Professional Documents
Culture Documents
Steel Plant
CLIENT : A multinational company who is a project supplier for the Steel Manufacturer
INTRODUCTION
The client is multinational company who was acting as a project supplier for a steel manufacturer in Middle East Asia.
The requirement was to do power system studies including load flow analysis, protection studies, and harmonic analysis.
The system had an Electric Arc Furnace, a Ladle furnace, an SVC, 6.6 kV Motors, Oxygen Plant and several 415 volts
switch boards supplying LT loads. The required power system studies were done by Kalkitech’s power system analysis
software- PowerApps. The final studies and reports were submitted successfully to the client.
Last Updated: 19 November,2011 Copyright © Kalki Communication Technologies Ltd .All Rights Reserved
www.kalkitech.com
SOLUTIONS
Load flow calculations provided active and reactive power flows and bus voltage magnitude and their phase angle at all
the buses for specified power system operating conditions. It is subject to the regulating capability of generators,
synchronous condensers, static var compensator, HVDC controls, FACTS controllers, tap changing under load
transformers and specified net interchange between individual operating systems (utilities). This information was
essential for the continuous evaluation of the current performance of the power system and for analyzing the
effectiveness of alternative plans for system expansion to meet increased load demand.
Last Updated: 19 November,2011 Copyright © Kalki Communication Technologies Ltd .All Rights Reserved
www.kalkitech.com
Short-Circuit Studies
Short-circuit studies helped to determine fault levels at various buses. This was useful in determining post fault bus
voltages in the entire system, post fault network currents in the entire system as well as negative and zero sequence
currents in various electrical network elements. These calculations also helped to provide the bulk of the information
needed for protection system design, protection setting calculations and relay coordination. These studies were carried
out for various operating scenarios of the plant with existing earthing system and the performance of the plant was
reviewed and remedies were suggested.
The starting current of most ac motors is several times normal full load current, when starting them directly on line at full
rated voltage. The starting torque varies directly as the square of the applied voltage. Excessive starting current results in
drop in terminal voltage and may result in the following:
Failure of motor starting due to low starting torques.
Unnecessary operation of under voltage relays.
Stalling of other running motors connected to the network.
Voltage dips at the power sources and consequent flicker in the lighting system.
Motor starting studies helped in the selection of best method of starting, the proper motor design and proper system
design for minimizing the impact of the motor starting.
Harmonic Analysis
Harmonics in power systems can result in undesirable influence such as Capacitor heating/failure, Telephone
interference, Rotating equipment heating, Relay mis-operation, Transformer heating, Switchgear failure, Fuse blowing.
The main sources of harmonics in power system are static power converters, arc furnaces, discharge lighting and any
other load that requires non-sinusoidal current. In order to limit the harmonic current propagation in to the network,
harmonic filters are placed close to the source of the harmonic currents
Last Updated: 19 November,2011 Copyright © Kalki Communication Technologies Ltd .All Rights Reserved
www.kalkitech.com
Relay Coordination Studies
The relays must be able to distinguish between the normal operating currents including short time overcurrents that may
appear due to certain equipment normal operation (example: Motor starting currents, Transformer inrush currents) and
sustained overcurrent due to fault conditions. During fault conditions, these relays were made to operate quickly,
isolating the faulted section of the network only and allowing for continued operation of the healthy circuits. In the event
of failure of primary relays meant for isolating the fault within its primary zone of protection, backup relays were tested to
operate after providing sufficient time discrimination for the operation of primary relays. Hence, the operation of backup
relays was coordinated with those of the operation of the primary relays. The flexible settings of the relays (namely plug
or tap setting, the time dial setting and possibly selection of suitable time-current operating characteristics), was set to
achieve the objectives stated in this section.
Last Updated: 19 November,2011 Copyright © Kalki Communication Technologies Ltd .All Rights Reserved
www.kalkitech.com
Time Current Characteristics
References
EFERENCES
1. www.kalkitech.com/offerings/solutions-powerapps
2. www.powerapps.org
Last Updated: 19 November,2011 Copyright © Kalki Communication Technologies Ltd .All Rights Reserved
www.kalkitech.com