Professional Documents
Culture Documents
Sec 14. - Flooring
Sec 14. - Flooring
14. FLOORING
GENERAL
The tier or levels which divide a building in two stages or storeys are called floors. These
are made of materials quite different both in composition and construction. They range from
relatively thin covering, contributing little or no structural strength to a building, to much
thicker materials capable of withstanding reasonable stresses, and in some designs,
essential to the strength of the building.
EARTH FLOORING
14.1.1 SCOPE
Unless otherwise specified, earth flooring shall be constructed in accordance with the
following specifications.
14.1.2 MATERIAL
Earth (clay) shall conform to following Specifications:
Source: Clay shall be obtained from good earth containing 20 % to 30% fine sand.
Quality: Clay shall not contain more than 0.5% soluble salts more than 0.2% sulphate and
more than 4% organic contents. It shall not contain any gravel, coarse sand, kanker roots of
the grass and plant.
14.1.4 MEASUREMENTS
Length and breadth of the flooring shall be measured correct to a cm and area shall be
calculated in square metres correct to two places of decimal. Length and breadth shall
be measured before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 sqm. Deduction for ends of dissimilar
materials or other articles embedded shall not be made for areas not exceeding 0.10
sqm.
MUD FLOORING
14.1.5 SCOPE
Unless otherwise specified, mud flooring shall be constructed in accordance with the
following specifications.
14.1.6 MATERIAL
a) Earth (clay) shall conform to Specifications as mentioned above 14.2.
b) Mortar shall conform to Specifications in Section 11- Brickworks Mud Mortar.
Laying
After laying earth floors as per Specifications 14.2 for Earth Flooring, the surface shall be
finished with one-inch-thick mud plaster with gobri leeping conforming to Specifications in
Section 15.1.12 for Mud Plaster.
1
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.7 MEASUREMENTS
Length and breadth of the flooring shall be measured correct to a cm and area shall be
calculated in square metres correct to two places of decimal. Length and breadth shall
be measured before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 sqm. Deduction for ends of dissimilar
materials or other articles embedded shall not be made for areas not exceeding 0.10
sqm.
14.1.9 MATERIAL
a) Brick or tile shall conform to Specifications as mentioned in Section 11 for Clay Bricks.
b) Mortar shall conform to Specifications as mentioned in Section 11– Brickwork, Mortars.
14.1.10 BASE
The construction and preparation of base for ground floor and subsequent levels shall
comply with the provisions of Clause 14.10.
14.1.12 PATTERN
The laying of bricks or tiles shall be plain, diagonal, herring-bone or any other specified
pattern.
14.1.13 JOINTS
a) Where pointing is not to be done the Joints shall not exceed 3/16 inch in thickness.
The mortar oozing out of the joints shall be struck off with trowel or wiped off with
damp cloth.
b) Where pointing is to be done the joints shall not exceed 3/8 inch in thickness. The
mortar in the Joint shall be raked out one inch deep while it is still green.
14.1.14 POINTING
Otherwise specified, the joints shall be flush pointed with specified mortar.
14.1.17 PROTECTION
Flooring shall be allowed to mature, undisturbed, and protected from the effects of weather.
It shall be kept wet for at least 7 days after completion. If pointing is to be done, it shall be
kept wet for at least 14 days after the completion of pointing.
2
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.18 SURFACE
Surface shall be finished to specified levels. All joints shall be uniform, true and parallel and
square bricks shall be rubbed to ensure this where it is very necessary, without extra cost.
14.1.20 MEASUREMENTS
Length and breadth of the flooring shall be measured correct to a cm and area shall be
calculated in square metres correct to two places of decimal. Length and breadth shall
be measured before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 sqm. Deduction for ends of dissimilar
materials or other articles embedded shall not be made for areas not exceeding 0.10
sqm.
14.1.22 MARBLE
Marble slabs of an approved quality shall be used. The marble shall be super white,
Lasbela, Ziarat, Loralai or Badal as specified.
14.1.23 MORTARS
Cement sand mortar on which marble tiles are placed shall be 1:3 unless otherwise
specified
14.1.24 BASE
For ground and subsequent floors, the base shall be laid as per Specifications 14.10.
14.1.29 LAYING
Slabs shall be laid in position on bedding mortar in specified pattern. The joints shall be filled
with specified putty.
3
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.30 LEVELS
The surface of marble slabs when laid shall be perfectly true, level, projected or sloped.
14.1.32 POLISHING
The day after the tiles are laid all joints shall be cleaned of the cement grout containing
matching pigment with a wire brush or trowel and all dust and loose mortar removed and
cleaned. Joints shall then be grouted with grey or white cement mixed with or without
pigment to match the shape of the marble tiles.
The surface shall thereafter be grounded evenly with machine fitted with coarse grade
grit block (No. 60). Water shall be used profusely during grinding. After grinding the
surface shall be thoroughly washed to remove all grinding mud, cleaned and mopped.
It shall then be covered with a thin coat of grey or white cement, mixed with or without
pigment to match the colour of the topping of the wearing surface in order to fill any pin
hole that appear. The surface shall be again cured. The second grinding shall then be
carried out with machine fitted with fine grade grit block (No. 120).
