Professional Documents
Culture Documents
For
KIRU HEP (624 MW)
DISTRICT KISHTWAR, J&K
October, 2015
Prepared for:
Chenab Valley Power Projects Pvt. Ltd.
(A Joint Venture of NHPC Ltd., JKSPDC & PTC India Ltd.)
Prepared by:
in association with
University of Jammu
Jammu
Chenab Valley Power Projects (P) Ltd. Executive Summary of Kiru HEP
EXECUTIVE SUMMARY
1.1 INTRODUCTION
Kiru hydroelectric project is a run-of-the river project located on Chenab river in the
Kishtwar District of Jammu & Kashmir State being developed by Chenab Valley Power
Projects Private Ltd. (CVPP Pvt. Ltd.). The proposed project lies between Kirthai II Project to
its upstream and Kwar Project to its downstream. Project dam site will be located within a
very steep gorge section on River Chenab. The location of the project is shown in Figure 1.
The catchment area of Chenab at Kiru is 10225 sq km. The rain fed catchment area is 2375
sq.km whereas snow fed catchment area is 7850 sq.km. The entire course of the river, with
high cliffs, on both sides, is through a rugged and mountainous region Figure 2 show the
catchment plan of the project.
Kishtwar High Altitude National Park, is about 40 km from Kishtwar town. The southern
boundary of the KHANP is approximately at an aerial distance of 10.49 km away from the
proposed project, which does not fall within study area. The activities proposed shall have
no impact on the National park. The location of Kishtwar High Altitude National Park
(KHANP) in relation to Kiru HE Project is shown in Figure 3.
Scoping clearance of Kiru HEP for 600 MW installed capacity was accorded by Ministry of
Environment Forests and Climate Change (MoEF&CC), Government of India vide its letter
no. J-12011/32/2008-IA-1 dated 09.09.2008. Subsequently, scoping clearance was
accorded by MoEF&CC for Installed capacity of 624 MW vide letter no. J-
12011/32/2008/IA-I dated 28.09.2015.
Location of Power House On left bank of river Chenab near village Kiru
Nearest Rail head (Newly built) Udhampur
Nearest Airport/ Railhead Jammu
HYDROLOGY
Catchment area at diversion site 10225 km²
Design Flood (PMF) 10196 cumec
RESERVOIR
Full Reservoir Level (FRL) EL. 1515.0 m.
Maximum Water Level EL. 1515.0 m.
MDDL EL. 1504.0 m.
Gross storage at FRL 41.50 Mcum.
Live Storage 10.5 Mcum.
Area Under Submergence at FRL 1.03 km²
Length of Reservoir 6.5 km
DIVERSION TUNNEL
No., Diameter & Shape 1 No., 9.0 m., Horse-shoe shaped
Length 700.0 m
1033 cumec (Max observed non-monsoon
Diversion Discharge flood )
(Period 1st Oct to 15th May )
Invert level at entry EL. 1401.0 m
Invert level at exit EL. 1385.0m
Diversion Tunnel Gate 2 No. Vertical lift gate
Size of opening 2 Nos. (3.75 m. x 9.0 m.)
Gate Operating platform level EL 1430.0 m.
COFFER DAMS
Type Rockfill with central clay core
Top of upstream coffer dam EL 1418.0 m.
Top of downstream coffer dam EL 1400.0 m.
DAM
Type Concrete gravity Dam
Dam Top EL. 1517.0 m.
FRL EL 1515.0 m.
