Professional Documents
Culture Documents
UTLAPPK Fuel Gas Measurement Best Practice PDF
UTLAPPK Fuel Gas Measurement Best Practice PDF
Appendices
1. Meter Audit, Repair and Compensation
2. BTU Measurement
3. Meter Selection
4. Drawings and Examples
5. Implementation Metrics
• Unit operators can track their units energy performance, make operating
changes to achieve the best possible performance with current equipment and
know they are improving the profitability of the refinery.
• Operating incidents may be avoided or minimized when operators have good
data available to trace system variation and upsets back to the source.
• System inefficiencies are understood and plans are formulated to improve
performance.
• New project fuel gas needs are met by cost effectively improving the system
efficiency rather than by just burning more fuel.
BOILER CRUDE
PLANT UNIT
Plot Limit
Meter
Fuel Gas
Mix Drum
FCC
Flow meters should be pressure, temperature and gravity compensated where neces-
sary using sensors installed near the flow meter or using data from the nearest
meter to enhance accuracy. If meters are not pressure, temperature and gravity
compensated with live sensors the readings will be in error during upsets if the
header pressure and temperature departs significantly from design.
Each system should balance. If a system (e.g. mix drum and group of plants) does
not balance, a dedicated maintenance effort must be undertaken to achieve closure.
See Appendix 1 - Meter Audit, Repair and Compensation for methodology. Subbal-
ances should be used to track and help achieve closure if maintenance efforts are
unsuccessful.
of the arrows is arbitrary). Using the flow directions shown, the subbalance calcu-
lated below should be equal to zero +/- 5% if all meters are working properly.
Subbalance = flow5-flow1-flow2-flow3-flow4-flow6
For the purpose of this Best Practice, the term “balance” is used to describe either a
system balance, or a subbalance of a system. The same method for achieving a
balance (Figure K-1) is used whether you are balancing an entire system or a
subbalance to a system. Experience shows that well maintained balances will add
to zero within about 5%1 of the total flow. (Total flow equals the flow into or out
of the balance which is also equal to one-half of the sum of the absolute value of all
the metered flows) For example if the absolute value of all the metered flows
equals 100 mscfh, then, one-half of that equals 50 mscfh which equals the flow into
the balance and the flow out of the balance. In this case a good metered balance
should trend around zero within +/- 5 mscfh.
The balance sums are computer monitored and trended around zero to insure data
validity. Figure K-3 is an example of a trended balance that at first does not balance
and after repairing two meters, does balance. Before the meters are working
correctly the sum of the meters does not balance, the meters sum to about 50
mscfh. After one meter is repaired the "balance" sums to about -25 mscfh (the
minus sign means that the sum of the metered flows out of the balance is greater
than the sum of the metered flows into the balance). After one more meter is
repaired the balance sums near zero. Once a balance balances regularly over a
period of time, each meter in that balance can be relied on to report accurate infor-
mation.
1. This is in contrast to a custody transfer meter where agreement between a sales meter and a company owned
check meter is desired to be within 2% with the variation tracked with a control chart to flag significant
changes.
Figure K-5 shows trend number 2 from Figure K-4 but with additional trends of
three of the meters that make up the balance. It is easy to see that meter #3 made a
significant change at the same time the balance went off. The instrument mechanic
would then focus attention on meter #3. This method, which has been used at Rich-
mond for several years, has resulted in the elimination of most preventive mainte-
nance for meters. This has led to a reduction in meter maintenance support from
six mechanics to one. With a dedicated Instrument Mechanic using this method
inaccurate/bad order meters are quickly identified and repaired. Meter failures and
repairs should be tracked so that recurring problems can be found and eliminated.
Assign Ownership
Balances
should trend
within 5%
If balances cannot be
maintained within target,
install additional meters to
construct new or
additional sub-balances
K3.0 Appendix 1
• For orifice meters, verify that the transmitter or recorder properly accounts for
the square root relationship between the flow and pressure drop.
• Check that orifice plate is stamped with the size shown on the orifice meter
data sheet.
• Check that meter reads zero by closing valve on one meter lead and opening
the equalizing valve on the 3-valve manifold. Also, use this zero test to insure
that the meter you are working on in the field is the correct meter in the moni-
toring computer.
• Verify piping is the diameter shown on the orifice data sheet.
• Verify sufficient lengths of straight run of piping both before and after the
sensing element.
• Ensure no leaks in the root valves, legs, or dP cell manifold.
• Insure safe blowdown valves are installed to keep root valves and legs clear.
• Verify positive flow direction of the meter. For DP meters, insure that the high
leg (+) on the DP cell is connected to the upstream side of the orifice in the
positive flow direction, or if this is difficult, block in one root valve and
partially blow down the leg to drive the meter to 100% positive or negative.
