. items of work for which a separate period of completion is
given subject to a maximum of Rupees twenty-five lakhs.
51. Laws Governing the Contract. - This Contract shall be governed by the Indian
Laws for the time being inforce.
52. Cancellation of Contract for Corrupt Acts- The Commander Contract whose
decision shall be final and binding, shall without prejudice to any other right or
remedy which shall have accrued or shall accrue thereafter to Government, cancel
the Contract in any of the following cases and the Contractor shall be subject to
payment of any loss or damage resulting from any such cancellation to the like extent
as is provided in the case of cancellation for default:
(a) offer or give or agree to give to any person in Government service any
gift or consideration of any kind as an inducement or reward for doing
or forbearing to do or for having done or forborne to do any act in
relation to the obtaining or execution of this or any other Contract for
Government service, or
(b) enter into a contract with Government in connection with which
commission has been paid or agreed to be paid by him or to his
knowledge, unless the particulars of any such commission and the
terms of payment thereof have previously been disclosed in writing to
the Accepting Officer, or
(c) Obtain a contract with Government as a result of ring tendering or
other non bonafide methods of competitive tendering without first
disclosing the fact in writing to the Accepting Officer.
If the Contractor: -
(a) being an individual or if a firm, any partner thereof shall at any time be
adjudged insolvent or have a receiving order or order for
administration of his estate made against him or shall take any
proceedings for liquidation or composition under any Insolvency Act
for the time being in force or make any conveyance or assignment of
his effort or composition or arrangement for the benefit of his creditors
or purpose so to do or if any application be made under any
Insolvency Act for the time being in force for the sequestration of his
estate or if a trust deed be granted by him for behalf of his creditors; or
(b) being a company shall pass a resolution or the court shall make an
order for the liquidation of its affairs or a receiver or manager on
behalf of the debenture holders shall be appointed or circumstances
shall arise which entitle the Court or debenture holders to appoint a
receiver or manager; or
Whenever the Accepting Officer exercises his authority to cancel the Contract
under this condition, he may complete the works by any means at the contractor's risk
and expense provided always that in the event of cost of completion of after
alternative arrangement have been finalized by the Government to get the Works
completed. Estimated cost of completion (as certified by OC Contract) being less than
the Contract cost the advantage shall accrue to the Govt. If the cost of completion or
after alternative arrangement have been finalized by the Government to get the works
completed, estimated cost of completion) as certified by OC Contract) exceeds the
moneys due to the contractor under this contract, the contractor shall either pay the
excess amount ordered by OC Contract or the same shall be recovered from the
Contractor by other means. The Government shall also be at liberty to hold and retain
in their hands materials, tackle machinery and stores of all kind on site, as they may
think proper and may at any time sell any of the said materials, tackle, machinery and
stores and apply the proceeds of sale in or towards the satisfaction of any loss which
may arise from the cancellation of the Contract as aforesaid.
(a) makes default in commencing the works within a reasonable time from
the date of the handing over the site, and continues in that state after
a reasonable notice from OC Contract.
or
(b) in the opinion of the OC Contract at any time whether before or after
the date or extended date for completion, makes default in proceeding
with the works, with due diligence and continues in that state after a
reasonable notice from OC Contract.
or
(c) fails to comply with any of the terms and conditions of the contract or
after reasonable notice in writing with orders properly issued
thereunder,
(d) fails to complete the works, works order and items of works with
individual dates for completion and clear the site on or before the date
of completion
The Accepting Officer may, without prejudice to any other right or
remedy which shall have accrued or shall accrue thereafter to Government
cancel the Contract as a whole or only such work orders of items of work in
default from the Contract. Whenever the Accepting Officer exercises his
authority to cancel the contract as a whole or in part under this condition he
may complete the work by any means at contractor's risk and cost, provided
always that in the event of cost of completion or after alternative
arrangements have been finalized by the Government to get the works
completed, estimated cost of completion (as certified by OC Contract) being
less than the Contract cost, the advantage shall accrue to the Govt. If the cost
of completion or after alternative arrangements have been finalized by the
Government to get the works completed, estimated cost of completion (as
certified by OC Contract) exceeds the money due to contractor under this
contract, the contractor shall either may the excess amount ordered by OC
Contract or the same shall be recovered from the Contractor by other means.
The Government shall also be at liberty to hold and retain in their hands
materials, tackle, machinery and stores of all kinds on site, as they may think
proper and many at any time sell any of the said materials, tackle, machinery
and stores and apply the proceeds of sale in or towards the satisfaction of
any loss which may arise from cancellation of the Contract as aforesaid.
He shall be paid at Contract rates for the full amount of the work executed
including such additional works, e.g. clearing of site, etc as may be rendered
necessary by the said foreclosing. He shall also be allowed a reasonable payment
(as decided by the Accepting Officer) for any expenses sustained on account of
labour and materials collected but which could not be utilized on the Works as
verified by the OC Contract.
58. FairWage-
(a) The Contractor shall pay not less than the fair wage as defined below
or the minimum wage fixed under the Minimum Wages Act, whichever is
higher to labourers engaged by him on the work.
"Fair Wage" means wage whether for time or piece-work notified at the time
of inviting tenders for the work and where such wages have not been so notified the
wages prescribed by the Chief Engineer for the Stations at which the work is done.
(e) Vis-à-vis the Government, the Contractor shall be primarily liable for
all payments to be made under and for the observance of the
Regulations aforesaid without prejudice to his right to claim indemnity
from his sub-contractors.
59. The Regulations aforesaid shall be deemed to be a part of this Contract and
any breach thereof shall be a breach of this Contract.
60. BLANK.
CHAPTER-IV
VALUATIONAND PAYMENT
61. Record and Measurement - All items having a financial value shall be
entered in the MES Measurement Book IAFW-2261 or in the case of terms Contracts
for maintenance and repair work, on other approved Army Form, as applicable so
that a complete record is obtained of all work performed under the Contract.
Building, etc priced in Schedule "A" as a unit lump sum will be entered by
number as the unit lump sum.
Work carried out for agreed lump sums will be described and similarly recorded.
(a) At applicable rate in the Bill of Quantities for the building/items or work,
in which the deviation is involved:
(b) At lowest applicable rate in any other bill of Quantities;
(c) At pro-rata rate based on lowest rate for analogous item in the Bill of
Quantities for the building/item of work to which the deviation refers;
(d) At pro-rata rate based on lowest rate for analogous items in any other
bill of quantities.
(a) At applicable rate in relevant part of Schedule "A" in which the deviation is
involved.
(b) At pro-rata rate based on analogous items in relevant part of Schedule
"A" in which the deviation is involved.
(c) At applicable rate in the MES Schedule.
(d) At pro-rata rate based on analogous items in the MES Schedule.
The rates at (a) to (d) above shall be subject to the Contractor's percentage.
(C) Applicable to Lump Sum Contracts based on Drawings and Specifications-
(a) At applicable rate in relevant part of Schedule "A" in which the deviation is
involved;
(b) At pro-rata rate based on analogous items in relevant part of Schedule
"A" in which the deviation is involved;
(c) At applicable rate in the MES Schedule.
(d) At pro-rata rate based on analogous items in the M.E.S. Schedule.
The rates at (c) and (d) above shall be subject to the percentage inserted in
tender documents for pricing deviations.
The rates at (a) and (b) above shall be subject to the Contractor's percentage.
The principles enunciated in paras (A) to (E) shall apply to the corresponding
parts of the contract.
(G) For all Contracts–
If any Work, the rate for which cannot be obtained by any of the methods
referred to in paras (A) to (E) above, has been ordered on the Contractors, the rate
shall be decided by the OC Contract on the basis of the cost to the Contractor at Site
of Works plus {15%} to cover all overheads and profit. Provided that if the Contractor
is not satisfied with the decision of the OC CONTRACT, he shall be entitled to
represent the matter to Commander Contract, within seven days of receipt of the OC
Contract's decision and the decision of the COMMANDER CONTRACT thereon shall
be final and binding.
64. Advances on Account: The contractor may at intervals of not less than 30
days submit claims on I.A.F.W.-2263 for payment of advances on account of work
done and of materials delivered in connection with Measurement and Lump Sum
Contracts. Advance payment against each individual work order issued under a
Term Contract shall be made also at intervals of not less than one month provided the
estimated value of the work performed is not less than Rs.3,000 for new works and
Rs.10,000 for repair services and the value of payment on account is not less than
Rs.1,500 and Rs.5,000 respectively. The Contractor shall be entitled to be paid in
respect of such claims at the following percentages of the value of work executed on
the Site to the satisfaction of the Engineer-in-Charge:- (a) For Works not exceeding
Rs.5 lakhs-90 per cent of the value of work executed (b) For Works exceeding Rs.5
lakhs but not exceeding Rs.10 lakhs – 90 per cent of the value of work executed for
the first 5 lakhs and 92 ½ per cent of the value of work executed for the balance. (c)
For Works exceeding Rs.10 lakhs - 90 percent of the value of work executed for the
first 5 lakhs; 92 ½ per cent of the value of work executed for the next 5 lakhs and 95
per cent of the value of work executed for the balance. Provided the amount the
retention money recovered from the contractor under the contract shall not exceed
Rs.1.5 lakhs. Provided further, the Contractor may be paid advance on account to the
full value of work executed on the Site on his furnishing Guarantee Bond(s) or Fixed
Deposit Receipt(s) from a Scheduled Bank for the amount of the retention money
which should otherwise be recoverable from him under the contract.
The Guarantee Bond shall be executed for a period and on a form as directed by the
Accepting Officer. The Contractor shall further arrange to extend the period of
Guarantee Bond or shall furnish a fresh Guarantee Bond of similar value so as to
cover the period till the payment of the final bill. In the case of Fixed Deposit Receipts,
the same shall be for a period exceeding 6 months beyond the period of contract and
shall be endorsed in accordance with the Government Securities Mannual for the time
being in force. If the Fixed Deposit Receipts are in the name of the Contractors, they
shall be transferred/endorsed to the Controller of Defence Accounts concerned in
such a way that they can be encashed by the said Controller of Defence Accounts
without reference to the Contractor. In the event of delay in the preparation of the final
bill, the Contractor shall make arrangements with the Bank for suitable extension of
the fixed deposit period. In the case of Measurement and Lump Sum Contracts the
Contractor shall also be entitled to be paid during the progress of the Works 85 per
cent of the value of any materials which are in the opinion of the Engineer-in-Charge
in accordance with the Contract and which have reasonably been brought on the Site
in connection therewith and are adequately stored and/or protected against damage
by weather or other causes, but which have not at the time of the advance been
incorporated in the Works. Provided always that payment shall not be made under
these periodical certificates in respect of perishable materials (the discretion of the
G.E. as to what is perishable being final and binding). Any sum due from the
Contractor on account of Transport, Stores, or any such matter provided by
Government shall be deducted from the first or next subsequent advance. The G.E.
shall from time to time certifies the sums to which the Contractor is entitled after
retaining the reserve. Any certificate relating to Work done or materials delivered may
be modified or corrected by any subsequent interim certificate or by the final
certificate and no certificate of the G.E. supporting an advance payment shall of itself
be conclusive evidence that any Work or materials to which it relates are in
accordance with the Contract.
65. Final Bill (Applicable only to Measurement and Lump Sum Contract): -
The Final Bills shall be submitted by the Contractor on IAFW-2262 in duplicate within
three months of physical completion of the Works to the satisfaction of the Engineer-
in-Charge.
It shall be accompanied by all abstracts, voucher, etc, supporting it and shall be
prepared in the manner prescribed by the OC CONTRACT.
No further claims shall be made by the Contractor after submission of the Final Bill
and these shall be deemed to have been waived and extinguished.
The Contractor shall be entitled to be paid the final sum less the value of payments
already made on account, subject to the certification of the final bill by the OC
CONTRACT
No charges shall be allowed to the Contractor on account of the preparation of the
final bill. 65 A. Final Bill (Applicable only to Term Contracts):-The final Bill
shall be submitted by the Contractor on I.A.F.W.-2262 in duplicate, accompanied by
all supporting abstracts a, vouchers, etc., except IAFs W-2158 and 1833 prepared in
the manner prescribed by the OC CONTRACT within three months of physical
completion of the Works to the satisfaction of the Engineer-in-Charge. In respect of
Works orders arising out of unit requisitions or B.R.O inspections for maintenance
and repairs, any portion of such an order which remains uncompleted at the date of
the next subsequent requisition or inspection may, purely to facilitate payment of
completed work and without prejudice to any other right or remedy of Government in
respect of any such delay, be deleted and the Works order, as so amended forthwith,
billed for final payment.
When fractions of a rupee occur in the totals of bills, fractions less than half a
rupee shall be disregarded and half a rupee and over taken as a rupee.
66. Payments of Bills- Payment of those items of the Final Bill in respect of
which there is no dispute shall be made within the period specified hereunder, the
period being reckoned from the date of receipt of the Bill by the OCCONTRACT: -
After payment of the amount of the final bill payable as aforesaid has been
made, the contractor, may if he so desires, reconsider his position in respect of the
disputed portion of the final bill and if he fails to do so within 90 days, his disputed
claim shall be dealt with as provided in the Contract.
All payments due under this contract shall be made by means of a crossed
cheque to the Contractor ‘A/c Payee’ only at the treasury located in the station where
either the work is executed or services rendered or at the treasury nearest to the
station where the office of the OC CONTRACT is located.
The Contractor is required to acknowledge receipt of all cheques
issued in his favour. With regard to cheques sent to him by post, he shall
acknowledge receipt within fifteen days from the date of their receipt. Failure on the
part of the Contractor to acknowledge receipt will render him liable to forfeit the
facility of receiving cheques by post and unless the Contractor furnishes a
satisfactory explanation for his default in this respect payment through cheques sent
by post shall not be resumed, and on this Contract from the office of the OC Contract
after rendering proper receipt.
