PROJECT - D'MART JABALPUR TILHARI

STRUCTURE - COMPOUND WALL


SHUTTERING FACTOR
SR.NO. STRUCTURE SHUTTERING REMARKS
FACTOR
(SQM / CUM)
1 RAFT - M30 0.740
2 RETAINING WALL -(M30) (WITH BOTH SIDE
SHUTTERING) 5.998

3 RETAINING WALL -(M30) (WITH ONE SIDE


SHUTTERING) 3.267

4 COLUMNS- M30 (WITH TWO SIDES


10.637
SHUTTERING)
5 COLUMNS- M30 (WITH ONE SIDE SHUTTERING)
4.258
6 M30 COPING (BOTH SIDE SHUTTERING) 8.971
7 M30 COPING (ONE SIDE SHUTTERING) 4.900