Professional Documents
Culture Documents
Oil and Natural Gas Commission v. Court of Appeals, 293 SCRA 26
Oil and Natural Gas Commission v. Court of Appeals, 293 SCRA 26
SYNOPSIS
Petitioner and private respondent entered into a contract whereby the latter
undertook to supply the former 4,300 metric tons of oil well cement in consideration of
$477,300.00. The oil well cement was loaded on board a ship at the port of Surigao City,
Philippines for delivery in India. But the cargo was held up in Bangkok and did not reach its
point of destination because of a dispute between the shipowner and the private
respondent. Despite the fact that the private respondent had already received payment
and several demands made by the petitioner, the private respondent failed to deliver the oil
well cement.
Private respondent agreed to replace the entire 4,300 metric tons of oil well cement
with Class "G" cement cost free at the petitioner's designated port. The cement, however,
did not conform to the petitioner's speci cations. The petitioner then referred its claim to
an arbitrator pursuant to Clause 16 of their contract.
The chosen arbitrator resolved the dispute in petitioner's favor. To execute the
award in its favor, petitioner led a petition before the Court of the Civil Judge in Dehra
Dun, India, praying that the decision of the arbitrator be made "the Rule of Court" in India.
Because of the refusal of private respondent to pay the amount adjudged by the
foreign court as owing to the petitioner, the latter led a complaint with the RTC of Surigao
City for the enforcement of the judgment of the foreign court. The RTC upheld the
petitioner's legal capacity to sue, but dismissed the complaint for lack of a valid cause of
action. The RTC characterized the erroneous submission of the dispute to the arbitrator as
a "mistake of law or fact amounting to want of jurisdiction." Thus, the proceedings had
before the arbitrator were null and void and the foreign court had therefore adopted no
legal award which could be the source of an enforceable right.
The petitioner appealed to the respondent Court of Appeals which a rmed the
dismissal of the complaint. It ruled that since the arbitrator did not have jurisdiction over
the dispute between the parties, the foreign court could not validly adopt the arbitrator's
award. A motion for reconsideration of the appellate court's decision was denied. Thus,
this petition.
The petitioner asseverates that granting that the non-delivery of the oil well cement
is not a proper subject for arbitration, the failure of the replacement cement to conform to
the speci cations of the contract is a matter clearly falling within the ambit of Clause 16.
The Court found merit in this contention. The replacement cement, upon inspection, was
rejected as it did not conform to the speci cations of the contract. What was then referred
CD Technologies Asia, Inc. 2018 cdasiaonline.com
to arbitration was no longer the mere non-delivery of the cargo but also the failure of the
replacement cargo to conform to the speci cations of the contract, a matter clearly within
the coverage of Clause 16. HaECDI
The private respondent was ordered to pay to petitioner the amounts adjudged in
the foreign judgment subject of this case.
SYLLABUS
DECISION
MARTINEZ , J : p
"The arbitrator may with the consent of parties enlarge the time, from time
to time, to make and publish the award.
On July 23, 1988, the chosen arbitrator, one Shri N.N. Malhotra, resolved the dispute
in petitioner's favor setting forth the arbitral award as follows:
"NOW THEREFORE after considering all facts of the case, the evidence, oral
and documentarys (sic) adduced by the claimant and carefully examining the
various written statements, submissions, letters, telexes, etc. sent by the
respondent, and the oral arguments addressed by the counsel for the claimants, I,
N.N. Malhotra, Sole Arbitrator, appointed under clause 16 of the supply order
dated 26.2.1983, according to which the parties, i.e. M/S Oil and Natural Gas
Commission and the Paci c Cement Co., Inc. can refer the dispute to the sole
arbitration under the provision of the Arbitration Act. 1940, do hereby award and
CD Technologies Asia, Inc. 2018 cdasiaonline.com
direct as follows:—
"The Respondent will pay the following to the claimant:—
"In addition to the above, the respondent would also be liable to pay to the
claimant the interest at the rate of 6% on the above among, with effect from
24.7.1988 up to the actual date of payment by the Respondent in full settlement
of the claim as awarded or the date of the decree, whichever is earlier.