The final grinding with machine fitted with the finest grade grit blocks (No. 320) shall be
carried out the day after the second grinding described in the preceding para or before
handing over the floor, as ordered by the Engineer-in-Charge.
For small areas or where circumstances so require, hand grinding/polishing with hand
grinder may be permitted in lieu of machine polishing after laying. For hand polishing the
following carborundum stones, shall be used:
In all other respects, the process shall be similar as for machine polishing. After the final
polish, oxalic acid shall be dusted over the surface at the rate of 33 gm per square
metre sprinkled with water and rubbed hard with a pad of woollen rags. The following day
the floor shall be wiped with a moist rag and dried with a soft cloth and finished clean.
If any marble tile is disturbed or damaged, it shall be refitted or replaced, properly jointed
and polished. The finished floor shall not sound hollow when tapped with a wooden
mallet.
14.1.33 MEASUREMENT
Length and breadth shall be measured before laying skirting, dado or wall plaster. No
deduction shall be made nor extra paid for voids not exceeding 0.20 sqm. Deductions for
ends of dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 sqm.
4
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
The flooring done either with strips (in one operation) or without strips (in alternate panels)
shall be treated as same and measured together.
14.1.34 RATE
Marble stone flooring with different kind of marble shall be measured separately and in
square metre correct to two places of decimal. Length and breadth shall be measured
correct to a cm before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 square metre. Deductions for ends of
dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 square metre. Nothing extra shall be paid for laying the floor at
different levels in the same room. Steps and treads of stairs paved with marble stone
slabs shall also be measured under the different item of work. The width of treads shall be
measured from the outer edge of the nosing, as laid, before providing the riser.
b) Quality
The tiles shall be non-slippery fully glazed on the face, uniform in colour free from cracks
and other defects arises to be sharp and true.
c) Shape
Tiles shall be true and even face and even thickness throughout. The backs shall be with
bond undercut key sufficient to ensure a good grip of the fixing medium. For wall tiling the
tiles shall have holed formed in the edges to take galvanized or copper clamps.
14.6.2.1 MEASUREMENTS
Length and breadth shall be measured before laying skirting, dado or wall plaster. No
deduction shall be made nor extra paid for voids not exceeding 0.20 sqm. Deductions for
ends of dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 sqm. The flooring done either with strips (in one operation) or without
strips (in alternate panels) shall be treated as same and measured together.
MEASUREMENTS
Length and breadth shall be measured before laying skirting, dado or wall plaster. No
deduction shall be made nor extra paid for voids not exceeding 0.20 sqm. Deductions for
5
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
ends of dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 sqm.
14.1.38 SOURCE
The mosaic tiles shall be obtained from an approved source. If manufactured by the
Employer through a contractor, the method of manufacturing shall be 'approved by the
Engineer-in-charge.
14.1.39 QUALITY
Tiles shall be hydraulically pressed and fully cured. They shall be uniform in colour, free from
cracks and other defects like efflorescence and crazing, the arises to be sharp and true.
Pattern tiles shall bear the approved pattern on their faces. Mosaic tiles shall have polished
surfaces. The constituent materials shall be as specified by the Engineer-in-charge.
14.1.40 SHAPE
Tiles shall be true and even on face and of even thickness throughout. The backs shall be
with bond under-cut key sufficient to ensure a good grip of the fixing medium. For wall tiling,
tiles shall have holes formed in the edges to take galvanized or copper cramps.
14.1.41 SIZE
The size of the tile shall be as specified.
14.1.42 TEST
A fully dried tile when immersed in water for any length of time shall not absorb water more
than 2.5 per cent of the weight of dry tile.
14.1.44 MEASUREMENTS
Length and breadth shall be measured before laying skirting, dado or wall plaster. No
deduction shall be made nor extra paid for voids not exceeding 0.20 sqm. Deductions for
ends of dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 sqm.
14.1.46 MATERIAL
a) Bricks shall conform to Specifications as mentioned in Section 11 for Clay Bricks.
b) Sand shall conform to Specifications No. 14.10 for Base for Flooring.
6
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.48 LAYING
Bricks shall be laid dry, on edge or flat in the specified pattern over half an inch-thick mud
plaster given on the surface. The joints shall not exceed one quarter of an inch in thickness.
After laying the bricks the Joints shall be sand grouted. Where required, the joints shall be
filled with specified cement sand mortar.
14.1.49 MEASUREMENT
Length and breadth of the flooring shall be measured correct to a cm and area shall be
calculated in square metres correct to two places of decimal. Length and breadth shall
be measured before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 sqm. Deduction for ends of dissimilar
materials or other articles embedded shall not be made for areas not exceeding 0.10
sqm.
Brick flooring when laid in diagonal herring bone bond or other pattern as specified or
directed by the Engineer-in-Charge shall be measured separately.
WOODEN FLOORS
14.1.50 FLOOR BEARER GROUND FLOOR
In the case of ground floors, floor joists (bridging joists) shall rest on pillars, dwarf walls, rails
or beams as may be specified.
