You are on page 1of 2

Sheet1

Sr. no. PERTICULARS

present food grade , Pharma buildings at different location in plant Following Approx. expenditure to
1
make suitable as per C- GMP requirement & audit Completion

a) One 6 TPH – C.F. & dryer to be installed Appox. Expenditure with civil –
b) Pharma Grade Automatic System – 06 Crs
c) Additional Starch Conveying system from System to Pharma Building& food grade building – 02 Crs
d) Civil expenditure for building Renovation – 04 Crs
e) Boiler Accessories - 02 Crs
f)Roads & Gutter - 2.5 Crs
g) Maize storage & Handling - 12 Crs
h)Gardening , Painting & other modification - 02 Crs
Total
Even after Implementing the above we have following constraints .
For Executing these jobs, We have get plant shut at least 8 Month to 1 Yr in phases so in facts to make
it to requirement total two Yrs will required
2 Space constraints – for Execution & locating the machinery.
3 Operational cost will be more
4 Pl. Shut losses will be huge which will make total USA – Unavoidable.

Page 1
Sheet1

PRICE

owing Approx. expenditure to


ompletion

il – 6 Crs
6 Crs
& food grade building – 02 Crs 2 Crs
4 Crs
2 Crs
2.5Crs
12 Crs
2 Crs
Total 36 Crs

r in phases so in facts to make

Page 2

You might also like