You are on page 1of 3

and particulates which have to be removed

before compression to maintain efficiency

Basic Guide to Pipeline and integrity. Efficient and safe handling of


the liquids collected from the scrubbers in a
compressor station is one of the keys to a good
design. Individual scrubbers (with or without

Compressor Stations standby unit) may be installed for each stage of


compression for each compressor unit.
A common scrubber should be considered
for multiple units on a common suction line.
By Saeid Mokhatab, Greg Lamberson and Sidney Pereira dos Santos
Filter/separators may also be used to remove
smaller liquid droplets and/or solid particles.
s natural gas moves through a pipeline, units, aftercoolers, pipes and valves. Controls In the case of reciprocating compressors being
the pressure decreases due to friction — including Supervisory Control And Data used in the transmission system a coalescer
of the gas along the pipe wall and the Acquisition (SCADA) system, monitoring and filter is of capital importance to guarantee that
gas must be recompressed to maintain data recording, alarms and shut down proce- cylinder lubricating oil will not enter the pipe-
the flow. Gas compressor stations are installed at dures, both routine and emergency — are an line and affect gas specification. Poor handling
optimum locations along the pipeline as the load integral part of the station. Provision also has to of these liquids can be the major source of
profile changes and are sized to sufficiently boost be made for venting the compressor and driver operating and maintenance problems and have
the gas pressure and maintain flow through the housing and buildings, complete with ventila- a significant impact on station economics. The
pipeline. Compressor stations may be small, situ- tion and fire protection, and safety equipment. suction scrubber should be equipped with a
ated on gathering lines (Figure 1) or laterals, or The financial elements include cost-of-ser- mesh type mist elimination section to avoid liq-
large on major trunk line transmission systems. vice calculations which include the installed uid entrainment into the compressor. Scrubbers
However, all are built up from the same functional cost of the equipment, fuel, maintenance and can take several forms, inertial — with or with-
blocks of equipment. Each functional element operating costs for the expected project life out demister pads — or the horizontal cyclonic
(Figure 2) plays a role in the work of the station (typically 10 – 25 years). A risk simulated dis- type. The latter are commonly used on mainline
and the design and sizing of each is essential to the counted-cash-flow (DCF), rate-of-return (ROR) transmission stations.
efficient and safe operation of the plant. method of investment (Santos, 2003) analysis There are three main concerns that should
The functional elements include gas scrub- is recommended. Fuel cost is the major item in be addressed in the liquid-handling design for
bing and liquid removal, compressor and driver this calculation and the projection for escalation any compressor station: safety, environmental
forms an important consider- impact, and economics. Another consideration
ation and must be included in should be operability, which includes issues like
the risk simulation analysis. hydrate formation (when water is present in the
gas composition), failure consequences, etc.
Inlet Receiving The gas compressor station’s inlet receiv-
The gas in a main transmis- ing facilities consist of “pig” receivers and a
sion line is nominally clean and slug catcher to remove large solid and liquid
dry while that in gas gathering contaminants followed by filter coalescers to
lines may contain liquids prior remove fine solids and hydrocarbon mist. A
to processing, but in all cases filter coalescer also cleans the gas in each
there can be entrained liquids fuel supply to the turbines and gas engines.
Removed liquids flow to a hydrocarbon storage
Figure 1: tank where they are separated by gravity and
Cabiunas Terminal - Onshore then transported by truck as saleable hydrocar-
Gas Gathering Compressor bon liquid or disposed of as waste product.
Station. (source: PETROBRAS -
Rio de Janeiro – Brazil) Design Pressures
Figure 2: The design pressure for station gas piping
Typical Compressor should at least equal the MAOP of the pipeline.
Station P&I Diagram For single-stage stations, the suction and dis-
(Mokhatab et al., 2007). charge piping should have the same design pres-
sure. For multi-stage stations, the suction piping
design pressure should at least equal the highest
attainable suction pressure under all operating
and startup modes, and the interstage and dis-
charge piping design pressures should at least
equal the maximum discharge pressure. Multi-
pressure systems must be designed to ensure that
each system is not over-pressured during normal
operation and is protected to the appropriate
pressure level during upset conditions.
It is a general rule to use design pressures
to accommodate use of a standard ANSI Class
rating for compressor station piping compo-
nents. The cost to increase design pressure
to a standard ANSI Class is minimal and will
provide greater flexibility in future use of the
equipment and materials.

