You are on page 1of 91

High Powered Committee

for Traffic Management of Delhi

Work Progress Presentation


29.03.2019

Ministry of Home Affairs: गह


ृ मंत्रालय
Implementation Plan (for 2019-2020)
As approved in the meeting held under the Chairmanship of Home Secretary on 9.10.2018

1. Improvements in Parking:
a. Nehru Place, Lajpat Nagar, CP, Bhikaji Cama Place, Karol Bagh
b. Notification of Parking Rules

2. Retrofitting of 100 intersections and 77 identified corridors

3. Street design, creation of pedestrian sidewalks and facilities for Non-Motorized Transport (NMT), and
public amenities of 70km of Dwarka streets (will also include some of the above junctions)

4. Addition of 3,000 buses to the existing fleet of buses


a. Incorporation of GPS devices in all buses and development of common mobile application/ user
information system.

5. IT based management of traffic


a. Approval of Integrated traffic management systems (ITMS)
b. Implementation of pilot projects
c. Linking of mobile phone with Vaahan database in respect of Delhi.

6. Multi-modal integration and management of traffic at Metro stations

2
Ministry of Home Affairs: गह
ृ मंत्रालय
Department Related Parliamentary Standing Committee
Meeting held on 14.12.2018

• Plan approved by HS was presented by MHA to DRPSC.


• Committee’s main observation were as follows:
 Plan to restrict # of vehicles entering Delhi everyday.
 Plan to restrict # of vehicles being registered in Delhi.
 Study on impact of non personal cars and taxi aggregators on the
flow of traffic.
 Impact assessment of Delhi metro in easing traffic situation in Delhi.
 No clear plan submitted by NDMC for creation of extra parking
spaces.
 Plans for fleet expansion of DTC and cluster buses was appreciated.
 Plan to create NMT infrastructure and cycle sharing in Dwarka needs
to be timelined.

3
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation Plan (for 1 year)
Meetings held
Sl. No. Chairmanship of No of Meetings.
1 Chief Secretary, Delhi 3
2 VC, DDA 2
3 AS(UT) 20
4 Commissioner, SDMC 3
5 Commissioner, NDMC 4
6 Special CP Traffic 5
7 With Knowledge Partner, MHA
SDMC 7
NDMC 9
DDA 11
Traffic Police 5
PWD 5
NHAI 2
EDMC 2
DMRC 6
Site Visits 42
4
Total number of meetings held 84+42 Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 1
Work Progress Presentation

Improvements in Parking

Nehru Place, Lajpat Nagar, CP, Bhikaji Cama Place, Karol Bagh
Notification of Parking Rules

5
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
South Delhi Municipal Corporation (SDMC)

Sl No Action Date of Completion


1 Action for MLCP /puzzle parking for 172 car December 2019
spaces
2 Plying of e-rickshaws between Lajpat Nagar Metro
Station to Market.

12 existing and 04 more to be added 31st March, 2019


3 Valet parking facility

05 existing and 05 more likely to be added 31st March, 2019


4 RFP for Streetscaping (for Parking and walkability South MCD needs to
improvements) including Parking mobile expedite and indicate
application timelines to the
Committee

6
Ministry of Home Affairs: गह
ृ मंत्रालय
12 E-Rickshaws
GPS Enabled
➔ Covering
Veer Savarkar Marg
Feroz Gandhi Road
Shiv Mandir Marg

➔ Connecting
Metro Station to Central Market.

Ministry of Home Affairs: गह


ृ मंत्रालय
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
Delhi Development Authority (DDA)
Bhikaji Cama Place
Sl. No. Action Date of Completion
1 Issuance of RFP for hiring of agency DDA needs to expedite
and indicate timelines to
2 Selection of agency the Committee
Provision of Multi Level car parking
3 Infrastructure at two locations for total 360 Aug 2020
ECS.
To facilitate pedestrian movement, provision
4 Oct 2020
of lifts, escalators, skywalk, toilets, Wi-Fi etc.
Provision of additional roads linking between
two ends of complex between Ring Road and
5 Dec 2020
August Kranti Bhawan for improving
movement of motorised transport

9
Ministry of Home Affairs: गह
ृ मंत्रालय
Existing barriers
Barrier

Plaza
M

Parking Parking

Dead Unsafe
Space
M

Ministry of Home Affairs: गह


ृ मंत्रालय
Car Parking

M OAT

Summer Winter
plaza plaza

Multi Level
Car Parking

Ministry of Home Affairs: गह


ृ मंत्रालय
12
Ministry of Home Affairs: गह
ृ मंत्रालय
Ministry of Home Affairs: गह
ृ मंत्रालय
13
Improvements in Parking
Delhi Development Authority (DDA)
Nehru Place
Sl. No. Action Date of Completion
1 Issuance of RFP DDA needs to expedite and
indicate timelines to the
2 Committee
Selection of agency

