You are on page 1of 67

Revision No.

: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 1 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Section Page

1.0 Introduction 6

2.0 Primary Cementing Engineering 7

2.1 Mud Removal 7

2.1.1 Mud Conditioning 7

2.1.2 Pipe Movement 9

2.1.3 Centralization 9

2.1.4 Displacement Pump Rate 10

2.1.5 Spacers 11

2.1.6 Mechanical Aids 13

2.2 Cement Lab Testing 13

2.2.1 Definitions 13

2.2.2 Cement Lab Audit 16

2.2.3 Pilot Testing 16

2.2.4 Blend Testing 20

2.2.5 Onsite QC 21

2.3 Cement Slurry Design 22

2.3.1 Cement Slurry Properties 22

2.3.2 High Temperature Slurry Design 25

____________________________________________________________________________________
Cementing Best Practices 1 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 2 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

2.4 Special Cementing Challenges 26

2.4.1 Annular Gas Flow 26

2.4.2 Lost Circulation 27

2.4.3 Liner Cementing 28

2.4.4 Salt Sections 31

2.4.5 Reactive Shales 32

2.4.6 Long Ratholes 32

2.4.7 Steam Injection 32

2.4.8 Foam Cement 32

2.4.9 Corrosive Environments 33

3.0 Primary Cementing Operations 34

3.1 Mixing and Pumping Cement 34

3.1.1 Pre-job Procedures 34

3.1.2 Job Procedures 36

3.1.3 Pressure Test Lines 38

3.1.4 Density Control 38

3.1.5 Pump Rate 39

3.1.6 Data Acquisition 39

____________________________________________________________________________________
Cementing Best Practices 2 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 3 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3.1.7 Displacement 39

3.1.8 Pump Casing Out of Hole 40

3.2 Float Equipment 41

3.3 Cement Wiper Plugs 41

3.4 Post Job Operations 42

3.4.1 Wait-On-Cement 42

3.4.2 Nippling Down BOPs 43

3.4.3 Pressure Test Casing 43

3.4.4 Shoe Tests 44

3.5 Cement Sheath Evaluation 45

3.5.1 Cement Evaluation Log 45

3.5.2 Temperature Log 47

3.5.3 Tracer Survey 47

3.6 Problem Jobs – “Cemented Up” Casing 47

4.0 Plug Cementing 50

4.1 Plug Setting Techniques 51

4.1.1 Balanced Plug Method 51

4.1.2 Unbalanced Plug Method 52

4.2 Achieving a Stable Cement Plug 53

____________________________________________________________________________________
Cementing Best Practices 3 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 4 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

4.2.1 Stabilizing the Wellbore 53

4.2.2 Providing a Base 53

4.2.3 Drillpipe, Stinger, and Diverter 54

4.2.4 Centralizers 54

4.2.5 Pulling Drillpipe Out of the Plug 55

4.3 Wellbore Preparation for Setting Cement Plug 55

4.4 Cement Slurry Design – Plug Cementing 55

4.4.1 Slurry Density 55


4.4.2 Thickening Time 56

4.4.3 Compressive Strength 56

4.4.4 Fluid Loss 56

4.4.5 Free Water 57

4.4.6 Rheological Properties 57

4.4.7 Spacers for Plug Cementing 57

4.5 Plug Cementing Displacement 58

4.5.1 Ball Catcher 58

4.5.2 Wiper Balls 58

4.5.3 Drillpipe Caliper 58

4.6 WOC and Cement Plug Drillout 58

____________________________________________________________________________________
Cementing Best Practices 4 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 5 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

4.7 Abandonment Cement Plugs 58

5.0 Health, Safety, and Environment 59

6.0 Tracking Results 60

6.1 Key Performance Indicators 60

6.2 Cementing Scorecards 62

7.0 Contractor Requirements 62

7.1 Cementing Proposal 62

7.2 Cement Testing 63

7.3 Pricing and Invoicing 64

7.4 Contract Specifications 64

____________________________________________________________________________________
Cementing Best Practices 5 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 6 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

1.0 Introduction

The purpose of this document is to outline and promote a “Best Practices”


philosophy throughout the Oxy Global Drilling Community. This document
provides direction for general planning and executing primary and plug cementing
operations on a global basis. It is understood that in many well situations, the
preferred “best practice” may not achieve the optimum result. Every cement job
should be designed individually dependent on its specific wellbore characteristics
to achieve the desired cementing objectives.

Promoting ‘Best Practices’ is an ongoing effort throughout Oxy drilling operations.


Given the wide variety of cementing operations performed throughout the Oxy
Drilling Community, a collective sharing of cementing practices and technologies
will help all areas obtain competent and economical cement jobs. To help
achieve this, a Global Cementing Network or ‘Community of Practice’ (COP) has
been formed. Visit the Oxy Cementing Network site on the Global Drilling
Community Website to view the network’s charter, goals, and members’ names
and contact information. In addition, the Oxy Cementing Network site includes:

o Engineering tools
o New cementing technologies
o Performance data – KPIs
o Cementing technical papers
o Reference materials
o Cementing presentations
o Job examples
o Rigorous technical specifications for cementing contracts
o Squeeze cementing documents
o Cementing Contractor Information
o Contacts
o Technical Information
o Lab Audits

____________________________________________________________________________________
Cementing Best Practices 6 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 7 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

o Cementing Scorecards
o Best Practice Updates and Notices

2.0 Primary Cementing Engineering

The first step in successfully engineering the cementing process is to clearly


define the objectives of each operation. The wellbore conditions and casing
design must then be evaluated to determine cement placement, hydrostatic
constraints, and volumes. The cementing contractor must be fully involved in this
stage.

2.1 Mud Removal

The top priority in achieving a successful cement job is to displace all of the
drilling mud from the annular section to be cemented, that is, to achieve a high
displacement efficiency. Displacement efficiency is defined as the percentage of
annular area at any given cross-section that is filled with cement. There are
several proven best practices that can be used together to help achieve a nearly
100 % displacement efficiency, including mud conditioning, pipe movement,
centralization, spacers, and mechanical aids.

2.1.1 Mud Conditioning

1. Mud Properties

Drilling muds are designed to help efficiently drill and transport cuttings to
the surface, but are not always conducive to good mud displacement
during cementing operations. Therefore, prior to running the casing and
cementing, the drilling fluid should be conditioned to exhibit “easy-to-
remove” properties including low fluid loss, thin rheological properties, and
a flat gel profile. General recommended production casing/liner values for
these properties are listed below, although significant variations can occur

____________________________________________________________________________________
Cementing Best Practices 7 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 8 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

based on mud type and weight.

o API Water Loss < 10 cc/30 min

o Yield Point < 15 (straight holes)


< 20 (hole angle > 30 degrees)

o 10 m gel strength < 25 or 10s/10m gel strengths < 2/3

o 30 m gel strength < 30 or 10m/30m gel strengths < 2/3

Additionally, if there is a concern for mud losses while running


casing or cementing, a LCM pill should be spotted on bottom prior
to POOH with drillstring.

Note: If there is to be excessive rathole during cementing, it is not


necessary to spot a heavy mud pill on bottom prior to POOH with
BHA. It is more problematic to have a heavy, more viscous mud
around the casing shoe prior to cementing, than any slight risk that
cement may fall into the rathole after placement.

2. Conditioning Volume

With casing at casing point, circulate hole clean of formation


cuttings and gas, and condition mud for cementing. The mud is to
be free of cuttings and of uniform density. It is recommended to
circulate at least 2 1/2 hole volumes (See Figure 1).

Figure 1

____________________________________________________________________________________
Cementing Best Practices 8 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 9 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Conditioning
Conditioning Time
Time after
after Landing
Landing Casing
Casing
(Halliburton
(Halliburton Research
Research Study)
Study)

3. Conditioning Rate

Stage pump rate to the maximum rate planned during the cementing
operation. Monitor well for whole mud losses. If mud circulation is lost
and cannot be regained, stop circulating and prepare to cement the
well.

4. Static Time After Conditioning

After the casing has been landed, and the drilling mud conditioned,
cementing should begin as soon as possible, preferably within 15
minutes. Increased static times may cause the mud to gel significantly
and make it difficult to remove from the annulus.

Note: For many cementing operations, it is a good practice to break


circulation every +- 3000 ft while running casing. This will break mud
gel strengths and remove cuttings/filter cake from centralizers or other
casing attachments.

2.1.2 Pipe Movement

While conditioning and cementing, the casing should be rotated or reciprocated

____________________________________________________________________________________
Cementing Best Practices 9 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 10 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

throughout the mud conditioning and cementing process. Pipe movement will
both physically scrape mud from the wellbore, as well as keep fluid moving
around all portions of the hole.

Reciprocation = 15 – 20 foot stroke length @ 1 stroke per minute


Rotation = 15 - 30 rpm

Note: Be aware of casing connection torque and strength limitations when


moving the casing

2.1.3 Centralization

Casing stand-off through critical sections should be a minimum of 70%. Standoff


is defined as NAC/(HR-CR), where NAC = the Narrowest Annular Clearance
between the casing and the wellbore, HR = hole radius, and CR = casing radius
(CR). Standoff can range from 0 % (casing against the hole wall) to 100 %
(casing perfectly centered in the hole). Centralizer placement to achieve at least
70 % stand-off can be determined using computer modeling or the techniques
outlined in API Specification 10D, Specification for Casing Centralizers, however,
please note the following general rules-of-thumb.

Deviation < 45 degrees = 1 centralizer per 30 ft joint


Deviation > 45 degrees = 2 centralizers per 30 ft joint (For tight radius bends
and severe doglegs, adding 2 centralizers per joint may increase the rigidity of
the casing string such that running in the hole may be more difficult.)

Use rigid, semi-rigid (double bow spring) or positive stand-off centralizers in open
hole sections if possible. Bow spring centralizers are recommended for liner laps,
casing-in-casing scenarios, and in washed out hole sections.

In addition to centralization, hole size versus casing size should be planned to


provide enough clearance not to restrict flow through the annulus. The effective
diameter of the annulus should be at least 1.5 inches (7” in 8 ½” e.g.).

2.1.4 Displacement Pump Rate

____________________________________________________________________________________
Cementing Best Practices 10 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 11 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Displacement rates should be specified based on the maximum pumping rate that
can be obtained without exerting sufficient annulus pressure (due to increased
ECDs) to break-down the formation and lose returns. Computer modeling of
allowable pump rates should be performed as part of the planning process to
enable accurate specification of cement rheological properties. To optimize mud
removal, the annular fluid velocity during displacement should exceed 70 m/min
or 200 ft/min – Figure 2. Slow the rate to bump the plug.

Note: Do not shut down and perform a hesitation squeeze on the casing shoe at
the end of a job. Field results have generally shown no benefit when attempting
to use the “hesitation method”.