The plinth under the flooring shall be excavated to the depth specified by the Engineer-in-
charge and dressed level and rammed. If directed a suitable protective layer as approved by
the Engineer-in-Charge shall be laid otherwise dwarf walls or pillars shall be built on the
specified concrete foundation. The dimensions and spacing shall be as indicated in the
drawings or otherwise directed by the Engineer-in-Charge.
7
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.55 JOINTS
The planks shall be planed true on one side (on both sides for uncoiled upper floors) the
edges to be planed, rebated or tongued and grooved as directed by the Engineer-in-charge.
Unless otherwise specified, the edges shall be tongued and grooved, with concealed joints
for teak wood floors, and rebated joints for other floors.
14.1.58 PLANNING
After the floor has been laid, it shall be planned in both directions and made perfectly
smooth. All depressions in the wood nail holes and all small defects of every kind, where
permitted by the Engineer-In-charge to remain in the work, shall unless otherwise specified,
be filled with "Beaumont age" or stopping out wax.
14.1.59 MEASUREMENT
Length and height shall be measured correct to a cm and its area shall be calculated in
sqm correct to two places of decimals for a specified the thickness. Length shall be
measured as the finished length of skirting. Height shall be measured from the finished
level of floor correct to 5 mm.
Source:
Clay shall be obtained from good earth approved by the Engineer-in-Charge containing 20
% to 30% fine sand.
Quality:
Clay shall not contain more than 0.5 % soluble salts more than 0.2 % sulphate and more
than 4% organic contents. It shall not contain any gravel, coarse sand, kanker, the grass
and plant.
Earth filling shall be done up to the specified level in a layer of six inches and shall be
properly watered and consolidated as specified hereunder:
8
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Earth shall be placed in layers and shall be sprinkled with water and rammed to such an
extent that a layer of 6 inches thick loose earth evenly spread is reduced to 4 inches in
thickness. The consolidated surface shall be such that a very faint impression can be made
on it with the heel of boot or the blow of hammer.
The sub-base shall be properly levelled before sand filling.
14.1.63 CONCRETE
Concrete shall be cement concrete as specified and shown on drawings complying with the
provisions of Section 5 – Plain and Reinforced Concrete.
9
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
avoid, cracks the area of a panel is restricted to 16 square feet unless otherwise approved
by the Engineer-in-Charge
b) The concrete for flooring shall comply with the requirements of Section 5 – Plain &
Reinforced Concrete.
c) Division strips shall be cut from 5 mm thick glass plate in width as specified in drawings or
as directed by the Engineer-in-Charge
14.1.69 MATERIALS
a) Cement, Sand, Aggregate for concrete and water shall conform to relevant
specifications given in Section - 5, Concrete.
b) Sub-base / Base shall conform to the provisions of Clause 14.10.
c) Marble chips shall be crushed marble and shall be best quality white or coloured. It
shall have an abrasive hardness of not less than 16 and the size shall vary from
No. 4 to 8 as specified or as directed by the Engineer-in-Charge.
d) Dividing strips of glass shall be 5mm thick and 38mm wide or as required in the
Drawings.
e) Mineral Pigment for colouring the matrix of terrazzo / mosaic shall be of the best
quality and purity and shall be alkali resistant, sun proof and lime proof with a
specific gravity similar to that of Portland Cement and as approved by the
Engineer-in-Charge.
f) Commercial products for polish shall be of the best quality available as approved
by the Engineer-in-Charge.
14.1.72 PLACEMENT
The cement concrete base shall be levelled with a trowel and straight edge, consolidated
and finished with steel trowels to an even but rough surface. the top layer of cement marble
chips mixed in the proportion of 1:2 (1 cement and 2 marble chips) and pigment, if required,
shall be laid over it within 24 hours. The cement and marble chips must be mixed dry in
such quantities as are sufficient for a unit of specified shade. Water shall be added to only
10
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
such quantities as can be mixed thoroughly and consumed in less than 30 minutes, the
quantity of water being. the minimum for workability. Mixing must be done on water tight
platform and any mix not used within 30 minutes shall be discarded .and removed from the
site. A layer of cement and marble chipping mixture should be well trowelled into the surface
of the base concrete before filling to the top level of the screeds. The layer should be well
compacted and all voids shall. be filled in. A layer of neat cement, of the specified colour
shall then be well trowelled into the surface leaving a plain smooth surface.
14.1.74 MEASUREMENTS
Length and breadth shall be measured correct to a cm before laying skirting, dado or
wall plaster. The area as laid shall be calculated in sqm correct to two decimal places.
The thickness of the under layer shall be measured correct to a cm. The thickness of
top layer shall not be less than that specified.
No deduction shall be made, nor extra paid for voids not exceeding 0.20 square metre.
Deduction for ends of dissimilar materials or other articles embedded shall not be made
for areas not exceeding 0.10 square metre. Nothing extra shall be paid for laying the
floor at different levels in the same room or courtyard.
Terrazo (Marble Chips) flooring laid as floor borders, margins and similar bands upto
30 cm width and on staircase treads shall be measured under the item of terrazo
flooring but extra shall be paid for such work. This extra in the case of staircase treads
shall include the cost of forming the nosing also. However, moulded nosing shall be paid
for staircase treads etc. extra in running metres except where otherwise stated, returned
11
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
moulded ends and angles to mouldings shall be included in the description. Extra
shall also be paid for laying flooring in narrow bands not exceeding 7.5 cm in width
and such bands shall be measured in running metres for this purpose.