3 For convenience of metro user a skywalk Dec 2020


connectivity from Nehru Place metro station (on
purple line) to podium area of Nehru Place.
4 Up-gradation of circulation roads, footpath and Dec 2020
surface parking areas.
5 Provision of multi-level car parking infrastructure in Dec 2020
existing surface parking space at two locations for
total 820 ECS (450+370)
6 Improvement for pedestrians by way of lift, Dec 2020
escalators, toilet facilities, Wi-Fi, etc

14
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
Delhi Development Authority (DDA)
Nehru Place

Ministry of Home Affairs: गह


ृ मंत्रालय
Improvements in Parking
Delhi Development Authority (DDA)
Nehru Place

Ministry of Home Affairs: गह


ृ मंत्रालय
Improvements in Parking
Delhi Development Authority (DDA)
Nehru Place

Ministry of Home Affairs: गह


ृ मंत्रालय
Improvements in Parking
Delhi Development Authority (DDA)
Nehru Place

Ministry of Home Affairs: गह


ृ मंत्रालय
BEFORE 21
AFTER 22
BEFORE 23
AFTER 24
Metro skywalks to main entries to Nehru Place

East Plaza at
2nd floor level

North Plaza at
Ground level

Metro Line 2:
Concourse level
Ministry of Home Affairs: गह
ृ मंत्रालय
Removal of Street Parking and Public Space Improvement

Plot A
Plot A-3a Plot A-3b
Plot A-9

Plot A-4

Ministry of Home Affairs: गह


ृ मंत्रालय
26
Improvements in Parking
North Delhi Municipal Corporation (NDMC)
SHORT TERM PLAN
Sl Location ECS Target date of completion
No.
1 Surface parking at Old Rajender Nagar, 1,955 Currently being run by North
Karol Bagh, Surface parking at Shastri DMC.
Park, Karol Bagh,Ajmal Khan Road Part-
I,Ajmal Khan Road Part-II, Arya Samaj Road
Par-I, Arya , Saraswati Marg Samaj Road
Par-II, Gurudwara Road
2 Ajmal Khan Park Lawn No.3 275 15th April 2019
3 Parking site at Adjoining Office of Income 120 Timeline to be specified
Tax Department Jhandewalan Extension
4 MCD land on Bank Street Karol Bagh 180 15th April, 2019
5 The land near Jhandewalan Mata Mandir 80 Timeline to be specified
6 22-B Block MCD Land Dev Nagar Karol 100 15th April 2019
Bagh Behind Liberty Cinema
7 Bhuli Bhatiyari Road behind Bhagga Link 100 15th April 2019.
Road Petrol Pump
Total 855
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
North Delhi Municipal Corporation (NDMC)

No Parking

One-side Parallel Parking

Two-side Parallel Parking


PROPOSED TRAFFIC CIRCULATION PLAN (I/C ONE WAY TRAFFIC ROADS) IN KAROL BAGH AREA.
APPROVED BY UTTIPEC

30
31
32
32
33 33
34 34
35
36
Improvements in Parking
North Delhi Municipal Corporation (NDMC)
SHORT TERM PLAN – Pedestrianization Plan for Karol Bagh
Sl No. Location ECS Target date of completion
1 Operationalization of 4 # Parking lots 635 15th April, 2019
2 Notification of Ajmal Khan pedestrianization and 15th April, 2019
One-way Traffic circulation system by Traffic
Police
3 Implementation of signage for one-way traffic 15th April 2019
movement
4 Cordoning off of Ajmal Khan Road from Pusa 20th April 2019
Road to Arya Samaj Road and start of
pedestrianization.
5 Marking of parallel parking slots on 6 roads. 15th May 2019

6 Implementation of one-way traffic system by 30th May 2019


Traffic Police
7 Start of implementation of street upgradation of 1st July 2019
6 streets by PWD

37
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
New Delhi Municipal Council (NDMC)

Sl No Action Date of Completion


On-street parking to go to MLCP at Baba
1 May 2019
Kharajsingh Marg & Sarojini Market

3 Parking to be planned for all other choke points. Plans to be expedited


38
Ministry of Home Affairs: गह
ृ मंत्रालय
Notification of Parking Rules
• Hon’ble LG constituted a committee in July 2017 to formulate Draft Parking
Rules of Delhi under the Chairmanship of Transport Commissioner, GNCTD.
• The Committee presented the Draft Parking Rules in December 2018
• Hon’ble LG approved the Draft Parking Rules in Jan 2019 and sent for the
consideration and notification of Transport Minister, GNCTD
• Supreme Court under the Graded Response Action Plan for Clean Air of Delhi
asked for status of notification of Parking Rules in April 2019
• Supreme Court referred to EPCA to reconsider residential parking rules.
• Further action is awaited.