67. Recovery from Contractor- (a) Whenever any claims for payment of sum of
money arise(s) out of or under this contract against the contractor, the Contractor
shall on demand make the payment of the same or agree for effecting adjustment
from any amounts due to him by the Government. If, however, he refuses or neglects
to make the payment on demand or does not agree for effecting adjustment from any
amounts due to him, Government shall be entitled to withhold an amount not
exceeding the amount of the claims, from any sum when due or which at any time
thereafter may become due to the Contractor, under this or any other contract with
the Government or from any other sum due to the contractor from the Government
(which may be available with the Government) or from the Contractor’s Security
Deposit or Security Bond amount, and retain the same by way of lien till such time
payment is made by the contractor or till the claims is/are settled or adjudicated
upon, or till the contractor, at his expense furnishes fixed Deposit Receipt(s) duly
endorsed as directed by the Accepting Officer, or a Guarantee Bond from a
Scheduled Bank for an amount equal to the amount of the claim (s), in the form as
directed by the Accepting Officer.
(f) Government reserve the right to carry out post-payment audit and
technical examination of the works and Final Bill, including all supporting voucher,
abstracts, etc. Government further reserve the right to carry out the aforesaid
examination and enforce recovery when detected, notwithstanding the fact that the
amount of the Final Bill may have been included by one of the parties as an item of
dispute before an arbitrator appointed under the Arbitration clause of the Contract
and notwithstanding the fact that the amount of the Final Bill figures in the Arbitrator's
award.
(g) If, as a result of such audit and technical examination, any over-
payment is discovered in respect of the work done under this Contract, the contractor
shall on demand make payment of a sum equal to the amount of over-payment or
agree for effecting necessary adjustment from any amount due to him by
Government. If however, he refuses or neglects to make the payment on demand or
does not agree for effecting adjustment from any amounts due to him, Government
shall be entitled to take action as in sub-Para (a) hereinbefore. If as a result of such
audit and technical examination any under payment is discovered, the amount of
under payment shall be duly paid to the Contractor by Government.
(i) All notices under this condition shall be given by the OC contract
69. Issue of notices. - Subject as otherwise provided in this Contract, all notice
to be given on behalf of the President of India and all other actions to be taken on his
behalf may be given or taken on his behalf by the OC Contract or any officer for the
time being entrusted with the functions, duties and powers of the OC Contract.
70. Arbitration - All disputes, between the parties to the Contract (other than
those for which the decision of the Commander Contract or any other person is by
the Contract expressed to be final and binding) shall, after written notice by either
party to the Contract to the other of them, be referred to the sole arbitration of an
[Serving Officer having degree in Engineering or equivalent or having passed
final/direct final Examination of sub-Division II of Institution of Surveyor (India)
recognized by the Govt of India.] to be appointed by the authority mentioned in the
tender documents.
The Arbitrator may from time to time with the consent of the parties, enlarge,
the time for making and publishing the award.
The Arbitrator shall give his award within a period of six months from the date
of his entering on the reference or within the extended time as the case may be on all
matters referred to him and shall indicate his findings, along with sums awarded,
separately on each individual, item of dispute. [The arbitrator shall give reason for the
award in each and every case irrespective of the value of claims or counter claims]
The venue of Arbitration shall be such place or places as may by fixed by the
Arbitrator in his sole discretion.
The Award of the Arbitrator shall be final and binding on both parties to the Contract.
71. Jurisdiction of Courts - Irrespective of the place of issue of tender, the place
of acceptance of tenders, the place of execution of contract or the place of payment
under the contract, the contract shall be deemed to have been made at the place
from where the acceptance of tenders has been issued and the work is
executed/executable. The Courts of the place from where the acceptance of the
tender has been issued or the place where the work is executed/ under execution
shall alone have jurisdiction to decide any dispute arising out of or in respect of the
contract.
1 Amended vide amendment No. 6 Previously amendment No. 4 stipulated (If
the value of the claim or counter claims in an arbitration reference exceeds
Rs. 1 lakh the arbitrator shall give reasons for the award.)
2 CONTRACTS: RECOVERY OF RISK PURCHASE LOSS OR GENERAL
DAMAGES FROM DEFAULTING CONTRACTORS
All amount due to the Govt from the Contractor by way of risk purchase
recoveries or forfeited security deposit/pending bills are outstanding “claims”
only, and cannot be recovered till these have been converted into “due” (debt)
by an award of the arbitrator. Once the award is given, the sum due to the
Government against the contractor will be in the nature of a “due’ (debt) and
the Government would be entitled to withhold any other sum under any other
contract, due to the same contractor to safeguard recovery of above “due”
(debt). Once the award become ‘Rule of the Court’ the Government can
legally adjust the amount of award from the pending bills/security deposit of
the contractor available with the Government, of any other contract.
Withholding of security deposit/pending bills of any other contract for
realization Govt claim of a disputed contract, without obtaining an arbitration
award, is not tenable before a Court of law. It is therefore necessary that all
cases where the Government claims are in excess to the pending
bills/security deposit of the contractor for the contract under dispute,
immediate steps will be taken to get the dispute adjudicated and obtain an
arbitration award. Then only, the security deposit/pending bills of other
contracts can be withheld to safeguard the interest of the State.
Headquarters, No. 68988/Q/ST-26 dated 12.12.1989.]
3 New condition 71 added vide amendment No. 9
ANNEXURE ‘A
CONTRACTOR’S LABOUR
REGULATIONS
(b) ‘Fair wages’ means wages whether for time or piece-work notified at
the time of inviting tenders for the Work and where such Wages have not
been so notified, the Wages prescribed by the Chief Engineer for the stations
at which the Work is done.
(d) ‘Wages’ shall have the same meaning as defined in the Payment of
Wages Act and include time and piece-rate wage.
(e) All payments of wages shall be made on a working day except when the Work
is completed before the expiry of the wage period, in which case final
payment shall be made within 48 hours of the last working day.
Note. – The terms “working day” means a day on which the work on which
the labour is employed is in progress.
6. Wage Book and Wage Slips etc. – (a) The Contractor shall maintain a
Wage Book of each worker in such form as may be convenient, but the same shall
include the following particulars: -
(i) Rate of daily or monthly wages.
(ii) Nature of work on which employed.
(iii) Total number of days worked during each wage period.
(iv) Total amount payable for the work during each wage period.
(v) All deductions made from the wages with an indication in each
case of the ground for which the deduction is made.
(vi) Wages actually paid for each wage period.
(b) The Contractor shall also maintain a Wage Slip for each worker
employed on the Work.
7. Fines and Deductions which may be made from Wages – (a) The Wages
of worker shall be paid to him without any deductions of any kind except the
following:
(i) Fines
(ii) Deductions for absence from duty, i.e. from the place or places
where by the terms of his employment he is required to work.
The amount of deduction shall be in proportion to the period for
which he was absent.
(iii) Deductions for damage to or loss of goods expressly entrusted
to the employed person for custody or for loss of money for
which he is required to account, where such damage or loss is
directed attributable to his neglect or default.
(iv) Any other deductions which the Central Government may from
time to time allow.
(b) No fines shall be imposed on a worker and no deduction for damage
or loss shall be made from his wages until the worker has been given an
opportunity of showing cause against such fines or deduction.
(c) The total amount of fines which may be imposed in any one wage
period on a worker shall not exceed an amount equal to three paise in a
rupee of the wages payable to him in respect of that wage period.
(d) No fine imposed on any worker shall be recovered from him by
installments or after the expiry of 60 days from the date of which it was
imposed.
8. Register of fines, etc - (a) The Contractor shall maintain a Register of fines
and of all deductions for damage or loss. Such register shall mention the reason for
which fine was imposed or deduction for damage or loss was made.
(b) The contractor shall maintain a list, in English and in the Local Indian
Language clearly defining acts and omissions for which penalty of fines can be
imposed. He shall display such list and maintain it in a clean and legible condition in
conspicuous places on Work.
9. Preservation of Registers - The Wage Book, the Wages slip and the
Register of Fines and Deductions require to be maintained under these Regulations
shall be preserved for 12 months after the date of last entry made in them.
11. Report of Labour Welfare Officer- The Labour Welfare Officer or other
person authorized as aforesaid shall submit a report of the results of his investigation
or enquiry to the OC Contract concerned, indicating the extent, if any, to which the
default has been committed, with a note that necessary deductions from the
contractor’s bill be made and the wages and other dues be paid to the labourers
concerned. [The OC Contract shall arrange payments to the labour concerned within
45 days from the receipt of the report from the labour welfare officer or other person
authorized as aforesaid, as the case may be]. In case an appeal is made by the
Contractor under clause 12 of these Regulations, the actual payment to labourers will
be made by OC contractor after the Regional Labour Commissioner has given his
decision on such appeals.
12. Appeal against the decision of Labour Welfare Officer- Any person
aggrieved by the decision and recommendation of the Labour Welfare Officer or
other person so authorized may appeal against such decision to the Regional
Labour Commissioner within 30 days from the date of decision, forwarding
simultaneously a copy of his appeal to the OC Contract concerned but subject to
such appeal, the decision of the Officer shall be final and binding upon the
Contractor.
14. Inspection of Registers- The Contractor shall allow inspection of the Wage
Book the Wage slips and the Register of Fines and Deductions to any of his workers
or to his agent at a convenient time and place after due notice is received or to the
Labour Welfare Officer, or any other person authorized by the Government of India
on his behalf.
15. Submission of Return - The Contractor shall submit periodical returns as
may be specified from time to time.
16. Amendment- The Government of India, may from time to time. add to or
amend these Regulations and on any questions as to the application, and on any
questions as to the application, interpretation of effect of these Regulations the
decision of the Chief Labour Commissioner or Deputy Chief Labour Commissioner to
the Government of India or any other person authorized by the Government in that
behalf shall be final.
ANNEXURE ‘B’
SAFETY CODE
1. Suitable scaffolds should be provided for workmen for all Works that cannot
safety be done from the ground or from solid construction except such short period
Works as can be done safely from ladders. When a ladder is used an extra Mazdoor
shall be engaged for holding the ladder and if the ladder is used for carrying
materials as well suitable foot-holds and hand-holds shall be provided on the ladder
and the ladder shall be given an inclination not steeper than ¼ to 1 (1/4 horizontal
and 1 vertical).
2. Scaffolding or staging more than 3.5 metres above the ground or floor, swung
or suspended from an overhead support or erected with stationary support shall have
a guard rail properly attached, bolted, braced and otherwise secured at least 1 Metre
high above the floor or platform of such scaffolding or staging and extending along
the entire length of the outside and ends thereof with only such openings as may be
necessary for the delivery of materials. Such scaffolding or staging shall be so
fastened as to prevent it from swaying from the building or structure.
3. Working platform Gangways and stairways should be so constructed that they
should not sag unduly or unequally, and if the height of the platform or the Gangway
or the Stairway is more than 3.5 Metres above ground level or floor level they should
be closely boarded, should have adequate width and should be suitably fenced, as
described in (2)above.
4. Every opening in the floor of a building or in a working platform be provided
with suitable means to prevent the fall of persons or materials by providing suitable
fencing or railing whose minimum height shall be 1 metre.
5. Safe means of access shall be provided to all working platforms and other
working places. Every ladder shall be securely fixed. No portable single ladder shall
be over 9 Metres in length while the width between side rails in rung ladder shall in
no case be less than 30 cms. For ladder upto and including 3 metres in length. For
longer ladders this width should be increased at least 6 mm for each additional 30
cms. Uniform step spacing shall not exceed 30 cms.
6. Excavation and Trenching - All trenches 1.2 metres or more in depth, shall
at all times be supplied with at least one ladder for each 30 metres in length or
fraction after thereof ladder shall be extended from bottom of the trench to at least 1
metre above the surface of the ground. The sides of the trenches which are 1.5
meters or more in depth shall be stepped back to give suitable slope or securely held
by timber bracing, so as to avoid the danger of sides to collapse. The excavated
materials shall not be placed within 1.5 mtrs of the edge of the trench or half of the
depth of the trench whichever is more. Cutting shall be done from top to bottom.
Under no circumstances undermining or under cutting shall be done.
7. Demolition- Before any demolition work is commenced and also during the
process of work:-
(a) All roads and open areas adjacent to the Works site shall either be
closed or suitably protected;
(b) No electric cable or apparatus which is liable to be a source of danger
over a cable or apparatus used by the operator shall remain
electrically charged;
(c) All practical steps shall be taken to prevent danger to persons
employed from risk or fire or explosion or flooding. No floor, roof or
other part of the building shall be so over-loaded with debris or
materials as to render it unsafe.
8. All necessary personal safety equipment as considered adequate by the
Engineer-in- Charge should be kept available for the use of the person employed on
the Site and maintained in a condition suitable for immediate use; and the Contractor
should take adequate steps to ensure proper use of equipment by those concerned.
(a) Workers employed on mixing Asphalted materials, Cement and lime
mortars shall be provided with protective footwear and protective
goggles.
(b) Those engaged in white washing and mixing or stacking of cement
bags or any materials which is injurious to the eyes shall be provided
with protective goggles.
(c) Those engaged in welding works shall be provided with Welder’s
protective eye shields.
(d) Stone breakers shall be provided with protective goggles and
protective clothing and seated at sufficiently safe intervals.
(e) When workers are employed in sewers and manholes, which are in
use, the contractor shall ensure that the manhole covers are opened
and are ventilated at least for an hour before the workers are allowed
to get into the manholes and the manholes so opened shall be
cordoned off with suitable railing, and provided with warning signals or
boards to prevent accident to the public.
(f) The Contractor shall not employment below the age of 18 and women
on the work of painting with products containing lead in any form.
Whenever men above the age of 18 are employed on the Work of lead
painting the following precautions should be taken: -
(i) No paint containing lead or lead products shall be used except
in the form of paste or ready-made paint.
(ii) Suitable face masks should be supplied for use by the workers
when paint is applied in the form of spray or a surface having lead
paint dry rubbed and scraped.
(iii) Overalls shall be supplied by the Contractors to the workmen
and adequate facilities shall be provided to enable the working
painters to wash during and at cessation of work.
9. When the Work is done near any place where there is risk of drowning all
necessary equipment’s should be provided and kept ready for use and all necessary
steps taken for prompt rescue of any person in danger and adequate provision
should be made for prompt first-aid treatment of all injuries likely to be sustained
during the course of the Works.
10. Use of hoisting machines and tackle including their attachments, anchorage
and supports shall conform to the following standard or conditions: -
13. These safety provisions should be brought to the notice of all concerned by
display on a Notice Board at a prominent place at the work spot. The persons
responsible for compliance of the Safety Code shall be named therein by the
Contractor.