Special surface finishes to treads, risers and the ends of concrete steps and the like
shall be measured separately and given in square metres and shall include form work, if
required.
14.1.75 TERRAZZO DADO & SKIRTING
The plastered surface over which the dado/skirting is to be applied shall be well roughened
and watered; cement mortar of specified ratio shall then be plastered over this well
roughened surface to. the indicated thickness. Before the base course has set the layer of
mosaic mixture shall be well trowelled into the surface of the base to a thickness which
after grinding shall result in the finished thickness. A layer of neat cement of the specified
colour shall then be well trowelled into the surface leaving a plain smooth surface. The
Contractor shall start finishing as specified for floors above. Mosaic skirting shall be
provided around all mosaic floors unless shown otherwise. Skirting and dado shall' be
straight, level and in plumb. Intersections at floors shall be straight and flush.
14.1.76 MEASUREMENT:
Same as 14.12.7
14.1.77 MATERIALS
a) Cement shall conform to ASTM C150 / C150M -09 Standard Specifications for Portland
Cement.
b) Fine Aggregate
Source:
Fine Aggregate shall be obtained from an approved source.
Grading:
Fine Aggregate shall consist of well graded sand, stone screening or other inert material of
similar characteristics, or a combination of these. The whole of it shall pass through 3/16
inch sieve and 2 to 10 per cent through sieve No. 100.
Cleanliness:
Fine aggregate shall be clean and free from clay lumps, soft and flaky particles shale, alkali,
organic matter, loam, mica and injurious amounts of deleterious substances. The sum of
percentages of all deleterious substances shall not exceed 5 per cent by weight.
Quality:
Fine aggregate shall be sharp, cubical, hard dense and durable.
Storage:
Fine aggregate shall be stacked on a brick, wooden or other suitable platform so as to
adequately protect it from dust and other impurities.
12
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
(d) Water
Source:
Water for construction shall be obtained from an approved source.
Quality:
Water shall be free from earth, vegetable, organic impurities and any other substance likely
to cause efflorescence or interfere with setting of mortars or otherwise prove harmful to the
work. Broadly speaking any water which does not show any intensive odour or brackish
taste shall be considered suitable for building works, whereas water fit for drinking shall be
accepted as suitable for all engineering works. PH value of water shall range between 6 & 8.
Storage:
Water shall be stored in watertight tanks or containers so as to be adequately protected from
the admixture of dust and other foreign matter.
14.1.78 BASE
The base for ground and subsequent floors shall be laid as per Specifications 14.10.
14.1.79 OPERATION
Unless otherwise specified conglomerate flooring shall consist of laying a topping of cement
concrete of specified thickness over the base.
13
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.84 CONSOLIDATION
Placing operation shall be specifically timed. No sooner the concrete has been evenly
spread in a panel, than it shall be beaten for about 5 to 10 minutes with "wooden thapies"
(about 5 Ibs weight).
14.1.85 FINISHING
Immediately after consolidation, the surface shall be levelled with a wooden trowel.
Excessive trowelling in the early stage shall be avoided. The surface shall be tested with a
straight edge to detect undulations, which, if found, shall be eliminated. The fines in the
concrete which has come to the surface with the stroking shall be quickly but carefully
smoothed with the steel trowel. When the concrete has hardened sufficiently, trowelling shall
be done with steel trowel. No dry cement or a mixture of dry cement with sand shall be
sprinkled on the surface for hardening the surface.
14.1.86 CURING
The concrete for topping shall be cured in accordance with Section 5 – Plain & Reinforced
Concrete.
Unless otherwise specified, the conglomerate flooring (two coat work) shall be constructed
in accordance with Specifications 14.13 for Conglomerate Floor (Single coat) except with
the following modifications: -
i) It shall be laid in two layers with a top layer half an inch thick, wearing surface composed of
cement and fine aggregate conforming to the provisions of Sub-section 14.13.1 and a
bottom layer of cement concrete conforming to Specifications as mentioned in Section 5 –
Plain & Reinforced Concrete, of specified thickness.
ii) Unless otherwise specified, the cement concrete for the bottom layer shall be composed of
one cubic foot of cement, 3 cubic feet of fine aggregate and 6 cubic feet of coarse aggregate
by volume and shall conform to the applicable provisions of Section 5 – Plain & Reinforced
Concrete.
iii) Unless otherwise specified, the surface layer shall compose of one part of cement and two
parts of fine aggregate by volume. The pigment of approved shade and colour may be
added to give the desired colour to the topping layer.
iv) The bottom layer shall be brought to a level so that top layer shall have a minimum
thickness of half an inch. The bottom layer shall be thoroughly compacted by tamping but
shall not be finished smooth. While the bottom layer Is still plastic, the top layer shall be
placed over it and levelled with a steel float after light tapping for five minutes.
a) General
14
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Such flooring shall consist of PVC flexible sheet or tile of the colour as per drawings or
directed by the Engineer-in-Charge. It shall conforms to the relevant Standards
PVC Tiles (Static): PVC tiles / sheet of requisite thickness shall be of best quality available in
the Country. Size, colour, shade and adhesive shall be as per the sample which shall be
submitted by the Contractor and approved by the Engineer.
