You are on page 1of 10

The Kern River Horizontal-Well

Steam Pilot
".K. Dietrich, SPE, The Dietrich Corp.

Summary. Sluggish oil response in the Kern River horizontal-well steam pilot was caused by placement of the wells in a
reservoir environment unfavorable for application of either conventional oil recovery processes or novel oil-mining techniques.
Encouraging pilot operational experience and the tremendous potential for improved ultimate oil recovery shown by preliminary
simulations suggest that future pilot testing of horizontal-well steam technology is warranted in a more favorable environment.

Introduction
The Kern River vertical-shaft and horizontal-well steam pilot was Thermocouples were installed in the chamber wall near embedded
designed and installed on the basis of a geologic model that emerged strain gauges and in 'h-in. [l.3-cm] pipe positioned within the for-
from analysis of numerous closely spaced wellbores drilled on the mation about 50 ft [15 m] radially from the chamber wall.
25-acre [lO-ha] test site. Numerical simulation was used to develop
both the strategy for steamflooding operations performed at the test Lateral Holes. Eight lateral holes were rotary-drilled by men and
site during the period 1982-83 and the projections of long-term proc- equipment placed in the chamber; four of these were about 430 ft
ess performance. [130 m] in length and four were about 700 ft [210 m] in length
Eight horizontal wellbores spaced at 45° [0.79-rad] increments (Fig. 3). These laterals were drilled parallel to the base of the gently
were rotary-drilled into the base of the heavy-oil column (18 to dipping heavy-oil zone (Fig. 4). The imaginary plane containing
20° API [0.95 to 0.93 g/cm 3]) from a 500-ft [150-m] vertical shaft the laterals is located at depths between 350 and 600 ft [105 and
positioned at the center of the 25-acre [lO-ha] rectangular pilot area. 180 m] below the irregular ground surface. The maximum difference
The original concept was to use only horizontal wells for cyclic in elevation between the tip of a lateral and the point where it meets
steaming and steamflooding operations; this concept was modified the chamber wall is about 50 ft [15 m].
on the basis of simulation results that indicated the potential for Sections of 8%-in. [22-cm] preslotted steel liner (with a plug at
early steam breakthrough and poor capture efficiency of the dis- the end of the first section) were pushed to the terminus of each
placed oil. The modification involved drilling conventional vertical of the holes created by rotary drilling. An unperforated 3-in.
wells (one well within each of the eight sectors formed by the [7.6-cm] steam-injection string was then placed within the full length
horizontal wells) and injecting steam into them while producing from of the slotted liner.
the horizontal wells (Fig. 1). Fig. 5 indicates that eight separate steam-injection strings and
The pilot was terminated because of unfavorable economics after eight separate produced-fluid strings pass through the vertical shaft
21h% of the oil in place (OIP) was recovered. The oil recovery and chamber. Eight conventional beam-pumping units were posi-
rate and process efficiency were each improving at the time the tioned on the surface with rods and pumps placed within 2%-in.
pilot was abandoned. Early sluggish oil response was predicted and [6-cm] tubing.
observed owing to low vertical permeability and extensively depleted
oil saturation and pressure conditions that exist at the pilot site. Geologic Conditions
Long-term pilot operations were shown to be capable of recovering Extraordinarily dense well control C!4 acre/well [3035 m 2 /well])
significantly more oil at equivalent oil/steam ratio (OSR) than that allowed a detailed description of the reservoir for this pilot.
expected from conventional steamflood development.
The concept of using horizontal wellbores to improve thermal Structural Features. A critical element of this pilot was the drilling
oil recovery was developed by Turk, Kehle and Assocs. of Austin, of the steam-injection/oil-recovery lateral holes radially from the
TX. The concept was called the heavy-oil process (HOP) and was central shaft, parallel to and a few feet above the base of the oil
initially commercialized by Barber Oil Exploration Inc. The tech- sand that was subsequently produced. To position the lateral holes
nology is currently owned by Ladd Petroleum Corp. properly, the structural configuration of the oil sand was carefully
The HOP pilot described here was installed and operated by Fenix defined by combination of geologic data from various sources.
and Scisson Inc. on Shell Oil Co. 's D&D lease at Kern River (Fig. Drillers' logs taken in many old wells drilled within the pilot area
2) with funding provided by private-sector investors. were used with data obtained in four new wells to prepare numerous
The purpose of this paper is to describe the geologic and reservoir structural cross-sections (e.g., Fig. 4) and contour maps.
engineering features of the project; details of the construction and The base of the Interval QI sand, which was paralleled by the
drilling techniques are proprietary. lateral holes, is not a planar surface; it exhibits some irregularity,
which was allowed for during placement of the laterals. The base
Drilling and Completion Practices of the Interval Ql sand was found to strike north 15 to 45° west
Vertical Shaft and Chamber. A 7-ft [2.1-m] -diameter cutter as- and dip an average of about 4 ° [0.79 rad] southwest across the pilot
sembly and a specialized drilling rig were used to drill a hole to area. The term "horizontal well" is used here to mean a lateral
a depth of about 500 ft [150 m] at the center of the 25-acre [lO-ha] that dips about 4° [0.07 rad].
rectangular pilot area. The hole was then lined with 5-ft [l.5-m]
-diameter steel casing from the surface to the top of a heavy-oil Lithology. Zone Q consists of very porous, unconsolidated sands
accumulation at about 350 ft [105 m]. Miners were lowered into interbedded with various types of nonreservoir deposits. The reser-
the shaft where they hand-dug a 25-ft [7.6-m] -diameter chamber voir sands are moderately to well sorted, range from very fine
within the interval selected for pilot operations and pressure-grouted grained to pebble and cobble size, and contain variable but gener-
the chamber walls and floor. ally small amounts of interstitial clay. The unconsolidated sands
are uncemented except for occasional small calcite concretions and
are held together mainly by the viscous oil. Igneous rock clasts of
Copyright 1988 Society of Petroleum Engineers cobble and boulder size occupy up to 20% of the oil-sand bulk

SPE Reservoir Engineering, August 1988 935


KERN RIVER FIELD

5000'
"COl.' tl '

j PRODUCTION WELL

n VERTICAL STEAM INJECTION WELLS T. 285


T 295
R.ZBE
R.2BE
........ SLOTTED LINER INTERVAL

Fig. 1-Schematlc of pilot Injection and production wells.

