1. GENERAL DESCRIPTION
The Project Health and Safety Plan is an overview (generally) of project safety preparation,
planning, engineering and execution process that will be applied and implemented at the
project site, to determine and ensure that all of safety activities are in accordance with and
under controlled of internal company needs and client requirement.
The importance and essence of this project HSE plan is guidance, monitoring and controlling
of project preparation stage, pre-execution and project execution stage of Safety activities at
the project site, in accordance with appearing high performance and team work coordination
internally within site management and Head office management.
The project HSE Plan is containing of Health, Safety & Environment work planning correlated
with scope of work.
PT. Len Industri (Persero) implements a quality management system, K3 and Environment to
create a consistent service, satisfy customers, safe for worker health and safety, and
environmentally friendly in organizing corporate activities and perform a good documentation
process so as to meet user needs and in accordance with international standards that serve
as a reference.
Name Company : PT. Len Industri (Persero)
Company's address : Jl. Soekarno Hatta No. 442 Bandung 40254
No. Telp/Fax : +62-22-5202682, Fax +62-22-52026
Site Office address : Signature Park Grande
Jl. MT. Haryono Kav 20 MO/6 Jakarta Timur 13630
No. Telp : +62-21-8001897
It is PT. Len HSE policy to provide and maintain a safe and healthy work environment at all
times. The goal of PT. Len management is to prevent occupational accidents, injuries,
illnesses, environmental issues and this will be achieved by management, who shall place
accident prevention and the protection of the health and safety of every employee and
environment, above any other consideration of job operation or administration. The ultimate
goal of PT. Len at every level of our organization shall be to ensure at all times, throughout
every phase of job operation, drug abuse, weapons and shines are something that is strictly
prohibited in the project, this is illegal and dangerous to work on.
Leading Indicator
1 Tool Box Meeting 95 %
2 HSE meeting 95 %
3 Inspeksi Patrol 95 %
4 HSE Reporting 100 %
5 HSE Management Visit 100 %
6 Closing Finding 100 %
For the implementation of the HSE work program in the project established the structure
responsible for the implementation of HSE in the project as follows:
Yadi Ramdani
Project Manager
Ketua
Fransisca A. Sirait
HSE Admin
Sekretaris
HSE Admin a. Develop HSE Report a. Filling and collect the HSE AK3 Umum
b. Collaboration with document hard copy and
HSE Officer for Deve- soft copy.
lop Report and HSE
Documentation b. Filling the document of
(Photo, Hard Copy HSE Project.
and evidence) c. Provide report for client
c. Support all inspection d. Ensure the report is under
activity sign by Related personel
d. Collaboration with
HSE officer to e. Send the report which
organize Safety meet- required by client, and HSE
ing and General Safe- of head office
ty Talk. f. Collect the data from
e. Inventarization HSE project activities and data
Equipment
f. Record HSE Training from other department
and HSE Activity g. Preparation for all HSE
Project. activity.
HSE Man a. Ensure project work a. Patrol the site frequently Basic knowledge
complies with and ad- and inspect for unsafe Safety
here to Project Safety activities and unsafe work-
Procedures and safe ing condition.
working practices. b. Advise or instruct cons-
b. Suggest or direct the truction supervisor, Fore-
person in charge of man, and workers to
the project to improve remedy unsafe activities
unsafe working condi- and unsafe working condi-
tions or detected viola-
tions.
tions.
c. Maintain a log of any
c. Together with HSE
defects or violation obser-
officers conduct a
ved and notification of
'follow-up' to ensure
remedial action taken.
corrective action has
d. Compile a comprehensive
been taken immedi-
ately. list of all equipment and
d. The results of the tools incorporated in to the
patrol including advice site.
or corrective actions e. Monitor and assist, if
taken should be recor- necessary, construction
Doc. No.: RS-03-GN-SG-HS-000180-03A
LRT JABODEBEK 10
Int. ID :
Health and Safety Plan Version : 03
of
Ext. ID : ---
DCC: --- Version : --- 53
LRT JABODEBEK
Signaling System
Operator Heavy a. Preparation for Heavy a. Appropriate heavy equip- SIO from Ministry of
Equipment equipment and lifting ment with material to be Manpower and trans-
gear to be used. lifted migration or Ministry
b. Check and Recheck b. Safely Lifting actifity of Energy and Mine-
document for Heavy c. Prepare Lifting Plan ral Recsources.
equipment and lifting d. Close communication with
gear are available. Rigger and All Crew.
c. Together with his crew e. Ensure Stabel ground for
to maintain condition Heavy Equipment and out
of Heave Equipment rigger
and Lifiting Gear. f. Always guided by Safe
d. Execute the lifting Working Load for all Lifting
activity with safe prac- Actifities
tice. g. Stop Activity if do unsafe.
