Professional Documents
Culture Documents
Solar PV Maintenance PDF
Solar PV Maintenance PDF
Contents
Annex 5: Information to be
obtained from System
Supplier or Manufacturers 44
A: Introduction 3
A: Introduction
Failure to follow
recommended
procedure could result
in injury.
Work Safely
A grid-connected power
system (GC) provides 240V
AC power by being
connected to the electricity
grid, often referred to as
Wear protective eyewear
power lines or mains power.
and appropriate clothing
during maintenance.
A: Introduction 5
Battery banks
The owner of the system
MUST NOT undertake any
Although 240V AC power is maintenance to battery
dangerous and can cause NOTE If the battery bank banks 120V DC or above.
death when live exposed has a nominal voltage of
The battery bank can include
wires/terminals are touched 120V DC or above,
either wet lead-acid or
or cause fire, it is generally maintenance can only be
sealed lead-acid cells.
safe when kept in good undertaken by a suitably
working order. licensed electrical
worker or contractor.
Low voltage (LV) is specified
in the Australian Standards
as any voltage equal to or
higher than 50V AC or 120V Wet lead-acid batteries
DC. Any service requiring LV
The hazards related to a wet • shor t i n g of ter minals on
wiring must be undertaken
lead-acid battery bank and between the individual
by a suitably licensed
include the risk of: cells; and
electrical worker or
• explosion due to hydr ogen • electrocution caused by an
contractor. The owner of the
gas; output voltage 120V DC or
system MUST NOT
• burns caused by acid in greater.
undertake any maintenance
the individual cells;
to LV wiring systems or the
output terminals of
equipment that produces low
voltage (LV).
To minimise the hazards the • clean water should be
following precautions should available near the
be taken when undertaking batteries to wash any acid
any maintenance: that comes in contact with
• no maintenance should be skin;
undertaken if there is a • bi-carbonate soda should
strong smell of sulphuric also be available to be
acid in the vicinity of the used, with water, to
battery bank; neutralise any acid that is
• no smoking or naked spilled onto the ground;
flames; and
• safety goggles MUST be • the end of spanners (or
worn; any other tools) that you
• acid resistant gloves will use near the battery
MUST be worn; bank should be insulated
• acid resistant apron or to avoid any accidental
clothing should also be shorts between the
worn; terminals.
6 Solar PV Systems: Users maintenance guide
The hazards related to a sealed lead acid To minimise the hazards, the following
battery include the risk of: precautions should be taken when
• explosion due to hydrogen gas (if undertaking any maintenance:
covered); • no smoking or naked flames
• shorting of terminals on and between the • no maintenance should be undertaken if
individual cells; and there is a strong smell of sulphuric acid in
• electrocution caused by having a nominal the vicinity of the battery bank; and
output voltage 120V DC or greater. • the end of spanners (or any other tools)
that you will use near the battery bank
should be insulated to avoid any
accidental shorts between the terminals.
A: Introduction 7
The hazards related to solar modules The hazards related to gensets include the
include the risk of: risk of:
• electric shock due to array open-cir c u i t • electrocution due to 240V AC output; and
voltage greater than 120V d.c; and • ignition of flammable and/or explosive
• falling from the roof when performing fuels
maintenance. • inhaling of exhaust gases
• combustion caused by exhaust sparks
• burns from hot exhaust pipe
• the presence of a battery (see above)
NOTE If the solar modules are connected • accidents from moving parts
in an array where the open circuit • ear damage due to noise.
voltage is 120V DC or above,
They also have rotating parts and these
maintenance can only be undertaken by
should be protected during operation.
a suitably licensed electrical worker or
contractor. To minimise the hazards the following
precautions should be taken when
The owner of the system MUST NOT undertaking any maintenance:
undertake any maintenance to these solar • follow all recommendations provided in
modules other than simple cleaning. the equipment manuals; or
• use a qualified service technician.
To minimise the hazards the following
precautions should be taken when
undertaking any maintenance:
• when working on roofs there is always the Any service required to the LV wiring
risk of falling. NEVER climb onto a roof to must be undertaken by a suitably
perform any service on the solar modules licensed electrical worker or contractor.
