You are on page 1of 2

Construction Management

Part – A (45 Marks)

Attempt any Five Question

1-what is construction management. Explain nature and scope of construction management.

2- Explain in details importance of equipment in construction industry in detail.

3- What if the difference between network diagram and time grid diagram? Discuss with suitable
example, use of network and time grid diagram

4-Explain planning, scheduling and controlling as a function of construction management with suitable
example.

5- Discuss various cost parameters that are considered and analyzed in order to formulate equipment
replacement policy

6-Explain meaning of cash flow analysis. Discuss its purpose. What is the difference between cash flow
for contractor and cash flow for owner?

Part – B (35 Marks)

Attempt any five Question

1-Describe safety requirement for demolition work and safety measure to be adopted for excavation

2-Discuss the factor influencing the selection of suitable excavating equipment.

3- Explain how output of power shovel can be improved

4- Explain the factor influencing the power of hoe

5-write short note on network updating

6- Discuss importance of safety in construction sites


Part – C (20 Marks)

Attempt any four Question

1- State rule for drawing network


2- Explain the term updating. Why updating is necessary
3- Describe in detail the concept of time value of money
4- State and describe various causes of accidents at the construction site.
5- Explain cash flow diagram with simple example.
6- Explain the term job layout and draw a job layout for construction site of a large multi-storey
building