Figure 2

Displacement
Displacement Efficiency
Efficiency vs.
vs. Annular
Annular Velocity
Velocity
SPE/IADC
SPE/IADC 18617,
18617, T.R.
T.R. Smith
Smith

2.1.5 Spacers

____________________________________________________________________________________
Cementing Best Practices 11 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 12 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

1. General

Spacers are pumped to separate mud and cement. They are designed to:

• Keep all fluids compatible in the wellbore


• Help remove mud from the annulus
• Leave the casing in a water wet condition for better bonding
• Maintain adequate hydraulic pressure while cementing

The best spacer to use for cementing operations is water with surfactants,
chemical additives, or salinity added as needed. Even if a weighted spacer
is required to maintain adequate downhole overbalance pressures, it is
recommended to precede the weighted spacer with +- 20 bbls of base fluid
(water or oil preflush) to provide turbulent flow properties and to dilute mud
filter cake. When adding a light preflush, the hydrostatics must be sufficient
at every point during the job to prevent formation fluid influx.

2. Spacer Density

Weighted spacer densities should be designed at the midpoint density


between mud and cement slurry densities. Weighted spacers should be at
least 0.5 ppg higher than the mud weight, and at least 0.5 ppg lower than
the cement slurry density.

3. Spacer Volume

The spacer volume should be designed to produce a minimum of 10


minutes annular surface contact time through intervals of critical cement
bonding. This requirement is critically important and should not be under-
designed. Example: If displacing at 10 bpm, a total of 100 bbls of spacer
should be employed, for a total contact time of 10 minutes.

In addition to the requirement of contact time, the spacer volume should be


sufficient to yield a minimum fluid height of 500 feet in the casing annulus.

4. Spacer Flow Regime

____________________________________________________________________________________
Cementing Best Practices 12 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 13 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Spacers should be designed to be in turbulent flow in the annulus at the


planned displacement rate for a particular cement job. If turbulent flow is
not achievable, high laminar flow rate is preferred. A cement job should
never be designed for plug flow conditions.

5. Spacer Salinity

The salinity of a water based spacer should match the salinity of the
cement slurry.

6. Spacer Wettability

When cementing in oil or synthetic based muds, a surfactant package


should be added to the spacer to help water wet the casing and formation,
and to prevent thick emulsions at the spacer/mud interface. Wettability
testing can be performed by the cementing service company to optimize
the surfactant loading.
2.1.6 Mechanical Aids

The following items may be employed to help remove mud from the wellbore
during cementing.

• Upjet Float Shoe – Holes in the float shoe circumferentially direct


approximately 60 % of the fluid rate upward and around the shoe joint.

• Wall Scratchers – Either rotating or reciprocating scratchers mechanically


remove filter cake/solids while moving the casing.

• Turbulator centralizers – contain fins or angled blades to cause turbulence


near the centralizer. Turbulators can affect mud removal +- 5-10 feet from
the centralizer location.

2.2 Cement Lab Testing

2.2.1 Definitions

____________________________________________________________________________________
Cementing Best Practices 13 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 14 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Placement Time – The amount of time elapsed between the start of cement
mixing to final placement of the cement in the annulus.

Thickening Time - The amount of time for a cement slurry to become “too thick
to pump”. Thickening time is measured in an HPHT consistometer at BHCT and
BHP. A slurry is considered “too thick to pump” when it reaches a cement
consistency of 70 Bc (Bearden Units)- See Figure 3.

Note: API defines thickening time as time to reach 100 Bc, but for Oxy best
practices, the 70 Bc should be considered to be the maximum pumpable
consistency.

Figure 3 – Thickening Time and Transition Time

100-----------------------------------------------------------------
Thickening Time
Consistency 70
(Bc)

40 --------------------------------------
Transition
Time

0
Time

Transition Time – The time for a cement slurry to transition from a liquid to a gel.
It can be measured dynamically in an HPHT consistometer, or in static conditions
in a Static Gel Strength Tester. While conducting a thickening time test, the
dynamic transition time is the difference in time between the 40 Bc to 100 Bc
consistency reading (See Figure 3). For a static gel strength test, the slurry
transition time is the elapsed time for cement to progress from 100 lb/100 ft 2 to
500 lb/100 ft2 gel strength.

____________________________________________________________________________________
Cementing Best Practices 14 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 15 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Right Angle Set – The term used to describe a cement slurry that has a very
quick transition time, i.e. the slurry consistency moves from 40 Bc to 100 Bc
rapidly.

Compressive Strength – The compressional force per unit area when set
cement fails. It can be measured by physically crushing a cement cube or
cylinder, or through non-destructive means with an Ultrasonic Cement Analyzer
(UCA).

Wait on Cement (WOC) - For operations, WOC is the waiting time required after
cementing in order to safely remove well control equipment with the annulus open
or casing/liner fluid underbalanced. For a cement slurry, WOC is the time
necessary for the cement to set and attain a compressive strength of 500 psi.
This is most efficiently determined through lab testing with the UCA, which plots
strength development over time.

Set Time (or Initial Set) – Set time is the time it takes for the cement to gain 50
psi compressive strength, becoming a hard solid. Early set time is one of the
most important properties in an oilwell cement.

Fluid Loss – The amount of water pressed from a cement slurry under a
differential pressure. In the lab, it is measured at BHCT by pressurizing the
cement across a 325 mesh screen at 1000 psi differential for 30 minutes.

Free Water –The amount of clear fluid that separates from a cement slurry in a
static condition. It is measured in the lab by filling a 250 ml graduated cylinder
with cement and observing it for 2 hrs. For deviated wells, the graduated cylinder
is usually placed at a 45 degree angle. A basic free water test is performed by
conditioning the cement slurry for 20 mins at BHCT and then pouring the slurry
into a 250 ml graduated cylinder at room temperature. An operating free water
test is also conditioned but poured into a 250 ml graduated cylinder sitting in a
water bath at BHCT. The operating free water test is a more severe and accurate
test. For HPHT (> 190o F) perform the free water test at 190o F or perform a high
temperature density segregation test.

____________________________________________________________________________________
Cementing Best Practices 15 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 16 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Density Segregation – The amount of density variation in a column of cement


after it has set. It is physically measured in the lab after the cement has set for 24
hrs at BHST and BHP.

Shear Bond Strength – The force per unit surface area required to shear
cement from a metal casing surface. It can be measured in the lab using a shear
bond mold.

Tensile Strength – The force per unit area for a cement to fail in tensile. It is
measured by physically pulling a “dogbone” shape cement specimen apart.

Cement Expansion – The linear or radial growth of cement during and/or after
set. This property can be physically measured in the lab. Note that conventional
cement slurries will normally shrink while setting due to hydration reduction.
Expansion additives help cement expand 0 – 2 % linearly.

Gel Strength – Gel strength is the yield point of a cement slurry at varying times.
Normally in the lab the gel strength is measured with a viscometer at 10 second
and 10 minute intervals.

2.2.2 Cement Lab Audit

An annual cement lab audit should be conducted for the cementing contractors
used by Oxy. The audit should be performed by Oxy using Oxy specifications and
scoring from the Oxy Cementing Lab Audit Form.

2.2.3 Pilot Testing

Pilot tests are cement slurry tests that use lab stock cement and additives prior to
actual bulk blending. A pilot test should be conducted for each cementing
operation. If possible, it is recommended to perform pilot tests with the cement
batch sample and additive lot numbers that will be used for the actual job. Pilot
tests are performed to determine the actual slurry design for the job. It may
require several pilot tests to perfect a cement slurry design. A pilot test should
consist of the seven (7) items listed below.

____________________________________________________________________________________
Cementing Best Practices 16 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 17 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

1. Thickening Time

Thickening time tests should be performed at the maximum anticipated


bottom-hole circulating temperature for the hole depth under consideration.
If field measurement of bottom-hole circulating temperature is not possible,
then this figure is to be estimated using the API circulating temperature
tables given in API Specification RP 10B. It should be noted that these
tables are only an approximation based on compilation of a considerable
amount of field data. Therefore, it may be appropriate in critical situations
to consult with offset operators or the cementing contractor to determine if
more accurate downhole temperature data is available.

Thickening time charts should be attached to all lab reports. Proper slurry
design should be employed to avoid gelation while the cement is being
pumped (See Figure 4).

Figure 4

70
Unacceptable
Gelation Spike

40 ------------------------------------------------------------------
Consistency
(Bc)

0
Time

For liner slurries, the thickening time test should include a 20 minute
hesitation time (static time) after placement time has been reached. This
simulates a 20 minute shutdown to release the drillpipe from the liner top.

For batch mixed slurries, the thickening time test should include a

____________________________________________________________________________________
Cementing Best Practices 17 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 18 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

simulated surface retention time on the HPHT consistometer prior to


increasing pressure and temperature to downhole conditions.

2. Density

The density of cement slurries is usually determined in the lab by mass


balance calculations. For slurries containing microspheres (hollow
spheres), the density should be verified using a pressurized mud balance
after proper mixing.

3. Compressive Strength

Compressive strength tests should be conducted as per API RP 10B


procedures. In some cases it may be beneficial to precondition cement
slurries at BHCT prior to the compressive strength test. This should be
noted on the lab report.

a. Ultrasonic Cement Analyzer (UCA)


The UCA chart should be attached to all lab reports.

b. Crush Test
The crush test may be performed using cube molds as per API RP
10B procedures. Another option is to use the UCA cylindrical
sample. When removed from the UCA cell, it may be crushed to
confirm the UCA compressive strength value.

4. Fluid Loss

Fluid loss tests below 190o F should not be performed according to current
API RP 10B procedures. Instead, the cell should be preheated to BHCT,
filled with conditioned cement slurry, 1000 psi pressure applied from the
top, and fluid loss measured for 30 minutes. For tests above 190 o F, a
high temperature cell should be used and tests performed according to
current API RP 10B procedures. The 325 mesh screens used in fluid loss
testing should be thoroughly cleaned. The screens should be thrown away
after they are used when testing cement slurries containing latex or
“pseudo-latex” (poly vinyl acetate) additive.

____________________________________________________________________________________
Cementing Best Practices 18 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 19 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

5. Free Water

Follow API RP 10B Section 15, with the following exceptions:

• Conditioning in an atmospheric consistometer is acceptable.

• Time to temperature of 6 minutes is not required.

Conduct the operating free water test with a heated static period at BHCT
or 194o F, whichever is lower. For deviated wells, place the graduated
cylinder at 45o angle in the water bath.

6. Rheological Properties

Rheologies and 10 s / 10 m gel strengths should be measured using a


Fann viscometer as per current API RP 10B proceduresIt is important to
use a heated cup at BHCT when measuring the rheological properties.

7. Mixability

Mix slurry as per current API RP 10B procedures 4000 rpm for 15 seconds
and 12,000 rpm for 35 seconds). If the slurry contains microspheres, the
12,000 rpm may be replaced by 4000 rpm.