(eg. clean them) unless there is a barrier
(eg. scaffolding) to prevent you from falling
or you are wearing an approved safety
harness which is supported correctly.
8 Solar PV Systems: Users maintenance guide
The hazards related to wind generators can The hazards related to pico-hydro generators
include the risk of: can include the risk of:
• electrocution due to dangerous voltages • electrocution due to dangerous voltages
(either DC or AC LV) ; (either DC or AC LV) ;
• falling from the top of a pole or structure; • falling whilst accessing pipes in steep and
• damage caused by rotating and/or moving slippery locations; and
parts. • accidents caused by rotating and/or
• an accident while lowering or raising of moving parts.
tower
To minimise the hazards, the following
• damage by stumbling into unfenced or
precautions should be taken when
unprotected guy wir es
undertaking any maintenance:
• being hit by tail in sudden wind gusts (if
• follow all recommendations provided in
structure tower is suitable for climbing).
the equipment manuals; and
To minimise the hazards the following • turn off water source or
precautions should be taken when • use a qualified service technician.
undertaking any maintenance:
• follow all recommendations provided in
the equipment manuals; and
• use a brake on turbine before lowering or
Any service required to the LV wiring
raising tower; or
must be undertaken by a suitably
• use a qualified service technician.
licensed electrical worker or contractor.
A: Introduction 9
Solar array
With most wind generators the maintenance • check that system regulators and dump
required will be specific to the machine and loads are functioning in windy conditions,
tower installed. (refer to system supplier if things don’t
look right).
The user manual should always be The wind generator is typically located on a
consulted before attempting any tower. Most of the maintenance that will be
maintenance. required on the wind generator will require
the tower to be lowered.
Typical checks by the system owner:
• inspection of guy wires on guyed tower—
check for tension, and excessive fraying or
corrosion of guy wires;
WARNING Do not attempt to lower a
• check the functioning of any manual
turbine tower unless you have been
furling mechanisms;
trained in this procedure and never in
• if a cable twist system is used, check the
windy conditions.
amount of twist and untwist if required;
and
W AT E R
STORAGE
I N TA K E
SYSTEM
PIPELINE
CONTROLS
I S O L AT I N G To Load
VA LV E G E N E R AT O R
To stream
TURBINE
SHUNT
LOADS
14 Solar PV Systems: Users maintenance guide
2. Battery bank
Safety first!
A typical process in shutting 1. Shut down (turn off) all are used, the fuse on the
down a system and isolating loads on the system negative terminal of the
the battery bank to make it starting from the battery bank should be
safe to perform the household appliances removed first followed by
maintenance tasks would and working back to the the fuse on the positive
follow the following steps. inverter. terminal.
2. Disconnect (turn off) all 4. If a switch-fuse is used,
energy generation devices opening the switch fuse
such as solar or wind disconnects the fuses
generators. from the batteries.
WARNING Refer to
3. Shut down the battery Remove the front
system user manual
bank—this would involve mechanism to prevent it
provided by system
either switching off being closed while you
supplier for exact
cir cuit br eakers or are working.
procedures relevant to
removing any fuses on 5. When a circuit breaker is
your system.
the battery bank. If fuses used, either place a ‘Do
B: Stand-alone solar PV systems 19
The inverter
The inver ter should be genset is starting and
installed in a clean, dry, and stopping at correct battery
ventilated area which is sep- voltage levels as specified
arated from, and not directly by manufacturer (refer to
above, the battery bank. system supplier or inverter
While the system is operat- operating manual).
ing the following operational
NOTE The third check can be
checks can be made: Typically the system owner
difficult to undertake as it
• check that the inverter is is only aware that the
can require disconnecting all
functioning correctly by genset has not started when
charging sources (eg. PV
observing LED indicators, the batteries have reached a
array) and turning on
metering and/or other dis- low voltage.
