You are on page 1of 1

Project Schedule Wilmont Pharmacy drone project Revision no.

025 Revision date:18thsept 2020

Weeks
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
1.1 INITIATING
1.1.1 Develop scope and plan
1.1.2 Engage stakeholders
1.1.3 Raise funds

1.2 Planning
1.2.1 Sysytems design
1.2.2 Cost estimate
1.2.3 Approvals

1.3 Execution/ construction


1.3.1 Purchase materials
1.3.2 payments
1.3.3 Engage specialists

1.4 Testings
1.4.1 Testing of mobile app
1.4.2 Testing of drone flight

#REF!
#REF!
#REF!

1.6 Closing
1.6.1 Establishing supplying by more pharmacies
1.6.2 Reconcile accounts and finalize payments

Indicates Critical Path Items