Professional Documents
Culture Documents
Cementing Best Practices PDF
Cementing Best Practices PDF
: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 1 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Section Page
1.0 Introduction 6
2.1.3 Centralization 9
2.1.5 Spacers 11
2.2.1 Definitions 13
2.2.5 Onsite QC 21
____________________________________________________________________________________
Cementing Best Practices 1 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 2 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
____________________________________________________________________________________
Cementing Best Practices 2 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 3 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
3.1.7 Displacement 39
3.4.1 Wait-On-Cement 42
____________________________________________________________________________________
Cementing Best Practices 3 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 4 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
4.2.4 Centralizers 54
____________________________________________________________________________________
Cementing Best Practices 4 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 5 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
____________________________________________________________________________________
Cementing Best Practices 5 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 6 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
1.0 Introduction
o Engineering tools
o New cementing technologies
o Performance data – KPIs
o Cementing technical papers
o Reference materials
o Cementing presentations
o Job examples
o Rigorous technical specifications for cementing contracts
o Squeeze cementing documents
o Cementing Contractor Information
o Contacts
o Technical Information
o Lab Audits
____________________________________________________________________________________
Cementing Best Practices 6 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 7 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
o Cementing Scorecards
o Best Practice Updates and Notices
The top priority in achieving a successful cement job is to displace all of the
drilling mud from the annular section to be cemented, that is, to achieve a high
displacement efficiency. Displacement efficiency is defined as the percentage of
annular area at any given cross-section that is filled with cement. There are
several proven best practices that can be used together to help achieve a nearly
100 % displacement efficiency, including mud conditioning, pipe movement,
centralization, spacers, and mechanical aids.
1. Mud Properties
Drilling muds are designed to help efficiently drill and transport cuttings to
the surface, but are not always conducive to good mud displacement
during cementing operations. Therefore, prior to running the casing and
cementing, the drilling fluid should be conditioned to exhibit “easy-to-
remove” properties including low fluid loss, thin rheological properties, and
a flat gel profile. General recommended production casing/liner values for
these properties are listed below, although significant variations can occur
____________________________________________________________________________________
Cementing Best Practices 7 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 8 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
2. Conditioning Volume
Figure 1
____________________________________________________________________________________
Cementing Best Practices 8 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 9 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Conditioning
Conditioning Time
Time after
after Landing
Landing Casing
Casing
(Halliburton
(Halliburton Research
Research Study)
Study)
3. Conditioning Rate
Stage pump rate to the maximum rate planned during the cementing
operation. Monitor well for whole mud losses. If mud circulation is lost
and cannot be regained, stop circulating and prepare to cement the
well.
After the casing has been landed, and the drilling mud conditioned,
cementing should begin as soon as possible, preferably within 15
minutes. Increased static times may cause the mud to gel significantly
and make it difficult to remove from the annulus.
____________________________________________________________________________________
Cementing Best Practices 9 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 10 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
throughout the mud conditioning and cementing process. Pipe movement will
both physically scrape mud from the wellbore, as well as keep fluid moving
around all portions of the hole.
2.1.3 Centralization
Use rigid, semi-rigid (double bow spring) or positive stand-off centralizers in open
hole sections if possible. Bow spring centralizers are recommended for liner laps,
casing-in-casing scenarios, and in washed out hole sections.
____________________________________________________________________________________
Cementing Best Practices 10 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 11 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Displacement rates should be specified based on the maximum pumping rate that
can be obtained without exerting sufficient annulus pressure (due to increased
ECDs) to break-down the formation and lose returns. Computer modeling of
allowable pump rates should be performed as part of the planning process to
enable accurate specification of cement rheological properties. To optimize mud
removal, the annular fluid velocity during displacement should exceed 70 m/min
or 200 ft/min – Figure 2. Slow the rate to bump the plug.
Note: Do not shut down and perform a hesitation squeeze on the casing shoe at
the end of a job. Field results have generally shown no benefit when attempting
to use the “hesitation method”.
Figure 2
Displacement
Displacement Efficiency
Efficiency vs.
vs. Annular
Annular Velocity
Velocity
SPE/IADC
SPE/IADC 18617,
18617, T.R.
T.R. Smith
Smith
2.1.5 Spacers
____________________________________________________________________________________
Cementing Best Practices 11 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 12 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
1. General
Spacers are pumped to separate mud and cement. They are designed to:
The best spacer to use for cementing operations is water with surfactants,
chemical additives, or salinity added as needed. Even if a weighted spacer
is required to maintain adequate downhole overbalance pressures, it is
recommended to precede the weighted spacer with +- 20 bbls of base fluid
(water or oil preflush) to provide turbulent flow properties and to dilute mud
filter cake. When adding a light preflush, the hydrostatics must be sufficient
at every point during the job to prevent formation fluid influx.
2. Spacer Density
3. Spacer Volume
____________________________________________________________________________________
Cementing Best Practices 12 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 13 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
5. Spacer Salinity
The salinity of a water based spacer should match the salinity of the
cement slurry.
6. Spacer Wettability
The following items may be employed to help remove mud from the wellbore
during cementing.
2.2.1 Definitions
____________________________________________________________________________________
Cementing Best Practices 13 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 14 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Placement Time – The amount of time elapsed between the start of cement
mixing to final placement of the cement in the annulus.
Thickening Time - The amount of time for a cement slurry to become “too thick
to pump”. Thickening time is measured in an HPHT consistometer at BHCT and
BHP. A slurry is considered “too thick to pump” when it reaches a cement
consistency of 70 Bc (Bearden Units)- See Figure 3.
Note: API defines thickening time as time to reach 100 Bc, but for Oxy best
practices, the 70 Bc should be considered to be the maximum pumpable
consistency.