sufficient appliances to
plays on the inverter
force the battery voltage to When inspecting the
• check to see if the
decrease to the set voltage inverter, remove any excess
inverter’s stand-by mode
for starting the genset. It dust from the unit and
(if present) is functioning
could also be simulated by especially from the heat-
correctly. This can be done
raising the voltage setting so sinks. This should only be
by turning off all loads and
checking that the generator done with a dry cloth or
appliances operating on
does start at the higher brush. Check that “vermin”
the system. Once in stand-
voltage, which is close to have not infested the
by mode, switch an
the actual voltage of the inverter eg. typical signs of
appliance on and the
battery bank. The exact this include spider webs on
inverter should start
testing method will depend ventilation grills or wasps’
almost immediately.
on the actual set-up of the nests in heat sinks. Contact
• check that any control
system and probably might system suppliers if you
functions for r emote
only be able to be suspect vermin are inside
star ting of diesel genset
undertaken by a suitably the inverter.
(if installed) are operating.
qualified person eg. the
Ensure that the diesel
system supplier/installer.
24 Solar PV Systems: Users maintenance guide
Regulator(s)
Each of the renewable used are known as shunt conditions. This is achieved
energy charging sources: PV regulators and will require by observing that the charge
array, wind generator and additional components currents from the different
pico-hydro generator will known as dummy loads, sources (solar, wind or pico-
require their own specific typically a bank of resistive hydro) are either removed or
charge regulator (or coils. When the battery bank reduced when specified
controller). Any regulator reaches the preset voltage, voltages are obtained. This
should be installed in a the current from the could be observed when the
clean, dry and ventilated generator source is voltage of the battery
area. “shunted” into the dummy reaches a certain point, this
load. indicates that the battery is
The regulator is an electronic
fully charged and the
device that controls the
regulators go from boost to
voltage of the charging
float mode.
sources (solar, wind, hydro)
WARNING These shunts
energy output to charge the Full operation tests might
can get very hot and
battery bank appropriately. need to be undertaken by a
should not be touched.
The regulators are designed suitably qualified person eg.
to disconnect or reduce the the system supplier/installer.
During maintenance checks,
charge current when preset
inspect the functioning of the When inspecting the
voltages are reached.
regulator to ensure that any regulators:
Typically there are boost
indicators or meters are • look for any loose wiring
voltage settings and float
correctly operating for the on the terminal
voltage settings.
various regulator modes. connections. If they are
Inspect and check the loose follow the shutdown
In general correct operation
functioning of the regulator procedures for the system
of the regulator(s) can only
to ensure that any indicators before tightening the
be observed in certain
or meters are correctly connections or contact
operating for the various your installer.
regulator modes. In the case
of a PV system, check that
when the batteries are fully
charged and it is sunny, that NOTE Loose connections
the solar regulator is can cause hot joints and
changing into float mode. possibly fire.
The wind generator and pico- • remove any excess dust
hydro regulator do operate from the unit and
differently to the solar especially from the heat-
regulator. If you have a wind sinks. This should only be
generator or pico-hydro done with a dry cloth or
generator the regulators brush.
B: Stand-alone solar PV systems 25
Battery chargers
The maintenance required for voltage of the genset. (if volt clean, dry and ventilated
battery charging equipment meter has been installed). If area.
is similar to that required for genset is not producing
When inspecting the charg-
inverters. correct output voltage, then
ing equipment remove any
the battery charger will not
Check that the charger does excess dust from the unit
operate correctly. If the
charge the battery bank and especially from any heat-
genset is OK then contact
when the genset is sinks. This should only be
system supplier/installer.
operating. If it does not done with a dry cloth or
appear to be operating Any battery charging equip- brush.
correctly check the output ment should be installed in a
System wiring
Check for any breaks or • regulator to battery bank;
deterioration in exposed • inverter to battery bank;
conduit and wiring. Also • genset to battery charger
inspect connections for any • battery charger to battery
signs of corrosion and/or bank
burning. If any damage is • inverter and genset to AC
noticed contact the system switchboard.
supplier/installer.
An example of poorly wired,
Inspect the condition of the
unprotected and
conduit and wiring from the:
unsupported cabling for
• charging source to its
a charger
regulator;
26 Solar PV Systems: Users maintenance guide
1. PV solar modules
WARNING
Typically modules are
located on a roof hence
there is a risk of falling.