Compensation of orifice meters for pressure and temperature are accomplished
through the use of the following algorithm:
FY = F * CF
FY = Corrected flow rate (MSCFH)
F = Uncompensated flow rate (MSCFH)
CF = Correction factor = @SQRT ((P+PO/RP) *
(RT/(T+TO))*(RG/G))
P = Measured Actual Gauge Pressure (PSIG)
PO = Factor to convert P from PSIG to PSIA, (e.g. 14.696 PSIA at sea
level)
RP = Orifice Data Sheet reference pressure (PSIA)
RT = Orifice Data Sheet reference temperature (degree R)
T = Measured temperature (degree F)
TO = Factor to convert to absolute temperature (459.69 F)
RG = Orifice Data Sheet reference specific gravity
G = Measured specific gravity
K4.0 Appendix 2
K5.0 Appendix 3
fuel gas lines for the purpose of installing flow meters has been successfully done
at the El Segundo refinery.
Application Install if line can be shut- Install if line cannot be Install if flow is steadily Install if flow is normally
down and if the normal shutdown or if flow varies over 175 ft/sec or has over 175 ft/sec or has
flow rate doesn't vary by by more than 3:1 regular excursions higher regular excursions higher
more than a factor of 3:1. Insure that line can be than 250 ft/sec. than 250 ft/sec.
safely hottapped. Insure that line can be Insure that line can be
safety hottapped. safety hottapped.
Design Recommenda- Insure that the normal Don't use a turbine meter Insure that the normal Insure that the normal
tions flow rate will be in the on lines where changes flow rate will be in the flow rate will be in the
upper two-thirds of the in fuel gas flow occur. upper two-thirds of the upper two-thirds of the
meter range. Specify 3 inch flanges on meter range. meter range.
Insure that the normal the meter and use a three Specify 3 inch flanges on Specify 3 inch flanges on
flow rate results in a inch full port valve. the meter and use a three the meter and use a three
"significant" pressure Initially install a 5 or 10 inch full port valve. inch full port valve.
drop across the orifice. degree rotor and monitor Insure that the normal
Use a smart DP cell to the rotor frequency to flow rate results in a
measure orifice pressure insure that the rotor does "significant" pressure
drop for improved accu- not overspeed drop across the flow
racy If the frequency is element.
If low DP's are expected normally greater than 600 Use a smart DP cell to
use a smart DP cell that hertz with a low pitch measure orifice pressure
maintains accuracy at rotor then consider drop for improved accu-
low ranges. installing an annubar or a racy
See Chevron Instrument vortex shedding meter. If low DP's are expected
Manual for further design use a smart DP cell that
information. maintains accuracy at
low ranges.
Effect of liquid in fuel Liquid can build up Slugs of liquid will Liquid will plug the lower Liquid shouldn't hurt the
gas line. behind orifice plate and destroy a 1.5 inch diam- holes of the annubar vortex meter but will
cause inaccuracies eter turbine wheel cause inaccuracies
Installation while Shut down required for Can be hot tapped Can be hot tapped Can be hot tapped
system is on-line installation
Service ability Requires a shutdown to Can be removed and Can be removed and Can be removed and
check orifice. serviced during operation. serviced during operation. serviced during operation.
Condensate in the line is death to turbine meter rotors. Condensate in fuel gas lines
is also not good for the lines themselves and the equipment the lines serve. With
proper drip legs and traps condensate problems can be controlled.
If the flow in the line is very high, such that it would overspeed a five degree rotor
then an insertion averaging pitot tube or vortex-shedding meter should be used.
K6.0 Appendix 4
Required or
Drawing Type Description Desirable
1. Offplot P&ID Offplot P&ID's schematically represent the Required
complete fuel gas distribution system up to the
plot-limit of each plant in the refinery.
2. Offplot Maps Offplot Maps geographically represent the Desirable
offplot fuel gas distribution system up to the plot
limit of each plant in the refinery. They show the
physical routing of lines, and the location of
main valves and meters. They are intended to
be used to locate lines, valves, meters, etc. in
the field, but not for purposes requiring a
detailed representation of the system (e.g. line
isolation plans). For these purposes, the offplot
p&id's should be consulted.
3. Offplot Utility Offplot UFD's are simplified versions of the Desirable
Flow Diagrams p&id's that also indicate typical flow information
not covered on the p&id's.
Required or
Drawing Type Description Desirable
4. On-plot P&ID’s On-plot P&ID’s (or equivalent such as UF&CD’s) Required
or equivalent schematically represent the fuel gas distribution
such as On- system inside the plant plot limit. The fuel gas
Plot Utility Flow system includes fuel gas lines, mixdurms,
& Control knockout pots, analyzers, and meters or instru-
Diagrams ments. UF&CD’s are intended to show all major
fuel gas lines and all branches off these lines.
Because UF&CD’s are not as detailed as P&ID’s,
they are not adequate by themselves for equip-
ment blinding and isolation planning.
The offplot UF&CD and the onplot UF&CD’s also detail the location of flow,
temperature, and pressure meters and analyzers that form the basis of the measure-
ment and validation system. Examples of the above drawings with design criteria
are attached.
K7.0 Appendix 5
Status Codes
00 Refinery decided against implementation
0 Not applicable to this facility
1 No plans underway
2 Evaluating applicability, feasibility and incentives for imple-
menting in facility
3 Developing/updating plans to implement
4 Implementing plan, <50% completed
5 Implementing plan, >50% completed
6 Fully implemented and completed; not confirmed by formal
audit or other means
7 Fully implemented and completed; confirmed by formal audit
or other means