100-----------------------------------------------------------------
Thickening Time
Consistency 70
(Bc)
40 --------------------------------------
Transition
Time
0
Time
Transition Time – The time for a cement slurry to transition from a liquid to a gel.
It can be measured dynamically in an HPHT consistometer, or in static conditions
in a Static Gel Strength Tester. While conducting a thickening time test, the
dynamic transition time is the difference in time between the 40 Bc to 100 Bc
consistency reading (See Figure 3). For a static gel strength test, the slurry
transition time is the elapsed time for cement to progress from 100 lb/100 ft 2 to
500 lb/100 ft2 gel strength.
____________________________________________________________________________________
Cementing Best Practices 14 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 15 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Right Angle Set – The term used to describe a cement slurry that has a very
quick transition time, i.e. the slurry consistency moves from 40 Bc to 100 Bc
rapidly.
Compressive Strength – The compressional force per unit area when set
cement fails. It can be measured by physically crushing a cement cube or
cylinder, or through non-destructive means with an Ultrasonic Cement Analyzer
(UCA).
Wait on Cement (WOC) - For operations, WOC is the waiting time required after
cementing in order to safely remove well control equipment with the annulus open
or casing/liner fluid underbalanced. For a cement slurry, WOC is the time
necessary for the cement to set and attain a compressive strength of 500 psi.
This is most efficiently determined through lab testing with the UCA, which plots
strength development over time.
Set Time (or Initial Set) – Set time is the time it takes for the cement to gain 50
psi compressive strength, becoming a hard solid. Early set time is one of the
most important properties in an oilwell cement.
Fluid Loss – The amount of water pressed from a cement slurry under a
differential pressure. In the lab, it is measured at BHCT by pressurizing the
cement across a 325 mesh screen at 1000 psi differential for 30 minutes.
Free Water –The amount of clear fluid that separates from a cement slurry in a
static condition. It is measured in the lab by filling a 250 ml graduated cylinder
with cement and observing it for 2 hrs. For deviated wells, the graduated cylinder
is usually placed at a 45 degree angle. A basic free water test is performed by
conditioning the cement slurry for 20 mins at BHCT and then pouring the slurry
into a 250 ml graduated cylinder at room temperature. An operating free water
test is also conditioned but poured into a 250 ml graduated cylinder sitting in a
water bath at BHCT. The operating free water test is a more severe and accurate
test. For HPHT (> 190o F) perform the free water test at 190o F or perform a high
temperature density segregation test.
____________________________________________________________________________________
Cementing Best Practices 15 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 16 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Shear Bond Strength – The force per unit surface area required to shear
cement from a metal casing surface. It can be measured in the lab using a shear
bond mold.
Tensile Strength – The force per unit area for a cement to fail in tensile. It is
measured by physically pulling a “dogbone” shape cement specimen apart.
Cement Expansion – The linear or radial growth of cement during and/or after
set. This property can be physically measured in the lab. Note that conventional
cement slurries will normally shrink while setting due to hydration reduction.
Expansion additives help cement expand 0 – 2 % linearly.
Gel Strength – Gel strength is the yield point of a cement slurry at varying times.
Normally in the lab the gel strength is measured with a viscometer at 10 second
and 10 minute intervals.
An annual cement lab audit should be conducted for the cementing contractors
used by Oxy. The audit should be performed by Oxy using Oxy specifications and
scoring from the Oxy Cementing Lab Audit Form.
Pilot tests are cement slurry tests that use lab stock cement and additives prior to
actual bulk blending. A pilot test should be conducted for each cementing
operation. If possible, it is recommended to perform pilot tests with the cement
batch sample and additive lot numbers that will be used for the actual job. Pilot
tests are performed to determine the actual slurry design for the job. It may
require several pilot tests to perfect a cement slurry design. A pilot test should
consist of the seven (7) items listed below.
____________________________________________________________________________________
Cementing Best Practices 16 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 17 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
1. Thickening Time
Thickening time charts should be attached to all lab reports. Proper slurry
design should be employed to avoid gelation while the cement is being
pumped (See Figure 4).
Figure 4
70
Unacceptable
Gelation Spike
40 ------------------------------------------------------------------
Consistency
(Bc)
0
Time
For liner slurries, the thickening time test should include a 20 minute
hesitation time (static time) after placement time has been reached. This
simulates a 20 minute shutdown to release the drillpipe from the liner top.
For batch mixed slurries, the thickening time test should include a
____________________________________________________________________________________
Cementing Best Practices 17 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 18 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
2. Density
3. Compressive Strength
b. Crush Test
The crush test may be performed using cube molds as per API RP
10B procedures. Another option is to use the UCA cylindrical
sample. When removed from the UCA cell, it may be crushed to
confirm the UCA compressive strength value.
4. Fluid Loss
Fluid loss tests below 190o F should not be performed according to current
API RP 10B procedures. Instead, the cell should be preheated to BHCT,
filled with conditioned cement slurry, 1000 psi pressure applied from the
top, and fluid loss measured for 30 minutes. For tests above 190 o F, a
high temperature cell should be used and tests performed according to
current API RP 10B procedures. The 325 mesh screens used in fluid loss
testing should be thoroughly cleaned. The screens should be thrown away
after they are used when testing cement slurries containing latex or
“pseudo-latex” (poly vinyl acetate) additive.
____________________________________________________________________________________
Cementing Best Practices 18 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 19 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
5. Free Water
Conduct the operating free water test with a heated static period at BHCT
or 194o F, whichever is lower. For deviated wells, place the graduated
cylinder at 45o angle in the water bath.
6. Rheological Properties
7. Mixability
Mix slurry as per current API RP 10B procedures 4000 rpm for 15 seconds
and 12,000 rpm for 35 seconds). If the slurry contains microspheres, the
12,000 rpm may be replaced by 4000 rpm.