14. To ensure effective enforcement of the rules and regulations relating to safety
precautions, the arrangements made by the contractor shall be open to inspection by
the Labour Officer, Engineer-in-Charge of the department or their representatives.
15. Notwithstanding the above clauses from (1) to (14) there is nothing in these to
exempt the Contractor, to exclude the operations of any other Act or Rules in force in
the Republic of India.
ANNEXURE – “C'
MODEL RULES FOR THE PROTECTION OF HEALTH AND SANITARY
ARRANGEMENTS FORWORKSMEN EMPLOYED BY
CONTRACTORS
1. Application - These rules shall apply to all the building and construction
Works in charge of BRO.
(b) ‘Large workplace’ means a place at which on an average 500 or more workers
are employed in connection with construction work.
(b) At large workplaces, where hospital facilities are not available within
easy distance of the Works, First-aid posts shall be established and be run by a
trained compounder.
(c) Where large workplaces are removed from regular hospitals, an indoor
ward shall be provided with one bed for every 250 employees.
(c) Every water supply of storage shall be at a distance of not less than
15 Metres from any latrine, drain or other source of pollution. Where water
has to be drawn from an existing well, which is within such proximity of latrine,
drain or any other source of pollution, the well shall be properly chlorinated
before water is drawn from it for drinking. All such wells shall be entirely
closed in and be provided with a trap door which shall be dust and
waterproof.
(d) A reliable pump shall be fitted to each covered well, the trap door shall
be kept locked and opened only for cleaning or inspection which shall be
done at least once a month.
(a) Adequate washing and bathing places shall be provided separately for
men and women.
(b) Such places shall be kept in clean and drained condition.
No. of Seats
(a) Where the number of persons does not exceed 50 2
(b) Where the number of persons exceeds 50 but does not exceed 100 3
(c) For every additional 100 3 per hundred
In particular cases the OC Contract shall have the power to vary the scale,
where necessary.
8. Latrines and Urinals for Women - If women are employed, separate latrines
and urinals screened from those for men and marked in the vernacular in
conspicuous letter "FOR WOMEN ONLY" shall be provided on the scale laid in rule
7. Those for men shall be similarly marked "FOR MEN ONLY". a poster showing the
figure of a man and women shall also be exhibited at the entrance of latrines for each
sex. There shall be adequate supply of water close to the latrines and urinals.
The Contractor shall at his own expense carry out all instructions issued to
him by the Engineer-in-Charge to effect a proper disposal of soil and other
conservancy work in respect of the Contractor's work people or employees on the
site. The contractor will bear the cost of any charge levied by the Cantonment
Authority for the execution of such Work on his behalf.
13. Creche - (a) At every workplace, at which 50 or more women workers are
ordinarily employed, there shall be provided two huts for the use of children under the
age of 6 years, belonging to such women, One hut shall be used for infant's Games
and Plan, and the other as their bed room. The huts shall not be constructed on a
lower standard than the following: -
(i) Thatched roofs (ii) Mud roofs and walls (iii) Plants spread
over mud floor and covered with mattings.
(b) Where the number of women workers is more than 25, but less than 50, the
Contractor shall provide at least one hut and one Dai to look after the children
of women workers. The size of crèche or crèches shall very according to the
number of women workers
(c) The Crèche or crèches shall be properly maintained and necessary
equipment like toys etc shall be provided
The huts shall be provided with suitable and sufficient openings for light and
ventilations. There shall be adequate provision of sweepers to keep the place clean.
There shall be two daises in attendance. Sanitary utensils shall be provided to the
satisfaction of the local Medical, Health and Cantonment Authorities. The use of the
huts shall be restricted to children, their attendants and mothers of the children.
14. Canteen: - A cooked food canteen on a moderate scale shall be provided
for the benefit of workers wherever it is considered expedient.
15. The planning, sitting and erection of the above buildings shall be approved by
the Engineer- in-Charge and the whole of such temporary accommodation shall at all
times during the progress of the works be kept tidy and in a clean and sanitary
condition to the entire satisfaction of the Engineer-in-Charge and at the contractor's
expense. The Contractor shall conform generally to the sanitary requirements of the
local Medical, health and Cantonment Authorities and at all times adopt such
precautions as may be necessary to prevent soil pollution of the Site.
1. GENERAL:
2. INSPECTION OF SITE:
The contractor shall have to make his own arrangements for land as
may be required by him for housing of his staff and labour and for erection of
stores sheds, office, godowns etc required by him for the work. The contractor
must ensure that the staff, labour, plants, equipments, machines, vehicles &
stores etc, employed or collected in connection with the work are so located
that there is no hindrance to the free flow of the traffic on the highway.
Suitable warning & sign boards and other measures are to be provided by the
contractor at his own cost, for safety of the traffic.
(a) The contractor shall pay wages not less than the fair
wage fixed from time to time by the State Govt. or minimum
wages fixed under the Minimum Wages Act by Central Govt.
5. ROYALTIES:-
(M/s )
6. BLASTINGROCKS- Blank
8. SECURITY RESTRICTIONS:
8.2 The contractor and his workmen shall observe all the rules
promulgated by the authority controlling the area in which work is to be
carried out e.g. prohibition of smoking, lighting, firm precautions, search of
persons on entry and exit, keeping to specified routes and restricted hours of
work etc. Thorough search of all persons and transport may be conducted by
the departmental authorities at the site of works at time and any number of
times for security reasons necessary permits etc to be obtained from Civil
authorities by the contractor, for himself, his staff and labour. Nothing shall be
paid extra on this account.
(b) (ii) The contractors shall within a reasonable time of his becoming
aware of variation in percentage rates and/or imposition of any further
“taxes directly related to contract value” give written notice thereof to
the OC stating that the same is given pursuant to this Special
Condition, together with all information relating thereto which he may
be in a position to supply. The contractors shall submit the other
documentary proof/information as the OC may require.
(b)(iii)The contractor shall, for the purpose of this condition keep such
books of account and other documents as are necessary and shall
allow inspection of the same by a duly authorized representative of
Govt and shall further, at the request of the OC contract furnish,
verified in such a manner as the OC may require, any documents so
kept and such other information as the OC may require.
Note :- The word Goods & Service Tax (GST) in the above clause
includes Central Goods & Service Tax (CGST), States Goods &
Service Tax ( SGST), Union Territory
Goods & Service Tax (UTGST) and Integrated Goods & Service Tax
(IGST) all as applicable.
12. SECURITY OFDOCUMENTS:
(a) The contractor shall furnish to the Engineer-in-charge a distribution return of his plant/
equipment on the site of works, stating the following particulars: -
Addition
since……………………………
Reduction since
……………………….
- (Signature of contractor)
Permanent Bench mark be fixed at any nearby safe location or considered from any existing
Permanent Building. RL be transferred and TBM be fixed at an interval of appx 200 mtr along
the existing alignment at safe place. This temp BM should remain intact till completion of the
work.
17 JOINTSURVEY:
Before commencement of the work, the contractor along with the rep of department/Engineer-
in- Charge/OC Contract, shall carryout detailed joint survey with total station.
Required L and X section of the existing road profile at an interval of 20 mtrs be verified.
Changes if any be incorporated in the X-sectional drawing provided with tender documents.
Details of fresh section be intimated duly signed by rep of contractor, OC Contract and
Engineer-in-Charge and Accepting Officer.
After completion of formation cutting, joint survey to be carried out with the help of Total Station.
L and X section be prepared at interval of 20 mtrs.
Volume of earth work to be computed with the help of survey details obtained before
commencement and after completion of work.
Records of the above survey details duly signed by rep of contractor, Engineer-in-Charge and
OC Contract be maintained by the contractor and copy of same be forwarded to OC Contract
and HQ CE(P).
Contractor must furnish the details of survey for release of RAR pertaining to earthwork.
18 Retrieved Material:
Hard rock encountered during the formation cutting and excavation shall become property of
the contractor after affording credit to Govt as specified here-in-after. Retrieved material of
Hard rock cutting shall be stacked neatly on specified ground as directed by Engineer- In-
Charge/OC Contract and no extra payment shall be made for stacking on ground. Credit for
retrieved hard rock @ Rs 400 /- per Cubic Mtr (to be specified by AO equal to prevailing market
rate of hard rock at site) shall be deducted from the bills of the contractor. In no case credit for
retrieved material shall be less than thirty three percent of hard rock cutting. Tested quality of
retrieved material may be incorporated in the work.
19 FOSSILS:
All fossils, coins, articles of value or antiquity, and structures and other remains or items of
geological or archaeological interest found on the site shall be placed under the care and
authority of the Employer. The contractor shall take reasonable precautions to prevent
contractor’s Personnel or other persons from removing or damaging any of these findings.
The contractor shall, upon discovery of any such findings, promptly give notice to
the Engineer-In-Charge / OC Contract, who shall issue instruction for dealing with it.
If the Contractor suffers delay and/or incurs cost from complying with the
instructions, the Contractor shall give a further notice the Engineer-In-Charge / OC
contract describing in detail the delay sustained by him and cost measured by him
for following the instructions of the Engineer-In-Charge/ OC Contract in dealing with
the fossils along with all supporting documents / proof, within 7 days of the
occurrence. The contractor then be certified for the following: -
An extension of time for any such delay, if completion is or will be delayed due to
such act in following the instructions of the Engineer-In-Charge / OC Contract.
Payment of any such cost, which shall be included in the contract price.
In case of any disputes, the matter shall be referred to the Accepting Officer whose
decision shall be final and binding.
(g) The time and progress chart to be prepared as per General Conditions
of Contracts shall consist of detailed network analysis and a time schedule.
The critical path network will be drawn jointly by the OC Contract and the
contractor soon after acceptance of the tender. The time scheduling of the
activities including a network for all preliminary arrangements for mobilization
of resources e.g. manpower, plant & machinery will be done by the
contractor, so as to complete the work within the stipulated time.
(h) On completion of the time schedule a firm calendar date schedule will be
prepared and submitted by the contractor to OC Contract who will approve it,
after due scrutiny. The schedule will be submitted in quadruplicate within six
weeks from the date of handing over the site.
(i) During the currency of the work the contractor is expected to adhere to
the time schedule and this adherence will be a part of the contractor’s
performance under the contract. During the execution of the work the
contractor is expected to participated in the review and updating of the
network undertaken by OC Contract. These reviews may be undertaken at
the discretion of the OC Contract either as periodic appraisal measures or
when the quantum of work ordered on the contractor is substantially changed
through deviation orders or amendments. Any revision of the schedule as a
result of the review will be submitted by the contractor to the OC Contract
within a week who will approve it after due scrutiny. The contractor will
adhere to the revised schedule thereafter. In case of the contractor’s not
agreeing to the revised schedule the same will be referred to the Accepting
Officer whose decision will be final, conclusive and binding. OC’s approval to
the revised schedule resulting in a completion date beyond the stipulated
date (s) of completion shall not automatically amount to grant of extension of
time. Extension of time shall be considered and decided by the appropriate
authority mentioned in condition 11 of General Conditions of Contracts and
separately regulated.
(k) No additional payments will be made to the contractor for any multiple
shift work or other incentive methods contemplated by him in his work
schedule even though the time schedule is approved by the department.
Contractor shall make his own arrangements for obtaining necessary permit
from local authorities for plying his vehicles for the work in accordance with
the Rules and regulations of the land.
(a) Unit rates shall be deemed to include the provisions for all materials,
stores, labour, process, operations and requirements detailed in particular
specifications/special conditions irrespective of whether these appear as
specific items or not in the Schedule “A”.
(b) Unit rates quoted shall also deemed to include all charges / expenses
on account of all Veh/Eqpt required for completing the work as specified in
Schedule “A”, GST, Sale Tax, Service Tax, Work Contract Tax, Octroi, 1%
labour welfare cess, social security cost to work force, Royalty, stacking of
materials, interstate barrier charges which are required for completion work
as per Schedule “A” / Work Order.
(c) The rate quoted shall also been include transportation of materials
required for completing the work including loading / unloading charges.
In the event of any dispute or difference between the parties hereto, such
dispute of difference shall be resolved amicably by mutual consultation or though the
good offices of empowered agencies of the Government. In the event of any such
dispute or differences relating to the interpretation and application of the provisions of
contracts where such resolution is not possible then the unresolved dispute or
difference shall be referred by either party to the Arbitration of one of the Arbitrators
in the department of public Enterprises to be nominated by the Secretary to the
Government or India In charge of the Bureau of Public Enterprises, and in such case
the Arbitration and Conciliation Act shall not be applicable to the arbitration under
the clause. The award of the Arbitrator shall be binding upon both the parties in the
dispute. Provided, however, any party, aggrieved by such award, may make a further
reference for setting aside or revision of the award to the Law Secretary, Department
of Legal Affairs, Ministry of Law & Justice, Govt. of India. Upon such reference the
dispute shall be decided by the law Secretary or the Special Secretary/Additional
Secretary when so authorized by the Law Secretary, whose decision shall bind the
parties finally and conclusively. The parties to the dispute will share equally the cost
of arbitration as intimated by the Arbitrator.
(c) 5% test check will be carried out by the Director before making
payment to the contractor.
(e) In case of discrepancies in arriving out work done details, the decision
of the Accepting Officer will be final and binding for both the parties.
(d) The Arbitrator shall give reasons for the award in each and every case
irrespective of the value of claims or counterclaims.
(e) The award of the arbitrator shall be final and binding on both the parties.
(f) The High Court at Shimla shall alone have jurisdiction to decide any
dispute arising out of or in respect of this contract.
28. BLANK
30. PAYMENT:
The Contractor will plan for supply and application of material on ground as soon as
possible, after the Work Order has been signed by the OC / Engineer – In Charge
Contract (which will be done within 30 days from the signing of Contract). 65% of the
BOQ Item Rate of Material Schedule A at site (brought by the contractor) will be made
immediately after the measurement by Engr-In-Charge/OC Contract and entry in MB.
Balance amount of the payment will be released after successful application of this
material on site in the proportionate manner as per progress of work on ground.
Commencement of any works at site and the start date shall be reckoned w.e.f. the
date of issue of Work Order by the OC Contract.
The contractor can submit the RAR once in 30 days, as per progress of work made on
the ground and payment shall be released through E-Payment mode, for which the
contractor is required to submit the NEFT/RTGS Mandate Form (enclosed at Appendix
‘A’) duly filled in the specified details.