Compression
The gas pressure in the pipelines is increased
by a combination of one or more compres-
sors connected in parallel or in series to the

60 Pipeline & Gas Journal / June 2008 / www.pgjonline.com


Figure 3:

pipelines by the station piping. Typically for


mainline stations, gas turbine-driven centrifu-
gal compressors are used as the base units to
compress the majority of the flow. These are
compressor drivers that are turbine engines
using natural gas for fuel.
Compressor selection is based on detailed
analysis of the operating conditions in terms of
flow and pressure ratio needed by the pipeline
hydraulics. Frequently these conditions will vary
over time and the compressor selection will have
to have flexibility, by restaging if necessary, to
accommodate all the expected conditions. From
transient analysis based on predicted ramp-p
gas demand and flow profiles a set of values is
defined that will be used to pre-select compres-
sor units, depending on the installation layout, thickness reduction from corrosion process). sor operation to ensure that it will not run
whether series or parallel (Santos, 1997; 2004). A slug refers to volumes of hydrocarbon liq- into surge. If the operation of the compres-
Typically the conditions for most mainline uids and water that accumulate in the pipeline sor nears the surge line, the unit control will
stations will require compressors with one or as entrained liquids in saturated natural gas con- instruct the recycle valve to open and so
two stages, and the compressor design may dense. Slugs also occur from cleaning solutions maintain safe operation. Should the recycle
be of the overhung rotor or barrel design. injected into the pipeline for integrity mainte- condition continue for a time, and if coolers
The determination of operating conditions nance pigging. Normal gas flow by-passes the are not provided in the recycle line or com-
and hence the development of the compressor slug catcher to reduce pressure losses. Flow is pressor discharge, the unit will be shut down
characteristics will have to take into account switched through the slug catcher for as-needed on high discharge temperature.
the gas characteristics, suction and discharge use. Where liquid slugs may be received, the In addition to control and safety, the unit
pressure, and suction temperatures, usually station should include a slug-catching system control will monitor key operating parame-
involving equations of state for the particular with adequate storage capacity for the largest ters and provide video output on demand and
gas composition, and the process environment expected slug. Typical slug catchers are con- printout on a routine basis to provide a con-
(i.e., climate, altitude, location, etc.). structed of pipe and fittings and create a change tinuous record of operation. These readouts
The pipeline and station designer will make of direction of the gas stream, allowing dropout and records can be used for troubleshooting
sure that the equipment selection and arrange- of the liquid slug (Figure 3). and maintenance. The station control system
ment including maintenance strategy and level Some facilities, (e.g. gas-fired power plants) will oversee the unit operation and also pro-
of availability will be subject to a feasibility use natural gas reciprocating booster com- vide the interface between the operators and
study (Santos, 2004). pressors. Turbine manufactures may require the plant. It will provide video and print data
Compressor power will be determined from carryover limited to 0.1 to 0.003 ppm (wt.) recording of all key station parameters. It has
range. A downstream coalescer filter will pre- become more common to operate stations and
the compressor characteristics and thus the
vent lubricating oil from compressor cylinders units remotely from central dispatch stations
driver BHP can be calculated. Driver selection
affecting turbine integrity. Filter and turbine and the station-control systems will report to
is principally influenced by energy consump-
manufactures specifications and also field the central station via a SCADA link.
tion (fuel used) and power capability to drive
experience should be considered to guarantee The overall control of a major gas pipe-
the compressor. Since gas turbines do not come
proper equipment selection. line transportation system typically originates
in an affinity of ratings, it is usually necessary
The compressor foundation should also be from a central “Gas Control” office that is
to select the nearest match for power above the
designed taking vibration into consideration. remote from all of the compressor stations.
maximum requirement. The optimum selection
Pressure drop in the compressor suction, interstage Gas control monitors flow measurement for
of compressor and driver is a complex process, or discharge piping system including scrubbers, the total station throughput as well as each
involving much negotiation with the suppliers, valves and related items in each system should be compressor’s throughput and fuel consump-
and is beyond the scope of this article. no more than 3 psi per stage or system (excluding tion. The programmable logic controller
It is recommended that all potential areas coolers and any gas treating facilities). (PLC) in each compressor unit’s control panel
of pipe stress be evaluated very carefully due communicates to gas control the operating
to the large temperature variations present in Station Control parameters for that compressor and the posi-
compressor system piping and the stresses Control functions are typically based on tions of the valves controlling the gas flow
occurring in large-diameter piping. Particular personnel safety, the operating parameters through that compressor. This example sta-
care should be taken to ensure that pipe stresses of the station, and the types and number of tion offers redundant communication using
do not impart excessive forces on compres- compressor units installed at the station. microwave, satellite, or conventional leased
sor nozzles. Shaft misalignment with resulting Compressor station controls can be divid- telephone systems. This station is designed
vibration and/or excessive wear can be caused ed into two sections, unit control and sta- for the option of completely unmanned oper-
if high loads from the piping are transmitted to tion control. Digital technology is now used ation by Gas Control. The PLC compressor
the compressor case. Compressor manufactur- throughout both systems. The unit control on/off operation, performance set points, and
ers will provide the maximum allowable loads. utilizes a microprocessor which will control all station-critical valves may be remotely
A complete pipe stress analysis should be the turbine compressor unit to run to set controlled. Gas Control may monitor all sta-
performed on compressor gas piping systems if points under the direction of the operator or tion alarms and shutdowns.
operating temperatures are greater than 200°F. the station control system. The set points can Gas turbine-driven centrifugal compressor
Mostly in the case of a gas gathering system, be flow or pressure. Commonly, a flow or unit panels typically include unit protective
gas compressor station inlet receiving facilities suction pressure will be the control parameter functions, local and remote starting, auto-
consist of pig receivers and a slug catcher to with discharge pressure and/or suction pres- matic unit valve operation and equipment
remove large solid and liquid contaminants, fol- sure as overrides. The control protocol will and process monitoring instrumentation. If
lowed by filter coalescers to remove fine solids include limits to ensure safe operation. These a multi-unit station is involved, a separate
and hydrocarbon mist to reciprocating compres- limits will include pressure and temperatures station panel may be used to automatically
sor cylinder and valves protection. A pig refers on discharge and suction on the compressor control station operation.
to a device that is pushed by the gas through the as well as speed and flow and pressure ratio
pipe either to clean the pipe of obstructive mate- in relation to surge. Acoustical Treatment
rial or inspect the pipe for defects (roundness or The unit control will monitor the compres- Noise is a significant environmental pol-