Cement is added to the mixing water during the first 15 seconds of mixing.
The “time required to add cement to the mixing water” should not exceed
15 seconds. The mixability or “time required to add cement to the mixing
water” should be recorded on all lab reports.
8. Compatibility
____________________________________________________________________________________
Cementing Best Practices 19 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 20 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
50/50, 25/75, 5/95, and 0/100, respectively. If the calculated PV/YP of any
of the mixtures is 1.5x greater or less than the 100/0 or 0/100 values, then
the fluids are deemed incompatible. For high temperature applications
above 190 oF, the compatibility tests should be conducted at 190 oF.
9. Special Tests
a. Transition Time
b. Density Segregation
For higher temperature cementing (> 200 F), the “BP Settling Test”
should be performed to determine if density segregation is a
problem.
c. Shear Bond
d. Expansion
e. Microsphere testing
____________________________________________________________________________________
Cementing Best Practices 20 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 21 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
1. Plant Blend
If a plant blend test fails, then the cement should be dumped, or liquid
additives used to properly adjust the cement design to the required
performance properties.
An improper plant blend is a small (50 – 100 sk) blended cement that is
taken prior to loading all of the cement. This type of plant blend test only
tests that the first 50-100 sacks that are loaded. Even if this test passes, it
leaves the remaining cement to be loaded untested. This plant blend test
is not therefore not representative of the entire cement blend that will be
pumped.
2. Mix Water
For plant blend testing, the location mix water and location liquid additives
____________________________________________________________________________________
Cementing Best Practices 21 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 22 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
should be used.
2.2.5 Onsite QC
Note: Set times of the surface samples may not be accurate due to lack of
bottomhole temperature, and also evaporation due to atmospheric
exposure.
In areas where water hardness and composition varies, the location mix
water should be tested with a mix water kit including chlorides and sulfate
content, pH, and specific gravity. In cases where the mix water is suspect
and may contain organic materials that would retard the cement, the
location water should be sent to the lab for cement slurry tests.
____________________________________________________________________________________
Cementing Best Practices 22 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 23 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
There are six (6) major slurry performance properties that are tested for each
cement design. These include slurry density, thickening time, compressive
strength, fluid loss, free water, and rheology.
< TTT + 4
Surface Lead PT2+ 1 hr NR3 50 > 250 NR 2.0 NR NR NR
hrs
< TTT + 4
Surface Tail PT+ 1 hr NR 500 > 800 1200 2.0 NR NR NR
hrs
< TTT + 3
Intermediate Lead PT+ 1 hr NR 50 > 250 NR 1.0 NR < 15 NR
hrs
< TTT + 3
Intermediate PT+ 1 hr NR 500 NR 1200 1.0 NR < 15 NR
hrs
< TTT + 3
Drilling Liner PT+ 1 hr NR 500 > 1500 NR 0.0 < 150 < 15 NR
hrs
< TTT + 2 > 300
Production Casing PT+ 1 hr < 30 min NR > 1500 NR 0.0 < 100 < 15
hrs psi
< TTT + 2 > 300
Production Liner PT+ 1 hr < 30 min NR > 1500 NR 0.0 < 70 < 15
hrs psi
Note: For a lner Thickening Time Test, hesitate for 20 mins after placement time and restart the consistometer
1 Local regulatory requirements supercede chart recommendations
2 PT = Placement Time
3 NR = No Requirement
1. Slurry Density
____________________________________________________________________________________
Cementing Best Practices 23 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 24 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
2. Thickening Time
For all thickening time tests, the elapsed time to 40 Bc, 70 Bc, and 100 Bc
should be measured in hours and minutes, with the 70 Bc figure taken
as the measured thickening time. The difference between the 100 Bc
and 40 Bc times should be used as an indication of rate at which the
cement slurry changes from a pumpable to an unpumpable condition, and
is noted as the transition time. The 40 Bc,70 Bc, and 100 Bc
measurements should be reported on all thickening time tests.
Lead Thickening Time = Lead slurry mixing time + Tail slurry mixing time
+ Time to launch top plug + Displacement time + Safety Factor
Tail Thickening Time = Total tail slurry mixing time + Time to launch top
plug + Displacement time + Safety Factor
Use synthetic retarders instead of lignin retarders when they are required
____________________________________________________________________________________
Cementing Best Practices 24 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 25 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
3. Compressive Strength
Cement slurries placed in the annulus should set as soon as possible. The
recommended compressive strength values are shown in Table 1. Note
that a properly designed slurry will have an initial set time (time to gain 50
psi compressive strength) only slightly longer than the thickening time
value.
4. Fluid Loss
For most wells drilled, the cement filtrate loss is controlled by the mud filter
cake that is deposited during drilling. However, for slurries that will contact
producing formations, slurry design should include the addition of fluid loss
additive as a precautionary measure. For the applications described
below, API fluid loss determined at 1000 psi differential pressure should be
as follows:
____________________________________________________________________________________
Cementing Best Practices 25 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 26 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
5. Free Water
The API free water content of all slurry designs shall be specified as
shown in Table 1, less than 2.0 % for surface casings, less than 1.0 % for
intermediate casings, and 0 % for drilling liners, production liners, and
production casings. This applies to vertical as well as inclined free water
tests.
6. Rheological Properties
For wells with anticipated bottom-hole static temperatures of 230 o F or above, the
cement slurry must be designed to prevent cement strength retrogression. This
can be accomplished through the addition of 15–40 % by weight of silica sand or
silica flour. In general, silica flour ground to 325 mesh is to be used at
temperatures between 230o F and 350o F. Coarser silica (200 mesh / 100 mesh)
is to be used at temperatures above 350 F. However, combinations of varying
mesh sizes have also been used together effectively. In all cases, compressive
strength performance should be tested at static bottomhole conditions over a
minimum period of 7 days to determine if retrogression will occur.