"I determine the cost at Rs, 70,000/-equivalent to US$5,000 towards the
expenses on Arbitration, legal expenses, stamps duly incurred by the claimant.
The cost will be shared by the parties in equal proportion.
To enable the petitioner to execute the above award in its favor, it led a Petition before
the Court of the Civil Judge in Dehra Dun, India (hereinafter referred to as the foreign
court for brevity), praying that the decision of the arbitrator be made "the Rule of Court"
in India. The foreign court issued notices to the private respondent for ling objections
to the petition. The private respondent complied and sent its objections dated January
16, 1989. Subsequently, the said court directed the private respondent to pay the ling
fees in order that the latter's objections could be given consideration. Instead of paying
the required ling fees, the private respondent sent the following communication
addressed to the Civil Judge of Dehra Dun:
"The Civil Judge
Dehra Dun (U.P.) India
Re: Misc. Case No. 5 of 1989
M/S Pacific Cement Co.,
Inc. vs. ONGC Case
Sir:
1. We received your letter dated 28 April 1989 only last 18 May 1989.
2. Please inform us how much is the court fee to be paid. Your letter did not
mention the amount to be paid.
3. Kindly give us 15 days from receipt of your letter advising us how much to
pay to comply with the same.
Thank you for your kind consideration.
CD Technologies Asia, Inc. 2018 cdasiaonline.com
Pacific Cement Co., Inc.
By:
Jose Cortes, Jr.
President" 3
Without responding to the above communication, the foreign court refused to admit
the private respondent's objections for failure to pay the required ling fees, and thereafter
issued an Order on February 7, 1990, to wit:
"ORDER
Since objections led by defendant have been rejected through Misc. Suit
No. 5 on 7.2.90, therefore, award should be made "Rule of the Court.
"ORDER
Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the Court. On the
basis of conditions of award decree is passed. Award Paper No. 3/B-1 shall be a
part of the decree. The plaintiff shall also be entitled to get from defendant
(US$899,603.77 (US$ Eight Lakhs ninety nine thousand six hundred and three
point seventy seven only) along with 9% interest per annum till the last date of
realization." 4
Despite notice sent to the private respondent of the foregoing order and several
demands by the petitioner for compliance therewith, the private respondent refused to pay
the amount adjudged by the foreign court as owing to the petitioner. Accordingly, the
petitioner led a complaint with Branch 30 of the Regional Trial Court (RTC) of Surigao City
for the enforcement of the aforementioned judgment of the foreign court. The private
respondent moved to dismiss the complaint on the following grounds: (1) plaintiff's lack
of legal capacity to sue; (2) lack of cause of action; and (3) plaintiffs claim or demand has
been waived, abandoned, or otherwise extinguished. The petitioner led its opposition to
the said motion to dismiss, and the private respondent, its rejoinder thereto. On January 3,
1992, the RTC issued an order upholding the petitioners legal capacity to sue, albeit
dismissing the complaint for lack of a valid cause of action. The RTC held that the rule
prohibiting foreign corporations transacting business in the Philippines without a license
from maintaining a suit in Philippine courts admits of an exception, that is, when the
foreign corporation is suing on an isolated transaction as in this case. 5 Anent the issue of
the su ciency of the petitioner's cause of action, however, the RTC found the referral of
the dispute between the parties to the arbitrator under Clause 16 of their contract
erroneous. According to the RTC,
"[a] perusal of the above-quoted clause (Clause 16) readily shows that the
matter covered by its terms is limited to "ALL QUESTIONS AND DISPUTES,
RELATING TO THE MEANING OF THE SPECIFICATION, DESIGNS, DRAWINGS
AND INSTRUCTIONS HEREIN BEFORE MENTIONED and as to the QUALITY OF
WORKMANSHIP OF THE ITEMS ORDERED or as to any other questions, claim,
right or thing whatsoever, but qualified to 'IN ANY WAY ARISING OR RELATING TO
THE SUPPLY ORDER/CONTRACT, DESIGN, DRAWING, SPECIFICATION, etc.,'
repeating the enumeration in the opening sentence of the clause.
