Surface dressing of the ground including removing vegetation and

inequalities not exceeding 15 cm deep and disposal of rubbish, lead


up to 50 m and lift up to 1.5 m. All kinds of soil

Required Ar. Of the plot 100 Sqm


S.No. Description Quantity Rate Amount
LABOUR
Beldar day 1.97 558 1099.26
Coolie day 1.29 558 719.82
TOTAL 1819.08
Add 1 % Water charges 18.19
TOTAL 1837.27
Add 15% CP & OH 183.73
Grand TOTAL 2021.00

Overhead costs are all those indirect costs like laqbor costs, rent, travel expenditures,
utilities and communication bills, supplies, advertising, insurance accounting, legal fees,
etc
Beldar Coolie
100 Sqm = 1.97 day 100 Sqm = 1.29 day
50.7614 Sqm/day 77.5194 Sqm/day
S.NO. CODE NO. DESCRIPTION QUANTITY
Surface dressing of the
ground including removing
vegetation and in-equalities
1 2.28 not exceeding 15 cm deep
and disposal of rubbish, lead
up to 50 m and lift up to 1.5
m.
2.28.1 All kinds of soil 645
UNIT RATE AMOUNT

Sqm 21.13 13628.85