Professional Documents
Culture Documents
Case Study On SF6 Leakage Arrest - Allahabad SS - July 20
Case Study On SF6 Leakage Arrest - Allahabad SS - July 20
2020
A Case study on impact of SF6 leakage and arrest of leakage with help of
Background
substation, various 400kV & 220kV SF6 type CBs of different makes are installed.
In total, 31 nos. SF6 type 400kV CBs and 11 nos. SF6 type 220 kV CBs are
installed. In these 42 CBs, a total of 2268.4 kg SF6 gas is filled under normal
condition.
more potent than CO2) with severe global warming potential. Not only is it a threat
to environment but some of its toxic by-products are also dangerous for persons
working in its environment (specially disulphur decafluoride S2F10, which was used
for chemical warfare during WW-I). A very stable compound, any leaked SF6 can
last for up to 3,200 years before it is broken down by UV rays. SF6 leaks reduce
the amount of dielectric insulation and heat transfer provided to T&D SF6-insulated
decreases the dielectric strength required to handle short current faults to a point
that can permanently damage insulators, shields, arcing contacts, and main
contacts.
Page 1 of 9
3. SF6 leakage from CBs had been one of the prime areas of concern in 400kV/220
Prayagaraj SS during last couple of years. Some CBs were identified, in which
frequent SF6 gas refilling had to be done due to unidentified leakages from the
CBs. Leakage problem was mainly found in BHEL make 400kV CBs (Bay No. 401,
405, 409) and CGL make 220kV CBs (Bay No. 204, 207 & 209).
4. Earlier we used leakage detector and soap detection methods for these breakers,
but even after spending considerable man-hours, the leakage spots could not be
properly identified.
5. Finally, Optical Gas Imaging Camera (FLIR make) was used for detection of leaking
SF6 gas. It is pertinent to mention that even the leakage spots with miniscule SF6
6. While using Optical Gas Imaging Camera, various points of leakages which were
identified and for which remedy action was taken to arrest the leakage were as
follows;
replaced.
405 Bay Leakage was detected in flange area Following O-rings were replaced
SG-90033015, SG-90033006,
Page 2 of 9
90033018, SG-90033020, SG-
90033021
204 Bay Leakage was detected in column P-260, P-170, P-7 O-rings were
207 Bay Leakage was detected in gauge P-7 O-ring was replaced
area of Y-pole
209 Bay Leakage was identified at point P-260, P-170, P-7 O-rings were
Page 3 of 9
Page 4 of 9
Page 5 of 9
Page 6 of 9
Main Leakage spots identified in drawing of CB:
Page 7 of 9
Major Common Lakage Points are as follow:
Page 8 of 9
Final Result
By taking above actions we had reduced the SF6 consumption up to negligible extent.
Page 9 of 9