~~
volume in some Zone Q intervals. The presence of this coarse clastic
material was an important factor in the decision to use rotary-drilling
rather than augering techniques to place the horizontal wells. @
\
MC:::-:OPERTV
Nonreservoir deposits include clays, silts and poorly sorted sands.
These sediments are usually poorly bedded and often appear mot-
tled, as though reworked by organisms or weathering processes. Fig. 2-Locatlon of Kern River horizontal-well steam pilot.

Stratification. Areally continuous and tight (e.g., 2- to lO-md)


claystone members separate Intervals Ql and Q2 (Fig. 6) and isolate volume. These nonreservoir sediments are present as lenses, which
both of them from overlying and underlying beds. These claystones are usually not continuous over the 25-acre [lO-ha] pilot area
are about 20 ft [6.1 m] thick and were probably formed as clay (Fig. 4).
drapes during stream deposition on a large alluvial fan. Numerous
conventional steam projects at Kern River demonstrate that these Saturation and Pressure Depletion. Shell Oil Co. drilled and com-
thick claystones confine injected steam to the intended displace- pleted 21 wells within the pilot area during 1947 and 1948 as part
ment intervals. of an overall program to develop its updip Kern River reserves on
Interval Ql consists of three distinctive sand packages (Figs. 6 1.25-acre [0.5-ha] well spacing. These wells were produced inter-
and 7) in the pilot area with a composite gross thickness of about mittently on primary until Shell initiated steam-soak operations dur-
90 ft [27 m] and an average net oil-sand thickness of 77 ft [23 m]. ing 1969. Several old wells located within the pilot area and
The three sand packages consist of a highly resistive (35- to 50-0 . m) numerous wells on adjacent acreage have been stimulated with mul-
upper zone, a low-resistivity (15- to 20-0· m) middle zone, and an tiple steam cycles.
intermediate-resistivity (25- to 35-0· m) lower zone. Suppressed During excavation of the chamber and horizontal-well drilling
resistivity in the middle zone is caused by a highly laminated or in the eastern area of the pilot, water inflow was a problem and
bedded structure. Numerous thin beds of sand and clay distinguish required pumping from the central shaft. The source of this mo-
this deposit from the massive oil sands that make up the upper and bile water at the base of Interval Ql is probably steam condensate
lower Interval Ql. from the prior steam-soak operations and percolation from the
Nonreservoir sediments within Interval Ql have permeabilities overlying aquifers, which are recharged by the adjacently flowing
in the range of 20 to 200 md and oil saturations <20% of bulk Kern River (Fig. 2).

I VERTICAL STEAM
l'\. IH"[CTOftS

Fig. 3-Posltlon and numbering of horizontal wells.

936 SPE Reservoir Engineering, August 1988


L L'
I-- S 67 1/2°W N67i12° E-...j

o 100

Fig. 4-Posltlon of horizontal well and lenses In cross-sectional view.

41/2·' PROOUCTlON~ 3"STEAM INJECTION WELL HOP # 4


STRING STRING

I
I
INDUCTION RESISTIVITY
(ohm METERS}
DEPTH
-450' 0 25

SHAFT
WALL

MOOEL LAYERS
1'I~16'

t~~:;Z· =:::i;==i:lCCliiiIllU:mONj[E=
SAND

LAMINATED SANDSTONE
e. IjU0Nt
SAND
,.,.0
_ _ _ _ ...L..6518"SL~~ _ ~EA. -800'
_ _ _ _ _ _ _ _ _- N
3"SH: .... INJECTION
STRING
41/2" PRODUCTION
STRING -650' h:82'
''''23%
5 0.32.6%

Fig. 5-Schematlc of horizontal-well piping.


-700'

WELL HOP /I 2

INDUCTION RESISTIVITY -715'


(ohm METERS)
DEPTH
-250' 0r-______~~~------~5~0---- Fig. 7-Layerlng model used In numerical simulations.

Modem logging suites (including compensated neutron/formation


density logs) obtained in many of the four exploratory wells and
eight vertical wells drilled specifically for the pilot indicate that
h=32.4'
-300' .'=29%
a thin gas cap (from 1 to 7 ft [0.3 to 2 m]) exists at the top of Interval
5 0 =66% Q lover most of the pilot area. The gas cap consists of air that en-
tered the shallow, unconfmed reservoir through numerous idle well-
bores during the 4O-year depletion history. This condition of liquid
desaturation is common in other reservoirs of the Coalinga and
_ 350~'4IIt"'l";;..>';>"7""~I.hT
Midway-Sunset fields in the San Joaquin Valley.
HORIZONTAL_ The presence of this air/liquid interface establishes an atmospheric
WELL POSITION 375. pressure boundary condition at the top of Interval Q 1. This low
reservoir energy was shown during the pilot design simulations to
be incapable of adequately supporting production rates during cy-
-400'
409
clic steaming operations. This led to a modification of the original
h=36'
cyclic steam concept for the HOP. As an alternative, a continuous
,'=26.1 % steam-injection program, which included both horizontal and ver-
5.=36.9% tical wells, was designed and installed to augment the low reser-
voir energy found at this pilot site.

OIP and Horizontal-Well Placement. The approach used to cal-


culate OIP included comparison of oil saturations determined from
-490' whole-core analysis in the pilot area exploratory wells to oil satu-
rations previously determined from log analysis on an analog Kern
Fig. 6-Typical resistivity vs. depth profile In pilot area. River property. The analog was the McManus lease (Fig. 2), where

SPE Reservoir Engineering, August 1988 937


TABLE 1-CURRENT OIP, AVERAGE PILOT BASIS

Oil
Saturation Porosity Net Pay Current OIP
Interval (%/100) (%/100) (It) (STB/NAF) (MSTB) (% Total)
01 upper 0.601 0.276 32.3 1,287 1,039 52
01 middle 0.399 0.278 17.0 861 403 20
01 lower 0.428 0.242 27.8 803 558 28
01 total 0.507 0.264 77.1 1,038 2,000 100
02 total 0.346 0.260 57.4 697 1,000 100

TABLE 2-ACREAGE AND OIL SATURATION x POROSITY x THICKNESS PRODUCT


FOR THE EIGHT PILOT SECTORS

Sector Area (acres)


