QUOTATION
No: 002/LTG/Q-MPP/RF/III/20
This quotation is subject to the terms and conditions as stipulated in this letter, unless otherwise specifically agreed in separate contract
CLIENT: Date : March 27th, 2020
PT. PEMBANGUNAN PERUMAHAN (PERSERO), TBK. Subject : Quotation of Feeder Cable PJI Perimeter
PJU Parimeter - NYIA, KULONPROGO

Attn : Bpk. Untung Susilo/ Ferdian From : KKH


Phone : Cc :
Fax : Attached : BOQ
Email : Email : kukuh@mandalapp.com

Dear Pak Untung/ Ferdian,


Kindly please find our quotation as following:

UNIT PRICE UNIT PRICE


NO. DESCRIPTION VOL UNIT
(IDR) (IDR)

PEKERJAAN PENGADAAN DAN PEMASANGAN KABEL FEEDER PJI


1 1 ls 576,564,000.00 576,564,000.00
PARIMETER YIA

TOTAL (IDR): 576,564,000.00


PPN 10% (IDR): 57,656,400.00 +
GRAND TOTAL (IDR): 634,220,400.00

1. TERM & CONDITIONS


1.1. Price are exclude 10% PPN & PPH
1.2. Term of Payment:
- 50%, DP 50% after finished

1.3. Services Condition:


- Delivery point: Franco on Site, NYIA, Kulonprogo, Yogyakarta

2. VALIDITY OF OFFER
2.1. This quotation valid for 1 (one) week from the date of this letter, afterward we reserve the right to review our price structure.

Should you have any further questions, please feel free to contact us. We are looking forward for your feedback. Thank you.

Sincerely Yours,

legitimate w/o signature

KUKUH PANUWUN
+62 81286456242
KEGIATAN : PEKERJAAN PENGADAAN DAN PEMASANGAN KABEL FEEDER PJI PARIMETER YIA
PELAKSANA : PT. PEMBANGUNAN PERUMAHAN (PERSERO), TBK
LOKASI PROYEK : KULONPROGO, YOGYAKARTA

Harga Satuan Jumlah Harga Total Harga Material &


No. Uraian Sat Volume Material Upah Material Upah Upah
Rp Rp Rp Rp Rp
1 2 3 4 5 6 7=4x5 8=4x6 9=7+8

1 Pengadaan dan penarikan kabel NYFGBY 4 x 50 mm2 unit 1150 377,000.00 52,000.00 433,550,000.00 59,800,000.00 493,350,000.00

2 Galian dan urugan termasuk pelindung kabel unit 1150 72,360.00 83,214,000.00 83,214,000.00

TOTAL F 576,564,000.00
Analisa Harga Satuan

Pengadaan dan penarikan kabel NYFGBY 4 x 50 mm2


No Uraian Satuan Qty Harga Total Harga
a Kabel NYFGBY 4 X 50 mm2 m 1 285,000 285,000
b Transport LS 1 5,750,000 5,000
Margin 87,000
total material 377,000
c Jasa Penarikan kabel m 1 52,000 52,000

Galian dan urugan termasuk pelindung kabel


No Uraian Satuan Qty Harga Total Harga
a upah gali dan urugan kabel m 1 54,300 54,300
b batu bata bh 5 1,200 6,000
Total Modal 60,300
Margin 12,060
Total Harga terevaluasi 72,360