MAPPING INSTALASI BU : BELUM UNIT

PROYEK COHIVE SAHID SUDIRMAN


PROGRESS KE-2 20/11/2019
RUANG LAMPU SAKLAR STK STK SPRIKLER HEAD
LANTAI TEMBOK DETECTOR
16 2
KORIDOR A 3 WALL
s/d B 4 PEND (BU)
BAR 3 PEND
6 1
EXPOSE 18 DL OUT 4 11 7
12 DL IN
18 PEND
2 WALL
PANTRY 5 PEND 1
3 DL
23 s/d 25 9 4 - 5
KORIDOR B 13
s/D C
RECEPTION 2 1 2
28 2 1
27
26

TOTAL TERPASANG
UNIT 30 11 14 14 0 0
KABEL 64 19 14 22