You are on page 1of 2

ENGINEERING & MACHINERY CORPORATION, petitioner, vs.

COURT OF Petitioner moved to dismiss the complaint alleging that the prescriptive
APPEALS AND PONCIANO L. ALMEDA, respondents period of 6 months had set in pursuant to Art. 1566 & 1567, in relation to
Art. 1571 of the Civil Code, regarding the responsibility of a vendor for any
G. R. No. 52267 | January 24, 1996 hidden faults or defects in the thing sold.

Private respondent countered that the contract dated Sept. 10, 1961 was
DOCTRINE(S): Special Contracts; Prescription not a contract of sale but a contract for a piece of work under Art. 1713 of
the Civil Code. Thus, in accordance with Art. 1144(1) of the same Code, the
PONENTE: Panganiban complaint was timely brought within the 10-year prescriptive period.

In its reply, petitioner argued that Art. 1571 of the Civil Code providing for a
6-month prescriptive period is applicable to a contract for a piece of work
FACTS:
by virtue of Art. 1714, which provides that such a contract shall be governed
Pursuant to the contract dated Sept. 10, 1962, Engineering & Machinery by the pertinent provisions on warranty of title and against hidden defects
Corp. undertook to fabricate, furnish and install the air-conditioning system and the payment of price in a contract of sale.
of Almeda’s building along Buendia Ave., Makati for P210,000.00. Petitioner
ISSUE(S):
was to furnish the materials, labor, tools and all services required in order to
so fabricate and install said system. The system was complete in 1963 and 1. Whether the contract is a contract of sale or a contract for a piece
accepted by private respondent who paid in full the contract price. of work
2. Whether or not the action was filed within the prescriptive period
In 1971, Almeda learned that there are defects in the air-conditioning
system of the building. He commissioned Engr. David Sapico to render a RULING:
technical evaluation of the system in relation to the contract with
petitioner. In his report, Sapico enumerated the defects of the system and A contract for a piece of work, labor and materials may be distinguished
concluded that it was not capable of maintaining the desired room from a contract of sale by the inquiry as to whether the thing transferred is
temperature of -2 degree Celsius. one not in existence and which would never have existed but for the order
of the person desiring it. In such case, the contract is one for a piece of
On the basis of this report, private respondent filed on May 8, 1971 an work, not a sale. On the other hand, if the thing subject of the contract
action for damages against petitioner with the CFI of Rizal. The complaint would have existed and have been the subject of a sale to some other
alleged that the air-conditioning system installed by petitioner did not person even if the order had not been given, then the contract is one of
comply with the agreed plans and specifications. sale.

CASE DIGEST: Sales | cassielawst.blogspot.com

1
To Tolentino, the distinction between the two contracts depends on the against hidden defects, but one for breach of the contract itself. It alleged
intention of the parties. Thus, if the parties intended that at some future that the petitioner, “in the installation of the air-conditioning system did not
date an object has to be delivered, without considering the work or labor of comply with the specifications provided” in the written agreement between
the party bound to deliver, the contract is one of sale. But if one of the the parties, “and an evaluation of the air-conditioning system as installed by
parties accepts the undertaking on the basis of some plan, taking into the defendant showed defects and violations of the specifications of the
account the work he will employ personally or through another, there is a agreement.
contract for a piece of work.
Having concluded that the original complaint is one for damages arising
Clearly, the contract in question is one for a piece of work. It is not from breach of a written contract – and not a suit to enforce warranties
petitioner’s line of business to manufacture air-conditioning systems to be against hidden defects – the Court declared that the governing law is Art.
sold “off-the-shelf”. Its business and particular field of expertise is the 1715. However, inasmuch as this provision does not contain a specific
fabrication and installation of such systems as ordered by customers and in period, the general law on prescription, which is Art. 1144 of the Civil Code,
accordance with the particular plans and specifications provided by will apply. Said provision states, inter alia, that actions “upon a written
customers. contract” prescribe in ten (10) years. Since the governing contract was
executed on Sept. 10, 1962 and the complaint was filed on May 8, 1971, it is
The obligations of a contractor for a piece of work are set forth in Articles clear that the action has not prescribed.
1714 & 1715 of the Civil Code.

In Villostas v. Court of Appeals, the Court held that “while it is true that
Article 1571 of the Civil Code provides for a prescriptive period of six
months for a redhibitory action, a cursory readying of the ten preceding
article to which it refers will reveal that said rule may be applied only in case
of implied warranties”; and where there is an express warranty in the
contract, as in the case at bench, the prescriptive period is the one specified
in the express warranty, and in the absence of such period, “the general rule
on rescission of contract, which is four years (Article 1389, Civil Code) shall
apply”.

Consistent with the above discussion, it would appear that this suit is barred
by prescription because the complaint was file more than 4 years after the
execution of the contract and the completion of the air-conditioning system.

However, a close scrutiny of the complaint filed in the trial court reveals
that the original action is not really for enforcement of the warranties
CASE DIGEST: Sales | cassielawst.blogspot.com

You might also like