You are on page 1of 6

Transforming Existing 220 kV Double Circuit

Line into 400 kV Single Circuit Line in


Romania
D. Marginean, E. Mateescu, IEEE Member, H.S. Wechsler, – Fichtner Engineering Co. Bucharest,
Romania
G. Florea, IEEE Member – P&L Tehnorob Co. Bucharest, Romania,
C. Matea – CN Transelectrica S.A. – Bucharest, Romania

Abstract — The transmission system operators the two countries will be advantageous as it can:
TRANSELECTRICA (TEL-Romania) and EMS (Serbia) - Secure the power supply of a large consumption
have decided to increase the interconnection capacity on zone of about 1,000 MW;
the common border by building a new 400 kV transmission
line. - Increase voltage stability in the zone and implicitly,
The aim of the new 400 kV interconnection line is to reduce power and energy losses;
serve both system operators in achieving the common goal - Increase the transmission service quality, the power
– a more reliable power supply to the customers at a lower quantity that can be transferred and the safety in the
electricity price. power supply of Romania’s and Serbia’s power
In the same context, TEL has decided to upgrade the systems;
transmission line corridor in the Western part of Romania - Increment the security in the fulfillment of
from 220 kV to 400 kV voltage level, in order to facilitate import/export contracts with the European power
the evacuation of exceeding power from Portile de Fier market;
area (including hydro power plants Portile de Fier, Portile
de Fier 2, thermal power plant Halanga and future wind - Increase the possibility of using renewable energy (a
power park planned in the same area). different one from that obtained by fossils
With these goals, the authors have been prepared a combustion).
report regarding the feasibility of the project. The
objectives of the report have been: In the conditions of the future interconnection, the
- Compare from technically and economically point of upgrading of the southwestern part of Romanian power
view two candidate interconnection lines with the system is compulsory. The weak part is represented by
Serbian system. the existing 220 kV double circuit corridor from Portile
- Identify and recommend an optimal configuration for de Fier to Arad.
upgrading the transmission corridor between Arad and The map of the Project with the 220 kV OHL target
Portile de Fier, taking into account the future 400 kV
corridor and future interconnection line with Serbia is
interconnection with the Serbian system.
presented below in figure 1.
The paper presents only the most important results The analysis was structured in two phases:
obtained regarding the system study and the optimal - the power system study for selecting the optimum
solution for corridor transforming. solutions for upgrading the southwestern part of the
Romanian transmission system and for the new
Index Terms - Upgrading – Interconnection – System - 400kV interconnection line;
Configuration - Corridor – Transforming – Optimal - the conceptual study for optimal solution regarding
the upgrading of the existing 220 kV double circuit
I. INTRODUCTION corridor.

R omania’s commitment to the power market of the


UE-Countries can be achieved only under the
strengthening of connection networks between member
II. SYSTEM STUDY
The main tasks of the study were:
countries, so that to acquire a high security and quality - identify the optimal alternative to upgrade the
of the power transmission services in compliance with transmission line corridor in Western Romania and
both international and domestic trade. interconnect the power systems of Romania and
At present, Romania and Serbia share a single Serbia, in harmony with regional power system
interconnection OHL, Portile de Fier - Djerdap (400 kV developments and energy resource sharing;
single circuit), and a new interconnection OHL between

1
978-1-4577-0567-0/11/$26.00 ©2011 IEEE
- evaluate the performances of the interconnection by Based on Steady State investigations, Net Transfer
power system analysis; Capacity calculation, dynamic investigations and
- estimate costs of the various alternatives; financial evaluation the analysis performed in the study
- undertake financial analysis for the most promising has revealed that:
alternative; - the location of the new interconnection line between
- confirm financial justification and prioritization for Resita and Pancevo is the best solution and it is
the interconnection between Romania and Serbia. recommended;
- for the 220 kV transmission corridor upgrade in
Based on the results of the previous study done by Romania the conceptual Variant I is the optimal
Transelectrica and EMS two alternatives for the new solution (Variant 1 consists in a new 400kV single
400 kV interconnection have been agreed (TABLE II): circuit OHL from Arad to Portile de Fier, new
400kV substations at Calea Aradului, Sacalaz,
TABLE II Timisoara and Resita and 400/110kV step-down
ALTERNATIVES FOR NEW INTERCONNECTION 400 KV OHL transformers at Arad, Sacalaz, Timisoara and
Romanian side Serbian side Resita).
Sacalaz Novi Sad
This arrangement was tested by simulations and
Resita Pancevo found to have good static and dynamic performance for
a maximum 1000 MW transfer in both directions
between from Romania and the UCTE system.