PVC Tiles (Anti-static): PVC tiles / sheet of requisite thickness shall be of best quality
available in the Country Size, colour, shade, import quality copper strips and conductive
adhesive shall be as per the sample which shall be submitted by the Contractor and
approved by the Engineer.
For new floors between two dry contact electrodes no individual reading shall be greater
than 5 x 106 Ω than 2x 104 Ω. The average of all readings shall remain between 2 x 106 Ω
and 5 x 104 Ω.
For existing floors between two dry contact electrodes no individual reading shall be greater
than 5 x 10 7Ω. The average of all readings shall be 2 x107Ω.
c) Installation Method
The base shall be prepared as per thickness shown on drawings keeping the margin of tile
thickness. After the base is cured, any irregularities found on the base shall be filled in and
levelled before the application of tiles. Surface to receive tiles shall be thoroughly cleaned of
all dirt, dust, oil and other objectionable matter. Approved manufacturer’s recommended
adhesive shall be applied as per specifications and in quantities recommended by him.
Tiles/sheets shall be laid starting from one side of the room or as per the instructions of the
Engineer and shall be so pressed that complete adhesion takes place.
Tiles/sheet shall be cut where required with suitable cutting tool and rough edges shall be
rubbed smooth. Tiles shall be laid to straight edges as per approved pattern
d) Preparation of Base
The base shall be prepared as per thickness shown on drawings keeping the margin of tile
thickness and network of Copper Strips. After the base is cured, any irregularities found on
the base shall be filled in and levelled before the application of sheets/ tiles. Surface to
receive tiles / sheets shall be thoroughly cleaned-off all dirt, dust, oil and other objectionable
matter. Approved manufacturer’s recommended adhesive shall be applied as per
specifications and in quantities recommended by him. Tiles/sheets shall be laid starting from
15
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
one side of the room or as per the instructions of the Engineer and shall be so pressed that
complete adhesion is ensured. Tiles/sheets shall be cut where required with suitable cutting
tool and rough edges shall be rubbed smooth. Tiles shall be laid to straight edges as per
approved pattern.
Lay the full lengths of copper strips across the room on both sides cutting each other. Each
strip must be at a distance of 12” from each other and 24” from the other. The joints of these
sheets must be properly acid welded. Keep as many points of the copper strip as you require
out from the ends for earthing purpose. Similarly the whole copper grid must be properly
earthed. To do so one part of this grid shall be attached to the earthing point of the room.
The non-static tiles shall then be laid on the floor. This grid shall only be necessary for
assuring the continuity. The strip shall pass beneath of the tile to give proper resistance.
Mark out the room area with chalk lines across length and width, positioned to allow
for reasonably sized tile cuts on all sides.
The new trowel blade enclosed with the adhesive shall be fitted when starting the
pack and used for spreading one pack only.
Stir the adhesive before use.
Spread the adhesive evenly holding the blade at an angle of about 60 degrees.
Good transfer is essential; the area spread with adhesive at any time shall be limited
to ensure that all the tiles and cuts can be laid while the adhesive is still wet.
Commence tiles laying at the point first spread so that the adhesive has been left
open for approximately 15 minutes. The actual area spread and the open time shall
depend on the absorbency of the sub-floor and ambient conditions. Do not spread
more than one pack at a time.
Ensure electrical conductivity by overlapping adjacent areas of adhesive application.
Put tiles closely and press them firmly to the floor to give good contact over the
whole tile area.
Approximately 1-hour after laying the tiles apply suitable pressure on them to ensure
overall good contact. Care shall be taken that adhesive shall not squeeze up
between the tiles, and if it happens then immediate cleaning of it shall be necessary.
Dried adhesive residue shall be removed with a slightly abrasive cloth.
g) Traffic
Electrical testing shall be carried out until at least 21-hours after completing the installation.
The method shall be as laid down or as specified. The following summarizes the procedure
recommended in NHS technical memorandum No. 2 (1977)
h) Equipment
An insulation testing ohm meter having an approximate open circuit voltage of 500 volts DC
and capable of measuring resistance values of between 104 and 5 x 107Ω.
i) Method
The finished surface of concrete screed as floor base shall be washed thoroughly and then
be allowed to dry (no test shall be carried out within 2-hours of floor being wetted) with
subsequent wiping over it with a dry cloth. Place the electrodes approximately 12” apart and
measure the resistance between them. In order to check the actual resistance the black
16
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
bottom layer shall have to be checked, to do this either puncture a tiny hole on the surface of
the tile or check the resistance from the left out copper strips on the ends of the floor.
14.1.90 POLISHING
After the washed floor has dried, a final gloss shall be given by polishing the surface to the
satisfaction of the Engineer-in-Charge.