Payment of RAR/Final bill will be made based on the rate quoted in Schedule “A” to the
Contractor after Standard Deductions as applicable. The retention money will be
cleared in the final bill and performance guarantee / bond will be released on
production of No claim/No demand certificate from the Contractor and OC Contract
respectively duly verified by AO TF after payment of Final Bill and completion of Defect
Liability Period.
Payment of the parties will be made in INR.GST, Sale Tax, Income Tax, VAT, Service
Tax, Work Contract Tax, Octroi, 1% labour welfare cess, Royalty, stacking of
materials, interstate barrier charges all other taxes in force by Central/ State Govt on
date of submission of tender which may have not been mentioned anywhere in this
tender document, which are required for completion work as per Schedule “A” / Work
Order shall be deducted at sources from the payment due to contractors as per
prevailing laws / statutory orders and TDS certificate shall be issued to the contractor.
All payments will be made by e-payment / account payee Cheque.
The Guarantee Bonds (s) or Fixed Deposit Receipt (s) shall be executed for a
period and on a form as directed by the Chief Engineer Project. The Contractor shall
further arrange to extend the period of Guarantee Bond(s) or fixed Deposit Receipt
(s) or shall furnish a fresh Guarantee Bonds(s) or Fixed Deposit Receipt(s) of similar
value so as to cover the period as stated above for its refund.
The contractor shall get himself registered with Astt Labour Commissioner,
Chandigarh as required under contract labour (Regulation and Abolition) Act, 1970. If
he does not fall within the purview of said act, he shall obtain a no objection
certificate from ALC Jammu to above effect. A copy of the certificate of Registration
or the no objection certificate (as the case may be) shall be submitted by him to the
Accepting officer within 15 days of the awarded of the work. In event of his non-
compliance, the contractor shall be liable for punitive action under CL (R&A)
Act1970.
38. LOSS OR DAMAGE ON ACCOUNT OF ENEMY ACTION
(a) If as result of enemy action, the contractor suffers any loss or damage,
the government shall reimburse to the contractor such loss or damages, to
the extent and in the manner herein after provided: -
39. REGISTRATION FEE / TRADE TAX. Tendered rates / amount shall also be
deemed to include the payment of all taxes to be like Registration fee. Trade Tax and
other taxes / levies to be paid to the Govt. of Himachal Pradesh or Central
Government already in force and as may be modified from time to time. The
contractor may ascertain full details on this respect from the concerned
department(s).
42 INCOME TAX Income Tax along with surcharge including education cess, will be
deducted at source as applicable.
44. REGISTRATION: Contractor is required to get his firm registered with GST,
Sales Tax Department and Asst Labour commissioner Shimla, Himachal Pradesh
under contract labour (R&A) Act and Building and other construction workers Act
1996. A copy of valid registration certificate issued will be submitted to Commander
Contract while processing RARs /Bills.
46. LEGALJURISDICTION
Legal jurisdiction for this Contract Agreement shall be High Court, Shimla only.
Note:- *Tenderers are advised to look over tender reference drawings as above before
expiry of clarification end date and pre-bid meeting.
Bank............................................
To,
ThePresident of India,
Sir,
1. With reference to Contract Agreement No........................... concluded
between the President of India, hereinafter referred to as “The Government”
andM/s..........................
Hereinafter referred to as the “The Contractor” for............................................... as
detailed in the above Contract Agreement hereinafter referred to as “the said
contract” and consideration of the Government having agreed to make an advance
payment in accordance with the terms of the said contract to the said contractor, we
the ............................................... bank, hereinafter call “the bank” hereby irrevocably
undertake and guarantee to you that if the said contractor would fail to provide work
in accordance with the terms & conditions of the said conditions of the said contract
for any reasons whatsoever or fail perform the said contract in any respect or should
whole or part of the said on account payments at any time become repayable to you
for any reasons whatsoever, we shall demand and without demur pay to you all and
any sum up to maximum of
`............................ (Rupees............................. only) paid as advance to the said
contractor in accordance with the provisions contained in clause. of the said
contract.
2. We further agree that the Government shall be the sole judge as to whether
the contractor has failed to provide works in accordance with the terms and
conditions of the said contract or has failed to perform the said contract in any
respect or the whole or part of the advance payments made to contractor has
become repayable to the Government and to the extent and monetary consequences
thereof by the Government.
3. We further hereby undertake to pay the amount due and payable under this
Guarantee without any demur merely on a demand from the Government stating the
amount claimed. Any such demand made on the bank shall be conclusive and
binding upon us as regards the amount due and payable by us under the Guarantee
and without demur. However, our liability under this Guarantee shall be restricted to
an amount not exceeding`.................
(Rupees. ................................ only).
4. We further agree that the Guarantee herein contained shall remain in full
force and effect for a period upto (03 months +due date of recovery of advance)
unless the Government in his sole discretion discharges the Guarantee earlier.
5. We further agree that any change in the constitution of the Bank or the
constitution of the contractor shall not discharge our liability here under.
6. We further agree that the Government shall have that fullest liability without
affecting in any way our obligations hereunder without our consent or knowledge to
very any of the terms and conditions of the said contract or to extend the time of
development / delivery from time to time or to postpone for any time or from time to
tome any of the powers exercisable by the Government against the contractor and
either to forebear or enforce any of the terms of conditions relating to the said
contract and we shall not be relieved from our liability by reasons of any such
variation or any indulgence or for balance shown or any act or omission the
Government or by any such matter or thing whatsoever which under the law relating
sureties would but for this provision have the effect of so relieving us.
7. We lastly undertake not to revoke the Guarantee during the currency of the
above said contract except with the prior consent of the Government inwriting.
Yours faithfully
Place................................
Seal of Bank
Date..................................
SCHEDULE -A
Project SLOPE STABILIZATION AND AVALANCHE PROTECTION AT KM 14.700 ON APPROACH ROAD TO SOUTH PORTAL (ARSP) UNDER
Name: PROJECT ROHTANG TUNNEL, CA No. CE (P) RTNL/03/2020-21
Sl.No: Item Description Quantity Unit BASIC RATE PER UNIT In Total
Figures To be entered by
the Bidder INCLUDING
Amount
ALL Taxes (Rs.)
1 Excavation in soil in hilly area by mechanical means including cutting and 29439 cum
trimming of side slopes and disposing of excavated earth with all lifts and
lead upto 1000 metres.
3 Providing & Backfilling behind reinforced soil wall with available backfill 3998 cum
material including all leads and lifts, including segregation, complete as
per drawing and technical specification (Reference to MoRT&H's
specification Clause 3100 and IRC:78 clause 710.1.4) & 2200. (Backfill)
4 Supplying and installation of Gabion facia unit with integrated tail as
secondary reinforcement of length 2m that is made of mechanically
woven, double twisted, hexagonal shaped wire mesh, Mesh type 10x12
as per IS 16014:2018, having D=100mm with tolerance of +/-10%, wire
dia ID/OD 2.7/3.7mm, (Zn +10%Al) + polymer coated, mechanically
edged/selvedged and shall have minimum 10 numbers of mesh openings
per meter of mesh perpendicular to twist, with partition at 1 m interval etc.
complete as per detailed technical specifications attached and as directed
by Engineer-in –Charge.
8 Supplying and laying drainage composite for use behind walls, between 2750 Sq.m.
two different fills, alongside and below drains of road, below concrete
lining of canals etc.having three dimensional composite with
thermobonding a draining core having “W” configuration in extruded
monofilaments of minimum thickness 7.2mm, with two filtering UV
stabilized polypropylene nonwoven geotextile of minimum thickness of
0.75mm charactersitic opening size (O90) of 110 micron and tensile
strength of 8.0 kN/m that will be working as separation or protecting layer,
Geocomposite having in plane flow capacity of 2.1 L / (m.s) at hydraulic
gradient of 1.0 & 20 kPa pressure and tensile strength of 18 kN/m, with
mass per unit area of 740 gsm, having minimum creep reduction factor of
1.15 for 100 years life at 100 kPa, at easily accessible location including
top and bottom, with all leads and lifts, manpower and machinery,
materials, labour etc. complete as per detailed technical specifications
and as directed by Engineer - In - Charge.
9 Supply and installation of Gabion units of 1 m height made of 1828 cum
mechanically woven, double twisted, hexagonal shaped steel wire mesh
as per IS 16014:2018, MORTH clause 2500 of required sizes, Mesh type
10x12 with mesh opening tolerances -10% to +10%, Mesh wire dia
2.7/3.7mm (ID/OD ), (Zn+10%Al + Polymer coated), mechanically edged/
selvedged ,with partition at 1 m interval and shall have minimum 10
numbers of mesh openings per meter of mesh perpendicular to twist,
tying with lacing wire of diameter 2.2/3.2 mm (ID/OD), placing at indicated
places in dry condition at easily accessible location as per direction of
Engineer including tools, plant, labour etc. complete in all respect,
carrying the material from nearest approach with all leads & lifts,
manpower & machinery, materials, labor etc. complete as per detailed
technical specifications and as directed by Engineer-In-Charge.
10 Supply and installation of 0.5 m thick Gabion mattress made of 1100 cum
mechanically woven, double twisted, hexagonal shaped steel wire mesh,
Mesh type 10X12 as per IS 16014:2018, Mesh wire dia 2.7 / 3.7 mm
(ID/OD ), (Zn+10%Al)+ Polymer coated, Mechanically edged/ selvedged,
with partition at 1 m interval , tying with lacing wire, placing at indicated
places in dry condition at easily accessible location as per direction of
Engineer including tools, plant, labour etc. complete in all respect,
carrying the material from nearest approach with all leads & lifts,
manpower & machinery, materials, labor etc. complete as per detailed
technical specifications and as directed by Engineer-In-Charge.
13 Providing and spreading High Resistance steel wire grid/mesh 3166 Sqm.
Geocomposite consisting of hexagonal double twisted wire mesh type
8x10 woven with steel wire with a diameter of 2.70 mm (EN 10223-3; EN
10218), Zn-5%Al coated (EN 10244 - class A), interlaced during
manufacturing in longitudinal and transversal directions with steel cable ,
grade 1770 MPa, having a diameter of 8 mm (EN 12385-4) Zl-5%Al
coated (EN 10244 - class A), at a spacing of less than 0.7 m, meeting the
minimum requirements:
including top and bottom support rope, lacing wire or rope required to
connect the nets and all accessories such as U-clamps, thimbles,
including safety, all other ancillary works, material, machinery, labour,
etc., with all leads and lifts and as per detailed technical specifications
and as directed by Engineer - In - Charge.
14 Supply and installation of three dimensional erosion control mat made of 24739 Sqm.
polypropylene polymer of minimum mass per unit area 450 gm / sqm
extruded on to a mechanically woven double twisted hexagonal shaped
steel wire mesh (as per EN 10223-3) made up of 2.7 mm dia having a
combined mass per unit area of the composite more than 2000 gm/sqm.
Steel wire and mesh type 8 x 10 having Zn-Al 5% coating as per EN
10244-2 longitudinally weaved with steel cable of 8 mm diameter at a
spacing of 2.0 m. Including all necessary accessories like U pins etc.
required for erosion control mats in place as per detailed technical
specifications and as directed by engineer in charge.
15 Providing and application of hydraulically applied erosion control products 26444 Sqm.
by means of hydroseeding/ hydromulching on the hill side and valley side
slope surface for erosion control by means of vegetation including
safety, all other ancillary works, material, machinery, labour, etc., with
all leads and lifts and as per detailed technical specifications and as
directed by Engineer - In - Charge.
19 Providing and placing drainage pipes behind the reinfiorced soil structure 500 RM
with perforated PVC pipe (lined with Non -woven Geotextile) of 160 mm
internal diameter by placing the perforated PVC pipe as per the drawings
etc. complete and as directed by Engineer -In -Charge.
20 Providing big size boulders of size more than 0.75m diameter designed 880 cum
as per IRC-89 to be placed in front of river side toe gabion wall and on top
of mattress (scour apron) as a protective layer from the impact of river
flow and debris.
21 Construction of PCC base for providing support below the reinforced soil 280 cum
structure
22 Construction of drains (berm drains, catch drains etc.) 1 m deep and 1 m 516 m
wide including excavation for drains and 0.2 m thick PCC/RCC lining of
M-15 grade concrete.
23 Providing and Installation of Flexible Snow avalanche mitigation units 120 Nos
made of cruciform shaped frame structure of height 4.25 m (minimum)X
3.40 m (minimum) of metallic beams in steel grade E275 or above
connected to steel tubular tieby flexible universal ball joint having
breaking load greater than 300 kN (along with 4/8 no.s of steel cable ties
to transfer the load from front facia to the tie) and having front facing steel
wire rope panel made of 8 mm diameter of mesh size 300 mm x 300 mm
with steel wire double knot connection at joint and mechanically woven
double twisted hexagonal shaped Zn coated wire mesh panel attached to
the cross-shaped frame and as per technical specifications and as
directed by Engineer-In-Charge.
Date:
PARTICULAR SPECIFICATIONS
SCOPE OF WORKS: -
Note Please attach a blank cancelled cheque for verification of the above particulars.
I, hereby, declare that the particulars given are correct and complete. If the
transaction is delayed or not effected due to incomplete or incorrect information of the
bank details, I will not hold the payment releasing authority responsible for it.
CERTITIFACTE BY
BANK
Certified that the particulars furnished above are correct as per our records.
I, the undersigned do hereby under take that our firm M/s__________________ agree to
abide by Terms and conditions of TENDER No. CE (P) RTNL/03/2020-21 for SLOPE
STABILIZATION AND AVALANCHE PROTECTION AT KM 14.700 ON APPROACH
ROAD TO SOUTH PORTAL (ARSP) UNDER PROJECT ROHTANG TUNNELfrom page
Notions advertised the CPPP site https://eprocure.gov.in/eprocure/app and it shall be
binding on us and may accepted at any time before the expiration of stipulated tender
conditions.
Title of Officer
Name of Firm
Date
TECHNICAL SPECIFICATIONS
1.1 Description
This work shall consist of furnishing, assembling, and filling mechanically
woven double twist hexagonal wire mesh gabions/gabion mattresses with
rock as specified in the contract to the dimensions, lines and grades shown
on the plans, or as determined by the engineer. These specifications are
mainly in accordance with Indian Standards IS 16014:2018, IRC SP 116
and MoRTH (Fifth Revision) 2013, Clause 2500 and specifications
mentioned in this section.