"The court is inclined to go along with the observation of the defendant
that the breach, consisting of the non-delivery of the purchased materials, should
have been properly litigated before a court of law, pursuant to Clause No. 15 of
CD Technologies Asia, Inc. 2018 cdasiaonline.com
the Contract/Supply Order, herein quoted, to wit:
'JURISDICTION
All questions, disputes and differences, arising under out of or in
connection with this supply order, shall be subject to the EXCLUSIVE
JURISDICTION OF THE COURT, within the local limits of whose jurisdiction
and the place from which this supply order is situated.'" 6
The RTC characterized the erroneous submission of the dispute to the arbitrator as a
"mistake of law or fact amounting to want of jurisdiction". Consequently, the
proceedings had before the arbitrator were null and void and the foreign court had
therefore, adopted no legal award which could be the source of an enforceable right. 7
The petitioner then appealed to the respondent Court of Appeals which a rmed the
dismissal of the complaint. In its decision, the appellate court concurred with the RTC's
ruling that the arbitrator did not have jurisdiction over the dispute between the parties,
thus, the foreign court could not validly adopt the arbitrators award. In addition, the
appellate court observed that the full text of the judgment of the foreign court contains the
dispositive portion only and indicates no ndings of fact and law as basis for the award.
Hence, the said judgment cannot be enforced by any Philippine court as it would violate the
constitutional provision that no decision shall be rendered by any court without expressing
therein clearly and distinctly the facts and the law on which it is based. 8 The appellate
court ruled further that the dismissal of the private respondent's objections for non-
payment of the required legal fees, without the foreign court rst replying to the private
respondent's query as to the amount of legal fees to be paid, constituted want of notice or
violation of due process. Lastly, it pointed out that the arbitration proceeding was
defective because the arbitrator was appointed solely by the petitioner, and the fact that
the arbitrator was a former employee of the latter gives rise to a presumed bias on his part
in favor of the petitioner. 9
A subsequent motion for reconsideration by the petitioner of the appellate court's
decision was denied, thus, this petition for review on certiorari citing the following as
grounds in support thereof:
"RESPONDENT COURT OF APPEALS GRAVELY ERRED IN AFFIRMING THE
LOWER COURT'S ORDER OF DISMISSAL SINCE:
A. THE NON-DELIVERY OF THE CARGO WAS A MATTER PROPERLY
COGNIZABLE BY THE PROVISIONS OF CLAUSE 16 OF THE CONTRACT;
B. THE JUDGMENT OF THE CIVIL COURT OF DEHRADUN, INDIA WAS AN
AFFIRMATION OF THE FACTUAL AND LEGAL FINDINGS OF THE ARBITRATOR
AND THEREFORE ENFORCEABLE IN THIS JURISDICTION;
C. EVIDENCE MUST BE RECEIVED TO REPEL THE EFFECT OF A
PRESUMPTIVE RIGHT UNDER A FOREIGN JUDGMENT." 1 0
The threshold issue is whether or not the arbitrator had jurisdiction over the dispute
between the petitioner and the private respondent under Clause 16 of the contract. To
reiterate, Clause 16 provides as follows:
"Except where otherwise provided in the supply order/contract all questions
and disputes, relating to the meaning of the speci cation designs, drawings and
instructions herein before mentioned and as to quality of workmanship of the
CD Technologies Asia, Inc. 2018 cdasiaonline.com
items ordered or as to any other question, claim, right or thing whatsoever, in any
way arising out of or relating to the supply order/contract design, drawing,
speci cation, instruction or these conditions or otherwise concerning the
materials or the execution or failure to execute the same during
stipulated/extended period or after the completion/abandonment thereof shall be
referred to the sole arbitration of the persons appointed by Member of the
Commission at the time of dispute. It will be no objection to any such
appointment that the arbitrator so appointed is a Commission employer (sic) that