____________________________________________________________________________________
Cementing Best Practices 26 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 27 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Annular gas flow can occur by flowing through the cement sheath (See Figure 5)
or can be the result of leakage at the cement/casing or cement/formation
interface.
When cementing across troublesome gas producing intervals, apply the following
recommendations to prevent gas flow through the unset cement.
Use expanding cements (gas generating additives will also cause cement
expansion)
____________________________________________________________________________________
Cementing Best Practices 27 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 28 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Displace the cement job with a lighter fluid so that a microannulus will not
be formed during completions operations
Spot LCM Pill – For severe losses, spot an LCM pill prior to POOH with
drillpipe. Refer to Drilling Fluids Best Practices(Section 2.1.10).
____________________________________________________________________________________
Cementing Best Practices 28 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 29 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Thin Cement – Design cement slurries for YPs < 10, if possible, to reduce
ECDs while cementing.
Stage Tools – A two stage cement job employing cementing stage tools
(with or without integral external casing packers) can be performed to
achieve full returns when a full column of cement cannot be obtained with
one stage.
The following pre-cement job circulating recommendations are given for cementing
liners:
2. After setting the liner hanger, begin circulating mud at low rate (1-2 BPM)
and slowly increase to cementing rate.
____________________________________________________________________________________
Cementing Best Practices 29 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 30 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
4. If pressures are abnormally high or erratic while circulating mud, the liner
hanger may be packing off. Review situation.
The following items are key issues that are critical to successful conventional liner
cementing. These key items are intended to be the basics, but are not intended
to be ALL of the issues that are involved in designing and executing successful
liner cementing jobs. Each item represents a key issue that should be addressed
AFTER the liner size has already been chosen.
Bow spring centralizers should be used in the lap region and achieve a
minimum standoff off of 70%.
____________________________________________________________________________________
Cementing Best Practices 30 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 31 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
The height of cement above the top of liner should be recalculated using
actual calculated job volumes of cement to be pumped (as above) but
assume gauge open hole. (Note that the reason for this second
calculation is to ensure that it is clearly understood where the top of
cement will be in relation to top of liner if the open hole is in gauge).
Circulation should be established while the liner is still inside the deepest
existing casing and before the liner is run into the open hole. Circulate the
well a total of at least one hole volume to break the static gel strength of
the drilling fluid system. The ECD applied to the formation will be less at
this point as annular clearance will normally be greater at this point in time
than when the liner is on bottom.
When the liner wiper plug is encountered, the volume pumped should be
noted and recordedas referenced by displacement tanks (and barrel
counter).
____________________________________________________________________________________
Cementing Best Practices 31 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 32 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
All drill pipe should be immediately pulled from the well after checking the
floats at the end of displacement of the primary cement. If the floats do not
hold, shut in, set liner top packer, and pull DP out of hole. If there is no
liner top packer used, shut in well, wait 15 minutes, and pull drillpipe out of
hole.
Should the drill pipe become stuck and fail to pull completely out of the
well, immediately start pumping the short way at the maximum rate
possible to help remove any restriction in the annulus between the drill
pipe and the casing.
Note: The short way in most cases involves pumping down the annulus
between the drill pipe and the casing with returns to surface through the
drill pipe. Calculate the displacement volumes required each way before
the job commences (i.e. before starting pumping operations).
• Determine the maximum pumping rate possible that will help erode
and remove the restriction in the annulus while minimizing negative
effects, such as excessive ECD’s (equivalent circulating densities)
on the top of the lap, and potential bridging by solids settling in the
drill pipe and casing annulus.
• Continue pumping the short way until a) the drill pipe is free to pull
completely out of the well, or b) the maximum safe pressure limit is
reached.
____________________________________________________________________________________
Cementing Best Practices 32 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 33 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
For plastic salt sections capable of moving and collapsing casing, 5 % KCL
slurries with fast setting properties should be used in conjunction with heavy
walled casing.
When cementing across reactive shales, especially at the casing point, consider
using 18 % salt or 7 % KCL bwoc in the spacer and cement design to inhibit
deteoration of the cement/formation bond.
Steam injection or producing wells should use at least 40 % silica flour or silica
sand in the cement design. To help long term integrity under steam cycling, the
cement should be designed with an expansion additive to achieve 0.5 – 1.5 %
linear post-set expansion. Expansion should be measured at both pre and post
steam temperatures. Additionally, long term compressive strength testing should
be performed to ensure that the cement design could withstand the high
temperatures. In some cases, a calcium aluminate cement must be used instead
of conventional Portland cement.
____________________________________________________________________________________
Cementing Best Practices 33 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 34 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
• Nitrogen Lines should be tested 2000 psi +- higher than the cement lines.
Often, cement lines are tested to 5000 psi and nitrogen lines to 7000 psi.
Even though the cement slurry line pressure may be 3000 psi, the nitrogen
line pressure may be 5000 psi.
For acidic environments, the cement design should include the following:
____________________________________________________________________________________
Cementing Best Practices 34 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 35 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
For sulfate resistance, the cement design should include the following:
____________________________________________________________________________________
Cementing Best Practices 35 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 36 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
4. Review laboratory blend test results, paying special attention to the thickening
time and the required WOC.
6. Calculate the mix water requirement, liquid additive requirements (if any), and
the resultant mix fluid volume for both lead and tail cement slurries.
8. Verify that suction rates required for the job can be achieved with both drilling
fluid and water.
10. Develop a pumping schedule based on the cement job simulator output.
11. Determine whether the available pumping time as indicated by the laboratory
thickening time test result is sufficient for the planned job.