Delimiter shall be established at the site p r ior to commencement of any site works
including construction of temporary facilities. This is to ensure that unauthorized personnel
are kept out of the project site and also to ensure that such personnel are not exposed to the
Suitable and sufficient lighting shall be provided in the Site Office, and working night area job
ensure that Leader provide their employees with suitable and sufficient lighting to perform
works during night operations.
List of First Aid Box and Its Contents can be seen at appendix 7.
List of First Aid Bag and Its Contents can be seen at appendix 8.
Letter of Cooperation with Public Health Center can be seen at appendix 9.
PT Len identifies the hazards and aspects of the HSE in the workplace in order to eliminate
or at least reduce the risks or impacts that may result in injury / damage to both employees
and other company assets. Results of HSE identification and hazard aspects are listed in the
HIRADC document.
The HIRADC document will be socialized to all employees involved and interested in the
project. The HIRADC document reviewed and updated if any changes to the process / activity
/ object. HSE hazards and environmental aspects at every stage of the process as well as the
current control projects execution have been identified, results can be seen in the Document
Identification Method Statement.
HIRADC (Hazard Identification, Risk Assessment, and Determining Control) is the process of
identifying hazards that can occur in routine or non-routine activities within the company, for
further assessment of the risks of these hazards. Those assessed in HIRADC are dangers or
risk of a job. The factors that are assessed are the probability and consequence of severity.
What is assessed to be revealed is not to the person but rather to the danger posed to the
extent that can be accepted by the company.
More comprehensive control methods include hierarchy of control, mitigation, and work
procedures. Control hierarchy is a system and risk control mechanism that is carried out in a
structured manner, from simple things to more complex ones. The control system should be
carried out in stages.
PPE is the fifth or final stage in the control hierarchy, and is the last 'defense' in minimizing
risk if the first four methods cannot be done. This used when hazards cannot be
eliminated through engineering or administrative controls, and must consider personal
protective equipment (PPE) necessary for employee protection. PPE is a tool used to
protect our body, or maybe even a certain object to protect themselves or the object from
a danger. In this APD technique is expected and able to reduce the level of risk of severity
due to danger from the surrounding environmental conditions.
The HSE legislation that is directly related to the project scope is as follows:
Law (UU):
Work Safety
1 UU No. 01 Thn 1970
Keselamatan Kerja
Manpower
2 UU 13 Tahun 2003
Ketenagakerjaan
Law (UU)
Waste management
1 UU No. 18 Tahun 2008
Pengelolaan Sampah
Government Regulation
Hazardous material handling
1 PP RI No. 101 Tahun 2014 Pengelolaan limbah bahan berbahaya dan
beracun
Air Pollution controll
2 PP No.41 tahun 1999
Pengendalian pencemaran udara
Regulation of the State Minister of the Environment
Labeling Procedure for Hazardous Material
1 PerMen LH No. 03 Tahun 2008 Tata Cara Pemberian symbol dan label
Bahan Berbahaya dan Beracun
Decree of State Minister of Environment
Label and Symbol Hazardous material and
PerMen LH RI toxic.
1
No. 14 tahun 2013 Label dan Simbol limbah Bahan Berbahaya
dan beracun.
For competencies and trainings can be viewed or refer to point 3.2 job description
personalized.
HSE IMPLEMENTATION
DESCRIPTION
COMMUNICATION PLAN
HSE IMPLEMENTATION
DESCRIPTION
COMMUNICATION PLAN
7. OPER AT ION AL
7.1 Work Permit
PT. Len will take care of the first letter prior to the commencement of work potentially result
in serious injury. PT. Len will apply for a work permit to PT Adhi Karya which is equipped with
JSA (Job Safety Analysis). As per legal and regulation apply.