North Northeast East Southeast South Southwest West Northwest
-- -- --- --
1.60 3.30 4.30 3.30 1.60 3.30 4.30 3.30
Sector Oil Saturation x Porosity x Thickness Product (It)
Interval North Northeast East Southeast South Southwest West Northwest
-- -- --
01 upper 5.1 6.2 6.2 6.2 5.5 4.8 4.4 4.1
01 middle 2.5 1.8 2.0 2.0 1.6 1.3 2.3 3.1
01 lower 2.6 2.2 2.6 3.1 3.2 3.4 3.2 3.1
01 total 10.2 10.2 10.8 11.3 10.3 9.5 9.9 10.3
02 total 5.2 1.1 2.3 3.5 4.8 6.1 7.8 9.5

highly saturated upper Interval Ql oil sand was not expected to con-
TABLE 3-MEASURED OIL VISCOSITY vs. TEMPERATURE tribute significantly to production during early time. The reason
ON UPDIP KERN RIVER ZONE Q OIL SAMPLE
is that viscous oil (Table 3) in upper Interval Ql would not become
Temperature Oil Viscosity effectively mobile until heat injected into the horizontal wells was
(OF) (cp) convected and conducted upward through intervening sediments,
which consist of several claystone/siltstone lenses (Fig. 4) and the
80 5,046.8
140 302.0
bedded (laminated) series of oil sands and silts in middle Interval
180 78.7 Ql (Figs. 6 and 7).
200 44.3
250 19.9 Pilot Design Simulations
300 8.9 The feasibility of using horizontal wells in a steam process was first
Rock and Fluid Properties for Simulator Input studied with thermal reservoir simulation during 1977. 2 Horizontal
PV compressibility, psi -1 0.00025 wellbores were shown at that time to be capable of improving ulti-
Irreducible water saturation, fraction PV 0.30 mate thermal oil recovery from conventional projects. On the basis
Critical gas saturation, fraction PV 0.05 of these promising feasibility results, the simulator was used to de-
Residual oil saturation to steam, fraction PV 0.01 to 0.08 sign the Kern River pilot with a site-specific geologic model and
Initial reservoir temperature, OF 110 many alternative well geometries and operating policies. The most
Rock heat capacity, Btu/lt3_oF 35.0 promising pilot design was installed and the project was operated
Rock thermal conductivity, Btu/D-It_oF 28.0 during 1982 and 1983.
Relative permeability Temperature independent
Thermal Reservoir Simulator. The volatile-oil steamflood simu-
Oil density at 60°F, Ibm/lt 3 59.9
lator described in the Appendix was used in all the pilot design and
Oil density at 110° F, Ibmlft 3 58.9
Oil gravity at 60°F, °API 15.9 monitoring work. Since its development in 1980, this simulator has
Oil gravity at 110°F, °API 18.4 been used extensively within the petroleum industry to design and
Oil compressibility, pSi-I 0.000008 analyze field projects worldwide. 3-9 Steam distillation, steam addi-
Oil thermal expansion coefficient, of-I 0.00034 tives, hydraulically induced fractures, and reservoir compaction
Oil specific heat, Btu/lbm-oF 0.44 were important elements in many of these field applications.

Reservoir Prototype. Although steam-distillation effects are ob-


the standard Waxman-Smits equations for shaly sand interpreta- served in Kern River projects, their importance in overall pilot de-
tion 1 were used for Interval Q. sign was thought to be minor. Therefore, only water and a dead-oil
Total Zone Q DIP beneath the 25-acre [1O-ha] pilot area is cur- component were used during analysis of the horizontal-well pilot.
rently about 3,000,000 STB [480 x 10 3 stock-tank m 3 ]. Interval The horizontal wellbores were represented by a standard radial
Ql was chosen as the target for the steam pilot because two-thirds well model running on pressure constraint. High flow coefficients
of the oil is contained there (Table 1). Saturation of oil in the upper were set for each gridblock penetrated by the horizontal well to
portion ofthe zone averages 50% higher than that in either middle eliminate any pressure drop from the wellbore to the reservoir. This
or lower Interval Ql (Table 1). The product of oil saturation, porosi- is a distributed source-and-sink approach to well modeling, meaning
ty, and oil-sand thickness for Interval Ql as a whole is remarkably that the sandface sees a uniform and constant potential along the
uniform, varying between 9.5 and 11.3 ft [2.9 and 3.4 m] among full length of the pipe under both injecting and producing conditions.
the eight sectors of the pilot area (Table 2). A sector's fraction of The converging nature of the horizontal wellbores toward the cen-
total pilot area OIP is therefore expected to be about equal to the tral vertical shaft led to our use of cylindrical coordinates. Large
fraction of total pilot area occupied by that sector. three-dimensional grid systems were used (1,056 active gridblocks)
The horizontal wellbores were placed in the basal portion of In- to model one-eighth elements of the 25-acre [lO-ha] pilot area.
terval Ql (Figs. 6 and 7), where oil saturation varies between 30 Several different one-eighth pattern elements (or sectors) were used
and 45% and averages about 42 %PV (Table 1). Oil from the more during the simulations, each with unique structural dip and geologic

938 SPE Reservoir Engineering, August 1988


0.8,.-----r---.,----,.---.... -----r---,
HEAVY OIL PROCESS SIMULATIONS

Z7 HORIZONTAL
~WELL \ / ZZ

0.7
\ /
-------
------- '----
>-
------- cr 0.6
w
>
o MODIFIED HOP
o STEAM FLOOD
W
23 a: 0.5

o
...J 0.4
«
z
o
t-
00.3
«
cr
u.
I
Z •
Fig. 8-Finite-difference grid system for heavy-oil process ..... 0.2
C1
0

/'
simulations. Z a
..J
/'
./'
~­ . / ' HOP CYCLIC
conditions; one of these is shown in Fig. 8. The grid system extends :K
./
0.1 ~
beyond the pilot area in the radial direction to represent the uncon- '"E /
fined nature of the pilot in that direction. Direction of true bed dip
0
with respect to the grid is along a radial vector 22 [0.38 rad] coun-
.
a
en
terclockwise from the direction of horizontal Well 26 (Fig. 3). °OL-~~~50~0~--I-O~O~O---'5~O-O---2-0~O-O---25~O-0---30~OO
Oil recoveries simulated with downdip pattern sectors were always DAYS FOLLOWING INITIAL STEAM INJECTION
10 to 20% higher than those simulated with updip sectors. This
0
results because gravity forces present with the 4 [0.07-rad] dip
held the steam injected downdip and the displaced oil within the Fig. 9-Simulated oil recoveries for alternative pilot designs.
pilot area; fluids were free to migrate upstructure beyond the pilot
perimeter in the simulations that used updip sectors.
The vertical dimension is described by an eight-layer grid, as A
shown in Fig. 7. Logs and cores available in many old and new
wells were used to describe both areal and vertical distributions
27
HORIZONTAL
............... ~WELL
\ 22