• Rig up procedure
• Safety concerns
• Pressure testing procedure
• Spacer type, density, and volumes to be pumped
____________________________________________________________________________________
Cementing Best Practices 36 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 37 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
13. If supplying the wiper plugs and cementing head, verify that the correct
equipment is on location and that the cementing head and associated
connections match and have been pressure tested.
14. Load the wiper plugs in the presence of the OXY Drill Site Manager.
15. Review checklists, lab test results (available pumping time and WOC time)
and job plan with the OXY Drill Site Manager.
16. Prepare spacer as required and check the weight with a pressurized mud
balance.
The Oxy Drill Site Manager and the Cementer should perform the job procedure
that includes the following steps.
1. Hold a safety meeting on the rig floor to review the job procedures, assign
support responsibilities, and address safety issues. Maintain an open line
of communication to the rig floor throughout the job.
____________________________________________________________________________________
Cementing Best Practices 37 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 38 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
4. Pressure test all cement lines to a pressure 1000 psi above that which is
expected during the cementing operation.
7. Drop the bottom plug. The cementer is responsible for seeing that wiper
plugs, darts, or balls are released at appropriate times. The Oxy Drill Site
Manager should witness the loading of all plugs into the cement head.
9. Mix and pump tail cement. Be sure that the lead cement mix has
completely cleared the mixing tub before increasing the density to the tail
cement specifications. Make sure the final 10 bbls of cement slurry is high
quality cement (0.1 – 0.2 ppg higher than designed density).
11. Confirm cement densities with a pressurized mud scale and catch cup
samples of cement slurry.
12. Close cementing head valve and open wash up line for critical cementing
operations.
13. Close wash up line, open cement head valve, and drop top plug.
14. Displace job with cement unit or with rig pump. To avoid displacement
volume error, do not switch from cement unit to rig pump, or vice versa,
during displacement. When using the rig pump to displace, the pump
____________________________________________________________________________________
Cementing Best Practices 38 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 39 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
16. If plug does not bump, pump theoretical displacement volume + ½ shoe
track volume and shut down.
18. The cementing service company should manually record the following
events during the job.
19. For surface wellhead systems, monitor casing annulus for pressure build-
up while cement sets.
20. Take three separate one-gallon mix water samples from the displacement
tank or tank truck, and 3 separate one-gallon dry cement samples from the
surge tank or transfer line after the job. Label and retain samples for
possible lab testing until the well is completed.
____________________________________________________________________________________
Cementing Best Practices 39 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 40 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Pressure test all cementing lines and the cementing manifold with water or
spacer prior to pumping any fluid into the casing. Test pressure is to be at least
1000 psi above maximum anticipated pumping pressure during cementing
operations.
Cement slurry density should not be sacrificed for pump rate. Mix cement at the
maximum mixing rate where density can still be accurately controlled.
Fluid densities, pump rate, pressure, and volumes pumped should be recorded
and submitted to the Oxy Drill Site Manager in an excel spreadsheet. If the rig
pumps are displacing the cement job, the cementing lines should be opened and
configured to allow the cement unit to record displacement pressures.
3.1.7 Displacement
1. Volume
____________________________________________________________________________________
Cementing Best Practices 40 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 41 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
• When using a cement unit to displace, the cementer should fill the
displacement tanks high, and empty the displacement tanks
completely, i.e. “fill high, suck low”.
• When using the rig pumps to displace, calculation of the total mud
pump strokes to displace the top plug to the float collar should be
based on the contractor's record of pump displacement efficiencies
measured during previous cement jobs. It must be remembered that
displacement efficiency will be a function of liner size, pump rate,
and pumping pressure. If the displacement efficiency is not known,
assume an efficiency of 97% (WBM) and 95 % (OBM) as a first
approximation. If rig pump efficiency is unknown, utilize the cement
pumps as the first option.
2. U-Tube
The pump rate should be reduced before bumping the plug. Bump the
plug to 500 psi over final circulating pressure.
____________________________________________________________________________________
Cementing Best Practices 41 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 42 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
For large diameter casing strings, the force exerted on the bottom of the casing
due to hydrostatic pressure and annular pressure losses should be determined to
help ensure that the casing will not be pumped out of the hole during cementing
operations. If it is possible for the casing to be pumped off bottom, then cement
slurry density and/or displacement rates will have to be adjusted to ensure the
casing remains on bottom.
For 30" and 20" diameter casing, a positive acting, single valve float shoe
assembly should be used. A float collar will not be required unless dictated
by well specific conditions. Inner string cementing may be used as
appropriate, however the potential for casing collapse should be
determined.
For 16” and smaller diameter casing, a positive acting, single valve float
shoe and a positive acting, single valve float collar spaced two pipe
lengths apart should be used.
For 7" and 5" liners, a double valve, positive acting float shoe and a conventional
liner wiper plug landing collar complete with a profile to accept a latchdown wiper
plug, should be used. Float shoe and float collar should be positioned at least two
pipe lengths apart.
The float shoe and float collar joints should be visually inspected by the Drill
Site Manager or Drilling Engineer to ensure that the float shoe, shoe track
joint, and float collar have been installed using thread locking compound.
Float collars and plug landing collars should be compatible with the cement
____________________________________________________________________________________
Cementing Best Practices 42 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 43 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
wiper plugs to ensure proper sealing of the plug on the landing area.
Use top and bottom wiper plugs. The bottom plug is used to separate the
spacer and cement in the casing, and wipe the mud film off of the casing
prior to the passing of cement and the top plug. The top plug separates the
cement from the displacement fluid and provides a positive pressure
indication when it lands on the float collar or landing baffle. If the cement
slurry contains lost circulation material (LCM), the bottom plug should have
a full opening bypass so that LCM does not bridge in the bottom plug.
