Professional Documents
Culture Documents
Earned Value
Year
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Planned value
Accumulated planned value PV $ - $ - $ - $ - $ - $ - $ - $ - $ -
Actual Cost
Accumulated Actual Cost AC $ - $ - $ - $ - $ - $ - $ - $ - $ -
Percentage of progress achieved during the month %comp
Earned value from work conducted $ - $ - $ - $ - $ - $ - $ - $ - $ -
Earned value from accumulated work conducted EV $ - $ - $ - $ - $ - $ - $ - $ - $ -
$0
$0
CPI lower than 1, the project is overspent
CPI greater than 1, the project has spent less than budgeted
$-
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12
SPI lower than 1, the project is delayed
SPI lower than 1, the project is ahead of schedule
Date on which earned value is reported.
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
PV
AC
EV
Earned Value
Project: Educational Support
ID: HT2011-12
Start date 6/1/2011 Finish Date: 6/30/2013 Cut-off date:
Year
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Planned value $ 20,000 $ 40,000 $ 60,000 $ 80,000 $ 120,000 $ 140,000 $ 160,000
Accumulated planned value PV $ 20,000 $ 60,000 $ 120,000 $ 200,000 $ 320,000 $ 460,000 $ 620,000
Actual Cost $ 20,000 $ 20,000 $ 40,000 $ 60,000 $ 80,000 $ 100,000 $ 150,000
Accumulated Actual Cost AC $ 20,000 $ 40,000 $ 80,000 $ 140,000 $ 220,000 $ 320,000 $ 470,000
Percentage of progress achieved during the month %comp 1.5% 3.0% 4.0% 6.0% 8.5% 10.0% 12.0%
Earned value from work conducted [EV= % comp x BAC] $ 18,300 $ 36,600 $ 48,800 $ 73,200 $ 103,700 $ 122,000 $ 146,400
Earned value from accumulated work conducted EV $ 18,300 $ 54,900 $ 103,700 $ 176,900 $ 280,600 $ 402,600 $ 549,000
$600,000
CV negative, the project is overspent
CV positive, the project has spent less than budgeted
$400,000
SV negative, the project is delayed
SV positive, the project is ahead of schedule $200,000
Year
Month 8 Month 9 Month 10 Month 11 Month 12
$ 180,000 $ 180,000 $ 120,000 $ 80,000 $ 40,000
$ 800,000 $ 980,000 $ 1,100,000 $ 1,180,000 $ 1,220,000
PV AC
EV