Cement is added to the mixing water during the first 15 seconds of mixing.
The “time required to add cement to the mixing water” should not exceed
15 seconds. The mixability or “time required to add cement to the mixing
water” should be recorded on all lab reports.

8. Compatibility

Compatibility tests should conducted by mixing varying percentages of


cement/spacer or spacer/mud and conditioning at atmospheric
temperature for 20 minutes. Rheological testing is then performed at room
temperature and at BHCT in a heated cup. The percentages of
cement/spacer or spacer/mud should be conducted at 100/0, 95/5, 75/25,

____________________________________________________________________________________
Cementing Best Practices 19 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 20 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

50/50, 25/75, 5/95, and 0/100, respectively. If the calculated PV/YP of any
of the mixtures is 1.5x greater or less than the 100/0 or 0/100 values, then
the fluids are deemed incompatible. For high temperature applications
above 190 oF, the compatibility tests should be conducted at 190 oF.

9. Special Tests

a. Transition Time

For all production casing cement slurries, the transition time


(dynamic transition time determined from the thickening time test)
should be reported on the lab report. Short transition times (< 30
minutes) may be beneficial to help prevent formation fluid influx into
the wellbore.

b. Density Segregation

For higher temperature cementing (> 200 F), the “BP Settling Test”
should be performed to determine if density segregation is a
problem.

c. Shear Bond

The cementing contractor should have available shear bond molds


to perform shear bond testing for critical production casing cement
testing.

d. Expansion

When expansive additives are being used in a cement design,


expansion tests should be conducted using linear molds. The linear
expansion of a cement slurry should never be more than 1.5 %.

e. Microsphere testing

For density, free water, and rheological testing, microsphere slurries


should be prepared as follows;

____________________________________________________________________________________
Cementing Best Practices 20 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 21 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

• Mix slurry at 4000 rpm – do not mix at 12,000 rpm


• Place cement slurry in plastic bag and tie off
• Place plastic bag in autoclave or HPHT consistometer and
pressurize to estimated maximum ECD pressure
• Remove bag from autoclave
• Measure density with pressurized mud balance
• Condition slurries in atmospheric consistometer for 20 minutes
at BHCT
• Perform rheological and free water testing

2.2.4 Blend Testing

1. Plant Blend

A proper plant blend sample is a composite of all cement loaded for a


specific cement job. In-line bulk samples from each load are collected and
then mixed to form a plant blend composite sample. Plant blends should
be performed for all cement jobs deemed critical, i.e. long placement
times, higher temperatures, complex blends, unconventional densities,
new or variable cements, etc.

If a plant blend test fails, then the cement should be dumped, or liquid
additives used to properly adjust the cement design to the required
performance properties.

An improper plant blend is a small (50 – 100 sk) blended cement that is
taken prior to loading all of the cement. This type of plant blend test only
tests that the first 50-100 sacks that are loaded. Even if this test passes, it
leaves the remaining cement to be loaded untested. This plant blend test
is not therefore not representative of the entire cement blend that will be
pumped.

2. Mix Water

For plant blend testing, the location mix water and location liquid additives

____________________________________________________________________________________
Cementing Best Practices 21 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 22 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

should be used.

2.2.5 Onsite QC

1. Dry Cement Sampling

A total of three (3) 1-gallon samples of dry cement blend should be


collected in a plastic sample bag from the bulk cement supply lines or
surge tank after cementing, and stored in a dry area on location for the
remainder of the well in case there are job issues that arise.

2. Cement Slurry Sampling

Cement slurry density should be measured at regular intervals during


cement slurry mixing. Catch at least 2 cup samples from each planned
slurry density. Place samples as far away from noise and mechanical
vibrations as possible, to prevent major free water separation.

Note: Set times of the surface samples may not be accurate due to lack of
bottomhole temperature, and also evaporation due to atmospheric
exposure.

2. Mix Water Testing

In areas where water hardness and composition varies, the location mix
water should be tested with a mix water kit including chlorides and sulfate
content, pH, and specific gravity. In cases where the mix water is suspect
and may contain organic materials that would retard the cement, the
location water should be sent to the lab for cement slurry tests.

2.3 Cement Slurry Design

2.3.1 Cement Slurry Properties

____________________________________________________________________________________
Cementing Best Practices 22 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 23 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

There are six (6) major slurry performance properties that are tested for each
cement design. These include slurry density, thickening time, compressive
strength, fluid loss, free water, and rheology.

The slurry property recommendations in Table 1 are generally accepted values


that should be considered on a global basis.

Table 1 – Recommended Slurry Properties


Compressive Strength1
Thickening
Transition Free Fluid Yield Shear
Casing String Time Test
Time At 72 Water1 Loss Point Bond
(TTT) Initial Set 24 hr
Drillout hr
(lb/100
(hr:min) (hr:min) (hr:min) (psi) (psi) (psi) (%) (ml/30min) (psi)
ft2)

< TTT + 4
Surface Lead PT2+ 1 hr NR3 50 > 250 NR 2.0 NR NR NR
hrs
< TTT + 4
Surface Tail PT+ 1 hr NR 500 > 800 1200 2.0 NR NR NR
hrs
< TTT + 3
Intermediate Lead PT+ 1 hr NR 50 > 250 NR 1.0 NR < 15 NR
hrs
< TTT + 3
Intermediate PT+ 1 hr NR 500 NR 1200 1.0 NR < 15 NR
hrs
< TTT + 3
Drilling Liner PT+ 1 hr NR 500 > 1500 NR 0.0 < 150 < 15 NR
hrs
< TTT + 2 > 300
Production Casing PT+ 1 hr < 30 min NR > 1500 NR 0.0 < 100 < 15
hrs psi
< TTT + 2 > 300
Production Liner PT+ 1 hr < 30 min NR > 1500 NR 0.0 < 70 < 15
hrs psi

Note: For a lner Thickening Time Test, hesitate for 20 mins after placement time and restart the consistometer
1 Local regulatory requirements supercede chart recommendations
2 PT = Placement Time
3 NR = No Requirement

1. Slurry Density

The cement slurry density should be specified to be as high as possible


throughout the cemented interval without causing formation breakdown
during placement. In general, the cement density should be a minimum of
1.0 ppg heavier than the drilling fluid density in the hole at the time of
cementing. Slurry density also may be varied in order to achieve optimum
cement slurry properties.

____________________________________________________________________________________
Cementing Best Practices 23 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 24 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Use cementing simulation software provided by the cementing contractor


to determine optimum density, rheologies, and pumping rate to
successfully achieve the desired Top-Of-Cement (TOC).

2. Thickening Time

For all thickening time tests, the elapsed time to 40 Bc, 70 Bc, and 100 Bc
should be measured in hours and minutes, with the 70 Bc figure taken
as the measured thickening time. The difference between the 100 Bc
and 40 Bc times should be used as an indication of rate at which the
cement slurry changes from a pumpable to an unpumpable condition, and
is noted as the transition time. The 40 Bc,70 Bc, and 100 Bc
measurements should be reported on all thickening time tests.

Thickening time is to be specified to allow for mixing and placement of


slurries, plus an allowance for possible equipment failure and downtime. In
general, slurry mix rates of 5-8 bbl/min should be allowed for in design
calculations. If the cement density is +/- 14 ppg or higher, then use 5.0
bbl/min. For lighter weight slurries in the +/-12.0 ppg range, use 8.0
bbl/min. These rates are based on maximum pumping rates that can be
reasonably achieved in the field with a conventional re-circulating mixer,
while still maintaining uniform slurry density. On this basis, thickening time
requirements are to be calculated as the sum of the following:

Lead Thickening Time = Lead slurry mixing time + Tail slurry mixing time
+ Time to launch top plug + Displacement time + Safety Factor

Tail Thickening Time = Total tail slurry mixing time + Time to launch top
plug + Displacement time + Safety Factor

As a rule of thumb, 15 minutes should be allowed to launch the top


cementing plug, and one hour should be allowed for equipment breakdown
safety factor. The other time elements will have to be calculated based on
the fluid volumes to be pumped and the planned pumping rates.

Use synthetic retarders instead of lignin retarders when they are required

____________________________________________________________________________________
Cementing Best Practices 24 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 25 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

to help control thickening time at higher temperatures.

3. Compressive Strength

Cement slurries placed in the annulus should set as soon as possible. The
recommended compressive strength values are shown in Table 1. Note
that a properly designed slurry will have an initial set time (time to gain 50
psi compressive strength) only slightly longer than the thickening time
value.

Although ultimate compressive strength is not the most important cement


slurry parameter, it should be noted that a cement with more compressive
strength would promote a stronger shear bond with the casing and
formation.

4. Fluid Loss

For most wells drilled, the cement filtrate loss is controlled by the mud filter
cake that is deposited during drilling. However, for slurries that will contact
producing formations, slurry design should include the addition of fluid loss
additive as a precautionary measure. For the applications described
below, API fluid loss determined at 1000 psi differential pressure should be
as follows:

• For production liners, specify 70 ml/30 minutes, or less

• For primary cementing of casing through productive


intervals, specify 100 ml/30 minutes, or less

• For drilling liners, specify 150 ml/30 minutes, or less

• For primary cementing of casing through non-productive intervals,


there is no recommended requirement.

• For air drilled hole sections through non-productive intervals,


specify at least 350 ml/30 minutes, or less

____________________________________________________________________________________
Cementing Best Practices 25 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 26 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

5. Free Water

The API free water content of all slurry designs shall be specified as
shown in Table 1, less than 2.0 % for surface casings, less than 1.0 % for
intermediate casings, and 0 % for drilling liners, production liners, and
production casings. This applies to vertical as well as inclined free water
tests.

6. Rheological Properties

Rheological properties of the cement are to be specified to ensure that the


slurry is as thin as possible without violating free water requirements. The
recommended low YPs given in Table 1 will help ensure low ECDs, ease
in mixing, and turbulent or high laminar flow regimes. The cement slurry
should never be designed to pump in plug flow.

2.3.2 High Temperature Slurry Design

For wells with anticipated bottom-hole static temperatures of 230 o F or above, the
cement slurry must be designed to prevent cement strength retrogression. This
can be accomplished through the addition of 15–40 % by weight of silica sand or
silica flour. In general, silica flour ground to 325 mesh is to be used at
temperatures between 230o F and 350o F. Coarser silica (200 mesh / 100 mesh)
is to be used at temperatures above 350 F. However, combinations of varying
mesh sizes have also been used together effectively. In all cases, compressive
strength performance should be tested at static bottomhole conditions over a
minimum period of 7 days to determine if retrogression will occur.

For steam injection wells, 35 % - 60 % by weight of silica sand or silica flour


should be added to the cement.

2.4 Special Cementing Challenges

2.4.1 Annular Gas Flow

____________________________________________________________________________________
Cementing Best Practices 26 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 27 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Annular gas flow can occur by flowing through the cement sheath (See Figure 5)
or can be the result of leakage at the cement/casing or cement/formation
interface.