Check the order of loading. The bottom plug is red or yellow and is hollow,
and is loaded first. The top plug is black and is loaded second, on top of
the bottom plug. The bottom plug contains a rubber diaphragm (or plastic
burst disk) that ruptures at +- 300 psi. Do not slit diaphragm or shatter disk
prior to loading.
Cement wiper plugs should be used with casing sizes 16" and smaller
according to the following schedule:
Liners: A single liner wiper plug complete with latch down facility for
landing/latching in landing collar should be run. For casing sizes requiring
the use of two cementing plugs, the bottom plug should be launched
following the spacer and/or pre-flush. The top plug should be launched
____________________________________________________________________________________
Cementing Best Practices 43 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 44 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
behind the tail slurry with allowance for +/- 2.0 bbls of cement on top of the
plug. For 5 ½” production liners and smaller, wash lines clean after
pumping cement before displacing so that no cement is placed on top of
the plug.Note: Two plug liner systems are now available, and are
recommended if available.
For operations, WOC is the waiting time required after cementing in order to
safely remove well control equipment or to allow the well to be underbalanced.
For this operation, cement compressive strength should be 50 psi.
For drilling out the shoe track, the cement compressive strength should attain a
compressive strength of 500 psi. This will provide the bond strength needed to
support the shoe track as it is being drilled. The time to 500 psi is most efficiently
determined through lab testing with the UCA, which plots strength development
over time.
For development wells with trusted offset information showing no gas flow history,
it is advisable to nipple down BOPS immediately after confirming that there is no
flow after cementing. The more time the cement gels, the more chance of gas
influx.
For exploration wells, or for development wells with offset information showing
gas flow history, do not nipple down BOPs until the cement has reached 50 psi
compressive strength. It is advisable to use a lead cement with fast setting
characteristics, such that the cement has 50 psi compressive strength in 6-8
hours.
____________________________________________________________________________________
Cementing Best Practices 44 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 45 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Casing pressure testing procedures and test pressures will be specified in the
drilling program for a specific well. However, it should be the responsibility of the
drilling supervisor to check the figures at the wellsite to ensure that the casing is
not burst or collapsed through negligence. Casing and liner pressure testing
should be performed as outlined below..
5. With surface wellhead systems, the annulus outlet for the casing string
being tested should be opened and monitored for fluid leaking past the
casing hanger pack-off element. If this is not possible, install a pressure
gauge on the casing annulus outlet and monitor for a pressure increase
during the casing pressure test.
____________________________________________________________________________________
Cementing Best Practices 45 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 46 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
6. All casing test pressures should be applied and removed slowly to avoid
adverse dynamic loading.
7. All pressure tests should take account of the annulus fluid density relative
to the fluid density inside the casing. The annulus fluid density should be
assumed to be equivalent to drilling fluid down to the cement top, then sea
water when offshore, or formation water when on land, from the cement
top to the previous casing shoe.
9. For all casing pressure tests, a record of applied pressure versus barrels
of mud pumped should be maintained. This information is particularly
useful during subsequent formation pressure testing.
A shoe test is usually conducted after drilling out a casing shoe and a small
section of new formation (usually 10 ft of new formation). Shoe tests are
performed to determine the strength of the new formation as well as the
competency of the cement sheath.
An FIT is a shoe test where the pressure is kept below the leakoff or
fracturing pressure of the rock. FITs may also be performed over long
openhole intervals while drilling.
____________________________________________________________________________________
Cementing Best Practices 46 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 47 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
pressure.
Refer to Oxy’s FIT and LOT standards to properly perform and analyze
shoe tests.
Sonic and ultrasonic logs are the most common ways to evaluate the quality of a
cement job. In addition, temperature surveys can determine the location of top-of-
cement, and tracer surveys can determine if hydraulic isolation has been
attained.
Cement evaluation logging tools emit sound waves (sonic and/or ultrasonic
waves) to help determine the bonding and presence of set cement in the annulus.
Cement Bond Log (CBL) – is a sonic tool that sends and receives sound waves
omni-directionally. The CBL can indicate the general quality of cement/casing and
cement/formation bond.
Segmented Bond Tool (SBT)– is a sonic tool that measures attenuation (sound
dampening) between points around the casing. Although not as accurate as an
ultrasonic tool, the SBL can give a rough estimate of cement channeling.
____________________________________________________________________________________
Cementing Best Practices 47 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 48 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Sometimes a good cement job is not properly represented as such by the logging
tool. The following items may negatively affect the bond log representation, and
show poor cement.
To overcome the negative affects from the above items, it is important to increase
shear bond to enhance the bond log representation. The following procedures will
help increase shear bond.
____________________________________________________________________________________
Cementing Best Practices 48 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 49 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Refer to the “Oxy Cementing Bond Log Best Practice” document for more details
on running bond logs.
Temperature logs are used to identify TOC. The temperature log should be run
6–12 hrs after the cement’s initial set, when most heat is being generated by the
exothermic reaction of cement hydration. A sharp temperature change of 10 – 40 0
F should be noticed at the TOC.
For development wells where excellent bond logs are common, consider running
a temperature log for TOC determination and eliminating the bond log run.
____________________________________________________________________________________
Cementing Best Practices 49 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 50 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
One of most costly failures in cementing occurs when maximum pressure limits
are reached before displacement is complete, resulting in a “cemented up” casing
or liner. Premature shutdowns and “cemented up” casings unfortunately occur on
a regular basis across the industry, and the cause is sometimes difficult to
determine. In general, however, these catastrophic failures fall into one of the
following categories.