River Bed Level EL 1394.0 m +
Dam height (above River Bed / 123.0 m /135.0 m
deepest foundation level)
Length of dam at top 193.0 m
SPILLWAY
Lower Spillway
Type Orifice type
Width of spillway 62.0 m
No. of bays 4 Nos
Crest level of spillway EL 1467.50 m
No & Size of Opening 4 Nos, 9.0 m x 12.50 m
Upper Spillway
Type Crest Type Gated
Width of spillway 31.0 m
No. of Spillways 2 Nos
Crest level of spillway EL 1498.40 m
No & Size of Opening 2 Nos, 9.0 m x 16.60 m
OUTLET FOR ENVIRONMENTAL
RELEASE
Size of Gate 1.5 m x 2.0 m
Crest EL 1501.90
ENERGY DISSIPATION ARRANGEMENT
Figure 2: Map of catchment area showing the main river network, rain gauge and snow gauge stations, G&D sites
Figure 3: Map showing distance of Kishtwar High Altitude National Park from Kiru HE Project
1.4.1 Soil
On the basis of general analysis, the soils of the region have been classified as Sandy
skeletal, Loamy skeletal, Fine loamy, Course loamy and Loamy. The soil of the study area
have been analyzed in laboratory of the University of Jammu. By and large, soils are sandy
loam to loam and immature containing large proportion of un-decomposed organic
materials. Particularly, the valleys bearing agriculture and plantations have loose porous
soil with good drainage. The soils are porous to semi-porous and poor in soil humus.
Generally, soils of this area are alkaline in nature.
The pH of the soils of the project sites and the catchment is primarily alkaline with pH
ranging from 7.1 to 7.9 except during post monsoon where it is marginally acidic. The soils
Sodium followed the same trend as potassium, but was more consistent than potassium. It
ranged between 44.7 kg/ha to a maximum of 60.6 kg/ha. The perusal of the data on the
physico-chemical analysis of the soils reveals that the soils of the Chenab catchment at this
particular area are not very fertile because it is deficient in most of the essential elements
and categorise in medium fertility range. The organic carbon is high at dam location on
both the banks with medium values at most of the sites and very low quantity at
Pathernakki. The microelements like zinc, iron, copper and manganese are also present in a
quantity that can be considered as moderately sufficient in a mountainous soil.
A total of 366 plant species have been recorded from the Kiru project catchment/ study
area during the site visits. The plants described belong to three groups namely,
pteridophytes, gymnosperms and angiosperms distributed in 91 families. The maximum
number of the plant species belongs to the family Asteraceae family comprising 48
representative species followed by Fabaceae and Lamiaceae with 21 species each. 39 of
the families are monotypic in this area represented by a single species.
The avifaunal surveys showed the presence of swiftlets, doves, pigeons, crow, drongo,
thrushes, redstart, bushchat, tits, bulbul, myna’s, forktails, etc in the study area. The
sighting of Plumbeous Water Redstart and White Capped Water Redstart was made mostly
near the water bodies like river and nalas. While Pigeons Dove, Swifts and Martin were
sighted mostly near the settlements. A total of 38 species of birds belonging to 21 families
was compiled based upon sighting as well as secondary data.
During the survey Laudakia tuberculata (Kashmir Rock Agama), Euphlyctis cyanophlyctis
(Skittering frog), Asymblepharus ladacensis (Ladakhi Rock skink) were sighted in the study
area. Besides these no other herpetofauna species were encountred during the survey.
R S Envirolink Technologies Pvt. Ltd. & University of Jammu 10
Chenab Valley Power Projects (P) Ltd. Executive Summary of Kiru HEP
A total of 13 species of butterflies belonging to 5 families were recorded from the
surroundings of proposed project area.
The pH of the river water and its tributaries at different sites was almost neutral. Mostly
the pH fluctuated from 6.3 to 7.1. The alkalinity of the water was mainly due to the Ca++
bicarbonates, which were present in sufficient amounts at different sites (16.0 to 72.0
mg/L). On the seasonal basis it was higher in winter and lowest in monsoons followed by
summers. The Mg++ concentration ranged from 0.19 mg/L to 6.7.
Phosphates were quite low in almost all the sites. It ranged between 0.00 mg/L to 1.36 mg/L .
The nitrates exhibited almost the same trend as that of Phosphate ranged from 0.00 mg/L to
5.58 mg/L.
The temperature of the surface water (Chenab river and its tributries) fluctuated from 14.0C
to 22.3C during the sampling period. The pH of the surface water samples varies from 6.86
to 7.12. The pH value of Chenab river tributaries water indicates slightly acidic while water of
Chenab river is alkaline in nature. DO values ranged from 10.4 mg/l and 12.1 mg/l.
The Electrical conductivity is the capacity of water to conduct current. The highest
Conductivity value recorded was 186 μS/cm and lowest was 135 μS/cm. The TDS value
ranged from 83.7 mg/l to 115.3 mg/l at various sampling locations. Total hardness
concentration varies from 29 mg/l to 39 mg/l.