Figure 5 – Gas channel

When cementing across troublesome gas producing intervals, apply the following
recommendations to prevent gas flow through the unset cement.

 Use foam cement or a gas-generating additive (alumina) to give the


cement compressibility to prevent gas influx.

 Use low fluid loss cement (< 70 cc/30 min)

 Use fast setting cements and right angle set cements


 For liners, set a liner top packer after cementing

 Use expanding cements (gas generating additives will also cause cement
expansion)

 Do not mechanically disturb the casing (nipple up BOPs or cut casing,


e.g.) until the cement has set (50 psi compressive strength)

____________________________________________________________________________________
Cementing Best Practices 27 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 28 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

When cementing across troublesome gas producing intervals, the following


recommendations should be considered to prevent gas leakage along the set
cement interfaces.

 Use a post set expanding agent such as magnesium oxide additive

 Sandblast the casing to increase shear bond

 Displace the cement job with a lighter fluid so that a microannulus will not
be formed during completions operations

 Use a fast setting cement

2.4.2 Lost Circulation

The greatest challenge in cementing wells is preventing lost circulation before or


during cementing operations. The following bullets outline potential solutions to
this common problem.

 Prevent losses before running casing – It is important to have full returns


before beginning cementing operations. It is very difficult to regain
circulation during cementing if losses are occurring while circulating mud.
To prevent losses while drilling, running casing, and conditioning the well,
refer to Drilling Fluids Best Practices (Section 2.1.10).

 Spot LCM Pill – For severe losses, spot an LCM pill prior to POOH with
drillpipe. Refer to Drilling Fluids Best Practices(Section 2.1.10).

 Running casing - Based on the anticipated drilling fluid rheology while


running casing, maximum casing running speeds should be specified that
will avoid formation break-down and/or loss of whole mud to weak zones.
Consider surge reduction float equipment.

 Thin mud – To help prevent losses during cementing, consider pumping a


large volume (150 – 250 bbls, e.g.) of sufficient density thin mud (YP < 10)
ahead of the spacer and cement.

____________________________________________________________________________________
Cementing Best Practices 28 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 29 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

 Thin Cement – Design cement slurries for YPs < 10, if possible, to reduce
ECDs while cementing.

 Reactive cross-linked spacers – A gelled sodium metasilicate spacer has


been successful in regaining losses while cementing in severe loss
situations, especially when used in conjunction with spotting LCM pill
before POOH with drilling assembly.

 Foam Cement – Foam cement (foam density 8 – 12 ppg) has been


successful in gaining full cement returns to surface.

 Hollow Spheres – Microspheres or glass beads can be used with foam


cement to reduce cement density to as low as 4 ppg to achieve full cement
returns in severe loss situations.

 Simulate ECDs / Pump Rate – Use cementing contractor simulation


software to model ECDs and remain below fracturing gradient of weak
formations. Control ECD’s with cement slurry density, rheology, and pump
rate.

 Stage Tools – A two stage cement job employing cementing stage tools
(with or without integral external casing packers) can be performed to
achieve full returns when a full column of cement cannot be obtained with
one stage.

2.4.3 Liner Cementing

The following pre-cement job circulating recommendations are given for cementing
liners:

1. Cuttings should be removed from the wellbore prior to running or setting


liner hanger as per Drilling Fluids Best Practice (Section 2.1.2).

2. After setting the liner hanger, begin circulating mud at low rate (1-2 BPM)
and slowly increase to cementing rate.

____________________________________________________________________________________
Cementing Best Practices 29 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 30 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3. Maintain a constant circulating rate and pressure before pumping spacer


or cement.

4. If pressures are abnormally high or erratic while circulating mud, the liner
hanger may be packing off. Review situation.

5. If there is any concern about packoff while circulating, reduce the


amount of spacer to 10 bbls and reduce the cement volume excess.

6. If losses occur when circulating, proceed with cement job.

The following items are key issues that are critical to successful conventional liner
cementing. These key items are intended to be the basics, but are not intended
to be ALL of the issues that are involved in designing and executing successful
liner cementing jobs. Each item represents a key issue that should be addressed
AFTER the liner size has already been chosen.

Conventional Liner Cementing Best Practices

 Liner should be run to provide a minimum of 300 feet of overlap with


previous existing casing. Run a float collar and float shoe.

 Bow spring centralizers should be used in the lap region and achieve a
minimum standoff off of 70%.

 Cementing simulation software should be utilized to design the maximum


cementing rate to be used while maintaining a safe ECD. Liner hanger
clearances and casing collar information should be included to achieve
accurate predictions.

 A weighted spacer system should be used that is compatible with the


drilling fluid. The weighted spacer should be 0.5 ppg heavier than the
drilling fluid weight (or half way between drilling fluid weight and cement
slurry weight). Enough spacer should be pumped to provide a minimum of
500 ft. of annular fill or 10 minute contact time. Run an additional 5 bbls of
spacer behind the bottom wiper plug.

____________________________________________________________________________________
Cementing Best Practices 30 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 31 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

 The cement volume should be calculated based on caliper readings plus


10% – 15% excess cement, and should include 300 feet of cement fill on
top of liner.

 The height of cement above the top of liner should be recalculated using
actual calculated job volumes of cement to be pumped (as above) but
assume gauge open hole. (Note that the reason for this second
calculation is to ensure that it is clearly understood where the top of
cement will be in relation to top of liner if the open hole is in gauge).

 Circulation should be established while the liner is still inside the deepest
existing casing and before the liner is run into the open hole. Circulate the
well a total of at least one hole volume to break the static gel strength of
the drilling fluid system. The ECD applied to the formation will be less at
this point as annular clearance will normally be greater at this point in time
than when the liner is on bottom.

 In most cases it is recommended to hang the liner prior to commencing


cementing operations, and use pipe rotation to achieve a successful
cementation. Setting the liner hanger first will help eliminate the risk of
excessive time hanging the liner while cement is on the backside of the
drill pipe, which can result in a stuck drillstring. If a rotating liner is not
available, the liner should be reciprocated while cementing, and the liner
hanger set after the cement slurry is placed

 Maintain Displacement pump rates should be constant while launching


liner plugs.. Slowing the rate down to launch a liner plug can cause the
dart to “wobble” and bypass displacement fluid.

 When the liner wiper plug is encountered, the volume pumped should be
noted and recordedas referenced by displacement tanks (and barrel
counter).

 Prior to landing the plug, the pump rate should be dropped to


approximately 3 bpm.

____________________________________________________________________________________
Cementing Best Practices 31 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 32 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

 All drill pipe should be immediately pulled from the well after checking the
floats at the end of displacement of the primary cement. If the floats do not
hold, shut in, set liner top packer, and pull DP out of hole. If there is no
liner top packer used, shut in well, wait 15 minutes, and pull drillpipe out of
hole.

 Drill pipe removal speed should be controlled to prevent swab/surge


pressures that can negatively affect the cement left in the well below the
top of the liner.

 Should the drill pipe become stuck and fail to pull completely out of the
well, immediately start pumping the short way at the maximum rate
possible to help remove any restriction in the annulus between the drill
pipe and the casing.

Note: The short way in most cases involves pumping down the annulus
between the drill pipe and the casing with returns to surface through the
drill pipe. Calculate the displacement volumes required each way before
the job commences (i.e. before starting pumping operations).

• Determine the maximum pumping rate possible that will help erode
and remove the restriction in the annulus while minimizing negative
effects, such as excessive ECD’s (equivalent circulating densities)
on the top of the lap, and potential bridging by solids settling in the
drill pipe and casing annulus.

• Continue pumping the short way until a) the drill pipe is free to pull
completely out of the well, or b) the maximum safe pressure limit is
reached.

2.4.4 Salt Sections

For cements to be used across massive salt sections, slurry formulations


incorporating 18 % - 31% salt by weight of cement (bwoc) should be used.
Spacer salinity should match that of the cement slurry.

____________________________________________________________________________________
Cementing Best Practices 32 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 33 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

For plastic salt sections capable of moving and collapsing casing, 5 % KCL
slurries with fast setting properties should be used in conjunction with heavy
walled casing.

2.4.5 Reactive Shales

When cementing across reactive shales, especially at the casing point, consider
using 18 % salt or 7 % KCL bwoc in the spacer and cement design to inhibit
deteoration of the cement/formation bond.

2.4.6 Long Ratholes

It should not be necessary to spot a weighted pill when cementing off-bottom. It is


a very low risk that cement will fall into the rathole after cementing. Spotting a
viscous/heavy pill prior to running the casing can be detrimental to the quality of
the cement job (i.e. mud removal may be more difficult).

2.4.7 Steam Injection

Steam injection or producing wells should use at least 40 % silica flour or silica
sand in the cement design. To help long term integrity under steam cycling, the
cement should be designed with an expansion additive to achieve 0.5 – 1.5 %
linear post-set expansion. Expansion should be measured at both pre and post
steam temperatures. Additionally, long term compressive strength testing should
be performed to ensure that the cement design could withstand the high
temperatures. In some cases, a calcium aluminate cement must be used instead
of conventional Portland cement.

2.4.8 Foam Cement

Foam cement is an effective cementing composition due to its low density,


compressibility, high strength-to-density ratio, and its long term ductility.

____________________________________________________________________________________
Cementing Best Practices 33 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 34 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Foam Cement Safety

• Nitrogen Lines should be tested 2000 psi +- higher than the cement lines.
Often, cement lines are tested to 5000 psi and nitrogen lines to 7000 psi.
Even though the cement slurry line pressure may be 3000 psi, the nitrogen
line pressure may be 5000 psi.

• Nitrogen is stored at an extremely cold temperature, pumped through a


heat exchanger and is placed downhole as a gas. Cryogenics and
energized fluids must be handled with extreme caution.

• If there is any chance of foam cement being circulated to surface during


the job, annular returns must controlled (shut in, divert, etc.).

• In rare occurrences, when drilling up a foamed cement shoe or liner top,


nitrogen gas has been released and this “kick” must be identified and
circulated out. This can also occur if an unset foam cement becomes
unstable.

2.4.9 Corrosive Environments

Set cement is susceptible to chemical attack by formation fluids and completion


fluids throughout the life of the well. In CO2 or H2S environments mixed with
water, carbonic acid and sulfuric acid can be formed respectively. Additionally,
HCl or HF acid jobs may be performed when completing the well, and these acids
may contact the cement.

Another potential detriment to set cement is the presence of sulfates. Sulfates in


the mixing water or in the formation waters can react with cement to expand the
cement potentially causing it to crack and crumble.

For acidic environments, the cement design should include the following:

• Add 50 % Pozzolan content to reduce acid solubility


• Add an expanding agent to the cement slurry. Expanding agents will

____________________________________________________________________________________
Cementing Best Practices 34 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 35 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

seal microannuli and preventing acid from moving up the annulus,


thus reducing exposure
• Add a true liquid latex> 10 % by weight to the slurry design
• Do not use powdered “latex” in small concentrations. This will not
reduce the acid solubility

Another potential detriment to set cement is the presence of sulfates. Sulfates in


the mixing water or in the formation waters can react with cement to expand the
cement potentially causing it to crack and crumble.