Before using the work tools and heavy equipment it is necessary to ensure that all equipment
that is required to be checked or tested, to meet the requirements. Use of the heavy
equipment such as cranes, forklifts, etc should meet the following requirements:
a. Operators and Rigger have a valid SIO (Surat Ijin Operasi) from ministry of Manpower
and Transmigration,
b. Heavy equipment already has a valid Special Permit or SILO (Surat Layak Ijin Operasi)
from ministry of Manpower and Transmigration before used,
c. Lifting Plan attached on Permit to work if necessary,
d. The heavy equipment is worthy of use and has passed the inspection covering the heavy
equipment itself include slings, and another lifting gear,
e. Inspection perform by dedicated persons by Subcontractor or Provider Heavy equipment,
f. Len HSE will ensure that all document of Heavy Equipment and operator are valid.
Heavy equipment shall be used for the intended purpose of the manufacturer. A copy manual
book or equipment manufacturer’s operation manual will be maintained on site by Site
management. No alterations or modifications shall be performed to the equipment without the
manufacturer’s approval that must be documented. Equipment will be operated within
capacity as outlined in the manufacturers operating manual.
The only modification which are required sometimes, and for which the above does not apply,
is when equipment is obtained from the manufacturer in an inadequately guarded condition.
Guards must then be fitted before the equipment may be used. All equipment will be provided
with necessary safety devices to prevent incidents. Inspection of these devices will be
included as part of the operators daily pre-operational inspection, as well in the formal
inspection. No equipment shall be operated with detective or missing safety devices.
All items that will be used in the project including heavy equipment must be inspected before
use. This aims to ensure that the item is safe to use.
Inspections are carried out every month. Inspection results will be recorded by HSE and the
inspector team. If any items that is damaged or not feasible is found, it will be recommended
not to be used again in the project.
After the inspection is carried out, the HSE will attach the sticker tag to the items. The tag
sticker used for the item is color code. The color code for the equipment before use will be
divided into two colors. Green sticker means that the equipment can be used, and the red
sticker means it is rejected. The color code for monthly inspection is divided into three colors
and the color code will change every four months. Blue for inspection marks in January,
February, March, and April, yellow for inspection marks in May, June, July, and August, and
grey for inspection marks in September, October, November, and December. The tag sticker
will be installed on the device and placed in a place that is easy to find. In case if the items
failed of inspection or rejected, the HSE team will put a red sticker tag. This is indicated that
the equipments cannot be used.
This programme is to promote safety consciousness, enthusiasm and interest in Safety and
Health in units and/or workers, this program also includes immediate positive reinforcement
personel the criteria of evaluation will be defined at site.
8.1 Reward
Generally, this awards programme is classified as follows.
This award given to workers are obedient with safety regulation. Compliance with PPE is one
of criteria in determining awarded. It is can be earned by Leader, worker or personnel from
Logistik Department. For this category, the winner gets cash or merchandise.
This program is reserved for group work unit assessed submissive regulatory safety. How
safe work and promote safety to the persons or group. This award will be given quarterly
rateable by safety team and aprooved by project manager. For those category, the winner
gets cash or merchandise.
PT. Len Industri (Persero) / LRT Jabodebek Project has the right and will exercise to remove
any persons this right to remove the persons from the project for condoning, supporting or
instructing any employee to commit unsafe act. Work in unsafe or unhealthy conditition or
work with unsafe equipment. Employees that continuously ignore or disregard the project
HSE requirements will be discipline. Employee has the right to refuse to do the job once an
unsafe condition is observed, such as working at height with no full body harness provided,
working in unstable platforme, etc.
If a subcontractor negelect their employee refusal. Contractor may issue warning letter/
disciplinary to subcontractor management it is management responsibility to find a safe way
to do the job.
Pinalty given to employee who violating safety regulation or work to harm himself and other.
It will be given Warning Letter.Warning Letter signed by worker, supervisor and HSE
Coordinator, and reported to Project Manager. To maintain the worker compliance with safety
regulation Pinalties for those violate will apply. Amercement realized on cash money.
Employee who violate safety regulations will be subjected to tiered sanctions. Some of
violation will arise Warning Letter. For example: violation is for disobedience wearing PPE,
activity without work permit, negligent use the required safety aids (example: full body
harness), and unsafe act that potentially risky to other workers and environment.
Warning Letter will be recorded and kept by HSE and Report to Project Manager.
Equipment including lifting gear upon arriving at the site shall be checked by a competent
person and witness by HSE Len designated before it is distributed to the LRT Jabodebek
Project.