of rock properties and fluid saturations within the one-eighth reser- ........ \
voir prototype. Horizontal and vertical permeabilities within the
......... VERTICAL
oil sands range from 300 to 700 md and from 60 to 470 md, re- ------- lNJECTOR'A

spectively; permeabilities within the claystone lenses range from


20 to 200 md. There is 253,350 STB [40280 stock-tank m 3 ] of
OIP within the gridblocks approximating the southwestern pilot area.
PV of this region is 502,650 bbl [79 900 m 3 ], resulting in an aver-
age oil saturation of 0.504 at the start of pilot operations. A
Simulation Operating Constraints. One 50 x 10 6 -Btu/hr [14.7-
W] steam generator was available for the pilot; hence, the maximum '0
injection rate for the entire pilot area was set at about 2,900 BID
[460 m 3 /d] of cold water equivalent (eWE) steam. The maximum
sandface injection pressure was limited to 350 psia [2.4 MPa] to Fig. 1O-Finite-difference grid system for modified heavy-oil
stay below expected fracturing or pressure-parting conditions. The process simulations.
minimum bottomhole operating pressures were set at 15 psia [103
kPa], and the maximum horizontal-well production rates were limit-
ed to 750 BID [120 m 3 /d] per well. tion to well interference effects caused by differing boundary con-
ditions, this reduced estimate of oil recovery is a result of two other
HOP. The initial concept for the HOP was one in which the horizon- factors: (1) the extent of the pressure depletion at the pilot site
tal wells were cyclically steamed to create a "hot-plate" effect at (visualize the atmospheric pressure condition at the top of Interval
the base of a heavy-oil accumulation. Early simulations of this Ql) was not recognized at the time of the early HOP simulations
process 2 were conducted with boundary conditions that assumed during 1977 and (2) operating out of phase (unlike in phase) does
that a fully confined pilot was operated "in phase." This meant not allow perforation of the entire length of the converging horizontal
that the pilot was assumed to be surrounded by an infinite number wells because of problems with early steam breakthrough.
of identical pilots and that each one-eighth pilot sector was simul- Simulation results for the unconfined pilot condition wyre gener-
taneously undergoing identical injection, soak, or production op- ated with the grid shown in Figs. 7 and 8 and are shown in Fig.
erations. Under these assumed boundary conditions, HOP was 9. The period simulated consists of five injection cycles for Horizon-
shown to be capable of recovering 65 % of the OIP during a 5-year tal Well 25 and four for Well 26 and covers a time of 2,050 days.
period at an overall OSR of 0.32 bbllbbl [0.32 m 3 /m 3 ]. Oil recovery during this time was 21,841 and 30,735 STB [3470
Later design simulations (described here) of the actual unconfined and 4890 stock-tank m 3 ] for Wells 25 and 26, respectively. This
pilot condition at Kern River in which practical facility constraints amounts to 20.8% of the OIP within the portion of the pilot area
require out-of-phase cyclic operations indicate that the original HOP enclosed between these two horizontal wells (Fig. 8).
process is capable of recovering 17.5% of the OIP during a 5-year The simulations indicate that after a short period of injection,
period at an overall OSR of 0.21 bbllbbl [0.21 m 3 /m 3 ]. In addi- the horizontal well on production begins to respond to the iniec-
SPE Reservoir Engineering, August 1988 939
TABLE 4-STEAM SLUGS w~

:::
1-..... 0.1
KERN RIVER HORIZONTAL-WELL STEAM PILOT

Total Steam c~
~<n
,,~

Well (bbl) ..J


"m
III O.O~
DSR "
~z
.
:Err.- 0 ·0
21 6,974 "<n ~C/lKi!lL
z-
00 0"
22
23
3,921
28,543
l..Jio..ruZONoT,-"A-".L) - - - - STEAM FLOODING
!WELLS ---,
J
.. "
-0
00
Wo
24 27,308 80 800..., a:
~
25
26
35,643
7,769
~.
0;
m
STEAM

~
/.,.,...

~a:
Q.

60 / WATER 600 : ~
27 36,620 W'
>z
.. c
/ .,;0
28
Total
34,966
181,735
-0
1-"-
c ..
~o
40

/
/ OIL
~D::
....
""020
~o
/ 200 ~~
:::1
0::: / ::
tion pressure wave with an increase in total production rate. As D~~~~~~~~~~~~~~~~~~~DIO
IJ A SON 0 1 F M A M IJ A SON ~~ J J
soon as the injection well is shut in, soaked, and put on produc- t 2nd/HALFI982 I tst/HALFI983 I 2nd/HALFI983 I
PILOT OPERATING MONTHS
tion, however, the opposing well's production rate rapidly decreases
as pressure is depleted.
To study the effect of increasing reservoir energy, a steamflood Fig. 11-0bserved pilot response-cumulative basis.
was simulated after several steam cycles (from 1,400 days). In this
case, steam was injected continuously into Horizontal Well 25 with
Horizontal Well 26 on production. Only a slight improvement in of the highly laminated middle Interval Ql (Figs. 6 and 7) that con-
oil recovery was shown as a result of steam-injectivity and capture- trols the rate at which hot oil moves downward into the horizontal
efficiency problems. The tight overlying middle Interval Ql prevent- wellbore. Although the lenses are less permeable, they are less im-
ed vertical steam-zone growth, and some displaced oil was pushed portant because they are areally discontinuous. Note that strong oil
out of the pilot acreage. Injectivity and capture efficiency were re- response was not predicted by the simulator during the first 2 years
duced by the short perforation intervals. of the pilot (Fig. 9).
Steam breakthrough was shown to occur in the modified HOP
Modified HOP. The design simulations indicate that a steamflood process at about 2,000 days when steam was injected into upper
process is necessary to provide reservoir energy at the pilot location Interval Q 1. An interesting feature of this process is that steam was
and that fully perforated horizontal wells are needed for capture shown to break through initially to a limited section of the slotted
efficiency. Because the total fluid throughput rate is set by the steam liner and subsequently to move radially along the horizontal well
generator capacity in this pilot, full length perforating was shown in both directions. Oil was shown to be severed by the steam and
to be more important to improve capture efficiency than overall to move by gravity drainage into the horizontal well in a manner
production rate. analogous to the movement of hot oil into the lower perforations
The original concept of HOP was therefore altered to a scheme of a vertical well after steam override in the conventional steam-
where conventional vertical wells were used for steam injection and flood process.
horizontal wells were used for production. In this modified program,
it was possible to produce all eight fully perforated horizontal wells
simultaneously (i.e., in phase) following their initial steam stimu- Pilot Operations
lation treatments. Steam Injection. Each of the eight horizontal wells was stimulated
The grid system shown in Figs. 7 and 10 was used to evaluate by injection of I,OOO-Btu/lbm [2326-kJ/kg] steam to initiate the
this modified process. In this case, the full steam generator capacity project using the eWE steam slugs shown in Table 4.
was allocated to the eight vertical injectors following 60,000- to These steam slugs were injected through a 3-in. [7.6-cm] tubing
80,000-bbl [9540- to 12 700-m 3 ] steam-soak treatments in each of string and placed at the radial terminus of each horizontal well (Fig.
the horizontal wells. 5). The disproportionate injection volumes were the result of differ-
Simulated oil recovery for the modified HOP process is shown ences in injectivity and the need to begin the production stage of
in Fig. 9. The slow response is caused by placement of the horizontal the project without incurring time delays. Wellbore surveys were
wells within the low-oil-saturation environment at the base of the not available in the horizontal wells; hence, the injection profiles
heavy-oil column. In this pilot, it is the low permeability (60 md) are unknown.