• EDMC is in the process of preparing Parking Policy.


• Other MCDs may take similar action

39
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvements in Parking
Actions Items Target Date of
Completion

1. South DMC to issue RFP for Streetscaping and Mobile Application April 2019
for Lajpat Nagar.
2. PWD to implement streetscaping in Lajpat Nagar. December
2019
3. North DMC to operationalize Karol Bagh parking sites and initiate
pedestrianization of Ajmal Khan Road and Parking Management. April 2019
Traffic Police to implement One-way traffic circulation system.
4. PWD to implement streetscaping of 8.1km of Karol Bagh roads. December
2019
5. NDMC to manage on-street parking at BKS Marg and Sarojini April 2019
Market, with the help of Traffic Police.

6. DDA to hire agency for implementation of Multi-Level Parking and May 2019
Pedestrian improvements and facilities.

7. MCDs to prepare their own Parking Policy. July 2019


40
Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 2
Work Progress Presentation

Retrofitting of 100 junctions and 77 identified corridors

41
Ministry of Home Affairs: गह
ृ मंत्रालय
Retrofitting of 100 junctions and 77 identified corridors
Public Works Department (PWD) and NHAI

Photograph of site visit

42
Retrofitting of 100 junctions and 77 identified corridors
Public Works Department (PWD), GNCTD

Sl. No. Action Items Target Date of Completion


1 Hiring of Consultants for design of PWD, GNCTD needs to expedite
100 junctions and indicate timelines to the
2 Design of junctions Committee

3 Execution of junctions

43
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress Report for 77 Corridors
Concerned Agencies: Delhi Police and PWD

Progress Made for retrofitting of 77 Corridors

Status of tasks Category ‘A’ Category 'B' Category 'C'


Completed 136 21 11

Regular & Continuous Action 37 10 7

Not found feasible 77 26 14


Under progress / pending 100 108 73
Total 350 165 105

 The matter is regularly taken up by the DCPs/Traffic Ranges, who are the convener of the
Task Force for their respective areas of jurisdiction, with the concerned agencies to
undertake the identified as per the specified timelines indicated by the agencies.

44
Ministry of Home Affairs: गह
ृ मंत्रालय
Categorization of 77 Corridors

The 77 corridors have been prioritised and categorized in


categories ‘A’ (28), ‘B’ (30) and ‘C’ (18) on the basis of
following principle:

 Volume: the number of road users utilizing the stretch of road or


corridor i.e. main arterial roads

 Visibility: the relative importance of the location of the corridors


and demonstration effect of the interventions on sub
arterial and other important roads

45
Ministry of Home Affairs: गह
ृ मंत्रालय
Aurobindo Marg : Adchini T Point
Improvement
Before Improvement After Improvement

Reduce Queue Length


Reduce Delay at Intersection
Better Safety

46
Ministry of Home Affairs: गह
ृ मंत्रालय
Improvement
Before Improvement After Improvement

Reduce Queue Length


Reduce Delay at Intersection
Better Safety

47
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress made for retrofitting of completed tasks on
Category ‘A’ corridor

Removal of obstructions on Aurobindo Closure of Unsafe Pedestrian Crossing


Marg

CNG
station
Relocated

CNG
Relocation of CNG Station opp. TB
Hospital to remove obstruction
Provision of iron grill on the median
due to queueing of vehicles
to avoid Pedestrian Jaywalking

Smooth flow of traffic Safety of road users


48
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress made for retrofitting of completed tasks on
Category ‘A’ corridor
Relocation of obstructions on Aurobindo Marg

1
1 Old location of Bus stop

2 New location of Bus stop

Existing Bus Stop 1 has been


moved to Bus stop 2 to avoid
vehicular conflicts

Smooth flow of traffic Safety of road users

49
Ministry of Home Affairs: गह
ृ मंत्रालय
Retrofitting of 100 junctions and 77 identified corridors
Actions Items Target Date of
Completion

