1. Functionality test of CT-Current Transformer hook at VRF Main Breaker
2. Availability of Tenant Side 3. Some of the indoor units have no Power Supply 4. List of ready available units to be tested 5. Manpower Breaktime; 11:30 am - 1:30pm then 4:00pm - 4:45pm