Professional Documents
Culture Documents
On With
Modular
Technology
Fernando Dueñas, Cemengal, details the advantages of
flexible and modular grinding units.
C
ementos Melón, a reference Project background
manufacturer of cement and In order to meet these trends,
ready‑mixed concrete in Chile Cementos Melón decided to upgrade its
is a private company on the production capacities at its grinding and
Chilean Market and controlled by the distribution plant in Puerto Montt. As a
Peruvian BRECA Industrial Group that result of this, in mid-2017 CEMENGAL
belongs to the holding of the BRESCIA was awarded with the supply of the
Family. Currently employing over 1000 staff equipment for the first Plug&Grind®
across Chile, the company’s production XTREME modular grinding unit. The
and distribution activities are based at its modular mill unit was delivered by July
clinker plant in La Calera, two grinding 2018, in order to allow the first cement and
units are located at the sites of Ventanas commissioning of the plant before the end
and Puerto Montt, and several batching of the year; this was just at the beginning
and aggregate plants for ready-mixed of the peak of demand during summer in
concrete preparation are placed across the southern hemisphere.
the country. The industrial grinding project includes all
Over the last years, the company has the mechanical, electrical, and automation
focused its expansion strategy in the equipment necessary on a modular ball
South of Chile, with the main objective mill circuit for 300 000 tpy of high strength
being to maintain the sustainable and cements, such as the MELÓN Extra and
environmental development of its MELÓN Especial premium products
MODULAR GRINDING
World Cement
sourced from local quarries in the region. The
clinker and additives are dosed separately by
Schenck weighfeeders, then the fresh feed is
transported to the mill inlet via enclosed belt
conveyors, in order to keep the facility free of
any dust. A hot gas generator is also included in
the scope of supply to dry the fresh feed when
pozzolana with moisture contents is used as an
additive.
In addition, due to the severe climatic
conditions of the site, this hot gas generator is
also used to heat up the circuit when starting up
the mill in the winter and on rainy days. To ensure Figure 3. Panoramic view of the Plug&Grind XTREME
the most efficient clinker comminution, the ball plant at the site installation stages.
mill is equipped with Magotteaux diaphragms
and liners in the first and second chambers. The
fine material flows from the first to the second
chamber through a diaphragm and finally
the fines leave the mill through a discharge
diaphragm. The two compartments of this
Plug&Grind XTREME mill have an approximate
filling degree of 30%. The first chamber is filled
with Maxicrom grinding media of between 60 mm
dia. and 90 mm dia., and the second is filled with
Hardalloy grinding balls of between 20 mm dia.
and 60 mm dia., both supplied by Magotteaux. Figure 4. View of the installation activities of the
The circuit is completed by a fifth generation Plug&Grind XTREME mill.
separator and a process bag filter, designed and
manufactured at CEMENGAL facilities, that follow ensure all safety, quality, and schedule requirements
modular configurations. The whole plant meets in order to meet the project goals.
European environmental regulations for emissions Project engineering began immediately after the
to be kept under 10 mgr/m3 at the filter outlet. completion of the contract’s formalities in July 2017.
With regard to the electrical and automation system, Manufacturing activities began in CEMENGAL’s
The Plug&Grind XTREME plant is fully engineered workshops just four months after the commencement
by the CEMENGAL engineering department to keep of the project, once the two parties had agreed on
all the main electrical components like motor control the general layout of the plant that fitted with the
centres, programmable logic controllers, variable existing facilities. By August 2018, all the supplies
speed drives, and cooling systems fitted inside a were delivered at the Chilean Ports and, by that
containerised room. All power cables, low voltage, time, the client was already at the final stages of
and instrumentation devices are pre‑installed at the civil works and site foundations to receive the
CEMENGAL workshops along trays and supports grinding infrastructure.
that are fixed at the transportable modules to The construction of the Plug&Grind XTREME
speed up the plant installation onsite. Technologies modular mill equipment started in October 2018
from partners like Siemens, ABB, and Schneider and, after nine weeks of installation work, the
are standard for the electrical and automation first cement was produced following simple
sub-supplies. Thus, connections to the central commissioning works that were conducted by the
electrical room are simple and fast. client’s staff and supervised by the CEMENGAL
Following the current trend for cement produced team of equipment specialists.
at low temperature in Chile, a cement cooler was
also incorporated at the end of the mill shop, in Conclusion
order reduce temperatures to 70°C for improved The Plug&Grind modular grinding configuration
cement handling by the clients at the ready-mixed with flexible ball mill equipment is a suitable solution
concrete plants. The cement cooler can also be for the brownfield expansion of existing plants
bypassed in case such a low temperature is not that are unable to cope either with strong cement
necessary. demand, or limitations on the existing equipment
to reach very high Blaine cements with blended
Project execution compositions.
Due to the close relationship and good cooperation With Plug&Grind flexible plants, there are
between the project teams: Cementos Melón, different possibilities for the extension and
CEMENGAL, and local sub-contractors were able to production of new products with a wide range
World Cement
of capacities. This means that new investors and
current producers can benefit from its advantages,
to implement the project’s investments in a shorter
time with limited CAPEX.
Since its official launch into the worldwide
market in 2013, CEMENGAL has supplied several
Plug&Grind modular units in different regions: from
South to Central America and the Caribbean, from
North to East and West Africa in the Sub‑Saharan
region, and from Western Europe to Southeast
Asia, with excellent results in performance,
reliability, safety, and environmental protection.
Thanks to the advantages of modular technology,
Cementos Melón managed to meet the quality and
quantity demands of its clients. Additionally, the
overall timing and cost initially expected for the
mill commissioning was reduced. This project
implementation is being replicated at other plants
in Southern Chile.
World Cement