TABLE 5-0BSERVED PILOT RESPONSE (STB)

Injected Steam Oil Produced Water Produced


Per Per Per Per Per Per
1982 Month ~ Cumulative Month Day Cumulative Month Day Cumulative
-- -- -- ---
July Steam soaking 40,000 357 12 357 10,102 326 10,102
Aug. Steam soaking 110,000 503 16 860 18,112 584 28,214
Sept. Steam soaking 182,000 689 73 1,549 2,908 97 31,122
Oct. Steam soaking 182,000 1,981 64 3,530 32,740 1,056 63,862
Nov. 40,231 1,341 222,231 3,763 125 7,293 48,762 1,625 112,624
Dec. 89,925 2,901 312,156 4,333 140 11,626 86,830 2,801 199,454
1983
--
Jan. 93,900 3,029 406,056 4,948 160 16,574 105,169 3,393 304,623
Feb. 77,745 2,777 483,801 4,630 165 21,204 86,671 3,095 391,294
March 80,211 2,587 564,012 3,670 118 24,874 86,938 2,804 478,232
April 80,776 2,693 644,788 4,447 148 29,321 83,698 2,790 561,930
May 92,138 2,972 736,926 5,187 167 34,508 84,878 2,738 646,808
June 50,921 1,697 787,847 5,348 178 39,856 64,006 2,134 710,814
July 0 0 787,847 3,822 123 43,678 39,002 1,259 749,816
Aug. 0 0 787,847 3,306 107 46,984 28,207 911 778,063

940 SPE Reservoir Engineering, August 1988


TABLE 6-0BSERVED PRODUCTION PERFORMANCE
PER HORIZONTAL WELL

Horizontal Oil Production Water Production


SCI\J<ING
~lZ0NTA'-'''''L+_ _ _ STEAM FLOODING --j Well bbl % of total bbl % of total
!""WELLS
Z 21 3,383 7.2 118,266 15.2
0400 4000 ~ 22 4,745 10.1 212,412 27.3
;;; I-
o 23 6,578 14.0 116,709 15.0
I-
:>
~ 300 3000 0 24 8,598 18.3 67,691 8.7
Z o 24,898 3.2
o a: O 25 4,229 9.0
I-
Q.,
26 2,725 5.8 17,117 2.2
0 200 2000 ~~
:> :>(/)
27 11,417 24.3 135,383 17.4
c
o a 28 5,309 11.3 85,587 11.0
a: 100 1000 ::;
100.0
Q. Totals' 46,984 100.0 778,063
(/)
.... (/)

o o • Allocations of total pilot production on the basis of weekly well tests.


AS 0 N 0IJ F M AM J,J A a:
2nd/HALFI982
PilOT
[ 'st/HALF/sa3
OPERATING
I
MONTHS
2nd/HALFI983
" to 300°F [120 to 150°C] before injection into vertical wells be-
gan. Although wellbore injection profiles were not available in the
Fig. l2-0bserved pilot response-rate basis. horizontal wells, some hot fluid leaving the 3-in. [7.6-cm] steam-
injection lines at the radial termini of the wells must have moved
After this preheating of the horizontal wells, the full generator through the annuli and exited through liner slots near the shaft.
capacity of about 3,000 BID [480 m 3 /d] was switched to the ver- Temperature data indicate that steam condensate from the vertical
tical injection wells. Steam was injected into only lower Interval injection wells reached the horizontal wells during the life of the
QI with injection rates allocated on the basis of the area served pilot. The breakthrough of live steam did not occur. Wellhead tem-
by each injector. It was planned to recomplete the vertical injection peratures for all but two of the horizontal wells were in the range
wells later in the project to place the majority of the steam into of 210 to 245°F [99 to 118°C]; Wells 26 and 28 averaged 180 to
upper Interval Q 1. 200°F [82 to 93°C]. The two wells that recovered the most oil and
Several injectors were unable to take their share of the generator the two that recovered the least (Table 6) were located in areas con-
capacity at the maximum allowed injection pressure during the early taining the highest and lowest products of oil saturation, porosity,
weeks of the project. Fig. II indicates that about 606,000 bbl and oil-sand thickness, respectively.
[96 300 m 3 ] CWE steam was injected into the vertical wells during
an 8-month period; this is an average daily rate of about 2,500 bbl Discussion of Pilot Response. Field pilot results are compared with
[400 m 3 ].
simulator predictions in Fig. 13. The simulation results for the modi-
fied HOP process were obtained before project startup. Several early
Observed Production Response. The pilot recovered about 47,000 simulations were conducted withaltemative sets of relative per-
STB [750 stock-tank m 3 ] oil in response to the injection of 788,000
bbl [125 000 m 3 ] CWE steam. This is a cumulative OSR of 0.06
bbIlbbl [0.06 m 3 /m 3 ] (Fig. 11). The project was terminated after
14 months of operation because oil revenue was not matching the
pilot operating costs.
Monthly fluid rates shown in Table 5 and in Fig. 12 indicate that
although the producing oil cut for the pilot as a whole averaged
less than 10 %, it was gradually increasing with time.
Peak temperatures recorded by the thermocouples installed in the KERN RIVER PROJECTS

chamber wall were about 240°F [115°C]; thermocouples installed (A) IMBIBITION CURVE FROM MATCH
OF [NJECTIVITY.(McMANUS STEAMFLOOD)
near the vertical shaft indicate that temperatures there reached 250 (9) CURvE FROM MATCH OF KERN"A"
STEAM FLOOD PILOT.