14.1.91 FINISHING
The walls and all surfaces of the finished works of other trades shall be properly protected
from damage and spoiling during the process of grinding and washing of the mosaic. After
the finishing grinding has been completed and the surface treatment and polish applied, the
floor shall be covered and protected with material approved by the Engineer-in-Charge until
completion of the work of all trades.
FLAGGED FLOORING
14.1.92 SCOPE
Unless otherwise specified, flagged flooring shall be constructed in accordance with the
following specifications.
14.1.93 STONE
The flags are the rectangular stone slabs of specified size. The specified stones from which
the flags are made shall conform to Sub-section 12.1.2 for Stone of Stone Masonry.
14.1.94 MORTAR
Mortar shall be cement mortar complying with Sub-section 11.7.2 (ii) – Brickwork.
17
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.95 BASE
The base shall be laid as per Sub-section 14.10, Flooring.
14.1.97 DRESSING
Flags shall be chisel dressed so as to have a flat surface, free from windings. All edges shall
be accurately dressed, truly square to their full depth. Flags projecting over the edges of
verandahs or steps shall have their outer edges bull-nosed.
14.1.98 SOAKING
Flags that be soaked in water for one hour before laying.
14.1.99 JOINTS
The thickness of joints shall not be more than 1/8 of an inch. Unless otherwise specified, the
mortar in joints shall be made flush with a trowel.
14.1.100 POINTING
If pointing has been specified, the flags shall be laid against wood or iron strips of uniform
thickness, so as to form joints not less than ¼ inch wide. When a row of flags is laid, the
strips shall be removed and the open joints shall at once be filled with specified mortar, and
shall then be flush pointed with specified mortar.
14.1.103 PATTERN
Flags shall be laid in the specified pattern. The courses shall be of uniform width and, unless
otherwise specified, parallel to the wall having the main entrance. Flags shall break joint in
adjacent courses by not less than 8 inches.
MURUM FLOORING
14.1.105 SCOPE
The work shall include furnishing all labour, materials, equipment, and performing all
operations specified herein to lay the murum floors in accordance with the drawings, or as
directed by Engineer-in-charge.
18
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.106 MATERIALS
a) All murum used in construction murum flooring shall be in complete conformity with the
applicable requirements set forth in this section
b) Rubble or broken bricks
14.1.108 LAYING
All murum floors shall be constructed in accordance with the detail shown on drawings, the
Engineer-in-charge’s instructions and the stipulations and requirements set forth herein, as
follows:
a) The dug out surface as mentioned in 14.9.3 above shall be properly watered and
rammed with hand rammers sufficiently to the entire satisfaction of Engineer-in-charge.
The consolidated surface shall be such that a very faint impression can be made on it
with the heel of boot or the blow of hammer.
b) Sub-base of broken bricks or hand packed rubble shall be laid to a template evenly and
watered thoroughly and allow to dry. The surface shall be fairly levelled and beaten with
rammers to produce one uniform level. Up-to the entire satisfaction of the Engineer-in-
charge.
c) Then a layer of good hard murum, 150 mm thick, shall be added and water thoroughly
for 2 days. When the whole mass has become too slushy, it shall be tempered over by
coolies so as to form a one uniform mass. Then the surface shall be fairly levelled and
beaten with hand rammers, to one uniform level. It shall be then allowed for dry for 2 to 3
days.
d) Finally, spread 25 mm layer of fine powder or flaky variety of murum, which shall be
thoroughly beaten by hand rammers. As a check of good work, the surface shall not now
crack on drying and the floor is complete.
14.1.109 MEASUREMENT:
Length and breadth shall be measured correct to a cm before laying skirting, dado or wall
plaster and the area calculated in square metre correct to two places of decimal. Where
coves are used at the junctions, the length and breadth shall be measured between the
lower edges of the coves.
No deduction shall be made nor extra paid for voids not exceeding 0.20 square metre.
Deductions for ends of dissimilar materials or other articles embedded shall not be
made for areas not exceeding 0.10 square metre.
19
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
14.1.111 SCOPE
The work shall include furnishing all labour, materials, equipments, plants, instruments,
accessories and services necessary to complete the work at the locations shown on the
drawings or as directed by Engineer-in-charge in accordance with these specifications.
Materials
a) Brick shall conform to Specifications as mentioned in Section 11 for Clay Bricks.
b) Mortar shall conform to Specifications as mentioned in Section 11– Brickwork,
Mortars.
14.1.112 LAYING
Grouting dry brickwork with cement mortar of specified mix proportion shall be done in
accordance with the details shown on drawings, the Engineer-in-charge instructions and the
stipulations and requirements set forth herein, as follow;
a) Grout shall be made by mixing specified cement: sand mix proportion with water to
produce mortar with specified consistency or as directed by the Engineer-in-charge, so
as to form a watery paste of about the consistency of cream to flow into the joints of dry
brick work and filled the joints fully upto the surface subject to the approval of Engineer-
in-charge. The surplus grout sticking to the surface of the dry brickwork shall be swept
over and the surface shall be cleared.
b) Only so much should be mix in one time as can be used before it commences to set and
any which has begun to stiffen should be rejected.
CARPET FLOORS/TILES
14.1.113 GENERAL
The Contractor will submit duplicate 3 foot square pieces of each type of carpet specified,
for the approval of the Engineer-in-Charge.