Chlorides vary considerably according to the mineral content of the earth. The
concentration was found between 5.2 mg/l and 7.23 mg/l at various sampling locations.
Nitrate concentration varies from 0.01mg/l to 0.38 mg/l and Phosphate concentration was
0.07mg/l to 0.48mg/l at various sampling locations.
The alkalinity of water is a measure of its capacity to neutralize acids. Alkalinity is a
measure of the water ability to absrob hydrogen ion (H+) without significant pH change.
Maximum concentration of total alkalinity was 71 mg/l and the minimum concentration
was 50 mg/l.
R S Envirolink Technologies Pvt. Ltd. & University of Jammu 11
Chenab Valley Power Projects (P) Ltd. Executive Summary of Kiru HEP
Total coliform in the sample water were absent at all sampling locations.
Macro-invertebrates
The macro-invertebrate fauna of the study area comprised 12 families. During the sampling
density of macro invertibartes was recorded from 161 to 229 ind./ m2 at all sampling sites.
The density of macro-invertebrate were observed to be less during monsoon season as
compared to summer and winter which may be due to fast flood and deposition of silt on
Substratum habitat of these fauna.
1.4.8 Fisheries
In the river Chenab, various Schizothoracids from the main river migrate for spawning in
turbulent streams. But establishing the dam at various part of river Chenab have blocked the
upstream migration of fish species. In section of Chenab where the project is proposed to
be constructed the species of the fishes like Schizothorax richardsonii, Glyptosternum
reticulatum, Oncorhynchus mykiss, Salmo trutta fario have been recorded.
At the time of peak construction work in the project, around 4200 persons are expected to
be engaged, including those from the local population. The congregation of large number
of construction workers during the peak construction phase may invite issues related to
sewage disposal, solid waste management, tree cutting to meet fuel requirement, etc.
For construction of main project components major activities are excavation, mechanical
and civil construction work. Excavation will have impact in terms of muck generation, quarry
excavation, road construction, use of various equipments, etc. leading to generation of
pollution in terms of emissions, wastewater, noise and solid waste.
Management of such impacts with operation control and appropriate pollution control
equipment is essential to minimize their effect on surrounding environment including local
population and wildlife and same is discussed in EMP. Additionally, proper setting of these
facilities shall also reduce the impact due to their location.
Total land requirement for the project has been assessed as 179.78 ha land comprising of
51.37 ha of state land, 82.05 ha of forest land and 46.36 ha private land. Major impact of
land acquisition is permanent change of land use, which is unavoidable. Additionally, land
acquisition has impacts on local population by way of loss of their agriculture land and
hence livelihood and also impact on flora and fauna by way of loss of forest land and
clearing of vegetation on acquired land.
The disposal and discharge of untreated wastewater and sewage can lead to water
pollution, resulting in increase in coliforms and other various pathogens, which can lead to
incidence of water borne diseases. In order to avoid any deterioration in water quality due
to disposal of untreated sewage from labour camps, appropriate sewage treatment
facilities will be commissioned in the labour camps.
The increased pressure may include uncontrolled logging, hunting of wildlife, non-timber
forest product collection, livestock husbandry, the cultivation in forest areas and forest fires.
The operation of various equipments will generate significant noise, especially during
blasting which may have adverse impact on fauna of the area. Increase in human
interference could have an impact on terrestrial ecosystem. The faunal species observed in
the project area are not migratory in nature. The proposed submergence area is not the
migratory route of wild animals.
Project has both positive and negative impact on socio-economic environment of the
project area during the project construction and operation phases. A number of marginal
activities and employment opportunities would be available to the locals during
construction phase. Education, medical facilities, transportation, road network and other
infrastructure will improve.
One critical impact of operation of hydropower projects is the decrease in flow in the
downstream stretch. Diversion of water from dams to powerhouse will make the
intermediate stretch of the river almost dry especially during lean season. Impact becomes
significant if several projects are planned in cascade and/or large headrace tunnels making
the intermediate stretch (es) very large. Low flow in the section of the river adversely
impacts the aquatic ecology including fish fauna, riparian vegetation and fauna dependent
on it; and downstream users.