Lid
Diaphragm
End
Back
H
End
Front
L
W
Fig 1
1.2 Material- Gabion
1.2.1 Wire:
All tests on the mesh, lacing wire and selvedge wire must be performed
prior to manufacturing the mesh.
Tensile strength: The wire used for the manufacture of Mesh shall have a
tensile strength minimum 350 N/mm2 in accordance with IS 280. Wire
tolerances (Table 1) shall be in accordance with IS 16014:2018 (Class T1).
Elongation: Elongation shall not be less than 10%, in accordance with IS
16014:2018 and MoRTH (Fifth Revision) Clause 3100. Test must be carried
out on a sample at least 20 cm long.
1.2.2 Internal Connecting Wires:
Cross Ties/ stiffener wire: Diameter 2.2 mm, Zn coated wire with
Polymer coating, 3.2mm when measured with Polymer coating.
2
Mesh wire(mm) Selvedge wire (mm) Lacing wire(mm)
10X12 100mm 2.7/3.7 3.4/4.4 2.2/3.2
Figure (2)
1.2.6 Tolerances
Wire: wire diameter tolerance and minimum metallic coating (Zn-Al10%)
coating requirement shall be as per following table
Table (1)
Wire Diameter mm 2.2 mm 2.7 mm 3.4 mm
Wire Tolerance (+/-) mm 0.06 0.07 0.09
Minimum Qty of Metallic coating (gm per sqm) 240 260 270
3
3mx1mx.5m and 2mx1mx0.5m as shown in table of standard sizes
Tolerance in gabion dimensions of + 5% in all dimensions (length, breadth
and height) shall be allowed as tolerance for Gabion units.
1.2.8 Fabrication
Gabions shall be manufactured with all components mechanically
connected at the production facility. The front, base, back and lid of the
gabions shall be woven into a single unit. The ends and diaphragm(s) shall
be factory connected to the base. The lid may be a separate piece made of
the same type mesh as the basket. All perimeter edges of the mesh forming
the basket and top, or lid, shall be selvedge with wire having a larger
diameter.
Gabion is divided into cells by means of diaphragms positioned at
approximately 1m centres. The diaphragms shall be secured in position to
the base so that no additional lacing is necessary at the jobsite.
1.3 Construction Requirements
Gabion filling and lacing and erection at site should be strictly as per the
instruction of approved (by engineer) manufacturer’s instructions as per the
site-specific requirements.
1.3.1 Assembly
Gabions are supplied folded flat and packed in bundles. Larger units may be
supplied in rolls. The units are assembled individually by erecting the sides,
ends, and diaphragms, ensuring that all panels are in the correct position,
and the tops of all sides are satisfactorily aligned. The four corners shall be
connected first, followed by the internal diaphragms to the outside walls.
The procedure for using lacing wire consists of cutting a sufficient length of
wire, and first looping and/or twisting the lacing wire to the wire mesh.
Proceed to lace with alternating double and single loops through every
mesh opening, pulling each loop tight and finally securing the end of the
lacing wire to the wire mesh by looping and/or twisting. Refer figure 3.
Figure (3)
1.3.2 Installation
After initial assembly, the gabions are carried to their final position and are
securely joined together along the vertical and top edges of their contact
4
surfaces using the same connecting procedure(s) described earlier.
Whenever a structure requires more than one layer, the upper empty
baskets shall also be connected to the top of the lower layer along the front
and back edges of the contact surface using the same connecting
procedure(s) described in Section 1.3.1.
1.3.3 Filling
Rock for the Gabion facia shall be hard, angular to round, durable and of
such quality that they shall not disintegrate on exposure to water or
weathering during the life of the structure. The rocks shall range between
150 mm to 250 mm for 10x12 type mesh. Each range of sizes may allow for
a variation of 5% oversize rock by number of particles, or 5% undersize rock
by number of particles, or both. The size of any oversize rock shall allow for
the placement of minimum of three layers of rock must be achieved when
filling the 1 m high units and a minimum of two layers for the 0.50 m high
units. The rock used for filling the gabion facia shall have a minimum density
of 24kN/m3 and Los Angeles abrasion value not more than 45.
The facing section shall be filled with rock in a careful way to get good
horizontal and vertical alignment. During the filling operation skilled manual
stone placement is required to minimize voids. The maximum permitted
porosity of stone filling shall be 40%. For vertical or near vertical structures
the exterior of the basket may be carefully hand placed to give a neat, flat,
and compact appearance. Care shall be taken when placing fill material to
ensure that the sheathing on the Polymer coated baskets is not damaged.
The facing stones should orient in such a way to get their flat surfaces
facing to the front.
The cells shall be filled in stages so that local deformation may be avoided.
At no time shall any cell be filled to a depth exceeding 0.30 m higher than
the adjoining cell. It is also recommended to slightly overfill the baskets by
25 mm to 50 mm to allow for settlement of the rock.
1.3.4 Internal Connecting Wires installation
Internal Connecting Wires shall connect the exposed face of a cell to the
opposite side of the cell. An exposed face is any side of a gabion cell that
will remain exposed or unsupported after the structure is completed. Lacing
wire or prefabricated internal connecting wires shall be used as internal
connecting wires.
1.3.4.1 1 meter High Gabions
1 meter high gabions shall be filled in three layers, 300 mm at a time.
Connecting wires shall be installed after the placement of each layer, that is,
at 300 mm high.
5
250 mm at a time. Connecting wires shall be installed after the placement of
the first layer, which is at 250 mm high.
6
Polymer Coating Thickness: The thickness of the Polymer coating shall be
determined on a randomly chosen individual piece of wire removed from the
coil at 3 places 1 metre apart.
Measure with a micrometer the diameter of the galvanized steel wire with
Polymer coating. Determine the thickness of the Polymer coating by
stripping the Polymer coating from the wire and measure the reduced
diameter with a micrometer. The thickness of the coating is the difference
between the diameter of the galvanized steel wire with Polymer coating and
the measured diameter of the galvanized steel wire divided by two. The
thickness values should be as per clause 1.2.4. While removing the
Polymer coating by stripping, take care not to remove any of the metallic
surfaces.
7
Supply and placing of gabion facia with integrated tail as secondary
reinforcement for Reinforced soil system, made of Mechanically Woven
Double Twisted Hexagonal Shaped Wire Mesh per IS 16014:2018, IRC SP
116 and MoRTH (Fifth Revision) Clause 3100, Mesh Type 10x12, Zn+10%Al
alloy + Polymer coated Mesh Wire dia. 2.7/3.7mm (ID/OD), mechanically
edged / selvedged, with partitions at 1m interval, tying with lacing wire of
dia 2.2/3.2 mm (ID/OD).
1. Material
These units are fabricated soft flexible Zn + 10% Al with polymer coated
double twisted steel woven wire mesh units (Figure 1). The facing section of
the unit is formed by connecting the back panel and a diaphragm to the main
unit. This creates rectangular shaped cells used for stone confinement.
Figure (1)
2. Wire
All tests on the mesh, lacing wire and selvedge wire must be performed prior
to manufacturing the mesh.
Tensile strength: The wire used for the manufacture of Mesh shall have a
tensile strength minimum 350 N/mm2 in accordance with IS 280. Wire
tolerances (Table 1) shall be in accordance with IS 16014:2018 (Class T1).
Elongation: Elongation shall not be less than 10%, in accordance with IS
16014:2018 and MoRTH (Fifth Revision) Clause 3100. Test must be carried
out on a sample at least 20 cm long.
Zn+ 10% Al alloy coating: Minimum quantities of Zn+ 10% Al alloy shall be
as shown in Table 1 in clause 4 “Tolerences”.
8
Adhesion of Zn+ 10% Al alloy coating: The adhesion of the Zn+ 10% Al
alloy coating to the wire shall be such that, when the wire is wrapped ten
turns around a mandrel having four times the diameter of the wire, it does
not flake or crack when rubbing it with the bare fingers in accordance with
IS 4826:1979.
9
a. Reinforced gabion facia shall be unfolded on the plain ground.
b. Any shrink in the unfolded Gabion Mesh shall be removed, by
stretching the Mesh panel.
c. Marking on the ground shall be made from the Centre of the twist of
one mesh and the second. Marking shall be done at 1 m distance.
d. The number of mesh Openings in the 1 m shall be counted &
verified.
4. Tolerances
Wire: The wire shall meet diameter tolerance and minimum Zn+10%Al
coating requirement mentioned in the following table
Gabion facia and tail unit tolerance: ± 5 % on the length, width, and height.
Table (1)
Wire Diameter mm 2.2 mm 2.7 mm 3.4 mm
Wire Tolerance (+) mm 0.06 0.07 0.09
Minimum Qty of Zn+ 10% 240 260 270
Al alloy (gm/m2)
5. Standard size
Gabion facia and tail with double hexagonal mesh units shall have the
following dimensions
Length of reinforcement (B), Width (L), m Height (H), m
m
3 2/3 0.5
3 2/3 1.0
10
6. Fabrication
Gabion facia and tail with double twist hexagonal mesh units shall be
manufactured with all components mechanically connected at the production
facility. The external face, reinforcing panel, and lid of the unit shall be woven
into a single unit. The ends, back, and diaphragm shall be factory connected
to the base. All perimeter edges of the mesh forming the basket shall be
selvedge with wire having a larger diameter.
The facing element of a Gabion facia and tail with double twist hexagonal
mesh unit is divided into two cells by means of a diaphragm positioned at
approximately 1 m centres. The diaphragm shall be secured in position to the
base so that no additional lacing is necessary at the job-site.
8. Construction Requirements
i. Assembly
Gabion facia and tail with double twist hexagonal mesh units are supplied
folded flat and packed in bundles. The facing section of the units are
assembled individually by erecting the sides, back, ends, and diaphragm,
ensuring that all panels are in the correct position, and the tops of all sides
are aligned. The four corners of the basket shall be connected first, followed
by the internal diaphragm to the outside walls. All connections shall be made
using lacing wire or ring fasteners.
The procedure for using lacing wire consists of cutting a sufficient length of
wire, and first looping and/or twisting to secure the lacing wire to the wire
mesh. Proceed to lace with alternating double and single loops through every
mesh opening approximately every 150 mm pulling each loop tight and finally
securing the end of the lacing wire to the wire mesh by looping and/or
twisting. Refer Figure 3.
11
Figure (3)
The use of ring fasteners shall be in accordance with the manufacturer’s
recommendations.
12
iv. Placement of the Structural Backfill
The soil reinforcement mesh panel should be unfolded; the shipping folds
flattened out, and pulled tight to minimize further creep age. Prior to starting
this operation, a filter geotextile shall be placed at backfill interface. The
geotextile should have a 250 cm return at both top and bottom.
v. Lid Closing
Once the baskets are completely full, the lids shall be pulled tight until the lid
meets the perimeter edges of the basket. A tool like a lid closer can be used.
The lid must then be tightly laced and/or fastened along all edges, ends, and
tops of diaphragm(s) in the same manner as described in the above sections.
9. Method of Measurement
Quantities shall be determined from cross sections and the linear distance,
and paid for under the appropriate bid items.
The quantity to be paid for “gabion facia and mechanically woven, double
twisted, hexagonal shaped Zn+10%Al alloy coated steel wire mesh integrated
tail as reinforcement” shall be the number of units measured in their final
position. Project conditions and design will determine the actual size of units
to be used.
The bid price shall include the in place cost of all materials, equipment, and
labour, including gabion facia and integrated tail mechanically woven, double
twisted, hexagonal shaped Zn+10%Al alloy coated steel wire mesh tail as
13
reinforcement.
11. Testing
The material should get approval from the client before the actual supply
start. The manufacturer of the Gabion facing unit should provide
“Manufacturers Test Certificate’ for the material with every lot/shipment.
Tensile strength test and Zn+10%Al alloy coating test on basic wire shall be
done on one sample per every 10,000 numbers of units supplied.
14
c. Sample shall be loaded on the UTM in a direction parallel to twist, with
the samples being gripped at the two selvedged wires & not mesh
twist.
d. The distance between the two selvedge wires shall be recorded as
Initial gauge length.
e. Distance between the two end gripping points (pins) along the width of
the sample shall be recorded as the unit width under test. The width
shall be at least 700 mm.
f. The load shall be applied gradually to the sample and the test be
continued till the break point.
g. The peak load and the % elongation shall be recorded.
h. The strength of the selvedge connection shall be (peak load/unit width
under test) expressed in kN/m.
NB. If the sample slips at any of the gripping point during the test, such a test
shall be discarded, and a new sample shall be taken.
15
Technical Specifications for providing and laying Geocomposite as
subsurface drain
Scope of Work
The specification covers a set of minimum physical and mechanical properties
that must be met by geocomposite. This specification also covers the
requirements of testing, handling and placing of geocomposite over the prepared
surface.
Material
The Geocomposite realized by Thermo bonding a draining core in extruded
monofilaments (GMA) with two filtering nonwoven geotextile and cores of “W”
configuration of longitudinal parallel channels shall be used. The drainage
composite shall compile to IRC 34 and MORTH specifications section 700. The
drainage core shall be made of polypropylene UV stabilized by carbon black and
made by extruded monofilaments set in longitudinal parallel configuration and the
external geotextile shall be made of polyethylene or Polypropylene or polyester
or similar fibres manufactured through machine made process of heat bonding or
needle punching techniques. The Values of Geocomposite shall be as shown in
Table 1.
Table 1 Properties of Drainage Composite
A) Geocomposite
Thickness at 2 kPa mm 7.2 EN 9863-1
Mass per unit area g/m2 740 EN ISO 9864
Tensile Strength MD* kN/m 18 EN ISO 10319
B) External Filter
Tensile Strength MD & CD kN/m 8 EN ISO 10319
Static Puncture Resistance N 1400 EN ISO 12236
Dynamic Puncture Resistance mm 33 EN ISO 13433
Flux perpendicular to plane l/(m2.s) 100 EN ISO 11058
Apparent Opening Size, O90 micron 110 EN ISO 12956
16
C) Drainage Core
Mass per unit area g/m2 500 EN ISO 9864
Method of measurement
Quantity of geocomposite shall be determined from cross sections and the linear
distance and paid for under the appropriate bid items.