For sulfate resistance, the cement design should include the following:

• Use HSR cement (cements containing less than 3 % Tricalcium


Aluminate)
• Add 50 % Pozzoland bwoc to reduce sulfate reactivity

3.0 Primary Cementing Operations

3.1 Mixing and Pumping Cement

3.1.1 Pre-job Procedures

The cementer is responsible for execution of all on-location procedures prior to


cementing operations, and should perform cementing duties as described below.

1. Prior to the cement job, obtain up-to-date information and cementing


objectives from the OXY Drill Site Manager. This information should include:

o Hole size with caliper data or required excess factor


o Casing length, size, and weight
o Drill pipe length, size, and weight
o Shoe track dimensions
o Required length of tail cement
o Liner hanger configuration
o Any other pertinent information

____________________________________________________________________________________
Cementing Best Practices 35 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 36 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

2. Confirm that sufficient equipment and material requirements (including mixing


water quantities) are on location for the job.

3. Review cement and spacer formulations with the Cementing Contractor


Engineer.

4. Review laboratory blend test results, paying special attention to the thickening
time and the required WOC.

5. Calculate cement volumes in units applicable to each Business Unit, including


sacks of cement required for the lead and tail formulations. The calculations
should also include a breakdown of these volumes showing cased hole, open
hole, and shoe track capacities.

6. Calculate the mix water requirement, liquid additive requirements (if any), and
the resultant mix fluid volume for both lead and tail cement slurries.

7. Calculate spacer volumes and material requirements, taking into account


available mixing space.

8. Verify that suction rates required for the job can be achieved with both drilling
fluid and water.

9. Calculate displacement volumes for the casing or liner and drillpipe as


required.

10. Develop a pumping schedule based on the cement job simulator output.

11. Determine whether the available pumping time as indicated by the laboratory
thickening time test result is sufficient for the planned job.

12. Prepare a job plan that includes the following;

• Rig up procedure
• Safety concerns
• Pressure testing procedure
• Spacer type, density, and volumes to be pumped

____________________________________________________________________________________
Cementing Best Practices 36 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 37 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

• Wiper plugs, dart/ball dropping sequence and procedure


• Cement slurry formulation(s), densities, and volumes
• Conversion factors for calculating sacks per unit volume of slurry, and unit
volume of slurry per unit volume of mix water
• Pumping schedule indicating rates, volumes, and times for pumping a
displacing each fluid
• Total job time including time to drop plugs and flush lines
• Anticipated job pressures during pumping, shearing, or bumping of darts or
plugs
• In-hole hydrostatic pressures of each fluid after placement
• Personnel requirements for the job
• Contingency plans for the unexpected; liner top packer fails, float
equipment fails, loss of returns while going in the hole
• WOC criteria prior to rigging down any well-control devices

13. If supplying the wiper plugs and cementing head, verify that the correct
equipment is on location and that the cementing head and associated
connections match and have been pressure tested.

14. Load the wiper plugs in the presence of the OXY Drill Site Manager.

15. Review checklists, lab test results (available pumping time and WOC time)
and job plan with the OXY Drill Site Manager.

16. Prepare spacer as required and check the weight with a pressurized mud
balance.

3.1.2 Job Procedures

The Oxy Drill Site Manager and the Cementer should perform the job procedure
that includes the following steps.

1. Hold a safety meeting on the rig floor to review the job procedures, assign
support responsibilities, and address safety issues. Maintain an open line
of communication to the rig floor throughout the job.

____________________________________________________________________________________
Cementing Best Practices 37 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 38 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

2. Use a data acquisition system to record pressure, rate, density, and


volumes pumped during job.

3. Pump spacer to break circulation.

4. Pressure test all cement lines to a pressure 1000 psi above that which is
expected during the cementing operation.

5. Pressurize the bulk cement tanks.

6. Pump the spacer.

7. Drop the bottom plug. The cementer is responsible for seeing that wiper
plugs, darts, or balls are released at appropriate times. The Oxy Drill Site
Manager should witness the loading of all plugs into the cement head.

8. Mix and pump lead cement.

9. Mix and pump tail cement. Be sure that the lead cement mix has
completely cleared the mixing tub before increasing the density to the tail
cement specifications. Make sure the final 10 bbls of cement slurry is high
quality cement (0.1 – 0.2 ppg higher than designed density).

10. Count and record mix water volume.

11. Confirm cement densities with a pressurized mud scale and catch cup
samples of cement slurry.

12. Close cementing head valve and open wash up line for critical cementing
operations.

13. Close wash up line, open cement head valve, and drop top plug.

14. Displace job with cement unit or with rig pump. To avoid displacement
volume error, do not switch from cement unit to rig pump, or vice versa,
during displacement. When using the rig pump to displace, the pump

____________________________________________________________________________________
Cementing Best Practices 38 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 39 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

efficiency should be known and applied to achieve accurate displacement.


Dependent upon mud type, rig pump efficiencies may range from 93 –
98 %.

15. Slow pump rate before bumping plug.

16. If plug does not bump, pump theoretical displacement volume + ½ shoe
track volume and shut down.

17. Check float equipment. If floats are leaking, shut in casing.

18. The cementing service company should manually record the following
events during the job.

• Pressure test, psi and time


• Start time for job
• Dropping of any plugs, darts, or balls
• Start and stop time for each fluid pumped
• Start of displacement
• Land or shearing of any plug or dart, and the observed pressure
• Mud returns and losses
• Cement returns
• Any unexpected pressure changes and any unscheduled
shutdowns
• Cement slurry lift pressure
• Top plug bumping pressure and whether or not floats held
• Cement in place

19. For surface wellhead systems, monitor casing annulus for pressure build-
up while cement sets.

20. Take three separate one-gallon mix water samples from the displacement
tank or tank truck, and 3 separate one-gallon dry cement samples from the
surge tank or transfer line after the job. Label and retain samples for
possible lab testing until the well is completed.

____________________________________________________________________________________
Cementing Best Practices 39 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 40 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3.1.3 Pressure Test Lines

Pressure test all cementing lines and the cementing manifold with water or
spacer prior to pumping any fluid into the casing. Test pressure is to be at least
1000 psi above maximum anticipated pumping pressure during cementing
operations.

3.1.4 Density Control

The cementing unit’s automatic density control should be utilized to maintain


cement density at +- 0.2 ppg within planned density throughout mixing. For small
volumes (< 100 bbl cement), consider batch mixing.

3.1.5 Pump Rate

Cement slurry density should not be sacrificed for pump rate. Mix cement at the
maximum mixing rate where density can still be accurately controlled.

3.1.6 Data Acquisition

Fluid densities, pump rate, pressure, and volumes pumped should be recorded
and submitted to the Oxy Drill Site Manager in an excel spreadsheet. If the rig
pumps are displacing the cement job, the cementing lines should be opened and
configured to allow the cement unit to record displacement pressures.

3.1.7 Displacement

1. Volume

• Actual displacement should not be more than theoretical


displacement + ½ shoe track volume.

• Selected joints of casing and drillpipe should be callipered to

____________________________________________________________________________________
Cementing Best Practices 40 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 41 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

achieve correct volume capacity and an accurate displacement


volume.

• When using a cement unit to displace, the cementer should fill the
displacement tanks high, and empty the displacement tanks
completely, i.e. “fill high, suck low”.

• When using the rig pumps to displace, calculation of the total mud
pump strokes to displace the top plug to the float collar should be
based on the contractor's record of pump displacement efficiencies
measured during previous cement jobs. It must be remembered that
displacement efficiency will be a function of liner size, pump rate,
and pumping pressure. If the displacement efficiency is not known,
assume an efficiency of 97% (WBM) and 95 % (OBM) as a first
approximation. If rig pump efficiency is unknown, utilize the cement
pumps as the first option.

2. U-Tube

If mud returns are being taken to surface while cementing, a constant


record of mud return volume should be maintained by the mud loggers and
checked against the theoretical volume of mud returns.

Recognize displacement U-Tube effects. When the casing is on a vacuum,


the volume of mud returned to the surface will exceed the theoretical
volume of mud returns (based on the actual volume of cement and mud
pumped at surface). When the cement U-tube balances, the mud
return rate may go to zero as the displacement fluid catches up with the
cement. This phenomenon may produce a complete loss of mud returns;
however, it should not be confused with whole mud losses to the
formation.

3. Bumping the Plug

The pump rate should be reduced before bumping the plug. Bump the
plug to 500 psi over final circulating pressure.

____________________________________________________________________________________
Cementing Best Practices 41 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 42 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3.1.8 Pumping Casing Out of Hole

For large diameter casing strings, the force exerted on the bottom of the casing
due to hydrostatic pressure and annular pressure losses should be determined to
help ensure that the casing will not be pumped out of the hole during cementing
operations. If it is possible for the casing to be pumped off bottom, then cement
slurry density and/or displacement rates will have to be adjusted to ensure the
casing remains on bottom.

3.2 Float Equipment

Casing float equipment should be specified to ensure the success of primary


cementing operations. In general, the following float equipment specifications are
to be followed:

 For 30" and 20" diameter casing, a positive acting, single valve float shoe
assembly should be used. A float collar will not be required unless dictated
by well specific conditions. Inner string cementing may be used as
appropriate, however the potential for casing collapse should be
determined.

 For 16” and smaller diameter casing, a positive acting, single valve float
shoe and a positive acting, single valve float collar spaced two pipe
lengths apart should be used.

For 7" and 5" liners, a double valve, positive acting float shoe and a conventional
liner wiper plug landing collar complete with a profile to accept a latchdown wiper
plug, should be used. Float shoe and float collar should be positioned at least two
pipe lengths apart.
The float shoe and float collar joints should be visually inspected by the Drill
Site Manager or Drilling Engineer to ensure that the float shoe, shoe track
joint, and float collar have been installed using thread locking compound.

Float collars and plug landing collars should be compatible with the cement

____________________________________________________________________________________
Cementing Best Practices 42 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 43 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

wiper plugs to ensure proper sealing of the plug on the landing area.

3.3 Cement Wiper Plugs

 Use top and bottom wiper plugs. The bottom plug is used to separate the
spacer and cement in the casing, and wipe the mud film off of the casing
prior to the passing of cement and the top plug. The top plug separates the
cement from the displacement fluid and provides a positive pressure
indication when it lands on the float collar or landing baffle. If the cement
slurry contains lost circulation material (LCM), the bottom plug should have
a full opening bypass so that LCM does not bridge in the bottom plug.

 The cementing head and cementing plugs should be carefully inspected to


ensure compatibility with the casing string to be run. Be certain the plugs
are designed to pass through the heaviest weight of casing being run.