Pipeline & Gas Journal / June 2008 / www.pgjonline.com 61


lutant and the reduction of noise is an essen- of the facility. Access to the station shall be Equipment should be standardized as fea-
tial part of the design of a compressor sta- granted at any weather conditions or climate. sible to minimize spare parts requirements.
tion. The technology of noise reduction has When it is not possible or feasible to locate Good human factor practices should be
reached the level that for most practical pur- adjacent to a public road, which may occur used in evaluating access to and viewing of
poses a compressor station can be designed due to remoteness of the pipeline route, pri- operating data, manipulation of controls,
to contribute less than 3dB to the pre-existing vate roads are used, providing an agreement installation of isolation devices, and removal
background noise level. Local requirements has been made with the property owners for and replacement of equipment (e.g. equip-
should be taken into account for a proper ingress and egress. ment and personnel access and egress, lifting
design. The design of the unit enclosures, Additional factors to consider in site selec- points, pull clearances, materials movement,
buildings, exhaust and inlet silencers are sub- tion include proximity to the connecting etc.). P&GJ
ject to stringent specifications. Double-wall pipeline and avoidance of crossing pipelines, Authors: Saeid Mokhatab is the process
enclosures are frequently used to control unit especially foreign pipelines; prior land use technology manager for Tehran Raymand
noise emissions as afore mentioned. (soil contamination, archaeological history, Consulting Engineers, Iran, specializing in
Normally an acoustic simulation study is wildlife habitat, etc.; soil conditions (load design and operations of natural gas trans-
done. If an acoustic simulation study has not bearing and stability, fill materials); topog- mission pipelines. He has participated as
been conducted, the following requirements raphy (required cut and fill, drainage); avail- a senior consultant in several international
for the piping system are the minimum: ability of required utilities (electric power, gas-transmission pipelines EPCM projects,
the use of elbows in the piping should be water, communications); and environmental and published numerous academic and indus-
minimized to the fewest number possible permit and noise requirements - and if sour try oriented papers and books.
and elbows should be eliminated between gas is present - the proximity to the public Greg Lamberson is the principal consultant
compressor cylinders and pulsation suppres- and prevailing wind. of International Construction Consulting,
sion devices. LLC, USA, with over 25 years experience in
Exhaust emissions from the gas turbines Emissions And all phases of business, project, engineering,
now have to meet the environmental limits Environmental Rules and construction management for upstream
of the location. Modern gas turbines are Equipment should be installed with provi- onshore and offshore oil, gas, and energy
designed with low emission combustion sions for containing leaks, spills and wash related facilities and pipelines in North,
systems to meet these requirements. These water as required to comply with federal, Central, and South America, the Caribbean,
systems may be dry or wet low NOx and are state and local regulations and permits. Tanks the Middle East, Central Asia, China, Russia,
now becoming the standard equipment for should be installed above ground unless spe- the Far East, and Africa.
all gas turbines. cific conditions require burial, and in either Sidney Pereira dos Santos, is a senior con-
Silencing equipment incorporated into the case, must comply with all environmental sultant at Petrobras Gas & Energy, Brazil,
engine air intake ducting and filters, engine regulations and state and local permits. For with more than 20 years of experience in the
exhaust systems, vent and blowdown exits, tanks that contain fluids potentially damaging design of most of the gas transmission pipe-