(C) DRAINAGE CURVE FROM MATCH OF


CYCLIC STEAM RESPONSE. (McMANUS PROPERTY)

>-
I-
:::;
0.05 -m
>- / <
a:
w
>
/ w
~

o / ~ IX 10-2
0 0 .04 Q.

w
a: / >
w
A)

(8)

...J / I-
<
-'
0 0 . 03
...J
/ w
a:
<
Z
/
~ 0.02
/ IXIO-!
t-
o
<
a: co
c
u.. :a:. - PILOT RESPONSE
I 0.01
go
-
Z

<>
Z
"'li
Ec--'
~-'
u;
- - IMBIBITION k rw
_.- DRAINAGE k rw

00 0.1 0.2 0.3 0.4 0.5 0.6


WilTPV-FRACTIONAL STEAM INJECTION

Fig. l3-Comparison of early pilot response-observed vs. Fig. 14-Drainage and imbibition relative permeability func-
simulated. tions for simulation.

SPE Reservoir Engineering, August 1988 941


O.Sr------r------.-----_.------~----_.----__, 25-ACRE MODULE
STEAMFLOOD PROCESS SIMULATIONS
(I) CONVENTIONAL 5-SPOT(IMSISITION)
(2) CONVENTIONAL 5- SPOT (DRAINAGE)
0.7 (3)
(3) MODIFIED HOP (IMBIBITION)
(4) MODIFIED HOP (DRAINAGE)

>
~ 0.6
>
0
0
w
a:: 0.5
..J

~ 0.4
Z Fig. 16-Finite-dlfference grid systems for conventional five-
0 spot steamflood analysis.
t-

~ 0.3 injection. These low OSR values are comparable with those ob-
a::
LL
I
. served and calculated for the McManus steamflood.
The series of 2V2-acre [1-ha] five-spot patterns shown in Fig .
Z
....... 0.2
a
~
...J
16 was assumed for analysis of the conventional steamflood. The
Z fluid throughput rate for the full 25 acres [10 hal was set to the
'"c
:i'_ same level assumed for analysis of the modified HOP process. A
~ CWE steam injection rate of 280 B/D [45 m 3 /d] per full injector
E
0.1
~ was used with only Interval Ql open. When a total of 1.2 PVof
;;;
CWE (1 ,OOO-Btu/lbm [2326-kJ/kg]) steam had been injected, the
simulated injection was switched to warm water containing 128
°0~~~~~--~~----~~----~-----25~OO~--~3000 Btu/Ibm [298 kJ/kg]. The 15 producing wells were operated with
DAYS INJECTION
a 50-psia [345-kPa] minimum bottomhole operating pressure and
a maximum lift capacity of 320 BID [50 m 3 /d] per full well. The
Fig. 15-Comparison of simulated oil recovery-conventional several different prototypes or pattern elements shown in Fig. 16
five-spot vs. horizontal-well steamfloods. were simulated to develop the composite production function for
the entire 25-acre [lO-ha] area.
meability functions to display the sensitivity of the modified HOP
process to this variable. The functions shown as imbibition and Modeling Limitations
drainage 5 in Fig. 14 were used; these were obtained by history The modeling approach described here has several limitations; two
matching cyclic steam response observed for the McManus lease of these are caused by the current cost of computer processing and
at Kern River (Fig. 2). Relative permeability functions published the other relates to inadequate field data.
for the Kern "A" pilot 10 in the central portion of the Kern River Computer run times and costs currently prohibit the use of a reser-
field are similar to those developed for the McManus lease. voir model (for practical engineering analysis) that includes the en-
The slope of the observed pilot response in the dimensionless plot tire pilot area. As an alternative, the pilot acreage was subdivided
of Fig. 13 falls within the envelope of performance predicted by into one-eighth sectors or elements that were assumed to be enclosed
the simulator with the alternative relative permeability functions. by no-flow boundaries that do not move. Overall pilot project
The slope of the early pilot response curve might have been even response was developed by adding the responses from the individual,
more favorable if the horizontal wells had been preheated with the relatively high-resolution, fine-grid simulations of reservoir pro-
larger steam injection design slugs. totypes. Each pattern element or sector was assigned to one of sever-
al classes of reservoir prototype, where a prototype class represents
Modified HOP vs. Conventional Steamflood any combination geometry/geology/process description that yields
Pilot oil recovery predicted by the simulator for the modified HOP a significantly different simulation response. In this pilot analysis,
is compared with that predicted by the simulator for conventional the variation in structural dip among the various sectors yielded
steamflood development in Fig. 15. Results generated from imbi- significantly different simulation responses. Each of the eight pattern
bition relative permeabilities after 8 years of project simulation for elements was therefore assigned to one of the appropriate simulated
the modified HOP indicate a cumulative oil recovery of 0.74 of prototype responses to develop estimates for its oil-rate-vs.-time
OIP and a cumulative OSR of 0.20 bbllbbl [0.20 m 3 /m 3 ]. Results function. The overall pilot oil rate was then obtained by addition
for the conventional five-spot steamflood indicate a cumulative oil of the individual pattern elements.
recovery of 0.47 of the OIP and an OSR of 0.19 bbllbbl [0.19 Cost constraints also led to the simplified modeling technique de-
m 3 /m 3 ]. scribed here for the horizontal wellbore. A more rigorous approach
Predictions made with imbibition and drainage relative permea- would involve using a series of small gridblocks scaled to the size
bility functions are considered to provide a lower and upper limit of the wellbore. This type of treatment for modeling either well-
to process performance, respectively. The improved ultimate oil bores or hydraulically induced fractures 3 .4.6 is possible with the
recovery potential shown by the modified HOP reflects increased fully implicit formulation of the simulator. However, preliminary
vertical sweep efficiency associated with injecting at the top of the simulations of this nature were discontinued for analysis of this pi-
formation and producing from the base. Early conventional steam- lot because they were prohibitively expensive. Simulation results
flood response was shown to be strong in the simulations because presented here assume that the steam injected at the terminus of
the high oil saturations present in upper Interval Ql (Figs. 6 and each horizontal well (through the 3-in. [7.6-cm] injection string)
7) are open in the production and injection wellbores. unloads the water and oil within the 8%-in. [22-cm] slotted liner
The cumulative OSR for the modified HOP process was 0.18 and contacts the sandface along the full length of the well.
bbl/bbl [0.18 m 3 /m 3 ] after nearly 7 years, when steam injection Finally, the inability to obtain either openhole or cased-hole logs
was terminated and pressure blowdown was initiated. In the five- in the horizontal wells (particularly profile surveys taken during
spot analysis, the cumulative OSR was 0.15 bbllbbl [0.15 m 3 /m 3 ] injection and production operations) limits the engineering analysis
after 5 years, when steam injection was converted to warm water of this pilot.