 Check the order of loading. The bottom plug is red or yellow and is hollow,
and is loaded first. The top plug is black and is loaded second, on top of
the bottom plug. The bottom plug contains a rubber diaphragm (or plastic
burst disk) that ruptures at +- 300 psi. Do not slit diaphragm or shatter disk
prior to loading.

 Cement wiper plugs should be used with casing sizes 16" and smaller
according to the following schedule:

Casings: If cementing conventionally with full bore landing string to


surface, use a top and bottom non-rotating plug system. Under certain
circumstances it may be advisable to use more than one bottom plug to
ensure segregation of spacers and/or flushes. This requirement is to be
reviewed based on well specific requirements. If using subsea cementing
system, only run a top plug

Liners: A single liner wiper plug complete with latch down facility for
landing/latching in landing collar should be run. For casing sizes requiring
the use of two cementing plugs, the bottom plug should be launched
following the spacer and/or pre-flush. The top plug should be launched

____________________________________________________________________________________
Cementing Best Practices 43 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 44 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

behind the tail slurry with allowance for +/- 2.0 bbls of cement on top of the
plug. For 5 ½” production liners and smaller, wash lines clean after
pumping cement before displacing so that no cement is placed on top of
the plug.Note: Two plug liner systems are now available, and are
recommended if available.

3.4 Post Cement Job Operations

3.4.1 Wait on Cement (WOC)

For operations, WOC is the waiting time required after cementing in order to
safely remove well control equipment or to allow the well to be underbalanced.
For this operation, cement compressive strength should be 50 psi.

For drilling out the shoe track, the cement compressive strength should attain a
compressive strength of 500 psi. This will provide the bond strength needed to
support the shoe track as it is being drilled. The time to 500 psi is most efficiently
determined through lab testing with the UCA, which plots strength development
over time.

3.4.2 Nippling Down BOPs

For development wells with trusted offset information showing no gas flow history,
it is advisable to nipple down BOPS immediately after confirming that there is no
flow after cementing. The more time the cement gels, the more chance of gas
influx.

For exploration wells, or for development wells with offset information showing
gas flow history, do not nipple down BOPs until the cement has reached 50 psi
compressive strength. It is advisable to use a lead cement with fast setting
characteristics, such that the cement has 50 psi compressive strength in 6-8
hours.

3.4.3 Pressure Test Casing

____________________________________________________________________________________
Cementing Best Practices 44 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 45 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Casing pressure testing procedures and test pressures will be specified in the
drilling program for a specific well. However, it should be the responsibility of the
drilling supervisor to check the figures at the wellsite to ensure that the casing is
not burst or collapsed through negligence. Casing and liner pressure testing
should be performed as outlined below..

1. All casing strings should be pressure tested in conjunction with pressure


testing of the BOP stack blind/shear rams. This is to be performed as the
last pressure test during the BOP test sequence (except as noted in Point
2 below). Casing test pressures should not exceed 80% of the internal
yield pressure of the casing or 80% of the casing connector pressure
rating, whichever is lower. If the Drilling Program calls for use of a higher
test pressure, consult with Drilling Superintendent, Engineer, or Manager
to confirm test pressures.

2. If it is required to run a cement evaluation log (CBL or Ultrasonic), then


pressure testing of the casing and blind/shear rams should be performed
following completion of the logging run. Another option is to perform the
casing pressure test immediately after bumping the plug at the end of a
cement job for 30 minutes. Ensure that the float equipment is rated to
withstand the pressure test loads.

3. The casing pressure test is to be staged up in several increments, with


each successive pressure increment held for a brief period to ensure no
leaks. The final holding period at test pressure is to be for a period not less
than 30 minutes.

4. Under no circumstances should the casing test pressure exceed the


working pressure rating of the ram preventers or the pressure rating of the
wellhead spool section exposed to the test pressure, whichever is less.

5. With surface wellhead systems, the annulus outlet for the casing string
being tested should be opened and monitored for fluid leaking past the
casing hanger pack-off element. If this is not possible, install a pressure
gauge on the casing annulus outlet and monitor for a pressure increase
during the casing pressure test.

____________________________________________________________________________________
Cementing Best Practices 45 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 46 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

6. All casing test pressures should be applied and removed slowly to avoid
adverse dynamic loading.

7. All pressure tests should take account of the annulus fluid density relative
to the fluid density inside the casing. The annulus fluid density should be
assumed to be equivalent to drilling fluid down to the cement top, then sea
water when offshore, or formation water when on land, from the cement
top to the previous casing shoe.

8. A chart recording pressure gauge should be used on all casing pressure


tests. This gauge can be supplemented by a more accurate, conventional
bourdon tube pressure gauge, if required for operational reasons.

9. For all casing pressure tests, a record of applied pressure versus barrels
of mud pumped should be maintained. This information is particularly
useful during subsequent formation pressure testing.

3.4.4 Shoe Tests

A shoe test is usually conducted after drilling out a casing shoe and a small
section of new formation (usually 10 ft of new formation). Shoe tests are
performed to determine the strength of the new formation as well as the
competency of the cement sheath.

1. Formation Integrity Test (FIT)

An FIT is a shoe test where the pressure is kept below the leakoff or
fracturing pressure of the rock. FITs may also be performed over long
openhole intervals while drilling.

2. Pressure Integrity Test (PIT)

A PIT is the general term related to pressure testing casing or formation in


the wellbore, where the test pressure is kept below leakoff or fracturing

____________________________________________________________________________________
Cementing Best Practices 46 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 47 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

pressure.

3. Leakoff Test (LOT)

An LOT is a shoe test where pressure is increased until the formation


fractures and leakoff is initiated. The test is usually stopped when leakoff
pressures/gradients are obtained.

Refer to Oxy’s FIT and LOT standards to properly perform and analyze
shoe tests.

3.5 Cement Sheath Evaluation

Sonic and ultrasonic logs are the most common ways to evaluate the quality of a
cement job. In addition, temperature surveys can determine the location of top-of-
cement, and tracer surveys can determine if hydraulic isolation has been
attained.

3.5.1 Cement Evaluation Log

Cement evaluation logging tools emit sound waves (sonic and/or ultrasonic
waves) to help determine the bonding and presence of set cement in the annulus.

Cement Bond Log (CBL) – is a sonic tool that sends and receives sound waves
omni-directionally. The CBL can indicate the general quality of cement/casing and
cement/formation bond.

Segmented Bond Tool (SBT)– is a sonic tool that measures attenuation (sound
dampening) between points around the casing. Although not as accurate as an
ultrasonic tool, the SBL can give a rough estimate of cement channeling.

Ultrasonic Log – is an ultrasonic tool that measures the impedance value of


cement directionally around the annulus. It can be used to detect channels in the
cement.

____________________________________________________________________________________
Cementing Best Practices 47 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 48 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Recommended Bond Logging Procedure:

 Run CBL and ultrasonic combination log.


 Do not pressure test the casing before running a bond log.
 Run the log with 0 psi
 If possible log a section of free pipe.
 If bonding is poor, repeat log with 1000 - 2000 psi pressure
 If bonding is still poor, evaluate the potential causes of the poor bond log
representation

Be cautious to perform remedial cementing on a well based solely on the bond


log representation. Consider if there were any problems during the cement job
before squeezing. Follow the rule of thumb, “Do not squeeze because of the bond
log, but use the bond log if you determine you must squeeze.”

Sometimes a good cement job is not properly represented as such by the logging
tool. The following items may negatively affect the bond log representation, and
show poor cement.

 Casings larger than 9 5/8” or heavy walled casing


 New casing or varnished casing
 Pressure testing before running a bond log (creating a microannulus)
 Exchanging heavier displacement fluid with lighter completion fluids before
logging (creating a microannulus)
 Lightweight cement (compressive strengths < 1500 psi)
 Thin cement sheaths (< ¾” clearance)
 Logging across sandstones
 Uncalibrated or eccentered logging tools

To overcome the negative affects from the above items, it is important to increase
shear bond to enhance the bond log representation. The following procedures will
help increase shear bond.

 Sandblast critical sections of casing (See Figure 6)


 Use expansion additives in the production cement slurry
 Do not pressure test casing before running a bond log

____________________________________________________________________________________
Cementing Best Practices 48 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 49 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

 Pressure the casing during logging to eliminate microannlus


 When using OBMs, run ample spacer with surfactant to water wet casing

Sandblasted section of casing

Figure 6 – Sandblasted Pipe Giving Excellent Bond

Refer to the “Oxy Cementing Bond Log Best Practice” document for more details
on running bond logs.

3.5.2 Temperature Log

Temperature logs are used to identify TOC. The temperature log should be run
6–12 hrs after the cement’s initial set, when most heat is being generated by the
exothermic reaction of cement hydration. A sharp temperature change of 10 – 40 0
F should be noticed at the TOC.

For development wells where excellent bond logs are common, consider running
a temperature log for TOC determination and eliminating the bond log run.

3.5.3 Tracer Survey

Radioactive tracers may be placed in stimulation fluids to help determine if the


cement sheath is providing hydraulic isolation.

____________________________________________________________________________________
Cementing Best Practices 49 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 50 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3.6 Problem Jobs - “Cemented Up” Casings

One of most costly failures in cementing occurs when maximum pressure limits
are reached before displacement is complete, resulting in a “cemented up” casing
or liner. Premature shutdowns and “cemented up” casings unfortunately occur on
a regular basis across the industry, and the cause is sometimes difficult to
determine. In general, however, these catastrophic failures fall into one of the
following categories.

• Shutdown while Pumping


Many catastrophic cementing failures occur immediately after “shutting
down” and allowing the cement to remain static for a period of time.
These shutdowns may be planned such as stopping to pull drillpipe
from a cement plug, or unplanned, such as stopping to fix an
equipment failure. Cement slurries may gel excessively during a
shutdown to the point where they cannot be moved by pump pressure.

• Mechanical Bridge
Mechanical blockages such as those listed below may cause sudden
excessive pressures during the cementing operation.
o LCM, cuttings, or debris blocking float equipment
o Cuttings packing off at liner hanger (However, pressures may be
increased to break down formation)
o Bottom plug does not bypass fluid
o Liner dart does not launch liner plug
o Surface equipment / manifolding plugged with cement or debris

• Cement Design – Cement Flash Set


Cement designs rarely “flash set”. When flash setting occurs, it usually
is due to one of the following;

o Wrong cement blend sent to location


o Wrong concentration of additives in the cement blend
o Contaminated cement

____________________________________________________________________________________
Cementing Best Practices 50 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 51 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

o Certain retarders (high temp lignosulfonate retarders, e.g.) may


exhibit a threshold effect. With slight variation in retarder
concentration or temperature, the thickening time may be
reduced significantly
o Cement mixed at wrong density (This is especially critical when
switching from lead cement and tail cement. Lead cement blend
and additives mixed with tail cement water requirements can
yield a thick “flash setting” slurry.
.
• Cement Contamination on Surface
Cement may be contaminated on surface by drilling mud or mixing
water. If reactive spacers or other strong accelerators are being used,
they should be kept separated from the cement slurry by fresh water
spacers.