equipment enclosures, and piping insula- to the environment, proper spill containment lines/compressor stations in Brazil such as the
tion accomplish noise control for the sur- is included. Bolivia-Brazil Pipeline project. He has been
rounding community and station employees. Compressor station reliability and avail- conducting technical and economic studies
Liners and baffles of noise reduction mate- ability are paramount to overall gas pipeline with risk analysis and conceptual design for
rial are used inside the engine air intake delivery dependability. Reliability consider- the upcoming gas pipeline expansion projects
ducting and filters, engine exhaust, and vent ations are incorporated into many areas of in Brazil, and has presented various interna-
and blowdown exits. Acoustical lining on the facility. Some reliability considerations’ tional papers on related subjects.
the internal walls and silenced ventilation are listed below. REFERENCES
systems reduce noise from the compressor The total amount of installed compression Mokhatab, S., Santos, S.P., and Cleveland, T.,
buildings. (stand by units) must be more than the normal “Compressor Station Design Criteria,” Pipeline & Gas
As much station gas piping as possible design requirement to allow for scheduled Journal, p. 26-32 (June, 2007).
is installed below grade to provide addi- and unscheduled maintenance. Santos, S.P., “Transient Analysis – A Must in Gas
tional noise reduction. Above grade sta- Spacing between compressors or compres- Pipeline Design,” paper presented at the Pipeline
tion gas piping is acoustically insulated. Simulation Interest Group, Arizona, USA (1997).
sor groups aims at preventing fire damage to
Internal noise-reduction modifications are Santos, S.P., “Compression Service Contract –
one compressor from harming others and to
required in flow control valves. Fan tip When Is It Worth?” paper presented at the Pipeline
ease maintenance work.
speed limitations and low-noise fan drive Simulation Interest Group, Bern, Switzerland (2003).
Using redundant and parallel filter
designs are required for gas and oil cool- Santos, S.P., “Gas Compressor Service with
coalescers prevents unexpected large amounts
ers. Station noise control provides a day- Turbo Compressors,” paper presented at the ASME
of contaminants from impeding the gas flow
night average sound level (Ldn) of less International Pipeline Conference, Alberta, Canada
and allows filtration cartridge replacement
than 55 decibels per the “A” rating (dBA) (2004).
without interrupting compressor operation.
of human response to noise at the nearest Santos, S.P., “Series or Parallel Arrangement for a
Monitoring and trending of vibration,
noise sensitive area. This complies with Compressor Station – A Recurring Question that Needs
bearing temperatures, and other critical oper-
current U.S. Federal Energy Regulatory a Convincing Answer,” paper presented at the Pipeline
ational parameters by the compressor PLC
Commission regulations. Noise levels Simulation Interest Group, California, USA (2004).
identify service needs to prevent catastrophic
within a 3-foot distance from equipment
for the employee’s average time of expo- equipment failures.
sure is less than 85 dBA. This complies Maintenance systems should be developed
with current U.S. Occupational Safety and to manage all aspects of maintenance prior to
Health Administration requirements. station startup.
All below ground steel pipe, conduit
Site Selection and structures are coated with a corrosion
And Aesthetics protective and electrically insulating coat-
Site selection is primarily defined from ing. Additionally, steel pipe installed below
thermo-hydraulic simulation optimizing, fuel ground is protected from external corrosion
usage and transmission costs. Site selection using cathodic protection.
depends upon pipeline hydraulic consider- Sufficient operational and capital spare
ations and land availability. Consideration parts inventories should be available based on
should be given to possible future expansion reliability-availability-maintenance (RAM)
analysis and life cycle cost considerations.

62 Pipeline & Gas Journal / June 2008 / www.pgjonline.com

You might also like