he had to deal with the matter to which the supply or contract relates and that in
the course of his duties as Commission's employee he had expressed views on all
or any of the matter in dispute or difference." 1 1
The dispute between the parties had its origin in the non-delivery of the 4,300 metric
tons of oil well cement to the petitioner. The primary question that may be posed,
therefore, is whether or not the non-delivery of the said cargo is a proper subject for
arbitration under the above-quoted Clause 16. The petitioner contends that the same was
a matter within the purview of Clause 16, particularly the phrase, ". . . or as to any other
questions, claim, right or thing whatsoever, in any way or relating to the supply
order/contract, design, drawing, speci cation, instruction . . .". 1 2 It is argued that the
foregoing phrase allows considerable latitude so as to include non-delivery of the cargo
which was a "claim, right or thing relating to the supply order/contract". The contention is
bereft of merit. First of all, the petitioner has misquoted the said phrase, shrewdly inserting
a comma between the words "supply order/contract" and "design" where none actually
exists. An accurate reproduction of the phrase reads, ". . . or as to any other question,
claim, right or thing whatsoever, in any way arising out of or relating to the supply
order/contract design, drawing, speci cation, instruction or these conditions . . ." The
absence of a comma between the words "supply order/contract" and "design" indicates
that the former cannot be taken separately but should be viewed in conjunction with the
words "design, drawing, speci cation, instruction or these conditions". It is thus clear that
to fall within the purview of this phrase, the "claim, right or thing whatsoever" must arise
out of or relate to the design, drawing, speci cation, or instruction of the supply
order/contract. The petitioner also insists that the non-delivery of the cargo is not only
covered by the foregoing phrase but also by the phrase, ". . . or otherwise concerning the
materials or the execution or failure to execute the same during the stipulated/extended
period or after completion/abandonment thereof . . .". prLL
Thus, this Court has held that as in statutes, the provisions of a contract should not
be read in isolation from the rest of the instrument but, on the contrary, interpreted in the
light of the other related provisions. 1 8 The whole and every part of a contract must be,
considered in xing the meaning of any of its parts and in order to produce a harmonious
whole. Equally applicable is the canon of construction that in interpreting a statute (or a
contract as in this case), care should be taken that every part thereof be given effect, on
the theory that it was enacted as an integrated measure and not as a hodge-podge of
con icting provisions. The rule is that a construction that would render a provision
CD Technologies Asia, Inc. 2018 cdasiaonline.com
inoperative should be avoided; instead, apparently inconsistent provisions should be
reconciled whenever possible as parts of a coordinated and harmonious whole. 1 9
The petitioners interpretation that Clause 16 is of such latitude as to contemplate
even the non-delivery of the oil well cement would in effect render Clause 15 a mere
super uity. A perusal of Clause 16 shows that the parties did not intend arbitration to be
the sole means of settling disputes. This is manifest from Clause 16 itself which is
pre xed with the proviso, "Except where otherwise provided in the supply order/contract . .
.", thus indicating that the jurisdiction of the arbitrator is not all encompassing, and admits
of exceptions as maybe provided elsewhere in the supply order/contract. We believe that
the correct interpretation to give effect to both stipulations in the contract is for Clause 16
to be con ned to all claims or disputes arising from or relating to the design, drawing,
instructions, speci cations or quality of the materials of the supply order/contract, and for
Clause 15 to cover all other claims or disputes.