Method of Testing
The supplier has to submit a Quality conformity certificate and Manufactures test
certificate for the parameters indicated in Table 1 for every lot/shipment.
Basis of Payment
Accepted geocomposite shall be paid for at the unit price (per square meter
area) for each pay item included in the contract.
17
PROVIDING AND LAYING NON WOVEN GEOTEXTILE TYPE III as per MORTH
(Fifth Revision) Clause 700 AS FILTER MEDIA BEHIND REINFORCED SOIL
WALL / GABION WALLS / AROUND PERFORATED PIPES
Material
The Nonwoven thermally bonded or needle punched or any equivalent geotextile
shall be used. The geotextile shall be made of polyester or similar fibres
manufactured through machine made process of heat bonding or needle punching
techniques. The Values of Geotextile shall be as shown in Table 1.
Table 1) Properties of Non-Woven Geotextile
PROPERTIES: Value Test Method
Mechanical Properties:
Method of Testing
The supplier has to submit a Quality conformity certificate for the parameters
indicated in Table 1 for every lot/shipment.
Basis of Payment
Accepted filter geotextile shall be paid at the unit price (per square metre area) for
each pay item included in the contract.
18
PROVIDING AND LAYING HIGH STRENGTH FLEXIBLE GEOGRIDS AS
PRIMARY SOIL REINFORCEMENT OF COMPOSITE SOIL REINFORCEMENT
SYSTEM
Material
The primary soil reinforcement shall be high strength flexible geogrid with a high
quality coating like LDPE or equivalent specification. Latex or PVC coating or
geotextile shall not be permitted. The selection of the geogrid need to be strictly
based on the long term design strength values for a design life of 120 years at 20°C.
The primary soil reinforcement shall conform to MORTH specifications: section 700
and 3100 and shall meet the minimum requirements as given in table 1.The Ultimate
tensile strength values indicated in table 1 are short term, which needs to be
reduced to long term strength for design purpose by applying suitable partial
material factors or reduction factors (RF) as explained in clause 2.2 . The selection
of the geogrid need to be strictly based on the long term design strength values for a
design life of 120 years at 20°C.
NOTE:
Tensile strength per metre should be based on tests performed as per ISO 10319
test procedure.
19
RF = Reduction factor
RFCR = Reduction factor for creep
RFID = Reduction factor for the effect of installation damage
RFW = Reduction factor for weathering
RFCH = Reduction factor environmental degradation (chemical and biological)
at the service temperature
FS = Reduction factor related to the mass of information available and to the
production quality.
The adoption of reduction factors should be strictly based on reliable test data
and performance data available with the manufacturer from accredited
independent agency or the manufacturer should provide a valid third party
accredited certification like BBA (British Board of Agreement) certifying the
Reduction Factor (RF) value for their geogrid for design temperature of 20°C
and design life of 120 years. Manufacturer should have creep test data from
independent accredited laboratory for period over 10 years at design
temperature of 20°C.
20
6. The run of primary soil reinforcement should be reasonably straight and all
elements should be flat and not twisted. No undulations in the geogrid
should be evident.
7. There shall not be any active connection between primary soil
reinforcement and secondary soil reinforcement by means of joining. The
stress transfer shall happen by the frictional interaction between the
primary and secondary soil reinforcement. For this, a minimum overlap
length of 3m shall be provided between the primary and secondary soil
reinforcement. (Figure 1).
8. Minimum overlap of 10cm shall be provided between two adjacent rolls of
the primary soil reinforcement geogrid, as shown in the figure below.
Joining of different rolls in tensile stress direction of the structure shall not
be permitted.
Tensile strength test shall be done on one sample per every 20,000 sqm of
geogrid supplied. Manufacturer of the geogrid should provide “Manufacturers
Test Certificate” for the tensile strength of geogrid elements.
In case of failure of any test /or contractor desire to source material from more
than one manufacturer, the cost of visit in respect of additional source or visit
for retesting by client and consultant shall be borne by Contractor. The cost of
Airfare to & fro, Lodging& Boarding, shall be borne by contractor. It is not
advisable to use geogrids of different characteristics and inherent material
properties together and that should not be allowed.
21
Figure 1: Plan Detail showing overlap Length between Primary Soil
reinforcement & secondary reinforcement
Method of Measurement
Quantities of primary soil geogrid reinforcement shall be determined from
cross sections and the linear distance of the structure. The measurement
shall be in square meters for different grades of geogrid, measured in their
final position in plan area. Site specific design and material availability will
determine the actual grade of geogrid to be used.
Basis of Payment
Accepted primary soil geogrid reinforcements will be paid per square meter
quantity of various grades for each pay item included in the contract.
22
SPECIFICATION FOR HIGH RESISTANCE STEEL WIRE GRID/MESH
GEOCOMPOSITE
The High Resistance Steel wire grid/mesh geocomposite shall be certified with a
valid ETA (European Technical Assessment) based on EAD 23008-00-0106 with CE
marking and shall meet the minimum requirements of Mechanically woven double
twisted (DT) hexagonal shaped Class A Zn+Al5% Coated wire interlaced with 8mm
steel wire rope during manufacturing in longitudinal and transversal directions as per
IRC Highway Research Board Special Report-23 or equivalent specifications.
Material Specifications:
The High Resistance Steel wire mesh geocomposite shall be mechanically pre-
fabricated to become a uniform hexagonal woven wire mesh wherein joints are
formed by twisting each pair of wires through two half turns commonly known as
Double Twisted, in such a manner that unraveling is prevented. The longitudinal
selvedge steel ropes and the intermediate steel ropes of 8mm are inserted during
the process of manufacture in order to form a cohesive and monolithic geocomposite
product or equivalent specifications.
All steel wires used in the manufacturing of High Resistance Steel wire mesh
geocomposite and in the lacing operation during construction shall confirm to EN
10223 – 3. The wire used for the manufacture of double twisted wire mesh shall
have a tensile strength in the range of 380-500 N/mm2 and elongation shall not be
less than 10%. Test must be carried out on a sample of at least 25 cm length. DT
mesh shall confirm properties indicated in table below. All tests on the mesh and
lacing wire rope must be performed prior to manufacturing the mesh.
Table – Required Properties of Mechanically Woven DT shaped mesh
Property Value
Mesh Type 8 x 10
Mesh Opening “D” (mm) (maximum) 80
Tolerance – Mesh Opening (%) +16 to - 4
Mesh Wire Diameter (mm) 2.7mm
Tolerance- Mesh Wire Diameter (+/-) 0.07
(mm)
Mesh Wire Zinc-Al alloy Coating 240 min
(gm/sqm)
23
Table – High Resistance Steel wire mesh Geocomposite should meet the
following minimum strength requirements:
Sr. Strength Parameter Value
No.
01 Wire rope spacing in Longitudinal and Transversal 0.70m (maximum)
directions
02 Longitudinal and Transversal Tensile Strength of High 85 kN/m
Resistance steel wire mesh Geocomposite
03 Punch Resistance of High Resistance steel wire mesh 180kN at maximum
Geocomposite displacement of 50
cm
The longitudinal and transversal steel ropes should meet the requirement as per IS
2266 / ISO 2408/ EN 12385-2 2008 / EN 12385-4 2008 and have a nominal
diameter of 8.00 mm. They shall be made from galvanized (Zn-Al alloy) steel in
accordance with 10244-2. The rope shall be of grade 1770 N/sq mm and with a
minimum breaking load of the rope as 40 KN. The longitudinal and transversal steel
ropes shall be spaced at maximum spacing of 0.7m c/c. Tensile test & zinc mass
test on steel ropes must be performed prior to manufacturing the High Resistance
steel wire mesh geocomposite or equivalent specifications.
The diameter of the lacing wire rope shall be of required diameter as suggested by
the supplier but shall not be less than 8 mm and shall have same characteristics as
the mesh wire rope. Typically, lacing wire rope is supplied at 3% of the total weight
of High Resistance Steel wire mesh geocomposite to enable the lacing to be
undertaken in an adequate manner. Alternatively, if required as per site conditions
and suggested by the Manufacturer, lacing wire ropes or lap links could be used for
joining of adjacent nets.
Installation Method:
The rolls of DT wire mesh high resistance composite should be rolled down the
surface from Top anchoring system as per the contract drawings. New Roll shall be
placed side by side of adjacent roll in the same manner such that longitudinal ropes
of both the rolls can be laced together by hand. Lap links can also be used as an
alternate to Lacing wire. The lap links are installed at every alternate location of
double twisting on DT wire mesh high resistance geo composite. Lacing shall
commence by twisting end of the lacing wire rope tightly between the two selvedges.
24
It shall then pass round the two edges being joined by passing through mesh
opening. The lacing wire rope shall be securely tied off at the bottom of the roll. Lap
links can also be used as an alternative to Lacing wire. The lap links are installed at
every alternate location of double twisting on DT wire mesh high resistance geo
composite. The bottom anchoring and surficial anchoring shall be done as per the
contract drawings.
25
Mode of Measurements : The mode of measurement shall be based on Sq.m of
Area of High Reistance Steel Wire Mesh Geocomposite supplied.
Three dimensional erosion control mats made of polypropylene polymer of
minimum mass per unit area 450 gm / sqm extruded on to a mechanically
woven double twisted hexagonal shaped steel wire mesh (as per EN 10223-3)
made up of 2.7 mm dia steel wire and mesh type 8x10 having Zn-AI 5%
coating conforming to EN 10244-2 longitudinally weaved with steel cable of 8
mm diameter at a spacing of 1 m including all necessary accessories like U-
Pins etc. required for fixing the erosion control mats in place {testing
procedures and technical specifications of erosion control mats shall conform
to Table 700-14 and clause 706 of MORTH Specifications for Road & Bridge
works (fifth revision)}
1.1.1 The synthetic mat reinforced with double twisted hexagonal steel wire mesh
shall meet the minimum requirements of polypropylene mono filament heat bonded
mat mainly mass per unit area, thickness, mesh type, wire diameter and coating as
specified in this document.
Synthetic mat shall be manufactured in a standard width of not less than 2m and
in roll length of 25m having tolerance limits of +/-5% in width & -0/+1% in length.
Type Roll Length (m) Roll Width (m) Roll area (Sq.m)
Synthetic Mat 25 2 50
27
1.5 Performance Criteria
Along with the bid, the manufacturer/authorized bidder shall provide the Test
certificates if required as per tender documents from independent Laboratories /
reputed agencies to demonstrate that the hexagonal steel wire mesh used to
reinforce the high strength reinforced polymeric geo-composite erosion control
mat have a minimum mechanical strength of 70 kN/m and Ultimate punching force
of 80 kN or equivalent specifications.
28
TECHNICAL SPECIFICATIONS FOR SELF DRILLING ANCHORS (SDA)
The SDA shall be designed and arranged in order to stabilize insitu strata. The grout
shall be made of OPC grade 43 (or more) with suitable admixtures.
Installation guideline
1) The SDA is driven in the required position with help of sacrificial drill bit at the
bottom of the anchor bar which facilitates in drilling the hole. The diameter,
length and spacing of SDA shall be as specified. Anymore / lesser length or
spacing of anchoring/nailing shall be carried out as per site condition and as
directed by engineer-in-charge.
2) The grout is pumped through the hollow bar during the drilling process. Grouting
shall be done by using OPC grade 43 (or higher) along with addition of suitable
admixture. Mixing shall be done along with potable water so as to form the
cementitious paste.
3) The base plates of size (min.) 200mm x 200mm x 10 mm shall be placed at rock
interface for tightening the nuts.
4) The fascia (if applicable) shall be installed in front and connected to the steel
rods with base plate and nuts.
1) Grout agitator
2) Compressor – 450 to 600CFM
3) Drilling equipment percussion/rotary type
Basis of Payment
The measurement and payment of SDA shall be at the unit price (per running meter
length) for each pay item included in the contract.
29
Perforated Drain Pipes Lined with Non-Woven Geotextile
General:
The subsurface PVC drain pipes of diameter minimum 50mm (internal), minimum
6kg/cm pressure and wall thickness of 2.2mm shall be provided. These pipes shall
be perforated (top half portion) and shall have a filtering geotextile on the outer
surface to avoid the obstruction by the fine soil particles. The nonwoven geotextile
should be needle punched or thermally bonded or any equivalent geotextile of
tensile strength of 5 kN/m (MARV Value) shall be used. The geotextile shall be
made of polyester or polypropylene manufactured through machine made process.
The pipe shall be inserted in the slope inclined upwards from 5° to 15°.The hole is
drilled into the slope with dimeter from 130 to 150 mm, and they can be realized with
dry drilling, with or without temporary sheeting of the hole. Once the drilling is
complete the pipe (which can be smooth or grooved) is inserted. Once the pipe is
fully inserted, the lower part of the hole (on the slope face side) is sealed with the
use of cement grout.
Figure : Double twisted hexagonal coated steel wire mesh with welded panel and
nonwoven biodegradable mat
2. Wire
All tests on the mesh, lacing wire and reinforcing steel rod must be performed prior to
manufacturing the mesh.
Tensile strength: The wire used for the manufacture of Mesh shall have a tensile
strength minimum 350 N/mm2 in accordance with IS 280. Wire tolerances (Table
1) shall be in accordance with IS 16014:2012 (Class T1).
Elongation: Elongation shall not be less than 10% in accordance with
IS 16014:2012. Test must be carried out on a sample at least 20 cm long .
3. ZN+10%Al coating
Zn+ 10% Al alloy coating: Minimum quantities of Zn+ 10% Al alloy shall be as
shown in Table 1 in clause 5.1.
Adhesion of Zn+ 10% Al alloy coating: The adhesion of the Zn+ 10% Al alloy
coating to the wire shall be such that, when the wire is wrapped ten turns
around a mandrel having four times the diameter of the wire, it does not flake
or crack when rubbing it with the bare fingers in accordance with IS 4826:1979.
4. Polymer Coating
5. Tolerances
5.1 Wire: The wire shall meet diameter tolerance and minimum ZN+10%Al
alloy coating requirement mentioned in the following table
Wire Diameter mm 2.2 mm 2.7 mm 3.4 mm
Wire Tolerance(+)mm 0.06 0.06 0.07
Minimum Qty of Zn+ 10% Al 230 245 265
alloy (gm/m2 )
6.2 Woven steel wire double twist hexagonal mesh with welded
wire panel unit:
± 5 % on the length, width, and height.