• Mechanical Bridge
Mechanical blockages such as those listed below may cause sudden
excessive pressures during the cementing operation.
o LCM, cuttings, or debris blocking float equipment
o Cuttings packing off at liner hanger (However, pressures may be
increased to break down formation)
o Bottom plug does not bypass fluid
o Liner dart does not launch liner plug
o Surface equipment / manifolding plugged with cement or debris
____________________________________________________________________________________
Cementing Best Practices 50 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 51 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
When cementing operations are shut down due to excessive pressures, the event
should be investigated thoroughly. The following steps should be part of this
thorough investigation.
1. Review the events that precede and follow the premature shutdown.
a. Pressures and rates
b. Cement density variations
c. Was the cement static?
2. Determine the position of fluids and plugs when anomalous pressures occur.
a. Were darts or bottom plugs landing ?
b. Were spacer and cement interfaces at critical points in the well?
____________________________________________________________________________________
Cementing Best Practices 51 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 52 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
3. If shutdown occurs when darts or plugs landed, re-examine plug type and
clearances. During drillout, examine returns to determine the location and type
of plug cuttings.
4. Check bulk callout sheets to ensure proper cement was delivered to location.
5. Interview cementer to check if any unusual events were observed during the
cement job.
8.Write a final report and submit learnings to the Oxy Cementing Communityof
Practice representative.
____________________________________________________________________________________
Cementing Best Practices 52 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 53 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
• Cement slurries and spacers should have the same salinity content
• Gather location samples of cement and mixing water as per Best Practices
(Sec 2.2.5)
• Caliper plugs and observe loading of plugs in cementing head as per Best
Practices (Sec 3.3)
As with all cementing operations, thorough planning and close adherence to good
operating practices are necessary to ensure job success on the first attempt to
set a Kickoff Plug. The common belief that multiple cement plugs will probably
have to be spotted before one "takes", simply is not true. In most cases, failure to
obtain an acceptable cement plug on the first attempt can be traced to poor
placement practices or incorrect slurry design. The guidelines outlined below
should be closely reviewed prior to implementing these operations.
The Balanced Plug Method and Unbalanced Plug Method are two legitimate plug
setting techniques that may be used to set a kickoff plug.
Balanced Plug Method is the most popular technique to set a kickoff plug. A
hydrostatically balanced plug is placed in the well, and the drillpipe is slowly
removed from the balanced plug. A balanced kickoff plug is set as follows:
1. Ensure that there is a solid base on which to set the balanced plug
(See “Establish Solid Base” guidelines in 4.2.2.B)
____________________________________________________________________________________
Cementing Best Practices 53 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 54 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
3. Condition wellbore
12. Pull drillpipe an additional 1000 ft above top of cement plug (Pull at
normal pull rate)
14. POOH and WOC (Check lab tests for set time and compressive
strength development)
15. RIH with drilling assembly – tag cement – time drill to kickoff
Note: For well depths greater than 12,000 ft , place a ball catcher in the
drillstring at +- 200 ft above calculated TOC. The ball catcher will signal the
location of the top of cement when the cement slurry is followed with a
____________________________________________________________________________________
Cementing Best Practices 54 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 55 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
The Unbalanced Plug Method is a legitimate technique that can be used to set a
successful kickoff plug. The advantages of the unbalanced plug method include
1) Eliminating the difficulty of pulling wet with oil base or heavy mud in the well
and 2) ease in placement since there are no balance calculations or ball catchers
required. An unbalanced kickoff plug is set as follows:
1. Ensure that there is a solid base on which to set the balanced plug
(See “Establish Solid Base” guidelines in 4.2.2)
4. Condition wellbore
7. Displace cement all the way to the bottom of the drillstring with
drilling mud and a final volume of water. The water volume should
equal the volume of drillpipe from surface to the IBOP.
____________________________________________________________________________________
Cementing Best Practices 55 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 56 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
13. WOC (Check lab tests for set time and compressive strength
development)
14. RIH with drilling assembly – tag cement - time drill to kickoff
Most failed cement plugs occur because the cement plug is destabilized or
contaminated during or after placement. The following best practices will help
ensure a stable cement plug is achieved.
Prior to setting the cement plug, cure lost circulation or formation fluid influx.
Losses or flows will contaminate the cement plug. If losses or flows are occurring
below the plug setting depth, run an inflatable openhole packer to stabilize the
wellbore and also provide a base on which to set the plug.
____________________________________________________________________________________
Cementing Best Practices 56 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 57 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
* Setting viscous pills have failed many times in plug setting operations.
Unless the pills are extremely viscous, they will not prevent cement slurry
from falling down the well and destabilizing the plug.
For hole sizes less than 8 ½”, use a 2 7/8” or 2 3/8” tailpipe stinger on the bottom
of the plug setting assembly. The stinger should be a minimum of 200 ft longer
than the plug length.
For 8 ½” hole and larger, a tail pipe is not required. Use drill pipe.
A diverter sub with upward angled ports (Figure 7) should be used when
cementing off-bottom.
Figure 7
4.2.4 Centralizers
____________________________________________________________________________________
Cementing Best Practices 57 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 58 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
The wellbore should be prepared for plug cementing in the same way the
wellbore is prepared for primary cementing. Recommended mud properties
include:
Prior to setting open hole cement plugs in old wells (i.e., previously cased off
interval), consider under-reaming the open hole interval that is to be cemented.
This is done in order to remove the old mud ring that may prevent a competent
cement plug from setting up in the entire wellbore.
In general, the density of kick-off plugs is to be +/- 17.0 ppg or higher. For shallow
plugs set in softer formations, standard cement densities (15.8 – 16.4 ppg) are
adequate.
____________________________________________________________________________________
Cementing Best Practices 58 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 59 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Thickening time for plug cementing shall be performed at BHCT in similar manner
as for casing jobs.
