Professional Documents
Culture Documents
PROJECT MANAGEMENT
LECTURE 8
Ir Ishak Arshad
1
Project Management
4/29/2014 2
Project Management
CO 2 :
• Able to evaluate elements of project management and cost
for civil engineering work.
4/29/2014 3
Project Management
As a contractor for a project, you have to target
your project to complete on time, with
acceptable quality and to get reasonable profit.
• Making profit
• Finishing on time - TIME
• Constructing within budgets - COST
• Finishing the projects safely - SCOPES
• Delivering quality projects - QUALITY
• Getting new projects
4/29/2014 5
Monitoring & Controlling A
Construction Project
Defn:
Monitoring and controlling are processes
required to track, review and regulate the
progress and performance of the project.
(to track = to follow ,to review = to go over, to regulate = to put in order)
2. What is monitoring ?
3. What is controlling ?
4/29/2014 8
Monitoring & Controlling A
Construction Project
To monitor Project Objectives & “Triple
Constraints” :
• Performance – to complete scopes of the
project
• Time
• Cost
With Quality
4/29/2014 9
Monitor & Control Project Work
• The process of tracking, reviewing and regulating
the progress to meet the performance objectives
defined in the project m’ment plan.
• Monitoring – collecting , measuring & distributing
performance information . Assessing
measurement & trends for process improvement
• Controlling– determine corrective or preventive
action or preplanning & following up actions to
resolve performance issue (to align with the
expected project performance)
• Monitoring & Control Project Work Process is
concerned with:
- Comparing actual project performance vs the
PMP
- Assessing performance – any corrective/
preventive action need to be done
Monitoring & Controlling A
Construction Project
1) Performance/scope
Some factors affecting project performance:
• Unexpected technical problems – eg
nature of the project beyond expectation
• Insufficient resources when needed
• Unexpected technical difficulties – eq due
to site condition or soil condition
• Client requires changes –ok with EOT &
4/29/2014
additional cost 11
Performance- Scope Control
Monitoring status of the project and managing
changes to work program
Activities:
• Work performance measurements – variance analysis
• Change requests – need client approval. Avoid implementing
unapproved changes.
• Project Management Plan (Programs) updates with all
approved changes
• Project document updates – updating drawings due to
changes done
Outputs:
• Work performance measurements
• Change requests
• Project management plans
• 4/29/2014
Projects documents updates 12
Monitoring & Controlling A
Construction Project
2) Time- schedule
• Technical difficulties take longer than planned
to solve
• Initial time estimate is not enough
• Task sequencing is incorrect – incorrect timing
• Required inputs of matl, personnel,
machineries are unavailable when needed –
idling & wasting of time – require extra time
• Client want changes and need rework
• New
4/29/2014
Government regulation 13
Time- Schedule Control
Monitoring status of the project to update
project progress and managing changes to the
schedule baseline
Activities:
• Work performance measurements
• Change requests – thru approved process
• Project Management plan updates
• Project document updates
Outputs:
• Work performance measurements
• Change requests
• Project management plans
• Projects documents updates
4/29/2014 14
Monitoring & Controlling A
Construction Project
3) Cost:-aspects that may increase project cost!
• Technical difficulties requires more
resources
• Scope of work increase – VO ?
• Tender price too low -
• Reporting is poor or untimely – can not
monitor !
• Budgeting is inadequate – working capital
is not enough !
•4/29/2014
Price of matl increase 15
Control Costs
Monitoring and controlling status of the project - update the
project budget - managing changes to the cost baseline
Activities
• Ensuring all change requests - approved by the client - do
not proceed unapproved changes – inform client all cost
implication on changes made
• Ensuring that cost expenditure do not exceed permissible
values
• Monitoring cost performance, understand variance – check
std or previous projects
• Monitoring work completed against expenditure – compare
cost between cost in BQ to actual cost spent !