1. Hiring of Consultants for design of junctions by PWD. May 2019

2. Implementation of 10 junctions by PWD. December


2019
3. Implementation of remaining 90 junctions by PWD. December
2020
4. Implementation of 3 junctions by NHAI December
2019
5. Implementation of 30 corridors December
2019
6. Implementation on remaining 47 corridors December
2020

50
Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 3
Work Progress Presentation

Complete Street Design

70km of Dwarka streets with pedestrian facilities, non-motorized


transport facilities and public amenities

51
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress Report on Dwarka
Complete Streets – DDA

9.5km of streets designed, and approved


by DDA. Implementation
to be started.
Dwarka Cycle Tracks and Footpath Improvements of 70 km
Concerned Agency: DDA

S. NO Item Target date


of completion

1. Preparation of Estimate for improvement of Metro Corridor of Sector- March 15th,


12, 13 and Marking of Cycle track for identification upto NSIT 2019
(Dwarka) (Estimated Cost: 6.50 Crores Approx)
2. Approval of Estimate April 30th
2019

3 Floating of Tender and award of work June 15th,


2019

4 Execution of Project work for Laying/ marking of cycle track for December
identification of cycle track for the stretch upto NSIT (Dwarka). 2019

5 Execution of 21km of cycle tracks and pedestrian walkway July 2020

6 Execution of remaining 40km of cycle tracks and pedestrian walkways July 2021

53
Ministry of Home Affairs: गह
ृ मंत्रालय
Dwarka Bicycle Infrastructure
10km street & 6 major Apartments Apartments

junctions in Phase 1
6.6 4.3 10.5 10.5 4.0 6.4
1.4 0.7
45.1
Existing 45m Road Section Service Footpath Carriageway Median Carriageway Footpath Service Footpath
Lane Lane

Apartments Apartments

4.5 2.5 4.3 10.5 10.5 4.0 2.5 4.5


1.4 0.1
45.1
Service Cycle Footpath Carriageway Median Carriageway Footpath Service
Lane Lane/ Lane
Proposed 45m Road Section Track

54
Ministry of Home Affairs: गह
ृ मंत्रालय
Large left turns, unsafe
pedestrian crossing

Large left turns, high speed of


vehicles

Junction unsafe for crossing of


cyclists

Left turn starts from Queue


Space of vehicles and therefore
clogged.

Ministry of Home Affairs: गह


ृ मंत्रालय
Large pedestrian crossings
from island to island with
refuge in the center for waiting

Raised slip lanes for safe


movement of vehicles,
pedestrians and cyclists
Entry to slip lane starts before
Queue Space, doesn’t clog left
turn

Improved signage
and road markings

Ministry of Home Affairs: गह


ृ मंत्रालय
Dwarka Bicycle Sharing
Station Coverage Map
250 stations | 2000 bicycles

57
Dwarka Bicycle Sharing System
Concerned Agency: DDA

S. NO Item Time Scheduled

1 Submission of RFP for Cycle Sharing in the Office of Chief Submitted on 20th
Engineer. Feb 2019

2. Approved of RFP Likely by competent authority 10th March 2019

3. Likely Date of receipt of tenders 30TH April 2019

4 Likely Date of Award of Tenders 31st may 2019

5 Likely date of start of Cycle sharing 30th Nov 2019

58
Ministry of Home Affairs: गह
ृ मंत्रालय
Complete Street Design - Dwarka
Actions Items Target Date of
Completion

1. RFP for Cycle Sharing to be floated and Service Provider to be June 2019
selected.

2. Commencement of Bicycle Sharing Services in Dwarka. December


2019
3. Selection of implementation agency for construction of bicycle May 2019
tracks and footpath improvements in Phase 1 streets (9km), which
include Sector 12 and 13 Metro stations.

4. Implementation of 9km of streets with cycle tracks and footpaths. December


2019
5. Implementation of all 45m and 60m roads with cycle tracks and July 2020
footpaths, rest of the 21km.

59
Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 4
Work Progress Presentation

Addition of 3000 buses to existing fleet

Incorporation of GPS devices in all buses and development of


common mobile application/ user information system.