The petitioner then asseverates that granting, for the sake of argument, that the non-
delivery of the oil well cement is not a proper subject for arbitration, the failure of the
replacement cement to conform to the speci cations of the contract is a matter clearly
falling within the ambit of Clause 16. In this contention, we nd merit. When the 4,300
metric tons of oil well cement were not delivered to the petitioner, an agreement was
forged between the latter and the private respondent that Class "G" cement would be
delivered to the petitioner as replacement. Upon inspection, however, the replacement
cement was rejected as it did not conform to the speci cations of the contract. Only after
this latter circumstance was the matter brought before the arbitrator. Undoubtedly, what
was referred to arbitration was no longer the mere non-delivery of the cargo at the rst
instance but also the failure of the replacement cargo to conform to the speci cations of
the contract, a matter clearly within the coverage of Clause 16.
The private respondent posits that it was under no legal obligation to make
replacement and that it undertook the latter only "in the spirit of liberality and to foster
good business relationship". 2 0 Hence, the undertaking to deliver the replacement cement
and its subsequent failure to conform to speci cations are not anymore subject of the
supply order/contract or any of the provisions thereof. We disagree.
As per Clause 7 of the supply order/contract, the private respondent undertook to
deliver the 4,300 metric tons of oil well cement at "BOMBAY (INDIA) 2181 MT and
CALCUTTA 2119 MT". 2 1 The failure of the private respondent to deliver the cargo to the
designated places remains undisputed. Likewise, the fact that the petitioner had already
paid for the cost of the cement is not contested by the private respondent. The private
respondent claims, however, that it never bene ted from the transaction as it was not able
to recover the cargo that was unloaded at the port of Bangkok. 2 2 First of all, whether or
not the private respondent was able to recover the cargo is immaterial to its subsisting
duty to make good its promise to deliver the cargo at the stipulated place of delivery.
Secondly, we nd it di cult to believe this representation. In its Memorandum led before
this Court, the private respondent asserted that the Civil Court of Bangkok had already
ruled that the non-delivery of the cargo was due solely to the fault of the carrier. 2 3 It is,
therefore, but logical to assume that the necessary consequence of this nding is the
eventual recovery by the private respondent of the cargo or the value thereof. What
inspires credulity is not that the replacement was done in the spirit of liberality but that it
was undertaken precisely because of the private respondent's recognition of its duty to do
so under the supply order/contract, Clause 16 of which remains in force and effect until
the full execution thereof.
CD Technologies Asia, Inc. 2018 cdasiaonline.com
We now go to the issue of whether or not the judgment of the foreign court is
enforceable in this jurisdiction in view of the private respondent's allegation that it is bereft
of any statement of facts and law upon which the award in favor of the petitioner was
based. The pertinent portion of the judgment of the foreign court reads:
"ORDER
Award dated 23.7.88. Paper No. 3/B-1 is made Rule of the Court. On the
basis of conditions of award decree is passed. Award Paper No. 3/B-1 shall be a
part of the decree. The plaintiff shall also be entitled to get from defendant
US$899,603.77 (US$ Eight Lakhs ninety nine thousand six hundred and three
point seventy seven only) along with 9% interest per annum till the last date of
realization." 24
As speci ed in the order of the Civil Judge of Dehra Dun, "Award Paper No. 3/B-1
shall be a part of the decree". This is a categorical decoration that the foreign court
adopted the ndings of facts and law of the arbitrator as contained in the latters Award
Paper. Award Paper No. 3/B-1, contains an exhaustive discussion of the respective claims
and defenses of the parties, and the arbitrator's evaluation of the same. Inasmuch as the
foregoing is deemed to have been incorporated into the foreign court's judgment the
appellate court was in error when it described the latter to be a "simplistic decision
containing literally, only the dispositive portion". 2 5
The constitutional mandate that no decision shall be rendered by any court without
expressing therein clearly and distinctly the facts and the law on which it is based does not
preclude the validity of "memorandum decisions" which adopt by reference the ndings of
fact and conclusions of law contained in the decisions of inferior tribunals. In Francisco v.