• Cement Contamination Downhole


Cement slurries and drilling fluids, especially synthetic or oil based
muds, are usually not compatible with cement, and can form a “non-
pumpable” mass when mixed.

• Plugged Surface Equipment

When cementing operations are shut down due to excessive pressures, the event
should be investigated thoroughly. The following steps should be part of this
thorough investigation.

1. Review the events that precede and follow the premature shutdown.
a. Pressures and rates
b. Cement density variations
c. Was the cement static?

2. Determine the position of fluids and plugs when anomalous pressures occur.
a. Were darts or bottom plugs landing ?
b. Were spacer and cement interfaces at critical points in the well?

____________________________________________________________________________________
Cementing Best Practices 51 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 52 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

3. If shutdown occurs when darts or plugs landed, re-examine plug type and
clearances. During drillout, examine returns to determine the location and type
of plug cuttings.

4. Check bulk callout sheets to ensure proper cement was delivered to location.

5. Interview cementer to check if any unusual events were observed during the
cement job.

6. Test dry cement samples using location mix water


a. Test thickening time at BHCT, BHCT plus15o F, and BHCT minus
15o F.
b. Compare rheologies to original cement tests.

7. Perform cement contamination testing.


a. Are the cement and mud compatible?
b. Does 10 % spacer contamination accelerate the cement slurry?

8.Write a final report and submit learnings to the Oxy Cementing Communityof
Practice representative.

The following general recommendations should be followed to prevent premature


cementing shutdowns.

• Condition the wellbore properly to remove cuttings before cementing

• Do not run auto-float with narrow clearances in high LCM muds

• Pump adequate volumes of spacers to separate mud and cement

• When using reactive spacers, pump 10 – 15 bbls of fresh water between


the spacer and cement to prevent flash setting

• Minimize shutdowns while cementing

• Design cement slurries to exhibit low gel strengths

____________________________________________________________________________________
Cementing Best Practices 52 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 53 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

• Cement slurries and spacers should have the same salinity content

• Do not use lignosulfonate retarders when cementing above 180 o F BHCT

• Gather location samples of cement and mixing water as per Best Practices
(Sec 2.2.5)

• Perform compatibility testing as per Best Practices (Sec 2.2.3 – Pt. 8)

• Caliper plugs and observe loading of plugs in cementing head as per Best
Practices (Sec 3.3)

4.0 Plug Cementing

As with all cementing operations, thorough planning and close adherence to good
operating practices are necessary to ensure job success on the first attempt to
set a Kickoff Plug. The common belief that multiple cement plugs will probably
have to be spotted before one "takes", simply is not true. In most cases, failure to
obtain an acceptable cement plug on the first attempt can be traced to poor
placement practices or incorrect slurry design. The guidelines outlined below
should be closely reviewed prior to implementing these operations.

4.1 Plug Setting Techniques

The Balanced Plug Method and Unbalanced Plug Method are two legitimate plug
setting techniques that may be used to set a kickoff plug.

4.1.1 Balanced Plug Method

Balanced Plug Method is the most popular technique to set a kickoff plug. A
hydrostatically balanced plug is placed in the well, and the drillpipe is slowly
removed from the balanced plug. A balanced kickoff plug is set as follows:

1. Ensure that there is a solid base on which to set the balanced plug
(See “Establish Solid Base” guidelines in 4.2.2.B)

____________________________________________________________________________________
Cementing Best Practices 53 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 54 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

2. Run drillpipe/stinger to plug setting depth

3. Condition wellbore

4. Pump spacer (recommended spacer length = 500 ft in annulus)

5. Drop ball to separate fluids, wipe drillpipe, and indicate cement


location.

6. Pump densified cement slurry (recommended plug length = 500 –


1000 ft in openhole)

7. Drop 2nd ball.

8. Reciprocate drillpipe until cement enters the annulus

9. Pump sufficient amount of spacer to balance plug

10. Displace cement at maximum rate with drilling fluid

11. Pull drillpipe/stinger out of plug at 30 – 50 ft/min to TOC

12. Pull drillpipe an additional 1000 ft above top of cement plug (Pull at
normal pull rate)

13. Circulate or reverse circulate bottoms up (Monitor returns for


cement / spacer contamination) Warning concerning pressures.

14. POOH and WOC (Check lab tests for set time and compressive
strength development)

15. RIH with drilling assembly – tag cement – time drill to kickoff

Note: For well depths greater than 12,000 ft , place a ball catcher in the
drillstring at +- 200 ft above calculated TOC. The ball catcher will signal the
location of the top of cement when the cement slurry is followed with a

____________________________________________________________________________________
Cementing Best Practices 54 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 55 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

rubber wiper ball.

4.1.2 Unbalanced Plug Method

The Unbalanced Plug Method is a legitimate technique that can be used to set a
successful kickoff plug. The advantages of the unbalanced plug method include
1) Eliminating the difficulty of pulling wet with oil base or heavy mud in the well
and 2) ease in placement since there are no balance calculations or ball catchers
required. An unbalanced kickoff plug is set as follows:

1. Ensure that there is a solid base on which to set the balanced plug
(See “Establish Solid Base” guidelines in 4.2.2)

2. Place IBOP in the drillstring at a depth below RKB which is equal to


the theoretical height of the cement plug in the openhole. For a
1000 ft openhole plug, the IBOP would be placed at a depth of 1000
ft below RKB.

3. Run drillpipe/stinger to plug setting depth

4. Condition wellbore

5. Pump spacer (recommended spacer length = 500 ft in annulus)

6. Pump densified cement slurry (recommended plug length = 500 –


1000 ft in openhole)

7. Displace cement all the way to the bottom of the drillstring with
drilling mud and a final volume of water. The water volume should
equal the volume of drillpipe from surface to the IBOP.

8. Reciprocate drillpipe until cement enters the annulus

9. Displace cement at maximum rate with drilling fluid

10. Pull drillpipe WET out of plug at 30 – 50 ft/min to TOC

____________________________________________________________________________________
Cementing Best Practices 55 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 56 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

11. Remove IBOP

12. Pull remaining drillpipe DRY at normal pulling rates

13. WOC (Check lab tests for set time and compressive strength
development)

14. RIH with drilling assembly – tag cement - time drill to kickoff

4.2 Achieving a Stable Cement Plug

Most failed cement plugs occur because the cement plug is destabilized or
contaminated during or after placement. The following best practices will help
ensure a stable cement plug is achieved.

4.2.1 Stabilizing the Wellbore

Prior to setting the cement plug, cure lost circulation or formation fluid influx.
Losses or flows will contaminate the cement plug. If losses or flows are occurring
below the plug setting depth, run an inflatable openhole packer to stabilize the
wellbore and also provide a base on which to set the plug.

4.2.2 Providing a Base

Perhaps the most important component of a successful kickoff plug is making


sure that the cement is placed on a solid base. Cement plug slurries are usually
more dense than the wellbore fluid and will easily fall down the wellbore if there is
not a sufficient base to support the cement plug. The recommended ways to
ensure a stable base include:
 Set the cement plug on bottom (TD) when practical
 Cement on top of a previous undrilled cement plug
 Set a cement plug base tool (Parabow, Bottomhole Kickoff Assembly, e.g.)
 Set an inflatable bridge plug

____________________________________________________________________________________
Cementing Best Practices 56 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 57 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

 Spot sacrificial cement plug


 Spot densified mud
 Spot a 250 ft to 500 ft reactive sodium silicate pill – weighted if necessary
 *Spot a 250 ft viscous pill (funnel viscosity of 150 + sec/qt)

* Setting viscous pills have failed many times in plug setting operations.
Unless the pills are extremely viscous, they will not prevent cement slurry
from falling down the well and destabilizing the plug.

4.2.3 Drillpipe, Stinger, and Diverter

For hole sizes less than 8 ½”, use a 2 7/8” or 2 3/8” tailpipe stinger on the bottom
of the plug setting assembly. The stinger should be a minimum of 200 ft longer
than the plug length.

For 8 ½” hole and larger, a tail pipe is not required. Use drill pipe.

A diverter sub with upward angled ports (Figure 7) should be used when
cementing off-bottom.

Figure 7
4.2.4 Centralizers

Do not run centralizers on the plug setting string. The centralizers


will serve to swab the cement plug when pulling out of the hole. Plug
setting success rates near 100 % are achievable without using centralizers.

4.2.5 Pulling Drillpipe Out of the Plug

Pull drillpipe/stinger slowly out of the plug at 30 – 50 ft/min to prevent stringing


the cement up the wellbore.

4.3 Wellbore Preparation for Setting Cement Plug

____________________________________________________________________________________
Cementing Best Practices 57 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 58 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

The wellbore should be prepared for plug cementing in the same way the
wellbore is prepared for primary cementing. Recommended mud properties
include:

• Yield Point - < 15 lb/100 ft2


• Gel Strengths – 10 sec, 10 min, and 30 min, < 25 lb/100 ft 2
• Fluid Loss, API < 10 and HTHP< 15
• Wash and rotate across plug interval from 200 ft above to bottom of
plug
• Pipe should be rotated and/or reciprocated during circulation
• 2 annular volumes should be circulated once pipe is on bottom
• Greater than 230 ft/min annular velocity
• Mud balanced, density in = density out

The plug is to be spotted in a section of gauge hole with minimum washouts. If


necessary, a caliper log is to be run to ensure an acceptable plug setting interval.
If plug spotting in a washed out section cannot be avoided, then allowance should
be made for excess cement volume.

Prior to setting open hole cement plugs in old wells (i.e., previously cased off
interval), consider under-reaming the open hole interval that is to be cemented.
This is done in order to remove the old mud ring that may prevent a competent
cement plug from setting up in the entire wellbore.

4.4 Cement Slurry Design – Plug Cementing

4.4.1 Slurry Density

In general, the density of kick-off plugs is to be +/- 17.0 ppg or higher. For shallow
plugs set in softer formations, standard cement densities (15.8 – 16.4 ppg) are
adequate.

4.4.2 Thickening Time

____________________________________________________________________________________
Cementing Best Practices 58 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 59 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

Thickening time for plug cementing shall be performed at BHCT in similar manner
as for casing jobs.

Plug Slurry Thickening Time = Total slurry mixing time + Time to drop ball* +
Displacement time + Time to pull out of plug** + Safety Factor***

*Use 10 minutes for time to drop ball


**Time to pull out of plug = 30 ft/min (= 30 minutes for 900 ft plug)
***Safety factor = 1 hr

4.4.3 Compressive Strength


Slurries should be formulated to develop high early and ultimate compressive
strength. The compressive strength of the cement should be greater than the
compressive strength of the adjacent rock In general, the 12 hr compressive
strength of a cement plug should be greater than 2000 psi. The 24 hr
compressive strength of a cement plug should be 3000 psi or greater.

