Ma Tf u ε
0.00529875 25 0.8 1200
anode m2 m2
278 2224 50
6.25
556
Bill of materials
Desc qty unit cost/unit total
Anode 15 ea 150 2250
cabling 50 m 8 400
Grounding 50 m 3 150
Reference anode 2 ea 100 200
Test point 2 ea 200 400 3400
Construction 1 lot 1020
Contingency (10%) 442
Grand Total 4870
Scope of Work
1. Cabling Work (pulling cable, termination)
2. Install anode
3. Excavation