60
Ministry of Home Affairs: गह
ृ मंत्रालय
Augmentation of City Bus Fleet

Sl. No Type & Number of buses Action Taken Target date


of
completion
1 1000 Standard Floor height Non- Agreement Signed August 2019
AC CNG buses
2 1000 Low Floor height CNG AC Technical Bids opened. Financial December
buses Proposal to be opened after MCoC 2019
3 1000 Low Floor height AC Pure Tenders have been floated, to be opened 10% in July
electric buses after MCoC 2019
4 ONE DELHI App – A Common DIMTS to developed App on pro-bono To be
Mobility App for Public Transport basis. Transport department is in expedited
users in Delhi process of acquiring the ownership of the and
app from DIMTS timelimes
5 Uploading of one Delhi app to Google specified
play store by transport department

61
Ministry of Home Affairs: गह
ृ मंत्रालय
Addition of 3000 buses
Actions Items Target Date of
Completion

1. Deployment of 1000 Standard Floor Non-AC and 1000 Low-floor December


CNG AC buses 2019

2. Deployment of 1000 Electric buses. December


2019
3. Operationalization of ONE DELHI mobile application by Transport July 2019
Department, GNCTD.

62
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress Report for Bus purchase
Concerned Agency: Transport Department

Plan to restrict number of vehicles registered in Delhi


1. Hon’ble Supreme Court has directed to augment buses to 11,000 from current 5,500. The
restrictions may be applied once the bus fleet is augmented to the required number.

Plan to restrict number of vehicles entering in Delhi


1. Restriction not legally permissible as informed Special Commissioner of Police (Traffic).
Traffic Police is already diverting the non-destined traffic.

Study on the impact of non-personal cars and taxi aggregators on flow of traffic
1. DIMTS was requested to carry out the study. Data awaited from Traffic Police, Transport
Department and Local bodies as requested by DIMTS.

63
Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 5
Work Progress Presentation

IT Based Management of Traffic

Approval of ITMS
Implementation of pilot projects

64
Ministry of Home Affairs: गह
ृ मंत्रालय
Progress Report on ITMS – Delhi Police

Decision Taken in the meeting chaired by HS on : Hiring of consultant, preparation


and approval of Detailed Project Report (DPR) by August 2019.

Progress Made for ITMS:


1. Tendering process has been initiated. Pre-bid meeting held on 07.01.2019.
2. Bids opened on 12.02.2019.
3. Purchase meeting held on 07.03.2019
4. Shortcoming of documents and other formalities under progress
5. Consultant expected to be hired by August, 2019 by floating RFP.

65
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation of pilot projects
1. Installation of 3D Radar Based Red Light
Violation Detection Camera (RLVD) (at 24
junctions - 96 Nos.) and Gantry-Mounted
Radar based Over Speed Detection
Camera (at 100 locations on major roads)
 Estimated cost - Rs. 20 Crores for RLVD
cameras and Rs. 27 Crores for Gantry
Mounted Radar based Over Speed
Detection cameras (Total cost Rs. 47
Crores)
 Work under progress for Central Control
Room , Speed Detection Cameras at 25
locations and RLVD cameras at 1 junction
 40% of the project cost to be utilized by 31st
March, 2019
 Remaining 60% shall be utilized by July,
2019 66
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation of pilot projects
2. Installation of RLVD and Speed Check Camera
(under CSR project by Maruti Suzuki Ltd.)

 10 signalized junctions on Ring Road from Dhaula


Kuan to Sarai Kale Khan
 Estimated cost - Rs. 15 Crores
 Project completed
 Issuance of notices u/s 133 MV Act, 1988 started
against traffic violators through SMS

Ministry of Home Affairs: गह


ृ मंत्रालय
Implementation of pilot projects
3. Acquisition of Portable Tripod
Mounted Radar
(Speed Guns - 55 Nos.)

 Estimated cost - Rs. 5.5 Crores


 Supply order placed to the firm on
07.02.2019
 Supply of 20 Laser Guns received
on 16.03.2019
 Remaining 35 Laser Guns shall be
received by 20.03.2019
 Technical inspection for acceptance
to be undertaken
 The entire purchase shall be
completed by 25th March, 2019
68
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation of pilot projects

4. Implementation of New E-challan


System (in collaboration with NIC)
 Estimated cost - Rs. 19 Crores
 Tender opened on 17.01.2019
 Revised tender opened on 22.01.2019
 Supply order for hand held devices
(HHDs) and other accessories placed by
NIC to the vendor
 Customization of software under progress
 The entire project to be completed by
May, 2019