When performing
maintenance, some
form of fall protection
equipment (eg. harness
or scaffolding), MUST
be used.
30 Solar PV Systems: Users maintenance guide
2. Inverters
These items generally • keep the inverter clean • check that the inverter is
require very little and minimise the functioning correctly by
maintenance but when possibility of dust being observing LED indicators,
maintenance is being blown over the equipment metering and/or other
performed on other parts of —clean with dry cloth displays on the inverter.
the system then the when required;
An example of an inverter
following should be • ensure the unit is not
log sheet is shown in
undertaken: “infested” by vermin; and
Annex 2.
3. Balance of system
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
C: Grid-connected solar PV systems 33
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
Date Name Intake Bearings Wheel Nozzles Pipes Electrical Comments
filters lubricated/ checked checked checked connections
cleaned changed
I I I I I I
I I I I I I
I I I I I I Pico-hydro log sheet
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
I I I I I I
Annex 1: SPS maintenance log sheets
I I I I I I
37
38 Solar PV Systems: Users maintenance guide
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
Annex 2: GC maintenance log sheets 39
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
I I I I
Annex 3: Glossary 41
Annex 3: Glossary
240V 240 volts AC – a deep cycling suitable for furling turning the blades to
lethal voltage large charge and avoid the wind
AC alternating current discharge cycles fuses protection devices
ambient surrounding depth of discharge that break the overload by
array A number of PV percentage discharge of a burning a wire inside their
modules electrically battery. casing—must be replaced
interconnected dump loads a load to when operated
balance of systems prevent the current from GC connected to the mains
includes regulators, overcharging the battery power grid
inverters, cables, control electrolyte solution in a gel the electrolyte in the
board and protection battery that stores energy battery is a gel as distinct
equipment and allows the current to to a liquid solution
bi-carbonate soda baking pass gensets a diesel, LPG or
soda – sodium energy generation devices petrol 240V generator
bicarbonate PVs, wind turbine, genset guy wires supports holding
boost charge A charging or pico-hydro generator tower of wind tower in
cycle that ensures the equalisation overcharging place
battery reaches close to to ensure all cells have heat-sinks finned steel to
fully charged also known equalised specific gravity help dissipate heat
as “topping up the and therefore each cell is hot exhaust pipe from a
battery” fully charged fuel genset and can cause
BOS Balance of System exhaust gases contain burns
brake prevents the turbine noxious fumes hot joints poor electrical
from turning exhaust sparks sparks in contact causing heating
cable twist A mechanism in fumes which can cause hydrogen a volatile gas
a wind turbine where the fire given off during charging
cables in the tower of the float sealed cylinder inside of batteries
wind turbine can twist one hydrometer hydrometer device for
way then another – working float charge intermittent measuring specific gravity
on the theory that the wind charging of the battery at incident striking
turbine will approximately a voltage specified by insulated prevents electrical
turn equally clockwise and manufacturer also known shorting
anticlockwise so that the as intermittent topping up integrity components
cable does not twist too of the battery working correctly and in
tight flooded A battery with wet harmony
cells a single battery unit electrolyte within the inverter converts DC
(usually 2 volts) battery case and around current into 240 V AC
circuit breakers an the electrodes isolate cut off electrically
electrical protection device forced ventilated powered lead-acid the electrolytic
that automatically by a fan compound and the
switches to off when fuels usually diesel, LPG or electrodes
overloaded petrol LED light-emitting diode
DC direct current
42 Solar PV Systems: Users maintenance guide
Safety first
DATE
1. Do not climb above 2 metres to maintain PV modules or wind turbines without safety
rails or harness
2. Do not touch any component with a voltage 120V DC, 50V AC or greater
3. Wear personal protective clothing when maintaining batteries
4. Do not maintain batteries while there’s an acrid smell in the vicinity
5. No smoking, sparks or naked flames in battery enclosure
6. Ensure clean water is readily accessible while maintaining batteries
7. Ensure all tools are insulated while maintaining batteries