Plug Slurry Thickening Time = Total slurry mixing time + Time to drop ball* +
Displacement time + Time to pull out of plug** + Safety Factor***
For temperatures below 230 degrees F, neat slurries (without sand, lost
circulation materials, etc.) should be used and retarded with dispersant. Above
230 degrees F, the slurry formulation should include 15-35% by weight of silica
flour or silica sand to prevent strength retrogression, and synthetic retarders
should be utilized.
For plug cement slurries, fluid loss control is not necessary when setting a kickoff
plug unless the plug is being set in an air-drilled hole where mud filter cake has
not been deposited.
Free water for a kickoff plug should be less than 1.0 %. For deviated wells (> 30
degree angle), the free water should be 0 %.
____________________________________________________________________________________
Cementing Best Practices 59 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 60 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
The plug cement slurry should be designed to mix easily with relatively low
viscosities. This can be achieved with a 17.0 – 17.4 ppg cement slurry containing
correct concentration of dispersants.
For plug setting using the balanced plug method, an indicating ball catcher
should be placed approximately 200 ft above the theoretical TOC of the cement
plug, especially when setting plugs deeper than 12,000 ft.
____________________________________________________________________________________
Cementing Best Practices 60 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 61 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
For plug setting using the balanced plug method, wiper balls should used ahead
and behind cement plug to give pressure indication of the cement position, and to
clean the drillpipe. Using wiper balls will help prevent “cement rings” in tool joints
that can cause severe problems later (such as debris in MWD tools). Check
temperature limitations on balls and catchers.
Do not attempt to kick off the cement plug until the cement has 2000 psi
compressive strength. The cement slurry can be designed to achieve this
strength within 12 hrs.
If the cement plug drills soft, pull out of plug a safe distance, and wait-on-cement
to gain more strength.
If the cement plug drills hard and soft, this is indication that the cement plug has
become unstable or contaminated.
For cement abandonment plugs that are not to be drilled out, a minimum plug
length of 250' should be used, although local regulatory rules must be followed.
This holds true for open hole as well as cased hole plugs.
For cement plugs set inside casing, expansive agent (magnesium oxide additive,
____________________________________________________________________________________
Cementing Best Practices 61 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 62 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Oxy HSE Standards and practices should be performed during each cementing
operation. The following safety measures specifically related to cementing
should also be observed.
• Wear impervious gloves when handling mixed cement slurries and cementing
chemicals. Understand the MSDS sheets and hazardous nature for all the
cementing materials on location. Even the cement slurry itself is a base and
is corrosive in nature.
• Care should be taken if gaining a sample of cement slurry from the mixing tub.
Hands should remain a safe distance from the tub agitators, and goggles
should be worn for protection.
• Ensure that cementing lines are clear of personnel during pressure testing
and pumping operations.
• Ensure that the rig floor below the cement head is clear of personnel when
dropping plugs.
____________________________________________________________________________________
Cementing Best Practices 62 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 63 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
The following KPIs should be accurately tracked for each primary cementing
operation via the Oxy Cementing Scorecard.
4. Trouble Time - How many hours of trouble time was related to cementing ?
(This may include waiting on service company, downtime, remedial work,
Wait-On-Cement (WOC), unplanned events on the critical path, etc)
5. Cementing Cost – What is the cost per bbl of total cementing services and
materials for the casing string? What was the planned cost versus the actual
cost?
6. Safety - Was there a safety incident or near miss related to the cementing
operation?
7. Liner Top Test – If the job was a liner, was the liner top test successful?
8. Bond Log - Was a bond log conducted ? If yes, was the bond log graded as
a) poor, b) marginal, c) good, d) outstanding ?
____________________________________________________________________________________
Cementing Best Practices 63 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 64 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
9. Top-Of-Cement – Did the actual Top of Cement meet the requirements of the
hole section? Was cement raised high enough to adequately satisfy all critical
requirements?
10. Remedial Work - Was any remedial work / squeeze job required to repair the
primary cementation ? This may be a shoe squeeze or a production casing
remedial job.
11. Lost Circulation - Were there mud losses while cementing? Indicate either a)
No losses, b) Partial losses, or c) Total Losses.
Additional KPIs not contained in the Oxy Cementing Scorecard may still be
tracked. These include: Casing Pressure Tests, Shoe Tests, Annular Flow
Incidents, Top Jobs Required, Float Equipment Holding, and Bumping Plugs
____________________________________________________________________________________
Cementing Best Practices 64 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 65 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
communicating with the OXY Drilling Engineer as required to obtain all necessary
information for preparation of this document.
• Operational details, pump rates, for each fluid and shear or bumping
pressures for wiper plugs
____________________________________________________________________________________
Cementing Best Practices 65 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 66 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
• Displacement volumes
• Tabular graph of fluids positions after placement
• Cost estimates for service and materials
Presentation of this report should include a hard copy and an electronic file in
either Microsoft Word or Excel format. Graphs may be generated to supplement
the reports.
Prior to each cementing job, the Cementing Contractor Engineer should update
the respective portion of the recommendation. Updates should be referenced to
initial recommendation and pertinent lab testing.
Note: No cement slurry should be considered “approved and finalized” until the
OXY Drilling Superintendent or Drilling Engineer confirms it. Do not pump this
slurry design without this approval.
____________________________________________________________________________________
Cementing Best Practices 66 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 67 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007
Cementing contractor pricing and invoicing should consider using a “cost plus”
scheme, as opposed to a book price minus discount. This strategy makes line
item auditing easier and more accurate, and allows Oxy to pay appropriate
charges (service and materials) for each job. Oxy can evaluate the actual value
of any particular job when the actual costs for that job are applied to the invoice.
____________________________________________________________________________________
Cementing Best Practices 67 02/26/2014
Revision 1