Permskul, 2 6 this Court held that the following memorandum decision of the Regional Trial
Court of Makati did not transgress the requirements of Section 14 Article VIII of the
Constitution:
"MEMORANDUM DECISION
After a careful perusal, evaluation and study of the records of this case,
this Court hereby adopts reference the ndings conclusions of law contained in
the decision of the Metropolitan Trial Court of Makati, Metro Manila, Branch 63
and finds that there is no cogent reason to disturb the same.
"WHEREFORE, judgment appealed from is hereby a rmed in toto." 27
(Emphasis supplied.)
This Court had occasion to make a similar pronouncement in the earlier case of
Romero v. Court of Appeals, 2 8 where the assailed decision of the Court of Appeals
adopted the findings and disposition of the Court of Agrarian Relations in this wise:
"We have, therefore, carefully reviewed the evidence and made a re-
assessment of the same, and We are persuaded, nay compelled, to a rm the
correctness of the trial court's factual ndings and the soundness of its
conclusion. For judicial convenience and expediency, therefore, We hereby adopt
by way of reference, the ndings of facts and conclusions of the court a spread in
its decision, as integral part of this Our decision." 2 9 (Emphasis supplied)
Hence, even in this jurisdiction, incorporation by reference is allowed if only to avoid the
cumbersome reproduction of the decision of the lower courts, or portions thereof, in
the decision of the higher court. 3 0 This is particularly true when the decision sought to
CD Technologies Asia, Inc. 2018 cdasiaonline.com
be incorporated is a lengthy and thorough discussion of the facts and conclusions
arrived at, as in this case, where Award Paper No. 3/B-1 consists of eighteen (18) single
spaced pages.
Furthermore, the recognition to be accorded a foreign judgment is not necessarily
affected by the fact that the procedure in the courts of the country in which such judgment
was rendered differs from that of the courts of the country in which the judgment is relied
on. 3 1 This Court has held that matters of remedy and procedure are governed by the lex
fori or the internal law of the forum. 3 2 Thus, if under the procedural rules of the Civil Court
of Dehra Dun, India, a valid judgment may be rendered by adopting the arbitrators ndings,
then the same must be accorded respect. In the same vein, if the procedure in the foreign
court mandates that an Order of the Court becomes nal and executory upon failure to pay
the necessary docket fees, then the courts in this jurisdiction cannot invalidate the order of
the foreign court simply because our rules provide otherwise.
The private respondent claims that its right to due process had been blatantly
violated, rst by reason of the fact that the foreign court never answered its queries as to
the amount of docket fees to be paid then refused to admit its objections for failure to pay
the same, and second, because of the presumed bias on the part of the arbitrator who was
a former employee of the petitioner.
Time and again this Court has held that the essence of due process is to be found in
the reasonable opportunity to be heard and submit any evidence one may have in support
of one's defense 3 3 or stated otherwise, what is repugnant to due process is the denial of
opportunity to be heard. 3 4 Thus, there is no violation of due process even if no hearing
was conducted, where the party was given a chance to explain his side of the controversy
and he waived his right to do so. 3 5
In the instant case, the private respondent does not deny the fact that it was noti ed
by the foreign court to le its objections to the petition, and subsequently, to pay legal fees
in order for its objections to be given consideration. Instead of paying the legal fees,
however, the private respondent sent a communication to the foreign court inquiring about
the correct amount of fees to be paid. On the pretext that it was yet awaiting the foreign
court's reply, almost a year passed without the private respondent paying the legal fees.