69
Ministry of Home Affairs: गह
ृ मंत्रालय
IT-based Management of Traffic

• Total No. of cars in Delhi is 1.17 crore of which 80 lakhs are less than 15 years
old. The remaining have been declared unfit for plying by the EPCA.
• NIC in Vaahan database has 28 lakh mobile numbers. Therefore, 52 lakh
vehicles do not have mobile number data captured.
Sl. No Action Taken Target date of
completion
1 MORTH to amend CMVR 1989 to make mobile number capture ?
mandatory
2 NIC to validate all the 28 lakh mobile numbers July 2019
3 Transport Department, GNCTD to procure the remaining mobile July 2019
numbers using PUCC and online form
4 NIC to validate the remaining numbers December 2019
5 IRDA/ IIB to examine the issue of linking premia with traffic July 2019
violations
6 Insurance companies to implement the premium escalation formula December 2019

70
Ministry of Home Affairs: गह
ृ मंत्रालय
IT-based Management of Traffic
Actions Items Target Date of
Completion

1. Installation of 3D Radar Based Red Light Violation Detection July 2019


Camera (RLVD) (at 24 junctions - 96 Nos.) and Gantry-Mounted
Radar based Over Speed Detection Camera (at 100 locations on
major roads)
2. Acquisition of portable tripod mounted radar March ’19
3. Implementation of new e-Challan system May 2019

4. MoRTH to amend CMVR 1989 to make mobile number capture December


mandatory 2019

5. NIC to validate all the 28 lakh mobile numbers July 2019


6. Transport Department, GNCTD to procure the remaining mobile July 2019
numbers using PUCC and online form. NIC to validate the
numbers.
7. Insurance companies to implement the premium escalation December
formula. 2019
71
Ministry of Home Affairs: गह
ृ मंत्रालय
Powered Committee for Traffic Management of Delhi
Action Item No. 6
Work Progress Presentation

Multi-Modal Integration and Management of Traffic


and Parking at Metro Stations

72
Ministry of Home Affairs: गह
ृ मंत्रालय
Metro Phase I: Length- 65.1 km; 58 Stations

73
Metro Phase I: Length- 65.1 km; 58 Stations
Metro Phase II: Length- 124.9 km; 87 Stations

74
Metro Phase I: Length- 65.1 km; 58 Stations
Metro Phase II: Length- 124.9 km; 87 Stations
Metro Phase III: Length- 159.5 km; 109 Stations
N Phase I+II+III = 349.5 km; 254 Stations

75
Metro Phase I: Length- 65.1 km; 58 Stations
Metro Phase II: Length- 124.9 km; 87 Stations
Metro Phase III: Length- 159.5 km; 109 Stations
N Phase I+II+III = 349.5 km; 254 Stations
Metro Phase IV: Length- 61.7 km; 46 Stations

Phase I+II+III+IV = 411.2 km; 300 Stations

Note:
- Total Phase IV proposed is 104 km (including 61.7 km approved for implementation)
76
- Rapid Metro (Gurugram) and Aqua Line (Noida) are additional integrated network corridors.
MMI and Parking Management at Metro Stations
• In the meeting held on 17.01.2019, CS, GNCTD directed the MCDs to
form committees under the Chairmanship of Deputy Commissioners of
various zones along with officials from DMRC, PWD, Traffic Police, DDA
and Knowledge Partners.
• Committees chaired by DCs of respective zones made joint site visits to
Phase 3 Metro stations and conducted detailed audits.
• Audit completed of of 35 Phase 3 metro stations out of 68.
• DMRC to hire consultants for Detailed MMI plans for 30 Metro Stations
of Phase 1 & 2
• DMRC to prepare detailed drawings for UTTIPEC approved MMI plans
of Phase 3 stations for implementation to be carried out by PWD and
DDA.

77
Ministry of Home Affairs: गह
ृ मंत्रालय
Name of station Issues

Implementation Pick-up drop off Cycle Stand, Drainage /


Footpath/plaza/ Road marking and Encroachment and Road & junction
status of UTTIPEC and pre-paid Public toilet & sanitation /
park signage illegal parking improvement
Plan system hawking electrical services

East Delhi Municipal Corporation - Shahdara (South) Zone

East Azad Nagar N.A. PWD EDMC & DMRC DMRC & DTIDC EDMC PWD EDMC BSES

Krishna Nagar N.A. DMRC & PWD EDMC & DMRC DMRC N.A. N.A. N.A. N.A.

DMRC, EDMC &


Karkardooma Court N.A. N.A. DMRC N.A. N.A. EDMC N.A.
Traffic Police
DMRC & Traffic
Karkardooma N.A. PWD RP cell EDMC DMRC EDMC PWD N.A.
Police
I.P. Extension DMRC DMRC N.A. DMRC N.A. DMRC EDMC N.A.