3 to 7 2 0.63 45
3 to 7 2 0.76 60
3 to 7 2 0.80 65
11. Fabrication
Woven steel wire double twist hexagonal mesh with welded wire panel units shall be
cut and pre-assembled at the production facility. The double twist hexagonal mesh
shall be present as tail, facia and top woven steel wire into which, welded wire panel,
erosion control blanket and performed steel bracket are attached as a pre-assembled
unit. Horizontal reinforcing steel rods shall be placed in the double twist of the front
face of the unit, spaced approximately every 162 mm. The welded wire panel shall
be factory connected to the base unit. Reinforcing steel brackets and erosion control
blanket shall be furnished attached within the packaged units.
The procedure for using lacing wire consists of cutting a sufficient length of
wire, and first looping and/or twisting to secure the lacing wire to the wire mesh.
Proceed to lace with alternating double and single loops through every mesh
opening approximately every 150 mm pulling each loop tight and finally
securing the end of the lacing wire to the wire mesh by looping and/or twisting.
Refer Figure 3.
Following assembly of the facing section the reinforcing panel shall be unfolded
to the required length and the shipping folds removed. Folds can be removed
by placing the fold over a 50 mm x 100 mm board and walking along the sides.
13.3 Installation
Prior to installing the assembled units, the foundation on which the woven steel
wire double twist hexagonal mesh with welded wire panel units are to be placed
shall be cut or filled and graded to the lines and grades shown on the
construction drawings. Surface irregularities, loose material, and vegetation
shall be removed during the preparation of the foundation. Units are carried to
and placed in their final position and the facing is raised. Facia of adjoining
units must be securely joined together, along the facing and top edges of their
contact surfaces. Reinforcing panel of adjacent units should be connected at
every 1m interval to avoid movement during backfilling. Whenever a structure
requires more than one layer of units, the upper unit shall also be connected to
the top of the lower layer.
13.7 Vegetation
Bioengineering techniques are to be adopted in the site to develop vegetation.
The methods of vegetation shall be insertion of live branches, live staking, and
planting creepers having long roots. A local horticulture expert should be
consulted to select the appropriate live stake and for vegetation methods. The
selection of the species should be done according to the local climate
variations. It is preferable to chose vegetation already existing near to the site.
Soil bioengineering techniques with woody types of vegetation need to be
developed in maximum area due to their deep root system development. Seeds
of local plants shall be scattered on the facia or mixed with the vegetative soil.
Hydro seeding techniques may also be used on selected areas with high
moisture content. Live stakes suitably selected by a local horticulture expert
should be horizontally placed between the facia units at 1.5m c/c.
14. Testing
The material should get approval from the client before the actual supply start. The
manufacturer of the Gabion facing unit should provide “Manufacturers Test
Certificate’ for the material with every lot/shipment.
Tensile strength test and Zn+10%Al alloy coating test on basic wire shall be done
on one sample per every 10,000 numbers of units supplied.
14.1 POLYMER Coating Thickness:
The thickness of the polymer coating shall be determined on a randomly chosen
individual piece of wire removed from the coil at 3 places 1 meter apart. Measure
with a micrometer the diameter of the galvanized steel wire with polymer coating.
Determine the thickness of the polymer coating by stripping the polymer coating
from the wire and measure the reduced diameter with a micrometer. The thickness
of the coating is the difference between the diameter of the galvanized steel wire
with polymer coating and the measured diameter of the galvanized steel wire
divided by two. The thickness values should be as per clause 4. While removing
the polymer coating by stripping, take care not to remove any of the metallic
surfaces.
1.1 SUMMARY
1.2 SUBMITTALS
A. Product Data: Submit manufacturer’s product data and installation instructions. Include
required substrate preparation, list of materials and application rate.
B. Certifications: Manufacturer shall submit a letter of certification that the product meets or
exceeds all technical and packaging requirements.
2. PRODUCT
2.1 MATERIALS
PROPERTIES: The Biotic Soil Media BSM shall conform to the following property values when
uniformly applied at a rate of 3,920 kilograms/hectare under laboratory conditions.
1
2.2 COMPOSITION
All components of the BSM shall be pre-packaged by the manufacturer to assure both
material performance and compliance with the following values. No chemical additives with
the exception of fertilizer, soil neutralizers and bio-stimulant materials should be added to this
product.
2.3 PACKAGING
3. EXECUTION
A. Soil Samples shall be taken and sent to a third-party, independent lab for analysis.
C. The soil testing methods used shall be compliant with recognized agronomic testing
standards, for revegetation of disturbed sites.
1. Soil pH
2. Soluble Salts
3. Excess Carbonate
4. Organic Matter
5. Nutrient readings for:
i. Nitrogen, Phosphorus, Potassium
ii. Magnesium, Calcium, Sodium, Manganese, Copper, Sulfur, Zinc,
Copper, Iron, Boron
6. Cation Exchange Capacity
7. Percent Base Saturation Sodium
Optional Hydraulically Applied erosion control Products - equal or higher specification of High
Performance Flexible Growth Medium (HPFGM) or Extended Term Flexible Growth Medium
(ET-FGM) or Engineered Fibre Matrix (EFM) or Hydraulic Mulch (HM) with/without tack - shall
be added as per their recommended application rate & specifications or equivalent
specifications, Other Soil Amendments like Bio-Prime for slow release / rejuvenates, Jump
Start to accelerate germination and establishment, Soil PH Modifiers – equal or higher
specifications of Aqua- pHix or Neutra Lime and other amendments shall also be applied with
the hydro-seeding slurry at Manufacturer recommended rates based on soil test results.
2
3.3 VEGETATION SPECIES SELECTION
A. Once soils have been analyzed for agronomic potential and amendment recommendations,
selection of suitable plant species for achieving sustainable growth and effective erosion
control shall be determined by a qualified seed supplier, consulting professional and/or
regulatory agency.
B. Site and project specific information considered for species selection shall include:
A. Examine substrates and conditions where materials will be applied. Apply product to
geotechnically stable slopes that have been designed and constructed to divert runoff
away from the face of the slope. Do not proceed with installation until satisfactory
conditions are established.
3.5 INSTALLATION
3
B. For Revegetation: To ensure proper application rates, measure and stake area.
For best results, allow BSM to dry slightly prior to application/installation of erosion control
products; more rapid drying will occur when temperatures exceed 60°F (15°C).
Drying times may be accelerated in high temperature, low humidity conditions with product
applied on dry soils. Use caution to insure overspray of hydraulic erosion control product
does not cause movement of the BSM. When installing rolled erosion control products
over BSM, take caution to minimize disturbance of the treated surface and avoid
excessive foot traffic.
1. Fill mechanically agitated hydroseeder with water to at least 1/3 of displacement. Turn
pump on and thoroughly purge pump and pre-wet lines. Turn pump off.
2. Turn agitator on and load low density materials first (i.e. seed).
3. Continue slowly filling tank with water while loading BSM and soil amendments.
4. Consult application and loading charts to determine number of bags to be added for
desired area and application rate. Mix at a rate of 45.4 kg/379 litres(Approx) in machines
equipped with gear or positive displacement pumps and 34.0 kg/379 litres(approcx) in
machines with centrifugal pumps. Contact Equipment manufacturer to confirm optimum
mixing rates.
5. All BSM should be completely loaded before water level reaches 75% of the top of tank.
6. Add fertilizer and other heavier materials and continue mixing.
7. Top off with water and mix until all material is fully broken apart and hydrated (minimum of
10 minutes — increase mixing time when applying in cold conditions). This is very
important to allow the BSM to fully hydrate.
8. Shut off recirculation valve to reduce potential for air entrainment within the slurry.
9. Slow down agitator to very low speed and start applying with optimum nozzle.
10. Spray in opposing directions for maximum soil coverage.
11. Return to water source as quickly as possible to purge pump and lines, then repeat mixing
and application process.
D. Typical Application Rates: These application rates are for standard conditions.
Designers may need to increase application rates on rough or rocky surfaces based on
actual site conditions.
Hydraulically applied erosion control products may be applied over the soil surface prior to the
installation of Rolled erosion control products or Erosion Control Blankets, wherever
applicable or as specified.
4
3.6 CLEANING AND PROTECTION
A. After application, thoroughly flush the tank, pumps and hoses to remove all material. Wash
all material from the exterior of the machine and remove any slurry spills. Once dry,
material will be more difficult to remove.
B. Clean spills promptly. Advise owner of methods for protection of treated areas. Do not
allow treated areas to be trafficked or subjected to grazing.
B. Initial inspections shall insure installations are in accordance with the project plans and
specifications with material quantities and activities fully documented.
5
Hydraulically-applied, 100% biodegradable, High Performance-Flexible Growth Medium (HP-
FGM) that is composed of 100% recycled, thermally refined (within a pressurized vessel) virgin
wood fibers, crimped interlocking biodegradable fibers, mineral activators, naturally derived
crosslinked biopolymers and water absorbents along with standard prescriptive agronomic
formulations such as soil pH modifiers, bio stimulant materials including Prime & seeds which
are hydraulically applied for erosion control over slopes
General
MATERIALS
The HP-FGM shall conform to the following property values when uniformly applied at a rate of 3,900
kilograms/hectare under laboratory conditions.
NOTE:
1. ASTM test methods developed for Rolled Erosion Control Products and have been modified to
accommodate
1
PROPERTIES: The Biotic Soil Media BSM shall conform to the following property values when
uniformly applied at a rate of 3,920 kilograms/hectare under laboratory conditions.
A. Examine substrates and conditions where materials will be applied. Apply products to geo
technically stable slopes that have been designed and constructed to divert runoff away from the face
of the slope. Do not proceed with installation until satisfactory conditions are established.
4.4 INSTALLATION
A. Strictly comply with Technology partner’s installation instructions and recommendations. Use
approved hydroseeding machines with fan-type nozzle (50-degree tip). To achieve optimum soil
surface coverage, apply HP-FGM from opposing directions to soil surface. Rough surfaces (rocky
terrain, cat tracked and ripped soils) may require higher application rates to achieve 100% cover. Slope
interruption devices or water diversion techniques are recommended when slope lengths (3H:1V)
exceed 100 feet (30 m). Slope interruption intervals may need to be decreased based on steeper
slopes or other site conditions. HP-FGM is not recommended for channels or areas with concentrated
water flow unless used in conjunction with a rolled erosion control product designed to accommodate
the anticipated hydraulic conditions. Unless approved by the Manufacturer, no chemical additives with
the exception of fertilizer, soil neutralizers and bio stimulant materials should be added to this product.
To ensure proper application rates, measure and stake area. For maximum performance, apply
HP-FGM in a two-step process*:
1. Step One: Apply fertilizer with specified prescriptive agronomic formulation, BSM & soil
amendments mentioned under section 3.2 and typically portion of specified seed mix with a small
amount of HP-FGM for visual metering. Do not leave seeded surfaces unprotected, especially if
precipitation is imminent.
2. Step Two: Mix balance of seed and apply HP-FGM at a rate of 22.7 kg/475 litres (approx.) of water
over freshly, seeded surfaces. Confirm loading rates with equipment manufacturer.
*Depending upon site conditions HP-FGM may be applied in a one-step process where all components
may be mixed together in single tank loads. Consult with Manufacturer for further details. Best results
and more rapid curing are achieved at temperatures exceeding 15°C. Curing times may be accelerated
2
in high temperature, low humidity conditions with product applied on dry soils. Over-application of
product may inhibit germination and plant growth.
C. Mixing:
A mechanically agitated hydroseeding machine to be provided by supplier for laying the item free of
cost
These application rates are for standard conditions. Application rates may need to be increased to
accommodate very rough based on actual site conditions.
Slope Gradient / Condition Rate (kg/ha)
< 4H to 1V 2,800
> 4H to 1V and < 3H to 1V 3,400
> 3H to 1V and < 2H to 1V 3,900
> 2H to 1V and < 1H to 1V 4,500
> 1H to 1V 5,100
3
TECHNICAL SPECIFICATIONS FOR PRESTRESSED GROUTED GROUND
ANCHORS
The prestressed grouted ground anchors shall be designed and arranged in order to
stabilize insitu strata.
Cement used for grouting of anchors shall comply with IS 12269. The grout mix shall
be designed to achieve a minimum 150 mm-cube-strength of 32 MPa at 7 days and
a minimum 150 mm- cube-strength of 40 MPa at 28 days. The grout shall comprise
water and cement in a ratio (by weight) of not greater than 0.40.
Drilling shall be carried out by suitable equipment. Prestressed cable anchors shall
be of 6 no.s of 7-wire prestressing steel strand with nominal diameter 15.2 mm dia
and nominal tensile strength 1860 MPa with minimum breaking strength of each
mono-strand 260.7 kN. Drill hole shall be of minimum150 mm dia. Fixed grouted
length shall be the 30% of the total length of the anchor with grouting in two stages
(stage 1: for the fixed grout length and stage 2: full grouting). For convenience of
installation, appropriate arrangement (casing) shall be made for drilling in collapsible
strata. The strands shall be arranged and located uniformly over the cross section of
the sheathing without twisting. Grout filled encapsulation shall be provided around the
strands for corrosion protection. Spacers shall be provided in the bond length to
ensure separation between the individual strands and thus to ensure the effective
penetration of grout to provide adequate bond and load transfer between the strands
and the grout. The spacers shall be designed to provide spacing between strands of
not less than 5 mm.
After the first stage grouting up to the fixed grout length, prestressing and locking off
shall be done. Stressing of grouted anchors shall be carried out under the
supervision of a Post-Tensioning Supervisor. Anchors shall not be stressed until the
grout surrounding the anchor has attained an age of seven days and the average
compressive strength of the grout in the hole has reached 32 MPa. A bond breaker
(smooth plastic sleeve) shall be inserted over the prestressing steel element in the
free (unbonded) length to prevent the prestressing steel from bonding to the
surrounding grout. Prestressing strand shall individually be covered with corrosion
inhibiting compound and sheathing in the free stressing length and grout filled
encapsulation shall continue for full length.
The second stage grout shall then be carried out through the grouting pipe attached
to the prestressing steel element until the hole is filled and grout flushes out through
the opening of the base plate and nail head.