14.1.116 PRODUCTS
Maintenance material: deliver to the Engineer-in-Charge additional carpet equal to 5% of
carpet used in the project and include a sufficient amount of adhesive in unopened
containers to apply the carpet. Identify each roll. Store where directed. Maintenance
materials to be full size piece of same production run as installed materials.
14.1.117 MATERIALS
Carpets as selected by the Engineer-in-Charge.
Carpet grippers: types recommended by carpet manufacturer.
Seaming tape: hot melt type as recommended by carpet manufacturer for purpose
intended.
Binder bars: brass of type recommended by carpet manufacturer.
Adhesive: release type, water resistant, non-staining adhesive as recommended by carpet
manufacturer.
20
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Carpet protection: non-staining heavy duty kraft paper or 0.15 mm thick polyethylene film.
b) Binder Bars
Use metal binder bars at exposed carpet edges and centre under doors in door openings.
c) Carpet Installation
Install carpet in accordance with shop drawings. Hot melt seams and cross-joints. Maintain
constant pile direction.
Fit sections of carpet into each space prior to application of adhesive. Trim edges and butt
cuts with seaming cement.
Apply adhesive uniformly to substrate in accordance with manufacturer's instructions. Butt
carpet edges tightly together to form seams without gaps.
Roll entire carpet area lightly to eliminate air pockets and ensure uniform bond.
Remove any adhesive promptly from the face of the carpet by a method that will not
damage the carpet surface and in accordance with the manufacturer's recommendations.
14.1.119 MEASUREMENT:
Length and breadth shall be measured correct to a cm before laying skirting, dado or wall
plaster and the area calculated in square metre correct to two places of decimal. Where
coves are used at the junctions, the length and breadth shall be measured between the
lower edges of the coves.
No deduction shall be made nor extra paid for voids not exceeding 0.20 square metre.
Deductions for ends of dissimilar materials or other articles embedded shall not be made for
areas not exceeding 0.10 square metre.
EPOXY FLOORING
21
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
a) General
Epoxies are polymer materials that begin life as liquids and are converted to the solid
polymers by a chemical reaction. An epoxy based polymer is mechanically strong,
chemically resistant to degradation of the chemical elements in the solid form and highly
adhesive during conversion from liquid to solid. There are a wide range of basic epoxy
chemicals from which an epoxy system can be formulated.
Epoxies are known for their excellent adhesion, chemical and heat resistance, good to
excellent mechanical properties and very good electrical insulating properties. Almost any
property can be modified. Epoxy is safe and there are no known harmful effects of the
chemicals used in the mixture. It also has a high resistance to chemicals such as gasoline,
salt, grease, oil and solvents.
Impact Resistance: Epoxy floors are generally used in areas of industry where goods are
handled in specific spaces, such as production lines, warehouses, loading bays, and where
compressive loads are generated by the movement of goods on trucks, pallets etc.
Slip Resistance: Pedestrian traffic areas require varying degrees of slip resistance
dependent on whether the environment is wet or dry.
Fire Resistance: Fire escape routes, explosive production and storage areas underground
car park decks.
Chemical Resistant: Epoxy floor coverings provide an impermeable seal to protect floor
from chemical attack.
Smooth Surface / New Casted Floor: Depending on surface we can provide the epoxy
system for smooth floor epoxy coating from 500-micron 1mm system
22
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Control Joints: Checking if joints / grooves are cut and filled with joint sealant.
d) Application Method: -
Surface preparation
Surface life of the sealer is primarily dependent on the good surface preparation. Sealers life
will be extended by following few key points:
The concrete must be cleaned free of old existing coatings, oils, grease, and dirt
and wax solutions.
Grind the floor to open the pores and remove dirt, debris and other containments.
If there are any cracks, filling of cracks
Filling of control joints.
Remove all debris from working area.
Mixing Procedures
Epoxy penetrating sealer is a two-component system. Mix component A “resin” with
component B “Hardener” in the ratio of 1:1, mix with the help of power mixer @ 200rpm-
300rpm until an even colour develops (2-3 minutes)
DOs DON’Ts
Clean Immediately with detergent and Warm water in
Spill chemical / oil / grease on the floor
the event of chemicals/Oil/grease spillage
Vacuum clean regularly clean floor with detergent and
warm water using soft Bristle to avoid scratch. Polish Let sand inside use air lock or air curtain
as per Manufacturer’s instructions.
Maintain reasonably constant temperature Store react able solvent without proper instruction
Regular maintenance of trolleys and forklifts. Prevent
Use imbalance wheels
locking of wheels.
23
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Keep mats underneath before placing heavy weights Drag heavy objects on the floor as it will lead to
on the floor. scratches
Check the pallets and ensure that no nails or protruding Drop sharp and heavy objects on the floor as it will
in trolleys/ forklifts leave dents and marks
Repair leakage in water pipes, air ducts immediately to
avoid pressure beneath the substrate which could lead
to blisters on the floor.
14.1.120 MEASUREMENT:
Length and breadth shall be measured correct to a cm before laying skirting, dado or wall
plaster and the area calculated in square metre correct to two places of decimal. Where
coves are used at the junctions, the length and breadth shall be measured between the
lower edges of the coves.