942 SPE Reservoir Engineering, August 1988


Review and Conclusions 7. Claridge, E.L. and Dietrich, J.K.: "Viscous Fingers and Gravity
Tongues in Carbon Dioxide/Steam Stimulation," paper SPE 11707
Reservoir conditions at the pilot site are unfavorable for application presented at the 1983 SPE California Regional Meeting, Ventura, March
of either conventional oil recovery processes or novel oil-mining 23-25.
techniques. OIP was low initially relative to that found in the central 8. Chase, C.A. and Dietrich, J.K.: "Compaction Within the Belridge Di-
portion of the Kern River field owing to abundant silt and clay frac- atomite," paper SPE 17415 presented at the 1988 SPE California
tions in the porous medium and proximity to groundwater. Fur- Regional Meeting, Long Beach, March 23-25.
thermore, previous development of the pilot area with both primary 9. Dietrich, 1.K.: "Steamflooding in a Water Drive Reservoir: Upper
and steam-soak operations partially depleted oil saturation and re- Tulare Sands-South Belridge Field," paper SPE 17453 presented at
the 1988 SPE California Regional Meeting, Long Beach, March 23-25.
duced reservoir energy to the atmospheric pressure level.
10. Chu, C. and Trimble, A.E.: "Numerical Simulation of Steam Displace-
The horizontal wells were placed at the base of the heavy-oil ment-Field Performance Applications," JPT (June 1975) 765-76.
colunm in an environment containing mobile water where they were
in poor communication with overlying oil-rich sands. Simulations Appendix-Simulator Description
of anticipated pilot performance made before project startup indi-
cated that these reservoir features would be responsible for a slow Overview. The compositional steamflood simulator was used to
oil response. design and monitor this horizontal-well steam pilot. This simulator
The following conclusions are based on the work reported here. is a fully implicit, finite-difference-based program capable of run-
I. The type of oil-mining process described is technically promis- ning in either an isothermal or thermal mode, with or without active
ing because it was shown to be capable of reducing the serious prob- reservoir compaction. The program can treat up to four mass-con-
lem of steam override, which is so pronounced in conventional servation equations and an energy balance. There are three phases:
steamflood operations. aqueous, liquid hydrocarbon, and vapor.
2. Oil cut and OSR were increasing throughout the life of the The four mass species are water, a nonvolatile heavy oil, and
pilot. The pilot was terminated because revenues from oil produc- two volatile components. The water and nonvolatile heavy-oil com-
tion were not covering operating costs. ponents are present in all simulations. The energy balance and one
3. Observed pilot performance is in agreement with simulator or both volatile components, however, may be added or deleted
predictions of pilot response, which were in hand before project at the user's option by setting the appropriate mode switches in the
startup. input data. This allows the simulator to be run in either thermal
4. Simulator predictions indicate that continuation of the pilot may or isothermal mode and with either zero, one, or two volatile com-
have ultimately recovered about SO% more oil at equivalent OSR ponents. At the user's option, the volatile components may also
than that oil recovery volume expected from conventional steam- dissolve in the aqueous phase. Noncondensables are treated as vola-
flood development. tile components with negligible solubility in the liquid hydrocarbon
S. The encouraging operational experience with this pilot and the phase.
tremendous potential for improved ultimate oil recovery shown by
preliminary simulations suggest that future pilot testing of the tech- Phases and Components. The simulator treats four components
nology may be warranted in a more favorable environment. and an energy balance. The four components may partition among
three phases: a liquid hydrocarbon phase, a vapor phase, and an
Nomenclature aqueous phase. Allowed partitioning among the phases is shown
in Table A-I.
h = thickness, ft [m] Partitioning of the two volatile components among the three phases
krw =relative permeability to water is determined from user-specified relationships of vapor pressure
N =OIP at pilot start, STB [stock-tank m 3 ] vs. temperature. Calculation of partition coefficients is purposely
Np =cumulative oil production, STB [stock-tank m 3 ] confined to a single subroutine, permitting easy modification to in-
r =radial coordinate clude more general phase behavior if desired.
So =oil saturation, fraction
Wi =cumulative barrels of steam injection in Additional Physical Properties. Vapor-phase density is calculated
I,OOO-Btu/lbm [2326-kJ/kg] CWE with the Redlich-Kwong equation of state (EOS). Behavior of the
z = vertical coordinate individual volatile components in the vapor phase is determined by
specifying either their Redlich-Kwong parameters or their critical
8 = tangential coordinate
temperatures and pressures. The Redlich-Kwong parameters for
</> = porosity, fraction
water are directly coded into the program. Use of the EOS in the
absence of the volatile hydrocarbon components rather than the more
Acknowledgments accurate steam table-lookup approach guarantees continuity of cal-
Many individuals participated heavily in the design and analysis culated results as volatile component concentrations go to zero.
of the pilot, including J.C. Allen (consultant), Don Lockwood and Liquid-hydrocarbon-phase and gas-phase viscosities are both
Bruce Russell of Fenix & Scisson Inc., and Richard Ellis (formerly concentration- and temperature-dependent.
of Completion Technology, Inc.). The concept of the modified HOP Enthalpies of hydrocarbon components are calculated from user-
was introduced by J.C. Allen, and strong geologic contributions specified heat capacities. Water enthalpies in the liquid and vapor
were provided by Bruce Russell. Appreciation is extended to Ladd phases at zero pressure come from table lookups. Vapor-phase en-
Petroleum Corp. for permission to publish this paper. thalpy is then adjusted for pressure with the Redlich-Kwong EOS.
Relative permeabilities are entered in tabular form as functions