Protective sheath shall be provided to cover each anchor head and protruding length
of tendon above the slope surface.
The cap shall provide a watertight seal and shall incorporate a system for complete
drainage of and refilling with grease and for visual monitoring of the internal grease
level. To allow for physical inspection of the anchor head without removal of the
complete cap the top of the cap shall incorporate a water tight inspection lid. Grease
for strands with sheathing and for the protection of anchor heads shall be neutral, inert
and free from any materials or additives which could promote corrosion or reduce the
life of the tendons.
The tendon assembly shall make suitable provision for grout lubes, spacers and
centralizers and shall permit the free flow of grout to and around all components
providing a complete grout cover.
Centralizers shall also be provided outside the sheathing to maintain the sheathing
centrally within the drilled hole. centralizers shall be firmly fixed to the sheathing and
shall be of form which will not cause any damage to, or impair the water tightness of,
the sheathing during installation.
A removable trumpet shall be provided at the collar of the hole to prevent damage to
the sheathing or the external centralizers during installation.
All anchors that have a bearing plate that would normally be placed on the ground at
the collar of the anchor borehole shall be provided with a concrete block to distribute
the pressure underneath the bearing plate into the ground. The size of the concrete
block is typically 1 m X 1m in plan. The concrete strength at 28 days shall not be
less than 40 MPa. The concrete block shall be reinforced as per final approved
drawings.
The anchor head shall possess a centering device so that the tendon force is
applied uniformly to the contact surface between the anchor head and the bearing
plate.
The critical post-tensioning activities such as drilling & cleaning and water testing
and waterproofing of drill holes shall be be carried out at site under the supervision
of a post-tensioning supervisor.
Basis of Payment
The measurement and payment of prestressed ground anchors shall be at the unit
price (per running meter length) for each pay item included in the contract.
2
PARTICULAR SPECIFICATIONS: FLEXIBLE SNOW BARRIER STRUCTURE
Technical specifications for Snow Avalanche protection measures using flexible
snow barrier structure.
1.1 General:
It is a lightweight modular structure with a pyramidal geometry provided with a
suitable anchorage element. It is used as protection measures that are placed in the
zones of snow avalanche formation zone and stabilize the snowpack and is certified
for technical suitability for use in snow by independent accredited / notified agencies
of repute. It features a flexible facing panel structure made with steel beams and
shaped to allow rapid jointing. One of the two beams is divided into two parts
connected in order to simplify the transportation of “folded units”. The single tubular
tie connects to the intersection of the cruciform with a universal ball joint which
allows rotational and directional movements during installation to suit the site
conditions. The anchoring system can be a suitable ground anchors based on
geological in situ conditions. The mesh panel attached to the flexible modular facing
frame helps to contain the snow material behind the unit.
Specifications:
It shall have preferably a cross-shaped structure made with metallic beams with
profile HEB 120 or above of steel grade E275 or above as defined in IS 2062 or
equivalent specifications, hot dip zinc coated.
The overall minimum dimension of a single unit shall be as follows based on snow
thickness, Dk:
Dk=4.0m: Height-4.25m , Width -3.45m
One of the two beams shall be divided in two parts joined together in order to simplify
the transport of folded units.
The joint between the tubular tie and the frontal beams shall be provided with a
suitable flexible joint shall have a minimum breaking load capable to sustain the
snow pressure acting on the unit and it should allow the unit to adjust to terrain
movements without loosing its stability. Further, it should allow rotational and
directional movements during installation to suit the site conditions.
Front and rear plate minimum dimensions 340x270 mm, thickness 10 mm, E275 or
above as defined in IS 2062 or equivalent specifications, provided with drill holes for
bolts.
The central spherical flexible joint shall have a minimum breaking load of 300 kN
capable to sustain the snow pressure acting on the unit and it shall allow the unit to
adjust to terrain movements without losing its stability.
The front panel shall be made with a Rhomboidal steel wire rope panel of mesh type
300x300 mm and steel cable with a minimum diameter of 8 mm Zn-Al5% coated
Class A (min) of steel wire rope of grade minimum 1770 MPa and metallic core as
defined in IRC – HRB – SR 23. The front panel shall have a nominal tensile strength
not less than 150kN/m and a nominal punching resistance not less than 245kN when
tested in compliance with ISO 17746 or equivalent specifications.
The joints of the Rhomboidal steel wire rope panel shall be made with a double steel
wire of diameter 3 mm or above and of tensile strength 380-550 MPa: this joint shall
be able to guarantee a maximum load of tear break of 22 kN as defined in IRC –
HRB – SR 23 or equivalent specifications.
The Rhomboidal steel wire rope panel shall be combined with a mechanically woven
double twisted hexagonal shaped steel wire mesh panel of mesh type 8x10 or less
and the steel wires are Zn-Al5% coated Class A (min) and made of wire of diameter
2.7 mm or above and of tensile strength 380-550 MPa as defined in IS 16014 or
equivalent specifications.
The Rhomboidal steel wire rope panel and the hexagonal double twisted wire mesh
shall be laced together by mechanical steel rings made with steel wire of diameter 3
mm (min) with nominal tensile strength of 1770 MPa.
The connection between the front panel and the anchoring shall be made through a
tubular stem of diameter minimum 113 mm, 5 mm thick (minimum) and with 4 (for
unreinforced) / 8 (for reinforced) steel ropes of diameter 16 mm coated with Zn-Al5%
alloy Class A (minimum). The ropes shall have a metallic core and nominal tensile
strength of 1770 MPA as per IS 2266 or equivalent specification. There is an
additional set of steel ties (4 No.s) and tubular arrangement in front side of flexible
snow barrier unit with specifications same as that of aforesaid tubular stem and steel
ties (ropes). Length of the tube and rope should be as per site conditions.
The front feet shall be made up of a tubular beam 80x80 mm, thickness 8 mm, E235
grade, made integral with shaped tinplate 30x30 cm, thickness 10 mm, E275 in
compliance with the project and the specifications or equivalent specifications given
by the Engineer – In - Charge.
All aforesaid components shall be available in the form of assembly kit (the
structures are partially pre-assembled in the factory), provided with clamps
(compliant with EN 134113-1 or equivalent Indian standard or equivalent
specification), wrist pins, bolts and relative nuts and any required accessory for the
highest performing structure, in compliance with the project specifications.
Suitable ground anchorage is to be used based on geological in-situ conditions as
restraint for snow structure.
The inputs related to snow shall be based on the consideration of SASE report and
will be provided by BRO to Contractor before start of work. Accordingly, the designs
shall prepare and same shall be vetted from IIT.
1.3 Material Testing and Acceptance criteria:
The following product documentation must be provided to Engineer – In – Charge for
approval prior to use in the project:
instruction manual
maintenance manual
The manufacturer/supplier shall provide Manufacturers Test Certificate / Certificate
of Conformity for the material with every lot/shipment. The Manufacturers Test
Certificate / Certificate of Conformity shall be provided for certifying that system
confirms to all the technical specifications if required as per tender documents and
instructions of Engineer-in-Charge.
Section AA
DR
AIN
CHUTE DRAIN
MAT
PERFO / MESH FLE
RMAN XIBLE
CE-FL F
BIOTIC
SOIL M EXIBLE ASCIA + HIG
LONG G H
@ 3MC EDIA+ SUR ROWTH MED
/C SPA FACE
CING IN ANCHO IUM+
BOTH RS
2M HIGH GA
BION TOE WA DIREC 2M
LL TIONS
U-pins 500mm Length
8mm dia @1m c/c spacing
SUB SURFAC
E
DRAINAGE PIP CHUTE DRAIN
ES
MAT /
ME
PERFO SH FLEXIBL
RMA E FAS
MEDIU NCE-FLEXIB CIA + HIGH
M LE GR
SURFA + BIOTIC S
3MC/C C E AN OIL ME OWTH
SPACIN CHORS 2M DIA+
G IN B LONG TOE DRAIN
OTH D @
IRECT
2M HIGH GA IONS
BION TOE WA
LL
CHUTE DRAIN
PERFO MAT
RMAN / MESH FLE
MEDIA CE-FL X
+ SUR EXIBLE IBLE FASCIA
FACE
ANCHO GROWTH M + HIG
RS 2M EDIUM H
BOTH LO + BIOT
DIREC NG @ 3MC/C IC SO
TIONS SPACIN IL SUB SURFAC
E
G IN DRAINAGE PIP
PRE STRESS ES
ED ANCHOR
S
@2M SPACING
LONGITUDIN IN
AL DIRECTIO U-pins 500mm Length
AND 3.0M SP N
TRANSVERSE ACING IN 8mm dia @1m c/c spacing
DIRECTION
10.08M HIGH
GREEN FASC
REINFORCE IA ROAD 2M HIGH GA
D WALL BION TOE WA
LL
SUB SURFAC
E
DRAINAGE PIP
ES
TOE DRAIN
PRE STRESS
ED ANCHOR MAT / MESH
SPACING IN S @2.5M FLEXIBLE FA
SCIA + HIGH
DIRECTION AN LONGITUDINAL PERFORMANC
E-FLEXIBLE
D 5M SPACING BIOTIC SOIL GROWTH ME
TRANSVERSE IN MEDIA+ SURF DIUM+
DIRECTION LONG @ 3M ACE ANCHOR
C/C SPACING S 2M
IN BOTH DIR
ECTIONS
MAT
/
PER MESH F
FOR LEX
MED MANCE IBLE FA
IUM - S
PRE STRESS
ED ANCHOR + BIO FLEXIBL CIA + H
S @2M TIC E IG
SPACING IN
LONGITUDIN SOIL GROW H
DIRECTION AL MED TH
AND 3.0M SP IA
IN TRANSVER ACING
SE DIRECTIO
N
CHUTE DRAIN
2M HIGH GA
BION TOE WA
LL
TOE DRAIN
CHUTE DRAIN
RIVE
R
Section AA
26.4M HIGH
COMPOSITE
REINFORCE
LAUNCHING APRON D WALL
WITH BOULDER FILL
Drain
2.0 ?
U-pins 500mm Length
8mm dia @1m c/c spacing
Subsurface drainage pipe
Surface Anchors (SDA)
2m long, :Dia = 32mm, Spacing
?
3.0m c/c in both directions.
Green Unit, Mesh Type 10x12,
Mesh Wire Dia. 2.7/3.7mm,
(Zn+10% Al )+Polymer coated.
Backfill
Non woven geotextile
2.0 Drain
3.0 Backfill
Green fascia Unit, Mesh Type Road Drain
Detail-A
Structural fill
30.0 spacing in longitudinal direction
10.08
Drainage Composite
High strength geogrid 0.63
?
Performance-Flexible Growth 0.2m thick PCC Pre-stressed anchors
Medium+ Biotic Soil Media for slope stability
2.0
3.0
3.0 Surface Anchors (SDA)
:3m Long, Dia = 32mm, Spacing
3.0m c/c in longitudinal direction.
and 3m c/c transverse
Surface Anchors (SDA)
2m long, :Dia = 32mm, Spacing
3.0m c/c in both directions.
? 25°
2.0 Drain
Backfill
Pre-stressed anchors @2.0m c/c
5.6
65°
Insitu Rock
Gabion unit with integrated tail
18.0
, Mesh Type 10X12, Mesh
Wire Dia. 2.7/3.7mm, (Zn+10%
Al )+Polymer coated. Surface Anchors (SDA)
0.5
Structural fill
10.0 10°
Mechanically Woven Double 10.0
1.0
21.60 Twisted Hexagonal Wire Mesh as
HFL Secondary Reinforcement
8.0
6° Surface Anchors (SDA)
:Dia = 32mm, Spacing
RCC Jacketing 3.0 2.0m c/c in both directions.
3.0
2.0 Berm
Insitu Strata
12.0
0.5
Detail-B
1.0
6.0 High strength geogrid
3.0
RCC Pedestal
0.5
Non woven geotextile
?
0.5
PROJECT: SHEET 2 OF 5
CROSS SECTION SLOPE STABILISATION MEASURES FOR N.T.S.
SINKING ZONE NEAR ROHTANG TUNNEL
INDICATIVE SCHEME
SECTION AA SOUTH PORTAL, HIMACHAL PRADESH
NOT FOR CONSTRUCTION
RCC nail head
Detail-A
?
65°
0.8 3.0 Structural fill
Mechanically Woven Double
5.6 Twisted Hexagonal Wire Mesh as
Secondary Reinforcement
High strength geogrid 17.0
10°
3.0
Berm 15.0
Gabion unit with integrated tail
18.0
, Mesh Type 10X12, Mesh
Wire Dia. 2.7/3.7mm, (Zn+10%
Al )+Polymer coated. Surface Anchors (SDA)
0.5
Structural fill
10.0 10°
Mechanically Woven Double 10.0
1.0
21.60 Twisted Hexagonal Wire Mesh as
HFL Secondary Reinforcement
8.0
6° Surface Anchors (SDA)
:Dia = 32mm, Spacing
RCC Jacketing 3.0 2.0m c/c in both directions.
3.0
2.0 Berm
Insitu Strata
12.0
0.5
Detail-B
1.0
6.0 High strength geogrid
3.0
RCC Pedestal
0.5
Non woven geotextile
?
0.5
DETAIL-1 DETAIL-2
PROJECT: SHEET 3 OF 5
SLOPE STABILISATION MEASURES FOR N.T.S.
SINKING ZONE NEAR ROHTANG TUNNEL
INDICATIVE SCHEME
SOUTH PORTAL, HIMACHAL PRADESH
NOT FOR CONSTRUCTION
RCC nail head
3.0 Backfill
Green fascia Unit, Mesh Type Road Drain
Non woven geotextile
10x12, Mesh Wire Dia. 2.7/3.7mm,
(Zn+10% Al )+Polymer coated.
Detail-A
45°
Mechanically Woven Double
Twisted Hexagonal Wire Mesh as Structural fill
Secondary Reinforcement
10.08
Drainage Composite
High strength geogrid 0.63
2.0
DETAIL-3
PROJECT: SHEET 4 OF 5
SLOPE STABILISATION MEASURES FOR N.T.S.
SINKING ZONE NEAR ROHTANG TUNNEL
INDICATIVE SCHEME
SOUTH PORTAL, HIMACHAL PRADESH
NOT FOR CONSTRUCTION
References