Mandawali N.A. PWD N.A. PWD & DMRC N.A. N.A. EDMC N.A.

West Vinod Nagar N.A. N.A. N.A. PWD & DMRC N.A. N.A. EDMC EDMC
DMRC & Delhi
Trilokpuri N.A. N.A. N.A. DMRC N.A. PWD EDMC
Police

Mayur Vihar Pocket 1 DMRC/DDA N.A. N.A. PWD & DMRC N.A. N.A. EDMC N.A.

North Delhi Municipal Corporation - Keshvpuram Zone


DMRC and Traffic
Netaji Subhash Place DMRC N.A. DMRC DMRC N.A. N.A. DMRC
Police
Shalimar Bagh
DMRC N.A. Traffic Police DMRC & PWD N.A. PWD & DMRC N.A. N.A.
(Wazirpur side)
Name of station Issues

Implementation Pick-up drop off Cycle Stand, Drainage /


Footpath/plaza/ Road marking and Encroachment and Road & junction
status of UTTIPEC and pre-paid Public toilet & sanitation /
park signage illegal parking improvement
Plan system hawking electrical services

South Delhi Municipal Corporation - Central Zone, Lajpat Nagar

Lajpat Nagar N.A. N.A. Traffic Police DMRC & PWD) N.A. DMRC DMRC N.A.

South Extension DMRC DMRC DMRC DMRC & PWD N.A. PWD DMRC N.A.

Hazrat Nizamuddin N.A. N.A. N.A. N.A. N.A. N.A. N.A. N.A.

Vinobapuri N.A. N.A. N.A. PWD N.A. PWD N.A. N.A.

Nehru Enclave N.A. N.A. DMRC DMRC N.A. N.A. DMRC & SDMC N.A.

Kalkaji Mandir N.A. DMRC N.A. DMRC N.A. N.A. N.A. N.A.
Traffic Police &
Okhla NSIC N.A. PWD DMRC N.A. PWD N.A. N.A.
PWD
SDMC & Delhi
Jamia Millia Islamia N.A. N.A. N.A. DMRC N.A. N.A. N.A.
Police
PWD, Local Police DMRC & Traffic PWD, Local Police
Okhla Vihar N.A. N.A. N.A. SDMC DMRC
& Traffic Police Police & Traffic Police
Jasola Vihar N.A. N.A. N.A. N.A. N.A. N.A. N.A. N.A.
Flood and
PWD, DMRC & Irrigation Dpt. UP
Kalindi Kunj N.A. PWD N.A. N.A. N.A. SDMC
Traffic Police Gov, PWD, SDMC
& DMRC
79
Name of station Issues

Implementation Pick-up drop off Cycle Stand, Drainage /


Footpath/plaza/ Road marking and Encroachment and Road & junction
status of UTTIPEC and pre-paid Public toilet & sanitation /
park signage illegal parking improvement
Plan system hawking electrical services

South Delhi Municipal Corporation - Central Zone, Lajpat Nagar


PWD, NDMC,
DMRC & Traffic
INA DMRC & Traffic N.A. DMRC N.A. PWD SDMC N.A.
Police
Police
Ashram N.A. PWD N.A. DMRC N.A. N.A. SDMC DMRC

ITO N.A. PWD SDMC DMRC N.A. N.A. SDMC N.A.

South Delhi Municipal Corporation - South Zone, Green Park

Greater Kailash N.A. PWD N.A. PWD & DMRC N.A. DMRC N.A. N.A.
SDMC, Traffic
PWD, SDMC &
Chirag Delhi N.A. PWD & SDMC DMRC Police & Delhi PWD N.A. M-II, SDMC
DMRC
Police
Panchsheel Park N.A. PWD & DDA PWD & DDA DEMS & SDMC SDMC PWD & DDA N.A. N.A.
Traffic Police &
Hauz Khas N.A. PWD N.A. N.A. SDMC N.A. N.A.
PWD
IIT N.A. PWD N.A. N.A. N.A. PWD N.A. N.A.
SDMC & Traffic
Munirka N.A. N.A. PWD SDMC & PWD PWD & DMRC SDMC & PWD SDMC & PWD
Police
Kailash Colony N.A. PWD SDMC & PWD PWD N.A. PWD Traffic Police N.A.
Sh. Anuj
Malhotra, Traffic
Vasant Vihar N.A. PWD N.A. N.A. N.A. N.A. PWD
police, PWD &
DMRC
Name of station Issues
Implementation Pick-up drop off Cycle Stand, Drainage /
Footpath/plaza/ Road marking and Encroachment and Road & junction
status of UTTIPEC and pre-paid Public toilet & sanitation /
park signage illegal parking improvement
Plan system hawking electrical services
South Delhi Metro Station, West Zone
DMRC & Traffic
Mayapuri DMRC PWD DMRC & PWD N.A. PWD SDMC N.A.
Police
Rajouri Garden N.A. DMRC N.A. DMRC N.A. DMRC SDMC N.A.
ESI N.A. N.A. N.A. DMRC N.A. PWD SDMC N.A.
Punjabi Bagh PWD N.A. N.A. N.A. N.A. PWD N.A. N.A.