Thus, on February 2, 1990, the foreign court rejected the objections of the private
respondent and proceeded to adjudicate upon the petitioner's claims. We cannot
subscribe to the private respondent's claim that the foreign court violated its right to due
process when it failed to reply to its queries nor when the latter rejected its objections for
a clearly meritorious ground. The private respondent was afforded su cient opportunity
to be heard. It was not incumbent upon the foreign court to reply to the private
respondent's written communication. On the contrary, a genuine concern for its cause
should have prompted the private respondent to ascertain with all due diligence the
correct amount of legal fees to be paid. The private respondent did not act with prudence
and diligence thus its plea that they were not accorded the right to procedural due process
cannot elicit either approval or sympathy from this Court. 3 6
The private respondent bewails the presumed bias on the part of the arbitrator who
was a former employee of the petitioner. This point deserves scant consideration in view
of the following stipulation in the contract:
". . . It will be no objection to any such appointment that the arbitrator so
appointed is a commission employer (sic) that he had to deal with the matter to
which the supply or contract relates and that in the course of his duties as
CD Technologies Asia, Inc. 2018 cdasiaonline.com
Commission's employee he had expressed views on all or any of the matter in
dispute or difference." 3 7 (Emphasis supplied.)
Finally, we reiterate hereunder our pronouncement in the case of Northwest Orient
Airlines, Inc. v. Court of Appeals 3 8 that:
"A foreign judgment is presumed to be valid and binding in the country
from which it comes, until the contrary is shown. It is also proper to presume the
regularity of the proceedings and the giving of due notice therein.
"Under Section 50, Rule 39 of the Rules of Court, a judgment in an action in
personam of a tribunal of a foreign country having jurisdiction to pronounce the
same is presumptive evidence of a right as between the parties and their
successors-in-interest by a subsequent title. The judgment may, however, be
assailed by evidence of want of jurisdiction, want of notice to the party, collusion,
fraud, or clear mistake of law or fact. Also, under Section 3 of Rule 131, a court,
whether of the Philippines or elsewhere, enjoys the presumption that it was acting
in the lawful exercise of jurisdiction and has regularly performed its o cial duty."
39
Consequently, the party attacking a foreign judgment, the private respondent herein,
had the burden of overcoming the presumption of its validity which it failed to do in the
instant case.
The foreign judgment being valid, there is nothing else left to be done than to order
its enforcement, despite the fact that the petitioner merely prays for, the remand of the
case to the RTC for further proceedings. As this Court has ruled on the validity and
enforceability of the said foreign judgment in this jurisdiction, further proceedings in the
RTC for the reception of evidence to prove otherwise are no longer necessary.
WHEREFORE, the instant petition is GRANTED, and the assailed decision of the Court
of Appeals sustaining the trial court's dismissal of the OIL AND NATURAL GAS
COMMISSION's complaint in Civil Case No. 4006 before Branch 30 of the RTC of Surigao
City is REVERSED, and another in its stead is hereby rendered ORDERING private
respondent PACIFIC CEMENT COMPANY, INC. to pay to petitioner the amounts adjudged
in the foreign judgment subject of said case.
SO ORDERED. LLjur
Footnotes
1*. Supply Order Contract, ANNEX "C" to PETITION in G.R. No. 114323, p. 5; Rollo, p. 114.
Note: The contract and the foreign judgments or awards by the Indian courts follow the
British spelling of words for which sic will no longer be indicated.
2. Arbitral Award dated July 23, 1988, ANNEX "D" of the Petition, p. 17; Rollo, p. 143-144.
3. DECISION in CA-G.R. CV NO. 37080 promulgated on October 29, 1993, p. 10; Rollo, p.
103; RTC Records, pp. 143-144.
34. Korean Airlines Co., Ltd. vs. Court of Appeals, 247 SCRA 599, 603 [1995].
35. Roces vs. Aportadera, supra, p. 114; Stayfast Sunset View Condominium Corporation
vs. NLRC, 228 SCRA 466 [1993]; Villareal vs. Court of Appeals, 219 SCRA 292 [1993].
36. B.R. Sebastian Enterprises, Inc. vs. Court of Appeals, 206 SCRA 28 [1992].
37. Supply Order, Supra.