No deduction shall be made nor extra paid for voids not exceeding 0.20 square metre.
Deductions for ends of dissimilar materials or other articles embedded shall not be
made for areas not exceeding 0.10 square metre.
LAMINATE FLOORING
Laminate Flooring is considered a “floating” floor and is installed using a floating floor
system. These floors are intended for indoor use only and can be installed over virtually any
existing floor structure. Since these floors are composed of natural cellulose fibres, they will
expand and contract with changes in relative humidity.
b) Wood subfloors must be suspended and have a minimum of 18” (45.7 cm) of well-
ventilated crawl space. Regardless of grade level, do not install over wood subfloors
applied directly to concrete or on sleepers over concrete. Installation of a polyethylene
film vapour barrier such as Armstrong Moisture Barrier Sheeting over the ground in the
crawl space is recommended. The polyethylene film acts as a moisture barrier when
seams are taped together with polyethylene tape.
24
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
to 3” (5 cm to 7.6 cm) wide facing strip such as ¼” (6.35 mm) plywood to the wall
at the stud location.
New wall base or moulding must be installed at the end of the job to cover the 1/4″
(6.35 mm) to 1/2″ (12.7 mm) expansion zone around the perimeter of the floor.
It may be necessary to plane or cut the bottom of the door to accommodate the
change in floor height.
While in layout of laminate floor special care must be taken for the natural light,
layout must be done to the incoming light from any windows, if natural light not
provided in the room layout must be done to the longest side of the room.
The floors must be moist free, if some dampness is observed, then dry the
dampness first.
If the cabinets exist in the flooring, then the laminate around the cabinets leaving
¼” (6.35mm) to ½” (12.7mm) expansion zone.
If installing cabinets after the laminate has been installed, most or all of the cabinet
weight should be supported by the wall mountings. To secure the cabinets to the
substrate with screws or nails, drill holes through the laminate 1/2″ (12.7 mm)
diameter larger than the screw or nail to allow for expansion.
Always check each laminate flooring panel for damage before installing.
d) Installation Method
Avoid narrow pieces at the finish wall. Measure the distance between the starting
wall and the finish wall.
Divide this number by the width of the board.
If the remainder is less than 2-1/2″ (6.35 cm), cut off 2-1/2″ (6.35 cm) from the
width of the first row or to balance the room add the difference to the plank width
and divide by two.
Roll out the moisture control sheeting as per recommendation of manufacturer or
as per instructions of Engineer-in-Charge then install the laminate flooring.
14.1.122 MEASUREMENT:
Length and breadth shall be measured correct to a cm before laying skirting, dado or wall
plaster and the area calculated in square metre correct to two places of decimal. Where
coves are used at the junctions, the length and breadth shall be measured between the
lower edges of the coves.
No deduction shall be made nor extra paid for voids not exceeding 0.20 square metre.
Deductions for ends of dissimilar materials or other articles embedded shall not be
made for areas not exceeding 0.10 square metre.
ASPHALT FLOORING
14.1.123 SCOPE
The work shall include furnishing all labour, materials, equipments, plants, instruments,
accessories and services necessary to complete the work at the locations shown on the
drawings or as directed by Engineer-in-charge in accordance with these specifications.
14.1.124 MATERIALS
Asphalt used in constructing the asphalt flooring shall be in complete conformity with the
applicable requirements set forth in the specifications for asphalt or as approved by
Engineer-in-charge
Bitumen used for mixing with the asphalt shall be refined cut-back bitumen having viscosity
(Standard Tar Viscometer) of 110 to 150 seconds at 40 degree centigrade or as approved.
25
Technical Specifications Chapter-14
Vol-III, 2018 [Flooring]
Clean sharp sand used for mixing with the asphalt shall confirm to specifications 5.3.1.3
14.1.125 BASE
The base should be prepared in conformity with specification 14.10.
14.1.126 LAYING
Asphalt flooring shall be done in accordance with the details shown on the drawings, the
Engineer-in-charge instructions and the stipulations and requirements set forth herein as
under;
All dust and sand shall be swept-off, and the asphalt having been mixed and melted in the
following proportions, unless otherwise specified or as directed by Engineer-in-charge.
Asphalt 1 part
Bitumen 1/32 part
Clean sharp sand ½ parts
Shall be laid on smoothly and evenly of uniform thickness as specified and carefully and
steadily rubbed with hand float until the surface shall be perfectly even and true.
14.1.127 FINISHING
The junction of the sections of the asphalting shall be carefully made, and before the surface
becomes hard, it shall be worked perfectly level and smooth with fine clean sand and left of
a uniformly dark colour.
14.1.128 MEASUREMENT
Length and breadth shall be measured correct to a cm before laying skirting, dado or wall
plaster and the area calculated in square metre correct to two places of decimal. Where
coves are used at the junctions, the length and breadth shall be measured between the
lower edges of the coves.
No deduction shall be made nor extra paid for voids not exceeding 0.20 square metre.
Deductions for ends of dissimilar materials or other articles embedded shall not be
made for areas not exceeding 0.10 square metre.
26