PWD, DMRC &


Janakpuri West N.A. N.A. DMRC N.A. N.A. N.A. N.A.
Traffic Police

81
82
83
CURRENT STATUS MMI PLAN -
KASHMERE GATE
` CONSTRUCTED ON SITE

NOT CONSTRUCTED ON SITE

CURRENT STATUS

Components of MMI Status of Implementation

Drop off & Pick Up point Implemented

Gokale Marg
Pedestrian Zone Partially Implemented
Bus stop/ Bus Bay Partially Implemented
Table Top Not Implemented
Traffic calming Not Implemented

Park & Ride Facility Implemented


Public toilets Partially Implemented
Kiosks Not Implemented
LandscapedArea Not Implemented
Signage Not Implemented
Summary 84
Approx. completion % 25%
85
CURRENT STATUS MMI PLAN – KARKARDUMA
COURT
CONSTRUCTED ON SITE

NOT CONSTRUCTED ON SITE

Maharaja Surajmal Marg Maharaja Surajmal Marg

CURRENT STATUS
Components of MMI Status of Implementation
Drop off & Pick Up point Implemented
Pedestrian Zone Implemented
Bus stop/ Bus Bay Not implemented
Table Top Not Implemented
Traffic calming Not Implemented
Park & Ride Facility Not implemented

Public toilets Not Implemented


Kiosks Not Implemented
LandscapedArea Not Implemented
Signage Not Implemented
Summary
86
Approx. completion % 25%
87
CURRENT STATUS MMI PLAN – MAYAPURI
CONSTRUCTED ON SITE

NOT CONSTRUCTED ON SITE

CURRENT STATUS

Components of MMI Status of Implementation

Drop off & Pick Up point Implemented


Pedestrian Zone Partially implemented
Bus stop/ Bus Bay Not Implemented
Table Top Not Implemented
Traffic calming Not Implemented
Park & Ride Facility Implemented
Public toilets Not Implemented
Kiosks Not Implemented
LandscapedArea Not Implemented
Signage Not Implemented
Summary 88
Approx. completion % 25%
CURRENT STATUS MMI PLAN – SOUTH
EXTENSION
CONSTRUCTED ON SITE

NOT CONSTRUCTED ON SITE

Mahatma Gandhi Marg

CURRENT STATUS

Components of MMI Status of Implementation

Drop off & Pick Up point Implemented


Pedestrian Zone Implemented
Bus stop/ Bus Bay Not Implemented
Table Top Not Implemented
Traffic calming Not Implemented
Park & Ride Facility Not Implemented
Public toilets Not Implemented
Kiosks Not Implemented
LandscapedArea Not Implemented
Signage Not Implemented
Summary
89
Approx. completion % 25%
MMI for Metro Stations
Actions Items Target Date of
Completion

1. Hiring of Consultants to design MMI for Phase 1, 2 & 3 Metro May 2019
Stations by DMRC.

2. Completion of design process of MMI Plans by hired consultants October


and approvals by UTTIPEC 2019

3. Completion of works as per audit carried out under the June 2019
committees chaired by Zonal DCs of respective MCDs, by DMRC,
DDA, Transport Department, BSES, PWD, MCDs, NDMC, Traffic
Police and Delhi Police.

4. Initiation of execution works by respective agencies – DMRC, PWD November


and DDA. 2019

90
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation Plan (for 2021-2025)
Public Transport Improvements

Ministry of Home Affairs: गह


ृ मंत्रालय
Implementation Plan (for 2021-2025)
Roll out of ITMS

NMT and Parking improvements

92
Ministry of Home Affairs: गह
ृ मंत्रालय
Implementation Plan (for 2021-2025)
Junction improvements

Freight Management

Under and Over bridges

93
Ministry of Home Affairs: गह
ृ मंत्रालय
Thank you