Tiempo Optimista Tiempo mas Tiempo

Actividad Precedente (a) Probable (m) Pesimista (b) Tiempo estimado

A - 1 3 5 3
B - 3 4.5 9 5
C B 2 3 4 3
D A,C 2 4 6 4
E D 4 7 16 8
F C 1 1.5 5 2
G F 2.5 3.5 7.5 4
H F 1 2 3 2
I B 4 5 6 5
J H,E,G 1.5 3 4.5 3

s^2= 5.80555555555556 m= 23
sqrt(s^2)= 2.40947204913349 x= 18

Z= -2.0751433915982

P(x=18)= 1.8986624%

Calculos hacia adelante Calculos hacia atrás


Evento TPi+dij TPj=Max(Tpi+dij) Evento TTj+dij
1 TP1=0 0 9 TT9=TT9=23

2 TP1+d12=0+3=3 8 8 TT9-d89=23-3=20
TP4+d42=8+0=8
3 TP1+d13=0+5=5 5 7 TT8-d78=20-4=16
TT7-d67=16-0=16
4 TP3+d34=5+3=8 8 6 TT8-d68=20-2=18
5 TP2+d25=8+4=12 12 5 TT8-d58=20-8=12
TT6-d46=16-2=14
6 TP4+d46=8+2=10 10 4
TT2-d42=8-0=8
TT9-d39=23-5=18
7 TP6+d67=10+0=10 10 3
TT4-d34=8-3=5
TP7+d78=10+4=14
8 TP5+d58=12+8=20 20 2 TT5-d25=12-4=8
TP6+d68=10+2=12
TP8+d89=20+3=23 TT3-d13=5-5=0
9 23 1
TP3+d39=5+5=10 TT2-d12=8-3=5

Actividad Ruta i->j TPi TPj TTi TTj


A 1->2 0 8 0 8
B 1->3 0 5 0 5
C 3->4 5 8 5 8
F1 4->2 8 8 8 8
D 2->5 8 12 8 12
E 5->8 12 20 12 20
F 4->6 8 10 8 16
F2 6->7 10 10 16 16
G 7->8 10 20 16 20
H 6->8 10 20 16 20
I 3->9 5 23 5 23
J 8->9 20 23 20 23

RUTA CRITICA= B-C-D-E-J


Varianza

0.444444444
1 I=5
0.111111111
H=2
0.444444444
4 3
0.444444444 B=5 C=3 F=2 6
0.694444444
0.111111111
1 4
0.111111111 F
0.25 F1 2 G=4

A=3 7
2

E=8
D=4
5

hacia atrás
TTj=Min(TTj-dij)
23

20

16

16

12
8
5

dij Crítica
3
5 SI
3 SI
0 SI
4 SI
8 SI
2
0
4
2
5
3 SI
9

H=2
J
=
3