References of saturations and temperature. Up to 10 sets of relative permeability
I. Koerperich, E.A.: "Utilization of Waxman-Smits Equations for De-
tables, corresponding to 10 rock types, may be entered. Relative
termining Oil Saturation in a Low-Salinity, Shaly Sand Reservoir," JPT permeabilities may be changed during a simulation at restart points
(Oct. 1975) 1204-08. to model important hysteresis effects in the single-well cyclic steam
2. "Heavy Oil Process, Kern River Project, Performance Predictions for process.
Cyclic Steam Stimulation," Intercomp Resource Development and En-
gineering Inc. report for Barber Oil Exploration, Houston (Feb. 1978). Conservation Equations and Unknowns. Depending on a mode
3. Soni, Y. and Hannon, R.A.: "Simulation of the Saner Ranch Fracture switch for the energy balance (NEB), a simulation is either isother-
Assisted Steamflood Pilot," J. Cdn. Pet. Tech. (Jan.-Feb. 1986). mal (NEB=O) or thermal (NEB = I). A second mode switch (NVC)
4. DeGrisogono, 1.: "Evaluation of the Steam Injection Test in the Nord- determines the number of volatile components: either zero, one,
horn Oil Sand Reservoir, ,. paper presented at the 1982 European Sym-
posium on Enhanced Oil Recovery, Paris, Nov. 8-10.
or two. Thus, there are six permutations. The number of conser-
5. Dietrich, J.K.: "Relative Permeability During Cyclic Steam Stimulation vation equations is 2 + NEB + NVC. The number of dependent vari-
of Heavy-Oil Reservoirs," JPT (Oct. 1981) 1987-89. ables solved for is always one more than the number of conservation
6. Dietrich, J .K.: "Cyclic Steaming of Tar Sands Through Hydraulically equations. An additional constraint equation is appended so that
Induced Fractures," SPERE (May 1986) 217-19; Trans., AIME, 282. the number of equations equals the number of unknowns.
SPE Reservoir Engineering, August 1988 943
operation. If, for example, the mode is isothermal w~th only~ne
TABLE A-1-PARTITIONING AMONG volatile component, the energy balance and conservatIon equatIon
PHASES IN SIMULATION
for the second volatile component are otnitted from the set of equa-
Liquid tions being solved. After application of the constraint equation, only
Hydrocarbon Vapor Aqueous three unknowns remain per gridblock, and each element of the
Component Phase Phase Phase coefficient matrix is a 3 x 3 submatrix. By contrast, for thermal mode
--- with two volatile components, there are five unknowns per grid-
Water X X
Nonvolatile hydrocarbon X block, and each element of the coefficient matrix for this case is
Volatile 1 X X X a 5x5 submatrix.
Volatile 2 X X X
Coordinate and Geometrical Capabilities. The user may specify
either Cartesian or cylindrical coordinates. Any other curvilinear
coordinate system (viz., gridblock edges parallel to flow stream-
The set of primitive unknowns is (1) aqueous-phase saturation, lines and isopotentiallines) may be "manually" specified by means
Sw; (2) vapor-phase saturation, Sg; (3) pressure, p; (4) tempera-
of individual modifications to gridblock PV's and interblock trans-
ture, T; (5) mole fraction Volatile Component 1, x(1); and (6) mole missibilities. This feature permits maximum flexibility in specify-
fraction Volatile Component 2, x(2)' .
ing heterogeneities in rock properties (permeabilities, porosities,
The set of conservation equations is (1) water (as a chelDIcal spe- conductivities, and heat capacities) and in reservoir configuration
cies), (2) nonvolatile heavy hydrocarbon component, (3) energy,
(variable-thickness layers and variable structural dip).
(4) Volatile Component I, and (5) Volatile Component 2.
The convention used in the program is that the unknowns and Reservoir Compaction. The simulator has been formulated to treat
conservation equations are always taken in the above order, even the effects of reservoir compaction on reservoir pressure and fluid
when the mode is such that not all of them are required. For exam- flow. The formulation allows for either linear or nonlinear strain
ple, if the mode is isothermal (NEB =0) with only one volatile com- as a function of effective stress, temperature-dependent strain, visco-
ponent (NVC = I), the appropriate unknowns are Unknown Sets elastic effects (creep), and hysteresis in the form of limited or no
1 through 3 and 5, and the appropriate conservation equations are rebound as pore pressure increases because of fluid in)ect!on ..
Equation Sets I, 2, and 4. . Details concerning the formulation used for compactIon In thIS
Additional quantities, such as liquid-hydrocarbon-phase saturatIon simulator are given in Ref. 8.
and component concentrations in the vapor and aqueous phases,
are computed from the primitive unknowns from phase-equilibrium SI Metric Conversion Factors
relationships.
acres x 4.046873 E-OI ha
Solution Method. The nonlinear coupled partial-differential equa- °API 141.5/(131.5+ °API) g/cm3
tions describing the conservation of energy and of the up to fo,ur bbl x 1.589873 E-OI m3
chemical species are spatially discretized with standard fimte Btu x 1.055056 E+OO kJ
differences. Btu/ft3 x 3.725 895 E+Ol kJ/m 3
For maximum stability, time discretization is fully implicit; i.e., Btu/(lbm-OF) x 4.1868* E+OO kJ/(kg·K)
at the end of a timestep, all quantities are evaluated at the new time cp x 1.0* E-03 Pa·s
level. ft x 3.048* E-OI m
OF (OF - 32)/1.8 °C
Newton-Raphson iteration is used to solve the time and spatially
discretized finite-difference equations. The resultant linear equations in. x 2.54* E+OO cm
are solved by Gaussian elimination with alternate diagonal orde?ng Ibm/ft 3, x 1.601 846 E+OI kg/m3
(D4) or by the conjugate-gradient-like iterative method. A mne- psi x 6.894757 E+OO kPa
point finite-difference formula is used to reduce grid orientation 'Conversion factor is exact. SPERE
effects in the areal plane.
Original SPE manuscript received for review April 8. 1987. Paper accepted for publication
For maximum efficiency, the program treats only those conser- Jan. 15.1988. Revised manuscript received Feb. 29, 1988. Paper (SPE 16346) first present-
vation equations and unknowns required by the current mode of ed at the 1987 SPE California Regional Meeting held in Ventura, Aprtl 8-10.

944 SPE Reservoir Engineering, August 1988

You might also like