In the present study, CAT Plan has been formulated for the free draining catchment upto
the proposed dam site on Chenab river. The total area of the free draining catchment is
285.75 sq km. The plan has been prepared as per the guidelines of Soil & Land Use Survey
of India (SLUSOI), Government of India.
A budgetary provision of Rs.798.59 lac has been kept for the Fishery Development and
Conservation Plan of the project.
The total budget in order to manage the solid waste generated from the construction
camp/colony, and also during operation phase has been proposed to Rs.199.40 lac.
Budgetary estimates for public health delivery system to be implemented for a period of 5
years have been worked out as Rs. 460.00 lac.
A total provision of Rs.75.00 lac has been assigned towards the arrangement of kitchen
fuel, and other facilities including establishment of community kitchen or canteens for the
migrant workers.
The estimated cost of the relocation and rehabilitation of excavated material will be
Rs.1483.67 lac.
1.6.8 Landscaping & Restoration for Quarry & Working Areas Plan
During the completion phase, a site specific plan shall be formulated considering the post
construction site condition. Landscaping and beautification shall be carried out around
dam, adit to powerhouse, quarry sites, muck dumping sites and at colonies, both of CVPP
and PAF’s. A garden shall be developed at dam location and a herbal park at colony area.
Plantation shall be carried out where ever possible according to the existing site condition.
Development of view point is feasible at one location viz. near Sin Gad.
The estimated cost for the restoration works, landscaping of quarry areas, road side
plantations, and creation of green belt around reservoir and colonies and working sites
would be Rs.331.60 lac.
Developer needs to ensure that all the required measures shall be implemented. A team to
monitor the implementation of mitigation measures, Institutional arrangement, essential
for ensuring the implementation of all the EMP components shall also be setup. Therefore,
an in-house dedicated team needs to be set up and budgetary provisions need to be kept
for outsourcing services of expert organizations.
A budget of Rs. 40 lac is proposed for out sourcing services of expert organization for
monitoring of air, noise and water quality parameters.
The cost of various engineering measures for prevention of slope failure and treatment of
landslides, involved in reservoir rim treatment plan is Rs. 416.77 lac.
The nursery development and plantation will be carried out under CAMPA. Half yearly
meeting shall be arranged with the monitoring team, executing authority and project
proponent in order to resolve any logistic problem in implementing the scheme. The
executing authority shall submit half yearly report to the project proponent, which will be
incorporated in the half yearly environmental progress report to be submitted to MoEF&CC
as per the guidelines.
For the development of Kiru Hydroelectric Project, land would be acquired for construction of
project components, submergence area, muck dumping, quarrying, construction camps and
colony, etc. Therefore, land requirement has been planned in a manner that out of total
land requirement of 179.78 ha for the project, only 46.36 ha is private land.
181 PAFs with a total population of 1009 from 4 villages have been identified as affected
families by the project authorities and same list have been used for socio-economic survey
and preparation of R&R Plan. Out of 181 PAFs, 140 belongs to ST category and 33 belongs
to SC category. A total of 92 PAFs shall be displaced and 4 PAFs shall lose their shops.
A sum of Rs. 75.00 lac has been allocated to implement various activities and programmes
envisaged under EMP.
The estimated total cost of execution of disaster management plan including the
equipment would be Rs. 125.50 lac.
Amount
S. No. Management Plans (Rs.in lac)
1 Biodiversity Conservation & Management Plan 139.50
2 Catchment Area Treatment Plan 1883.82
3 Fisheries Development Plan 798.59
4 Solid Waste Management Plan 199.40
5 Public Health Delivery System 460.00
6 Energy Conservation Measures 75.00
7 Muck Disposal Plan 1483.67
8 Landscaping and Restoration Plan 331.60
9 Air & Water Management Plan 40.00
10 Reservoir Rim Treatment 416.77
11 Compensatory Afforestation Plan 1036.00
12 Rehabilitation and Resettlement Plan 5800.00
13 Environmental Monitoring Programme 75.00
14 Dam Break Modeling 125.50
Total 12864.85