For temperatures below 230 degrees F, neat slurries (without sand, lost
circulation materials, etc.) should be used and retarded with dispersant. Above
230 degrees F, the slurry formulation should include 15-35% by weight of silica
flour or silica sand to prevent strength retrogression, and synthetic retarders
should be utilized.

4.4.4 Fluid Loss

For plug cement slurries, fluid loss control is not necessary when setting a kickoff
plug unless the plug is being set in an air-drilled hole where mud filter cake has
not been deposited.

4.4.5 Free Water

Free water for a kickoff plug should be less than 1.0 %. For deviated wells (> 30
degree angle), the free water should be 0 %.

____________________________________________________________________________________
Cementing Best Practices 59 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 60 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

4.4.6 Rheological Properties

The plug cement slurry should be designed to mix easily with relatively low
viscosities. This can be achieved with a 17.0 – 17.4 ppg cement slurry containing
correct concentration of dispersants.

4.4.7 Spacers for Plug Cementing

Spacers should have the following characteristics:

• Be compatible with the cement and drilling mud.


• Leave the wellbore in a water wet condition for better bonding
• Maintain adequate hydraulic pressure during and after plug setting
• Have a density at least 0.5 ppg higher than the mud weight, and at
least 0.5 ppg lower than the cement slurry density.
• Be designed for turbulent flow in the annulus at the planned
displacement rate for a particular cement job.
• Have a salinity that matches the salinity of the cement slurry. Note:
For plug setting in reactive shales, the spacer should contain at
least 18 % salt, to help inhibit clays and prevent hole collapse.
• The spacer volume for setting plugs should yield a minimum fluid
height of 500 feet in the drillpipe annulus.

4.5 Plug Cement Displacement

4.5.1 Ball Catcher

For plug setting using the balanced plug method, an indicating ball catcher
should be placed approximately 200 ft above the theoretical TOC of the cement
plug, especially when setting plugs deeper than 12,000 ft.

4.5.2 Wiper Balls

____________________________________________________________________________________
Cementing Best Practices 60 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 61 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

For plug setting using the balanced plug method, wiper balls should used ahead
and behind cement plug to give pressure indication of the cement position, and to
clean the drillpipe. Using wiper balls will help prevent “cement rings” in tool joints
that can cause severe problems later (such as debris in MWD tools). Check
temperature limitations on balls and catchers.

4.5.3 Drillpipe Caliper

The drillpipe should be physically calipered to determine the accurate drillpipe


capacity.

4.6 WOC and Cement Plug Drillout

Do not attempt to kick off the cement plug until the cement has 2000 psi
compressive strength. The cement slurry can be designed to achieve this
strength within 12 hrs.

If the cement plug drills soft, pull out of plug a safe distance, and wait-on-cement
to gain more strength.

If the cement plug drills hard and soft, this is indication that the cement plug has
become unstable or contaminated.

4.7 Abandonment Cement Plugs

Abandonment plugs are to be formulated and spotted largely in accordance with


the guidelines given above for kick-off plugs.

For cement abandonment plugs that are not to be drilled out, a minimum plug
length of 250' should be used, although local regulatory rules must be followed.
This holds true for open hole as well as cased hole plugs.

For cement plugs set inside casing, expansive agent (magnesium oxide additive,

____________________________________________________________________________________
Cementing Best Practices 61 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 62 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

e.g.) should be considered.

5.0 Health, Safety, and Environment

Oxy HSE Standards and practices should be performed during each cementing
operation. The following safety measures specifically related to cementing
should also be observed.

• NIOSH-approved dust masks and standard protective goggles should be worn


on the cementing unit and in the vicinity of cement dusting areas.

• Wear impervious gloves when handling mixed cement slurries and cementing
chemicals. Understand the MSDS sheets and hazardous nature for all the
cementing materials on location. Even the cement slurry itself is a base and
is corrosive in nature.

• Care should be taken if gaining a sample of cement slurry from the mixing tub.
Hands should remain a safe distance from the tub agitators, and goggles
should be worn for protection.

• Perform a cementing pre-job safety meeting prior to start of cementing


operations.

• Ensure that cementing lines are clear of personnel during pressure testing
and pumping operations.

• Ensure that the rig floor below the cement head is clear of personnel when
dropping plugs.

• Safety areas and escape routes should be diagrammed relative to cementing


lines prior to performing a cement job, especially when pumping foam
energized fluids (See Sec 2.4.8 Foam Cement)

• Restrict area while cementing to authorized personnel only.

____________________________________________________________________________________
Cementing Best Practices 62 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 63 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

6.0 Tracking Results

It is important to track cementing success to determine if the practices being


employed are working. The Oxy Cementing Scorecard should be used to track
the success of the cement job. Ultimately it is the success of the cementing
operation that will confirm which are the best cementing practices.

6.1 Key Performance Indicators (KPIs)

The following KPIs should be accurately tracked for each primary cementing
operation via the Oxy Cementing Scorecard.

1. Job Count – A running total of casing strings that are cemented.

2. Cementing Contractor – Which service company performed the cementing


work?

3. Casing String – What type of casing string was cemented (Conductor,


Surface, Intermediate, Drilling Liner, Production Casing, Production Liner)

4. Trouble Time - How many hours of trouble time was related to cementing ?
(This may include waiting on service company, downtime, remedial work,
Wait-On-Cement (WOC), unplanned events on the critical path, etc)

5. Cementing Cost – What is the cost per bbl of total cementing services and
materials for the casing string? What was the planned cost versus the actual
cost?

6. Safety - Was there a safety incident or near miss related to the cementing
operation?

7. Liner Top Test – If the job was a liner, was the liner top test successful?

8. Bond Log - Was a bond log conducted ? If yes, was the bond log graded as
a) poor, b) marginal, c) good, d) outstanding ?

____________________________________________________________________________________
Cementing Best Practices 63 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 64 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

9. Top-Of-Cement – Did the actual Top of Cement meet the requirements of the
hole section? Was cement raised high enough to adequately satisfy all critical
requirements?

10. Remedial Work - Was any remedial work / squeeze job required to repair the
primary cementation ? This may be a shoe squeeze or a production casing
remedial job.

11. Lost Circulation - Were there mud losses while cementing? Indicate either a)
No losses, b) Partial losses, or c) Total Losses.

Additional KPIs not contained in the Oxy Cementing Scorecard may still be
tracked. These include: Casing Pressure Tests, Shoe Tests, Annular Flow
Incidents, Top Jobs Required, Float Equipment Holding, and Bumping Plugs

6.2 Cementing Scorecards

Scorecards must be used to track and grade “on-location” cementing


performance, end results, and other operational parameters. Cementing
scorecards for general primary cementing are available on the Cementing CoP
Portal. (Refer to the Contract Performance Management Standard)

7.0 Contractor Requirements

In addition to the responsibilities outlined in Section 3.1 – Mixing and Pumping


Cement, the Cementing Contractor should also apply the following
recommendations outlined in Sections 7.1 – 7.2.

7.1 Cementing Proposal

The Cementing Contractor Engineer should be responsible for preparing a


Cementing Recommendation, as requested for upcoming wells, and

____________________________________________________________________________________
Cementing Best Practices 64 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 65 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

communicating with the OXY Drilling Engineer as required to obtain all necessary
information for preparation of this document.

The Cementing Contractor Engineer should be fully capable of running the


cement job simulation software, analyzing the output data and making the
appropriate job recommendations, and should use standardized software for
generating this recommendation.

The Cementing Recommendation should contain the following:

• Detailed objectives of the cement job(s)


• Cementing operational issues and detailed solutions
• Thickening time requirement for the cement slurry(s)
• Detail of well geometry, including hole, casing, and annular volumes, and pore
and fracture pressures
• Required cement slurry volumes
• BHST and BHCT with detail on the method of calculation
• Cement and spacer formulations including how the designs achieve the job
objectives; The designs should include;
o Slurry densities, yield, and material requirements of the proposed
slurries and spacers
o Spacer density and rheological properties
o “Pilot” laboratory test results for the cement slurry formulation(s)

• Operational details, pump rates, for each fluid and shear or bumping
pressures for wiper plugs

• A computer-generated simulation of the cement job(s) that is based on the


proposed cement slurries, well information and geometries, with clear and
accurate inputs. The output should include:
o Centralization spacing
o Flow regime of each fluid
o U-tube simulation for the cement job under dynamic conditions
o Temperature simulation profile of cement slurry temperatures

____________________________________________________________________________________
Cementing Best Practices 65 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 66 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

o Well security and control (Equivalent Circulating Densities at total depth


and other selected points, graphed against pore and fracture
pressures)

• Displacement volumes
• Tabular graph of fluids positions after placement
• Cost estimates for service and materials

Presentation of this report should include a hard copy and an electronic file in
either Microsoft Word or Excel format. Graphs may be generated to supplement
the reports.

Prior to each cementing job, the Cementing Contractor Engineer should update
the respective portion of the recommendation. Updates should be referenced to
initial recommendation and pertinent lab testing.

7.2 Cement Testing

• All “pilot testing” data should be clearly referenced to the appropriate


cementing recommendation with a unique project or job number
• All laboratory testing should be conducted in a timely and accurate manner
• Sufficient lead-time should be incorporated into the testing program so that
the designs are ready well in advance
• Testing should be conducted with the representative samples of materials that
will be used on the job (bulk plant or rig samples) as appropriate.
• Contingency planning should be incorporated into the testing program, taking
into account variations in well parameters that may require adjustments in
density or thickening time
• Whenever possible, the cement job should be designed to achieve turbulent
flow of the spacer in the open hole

Note: No cement slurry should be considered “approved and finalized” until the
OXY Drilling Superintendent or Drilling Engineer confirms it. Do not pump this
slurry design without this approval.

____________________________________________________________________________________
Cementing Best Practices 66 02/26/2014
Revision 1
Revision No.: 00
Revision Date:
Occidental Oil and Gas Corporation Page No. 67 of 67
Global Drilling Community Approved By:
Endorsed By:
G. Bush
K. O’Donnell
Global Cementing Best Practices Last Review April 5, 2007
Date:
Effective Date: April 5, 2007

7.3 Pricing and Invoicing

Cementing contractor pricing and invoicing should consider using a “cost plus”
scheme, as opposed to a book price minus discount. This strategy makes line
item auditing easier and more accurate, and allows Oxy to pay appropriate
charges (service and materials) for each job. Oxy can evaluate the actual value
of any particular job when the actual costs for that job are applied to the invoice.

7.4 Contract Specifications

Cementing contracts should be written to contain rigorous specifications for


personnel, services and equipment, goods and materials, HES, and
commercial/pricing. The cementing contractor should perform confirmation lab
testing to ensure that the submitted slurry designs meet Oxy requirements.

____________________________________________________________________________________
Cementing Best Practices 67 02/26/2014
Revision 1

You might also like