The first entry equipment inspection shall be documented on the appropriate equipment
inspection form, copy of the most recent inspection report will be maintained on each piece
of equipment as well as in the HSE Department for the file.
Safety Meetings
Meetings on occupational 10 – 30
safety topics Incident / minutes
All persons working at Len Project Manager /
Accident or danger reports,
the construction site Leader 1 x weekly (as
HSE instruction topics, HSE
matters per condition)
Internal :
Daily inspection of
construction site Construction Site HSE Officer Daily
External :
PT. Len will take care of the permit before performing the work on the altitude. The terms of
working at altitude in general are as follows:
a. Worker conditions should be healthy and there is no fear or height trauma and use the
appropriate PPE,
b. Use barricades to prevent personal falling from edges or openings,
c. Training working at height will perform to all worker who will work on height and possibility
falling more than 2 meters.
d. Full Body Harness is required if there is a possibility of falling more than 2 meters.
In general, prospective subcontractors prior to bidding or in the stage have been described
about the terms and conditions of the HSE system if later selected as subcontractors.
Specifically, prior to the execution of the work, it is ensured that all aspects of the HSE will be
implemented by the sub-contractor. Subcontractors are required to follow the rules specified
in the HSE Plan of this project. The HSE Officer project oversees all work performed in
accordance with applicable HSE rules or best practices including work performed.
PT. Len have responsible to Make sure that worker health fitness before mobilization tp site.
and during project ecxecution. PT. Len shall ensure that all personnel coming into Site have
healthy Letter from a doctor and Free Narkoba from related institution which shall determine
in confidence the fitness for work of the prospective workforce to the job offered.
d. Define Job and its hazard exposure that may require health surveillance (there may be
none), identify all individuals doing those job, get professional advice in instituting
appropriate health surveillance program, and ensure the implementation
e. Assure their staffs do not have health problems associated with the fitness for the job or
work.
10. EMERGENCY ST AT E
Emergency response plan is to give protection best for health and safety all employees in
proyek and other people nearby and also for keep workplace in an emergency. All activities
tactical must be taken based on on priority the following:
a. Save life other people
b. Secure society and environment.
c. Maintain security workplace, equipment, materials and important documents.
The task and responsibilies of he Emergency Response Tean can be explained as follows.
Basic HSE
Chairman of As the highest command holder during an
Emergency Response
TTD emergency
System
First Aid Team Carry out the functions of first aid in each
Basic HSE / First Aid
(P3K) case of accidents and emergencies
PT. Len will provide equipment for emergencies during this project takes place such as: fire
extinguisher, first aid kit, and others required. PT. Len Industri will conduct inspection checks
against completeness and facilities of this emergency to ensure it is ready for use at the time
require.
In the case of an emergency, all workers should know the location of the assembly point and
evacuation access point. Designated assembly point will be provided by PT. Len. For
determine the location of assembly point, PT. Len will coordinate with HSE team of PT. Adhi
Karya LRT Department. PT. Len also provides an evacuation sign to make it easier for
workers to find the assembly point area.
INCIDENT REPORTING
START
ACCIDENT
TREATMENT
ACTION
ENDS
HSE Man / Officer conducts HSE inspection everyday to ensure there are no unsafe or unsafe
conditions in the project environment, such examination parameters include:
a. Unsafe Action and Unsafe Condition,
b. Floor & Wall, Alley / Corridor, Window / Ventilation,
c. Lighting,
d. Machinery / Equipment,
e. Personal Protective Equipment,
f. Sign / Poster HSE,
g. Hazardous Material,
h. Light Fire Extinguishers,
i. First Aid Kit,
j. Trash can / Trash Bag.
In accordance with the specified schedule, the HSE Coordinator of the center conducts field
visits to conduct HSE inspections. In accordance with the specified schedule, the
representative of the management (Board of Directors / GM / Manager) conducts field visits
to conduct HSE inspections.
HSE audit can be seen at point 9.0 about safety meeting and audit inspection.
Any accident will be investigated by HSE to find the root of the problem so that no similar
incidents will happen again.
The HSE performance indicator called KPI (Key Performance Indicator) for Occupational
Health and Safety Management System is important tools used by companies to measure
the effectiveness of their programs to reducing the opportunities and risk of occupational
health and safety. KPI is able to measure performance achievement. Is it appropriate or not
yet.
Appendix: