Professional Documents
Culture Documents
Seleccion de Metodos PDF
Seleccion de Metodos PDF
4
SELECTION PROCEDURE
D AVID E. N ICHOLAS
must be undercut full width, and for a length greater than the mining method, or, in cases where the total sum is nearly equal,
width. This may mean that the production schedule will have to one can determine which characteristics are the most suitable
allow for additional time to undercut the large area or for some for the mining method. For the example given, the preferred
type of inducement. Either that or a sublevel cave operation may mining methods would be open pit mining, top slicing, square
be used instead. set stoping, block caving, and sublevel caving.
Nicholas’ example is summarized in Table 23.4.7. The first All of the method selection techniques arrive at similar con-
step is to list the geometry/grade distribution and rock mechan- clusions (Table 23.4.9). One might surmise that the conclusions
ics characteristics of the deposit (Table 23.4.7, column 1). The were obvious from the beginning. This may be true for this
columns of characteristics in Tables 23.4.5 and 23.4.6 are then example but is not so in all cases. Important factors may be
identified for the deposit, and the values summed for the geom- overlooked; using a method selection scheme, one is forced to
etry/grade distribution, ore zone rock mechanics, hanging wall consider all of the parameters. As is shown by Nicholas’ scheme,
rock mechanics, and footwall rock mechanics for each mining in which the main drawback to using sublevel caving is the poor
method (Table 23.4.7, columns 2 and 3). ground conditions of the footwall, one unfavorable factor does
The ore zone, hanging wall, and footwall should be not necessarily eliminate a method. Some technical problems can
multiplied by the weighting factors and then summed. This total be overcome. Sublevel caving requires extensive drifting and ore
should then be added to the geometry/grade distribution sum pass work in the footwall, so the poor ground conditions will
(Table 23.4.8). Using this type of characteristic grouping, one call for additional ground support, meaning development may
can see which grouping(s) reduce the chance of using a particular take longer. This does not rule out the feasibility of the method;
SELECTION PROCEDURE 2099
Table 23.4.8. Characteristic Values Multiplied by Weighting Factors
Table 23.4.9. Summary of Methods Selected Table 23.4.10. Ranking of Mining Methods Based on
Relative Operating Costs
23.4.5 SUMMARY
In performing the mining method selection task, it is impor-
tant to remember that no one method is able to meet all of the
requirements and conditions. Rather, the appropriate mining
method is that method that is technically feasible for the ore
geometry and ground conditions, while also being a low-cost
operation. This means that the best mining method is the one
with the technical problems that are the cheapest to deal with.
The mining engineer must balance all of the input parameters
and select that method that appears to be the most suitable,
making method selection both an art and a science. Still, by
ensuring the maximum use of available data and performing
detailed economic analyses on paper, the chances of making the
most appropriate selection are vastly improved.
REFERENCES
Alder, H., Potts, E., and Walker, A., 1951, “Research on Strata Control
in the Northern Coalfield of Great Britain,” Proceedings Inichar-
International Conference at Leige, pp. 106–420.
Barton, N., Lien, R., and Lunde, J., 1974, “Engineering Classifications
of Rock Masses for the Design of Tunnel Support,” Journal of the
International Society for Rock Mechanics, Vol. 6, No. 4, pp. 189–
236.
Boshkov, S.H., and Wright, F.D., 1973, “Basic and Parametric Criteria
in the Selection, Design and Development of Underground Mining
Systems,” SME Mining Engineering Handbook, A.B. Cummins and
I.A. Given, eds., Vol. 1, SME-AIME, New York, pp. 12.2 to 12.13.
Brady, B.H.G., and Brown, E.T., 1985, Rock Mechanics for Under-
ground Mining, Allen and Unwin, London, pp. 369–382.
Call, R.D., 1979, “Development Drilling,” Open Pit Mine Planning and
Design, J.T. Crawford and W.A. Hustrulid, eds., SME-AIME, New
York, pp. 29–40.
Hartman, H.L., 1987, Introductory Mining Engineering, Wiley, New
York, 633 pp.
Janelid, I., and Kvapil, R., 1966, “Sublevel Caving,” International Jour-
nal of Rock Mechanics and Mining Sciences, Vol. 3, pp. 129–153.
Kendorski, F.S., 1975, “Caving Operations Drift Support Design,” Pro-
ceedings, 16th US Symposium on Rock Mechanics, University of
Minnesota, pp. 173–180.
Kvapil, R., 1982, “The Mechanics and Design of Sublevel Caving Sys-
tems,” Underground Mining Methods Handbook, Chap. 2, W.A.
Hustrulid, ed., SME-AIME, New York, pp. 880–897.
Laubscher, D.H., 1981, “Selection of Mass Underground Mining Meth-
ads,” Design and Operation of Caving and Sublevel Stoping Mines,
Chap. 3, D. Stewart, ed., SME-AIME, New York, pp. 23–38.
Laubscher, D.H., 1990, private communication.
Fig. 23.4.13. Cumulative displacement plot and velocity plot. MacMillan, P.W., and Ferguson, B.A., 1982, “Principles of Stope Plan-
ning and Layout for Ground Control,” Underground Mining Meth-
ods Handbook, W.A. Hustrulid, ed., SME-AIME, New York, pp.
526–530.
Even though the design has been engineered in the feasibility Marek, J., and Welhener, H., 1985, “Cutoff Grade Strategy—A Balanc-
study, the engineering approach at this point should be to ing Act,” SME-AIME, Fall Meeting, Albuquerque, NM.
broaden and improve the database and to re-evaluate the mine Morrison, R.G.K., 1976, AQ Philosophy of Ground Control, McGill
design during development and production. University, Montreal, Canada, pp. 125–159.
2106 MINING ENGINEERING HANDBOOK
Nicholas, D.E., 1981, “Method Selection—A Numerical Approach,” Soderberg, A., and Rausch, D.O., 1968 “Pit Planning and Layout,”
Design and Operation of Caving and Sublevel Stoping Mines, Chap. Surface Mining, E.P. Pfleider, ed., 1st ed., SME-AIME, New York,
4, D. Stewart, ed., SME-AIME, New York, pp. 39–53. p. 151.
Panek, D.R., 1978, “Geotechnical Factors in Undercut Mining,” Pre- Wilson, A.H., 1972, “Research into the Determination of Pillar Size—
print, AIME Meeting, Lake Buena Vista, FL. Part 1: A Hypothesis Concerning Pillar Stability,” Mining Engineer,
Peele, R., ed., 1941, Mining Engineers’ Handbook, 3rd ed., Wiley, New Vol. 131, No. 141, pp. 409–417.
York, pp. 10-428 to 10-430.
Peters, WC., 1978, Exploration and Mining Geology, Wiley, New York,
696 pp.