• Taking action to ensure cost overrun within acceptable limit
4/29/2014 16
Control Costs
Outputs:
• Work performance measurements – check
progress report
• Budget forecasts & actual expenditure
• Change requests
• Project management plans
- cost performance baseline & cost
management plan
• Projects documents updates
4/29/2014 17
Control Costs
4/29/2014 18
Time- Schedule Control
Monitoring status of the project and managing changes to the
schedule baseline
Activities:
• Determining the current status of the project schedule
• Determining that the project schedule has changed
• Managing the actual changes – how to catch up with the
time!
Outputs
• Work performance measurements – project program
• Change requests – thru approved process
• Project Management plan updates
• Project document updates
4/29/2014 19
Monitoring & Controlling A
Construction Project
4) Quality Control
• Quality ?
• Quality Control – depends upon the control of
construction itself
• Quality of finished product is responsibilities of
Designer (Consultants) and Contractors
• Responsibilities of all participants – RE, COW,
Supervisors, Skilled Workers, Workers - right attitude
- let them proud with their work !
• Good design + good materials & workmanship
= Quality product
4/29/2014 20
Monitoring & Controlling A
Construction Project
Quality Control
• Inspection of work quality at every part of the work
• Selecting samples of matl to be used – sizes,
appearances, testing the samples
• Testing materials and workmanship at every stage of
construction to make sure the work meets
requirements of the drawings and specifications
• For big project – they have a Quality Control Officer
• Contractor to have A Program of Quality Control
• ISO 9000/9001
4/29/2014 21
Perform Quality Control
Outputs
• Quality control measurement
• Validated changes
• Project Management plan updates
• Project document updates
4/29/2014 23
Monitoring & Controlling A
Construction Project
Who to control ?
• Clients )
• Consultants ) - Have to play their roles
• Contractors )
How ?
• Progress Reports – reporting progress
• Site meetings – check & monitor progress,
time, cost & quality
• Technical meetings
•4/29/2014
Regular site visits by the client, Director of24
the consultant firms
Management of Changes
Changes sometimes cannot be avoided during
construction
Changes by owner, designer or contractor:
• Owners – changes to better achieve intended use of
the project - caused VOs
• Designer – changes to original drawings or spec –
must get owner’s approval
• Contractor – to change matl, system of work, method
of construction – must get SO approval
4/29/2014 27
Projects Organisation
Contractor Site Staff:
( Number of post and number of Staff depend on the project size)
4/29/2014 29
Project Site Office:
4/29/2014 33
Samples
• Samples Approved & dates
• Kept at the Site Office
• Recorded in “ List Of Sample Approved & Reported in the
Contractor’s Monthly Report
Material Testing
• For quality control
• To check whether materials proposed by the contractors are
in accordance with the contract specifications eg in term of
sizes, strength, contents
• Concrete mix - cube tests for 7 days & 28 days
• Cone test for concrete mix
• Reinforcement tensile tests
4/29/2014 34
• Timber – chemical contents for tanalised timber
Site Meetings :
• Schedule site meetings eg every 2 weeks or every
month at the Site Office
• Chair by SO (from Client) or RSO (Consultant)
• Attended by all Consultant Site Staff, Main
Contractor’s Representatives, NSC Rep
• Purposes –Progress Monitoring – to discuss all
problems related to the project
• Discussed Project’s Progress – Progress Report
• Minutes of the meetings – prepare by the
consultant’s site staff
4/29/2014 35
References:
1. Frederick E. Gould and Nancy E. Joyce. 2003. Construction
Project Management. Prentice3 Hall Publisher.
2. Peter G. 1989. Management and Construction Control. New
York: Longman Inc.
3. Oberlender G.D. 2000. Project Management for Engineering
and Construction. McGraw-Hill
4. PMI.2008. A Guide to the Project Management Body of
Knowledge (PMBOK)
5. Twort A.C and Rees J.G .2005, Civil Engineering Project
Management . 4th Edition, UK: Elsevier Butterworth
Heinemann
4/29/2014 36