AGREEMENT

OWNER : ROLANDO L. ALMANZOR & ALNORA M. ALMANZOR


CONTRACTOR: JULIO BISNAR
PROJECT: Proposed Mausoleum at Paraiso Memorial Park, San Mateo Rizal
TOTAL PROJECT COST: Php 1,000,000.00

SCOPE OF WORKS
1. EXCAVATION
2. STEEL WORKS
3. CONRETE WORKS
4. MASONRY WORKS
5. TILE WORKS
6. ELECTRICAL WORKS
7. PLUMBING WORKS
8. PAINTING WORKS
9. NITCH (PRESIDENTIAL,RESERVE VAULT,VONE VAULT,ALTAR)
10. STAIRS,RAILINGS,DOORS AND WINDOWS, GRILLS AND OTHERS

SPECIFICATION OF MATERIALS
1. STEEL WORKS
1.1. 16mmø round steel bars
1.2. 12mmø round steel bars
1.3. 10mmø round steel bars
2. CONCRETE WORKS
2.1. Republic Portland Cement
2.2. Sand
2.3. ¾” Gravel
3. MASONRY WORKS
3.1. CHB 4” (exterior walls)
3.2. CHB 5” (Interior walls)
4. TILE AND STONE WORKS
4.1. 60cm x 60cm tiles
4.2. Black Granite
5. PAINTING WORKS
5.1. Boysen Paint
6. DOORS AND WINDOW
6.1. Analox Sliding Window Brown
6.2. Dual Opening Glass Door
6.3. 2x2 Stainless Tubular for Main Gate
6.4. 1x1 Stainless Tubular for Grills
7. STAIRS, RAILINGS AND PARAPET
7.1. 2X2 Stainless Tubular for Railings Main
7.2. 1x1 Stainless Tubular for Railings braces
7.3. Spiral Stairs
7.4. 1x1 Stainless Tubular for parapet
8. WATER TANK

TERMS AND CONDITION


1. In consideration for performing the works, Contractor shall be paid a total contract price of Php
1,000,000.00. Payment by percentage is 40% DP, 30% for 2 nd collection and 30% for the last
collection
2. The amount of Php 400,000.00, representing the 40% downpayment, shall be paid by OWNER upon
signing this agreement.
3. The balance of Php 600,000.00 is divided by 2, shall be paid by OWNER based on accomplishment,
Php 300,000.00 upon 50% of accomplishment and the remaining Php 300,000.00 upon turn over of
the project.

Signed by:

ROLANDO L. ALMANZOR & ALNORA M. ALMANZOR JULIO BISNAR


OWNER CONTRACTOR