ROMANIA

NOVISAD Target corridor


Existing 220 kV OHL
SERBIA Existing 400 kV OHL
New 400 kV OHL
400 kV interconnection
PANCEVO (alternatives)

Fig. 1 – Southwest Romanian Transmission System

Regarding the optimal configuration for upgrading From a financial perspective, this arrangement leads
the transmission corridor between Arad and Portile de to the minimum capital expenditure for the 400 kV
Fier, various variants were retained for a preliminary transmission corridor in Western Romania and
technical evaluation, followed by an in–depth power maximizes the benefits from the increase in border
system analysis of the most promising ones. capacity by the new interconnection line.
Each of the variants can have two options,
corresponding to the interconnection line Sacalaz-Novi Also, a study about switching overvoltages for the
Sad or line Resita –Pancevo. new 400 kV axis in south-west Romanian transmission
network has been performed using the Alternative
Conclusions of System Study: Transients Program [4].

2
The results of the study reveals that, with the 400 kV downward oriented peak frame. This solution is
upgrade, the switching overvoltages values will be achieved keeping the middle crossarm and one of the
between accepted limits. The risk analysis shown an lower crossarms of the 220 kV tower geometry;
increased level of risk compared with existing situation, - delta solution, consists of replacing „hexagon” frame
but surely below a dangerous value. of the existing 220 kV tower geometry with a „delta”
tower top geometry.
III. UPGRADING TRANSMISSION LINE CORRIDOR BY While the technical advantages of a 400 kV corridor
TRANSFORMING EXISTING DOUBLE CIRCUIT LINES with new 400 kV OHL is evident (new equipments, no
need for disconnecting the link during construction
stage, etc.), some other aspects were taken in
As resulted from the power system study, a 400 kV
consideration:
connection between Portile de Fier and Arad is essential
for the efficiency of the whole project. - difficulties related to obtaining the right-of-way for
the new lines;
Solutions for setting up the 400 kV corridor: - environmental restrictions due to the presence of
National Parks and Nature Reserves in the area of
Were compared technically and economically the
the project;
following possible solutions:
- increased costs for land acquisition;
- new 400 kV single circuit OHL on existing 220 kV
- important modifications of the substations
double circuit route;
configuration and equipments;
- new 400 kV single circuit OHL on a new route;
- modifications of other existing OHL, mainly in the
- transforming existing 220 kV double circuit OHL proximity of the substation.
into a 400 kV single circuit OHL.
The main problem of the solutions with transforming
The upgrading of the existing 220 kV double circuit
existing towers is the periods when the existing 220kV
OHL by transforming into a 400 kV single circuit OHL
link is necessary to be disconnected for erection works.
has been already studied in Romania [1], [2].
For very important links, as Timisoara – Arad is, this is
not an accepted option.
Two solutions were studied and detailed until now
(see figure 2):

Fig. 2.a: Fig. 2.b: Fig. 2.c:


„Triangle” solution Existing tower „Delta” solution

Fig.2: Solutions for transforming 220 kV double circuit OHL into a


The proposed solution is to use emergency towers to
400 kV single circuit OHL bypass the power transit on the OHL. As described in
[3], the emergency towers will be installed in parallel
- triangle solution, consisting of transforming the with existing line and will be equipped with one 220 kV
existing 220 kV „hexagon” frame into a „triangle” circuit. The line will be disconnected only at by-pass
connecting/disconnecting operations. Those periods are
3
in range of one to two hours and could be accepted. related to environmental coexistence:
The financial evaluation of the analyzed solutions is - less visual impact, because of lower height towers,
presented in TABLE II below (costs in Euro/km, prices with improved aesthetic;
beginning of 2009): - narrow occupied corridor. Distance between outer
phases is 12 meters for „delta” solution, compared
TABLE II with 16 meters for „triangle” solution.
FINANCIAL COMPARISSION OF ANALYZED SOLUTIONS
Based on all these findings, the „delta” solution was
400 kV single circuit OHL by selected as favorite and all subsequent analysis were
New 400kV transforming
Solution OHL single
focused on this solution.
220 kV double circuit OHL
circuit on
Costs new route „Triangle” „Delta” IV. DETAILED ANALYSIS OF „DELTA” SOLUTION
solution solution
Equipments and
This part of the study investigated the real
175000 88900 91300
erection possibilities of implementation of the „delta” solutions
Dismantled 0 3600 7300 for the 220 kV double circuit OHL that are included in
materials revenue this project.
Rehabilitation of
reused 0 10900 9700
equipments As described above, the „delta” solution consists of
175000 96200 93700 replacing the existing „hexagon” tower-top by a „delta”,
Total direct costs 400 kV dimensioned, tower-top. In this solution,
(100.0%) (55.0%) (53.5%) existing foundations and tower trunks will be reused,
Land acquisition
same for phase conductors and earthwires.
17000 0 0
(definitive)
Land acquisition The main characteristic (existing and after
(temporary, 21000 19500 19500 transformation) of the 220 kV OHL involved in this
during works)
project are presented in TABLE III.
Right-of-way 25000 3125 0
obtaining
TABLE III
Corona losses 22300 27600 24500 MAIN CHARACTERISTICS OF ANALYZED OHL
(actualized)
Periodic
restoration of Main characteristics
anticorrosive OHL
0 9200 5468
protection of Existing After transformation
reused parts - OHL type: 220 kV
(actualized) double circuit - OHL type: 400 kV
260300 154625 143168
Actualized Total - Length: 72.8 km: single circuit
(30 years, 8% - Year of commissioning: - Length: 72.8 km:
rate) (100%) (59.8%) (55.0%)
1971; - Tower-top geometry:
- Tower-top geometry: „delta”;

Taking in consideration the results of technical and Re i a –


„hexagon”; - Phase conductors:
Timi oara - Phase conductor: 2xACSR 450/75 mm2;
economic analysis, both solutions with transforming 1xACSR 450/75 mm2; - Earth wire: 1xOPGW +
existing 220 kV double circuit OHL into a 400 kV - Earth wire: 1xOPGW 1xACS (new);
single circuit OHL were selected for detailed analysis. (2004); - Insulation: composite,
- Insulation: glass, cap and long road;
If the financial evaluation gives a similar value for pin; - Foundations: keep
both solutions (table 2), the technical analysis revealed - Foundations: casted in- existing ones
that the „delta” solution has some certain advantages: situ.

- better symmetry factor (defined as ratio between - OHL type: 220 kV - OHL type: 400 kV
double circuit single circuit
direct and inverse reactance);
- Length: 53.7 km: - Length: 72.8 km:
- lower corona losses, due to lower intensity of -
electric fields values at conductors surface;
Year of commissioning: - Tower-top geometry:
1974; „delta”;
- lower intensity of electric field above ground; Timi oara
– Arad - Tower-top geometry: - Phase conductors:
- reduced number of line outages because shielding „hexagon”; 2xACSR 450/75 mm2;
failure, due to the presence of two earthwires. - Phase conductor: - Earth wire: 1xOPGW +
1xACSR 450/75 mm2; 1xACS (new);
The „delta” solution has also some advantages - Earth wire: 1xOPGW; - Insulation: composite,
- Insulation: glass, cap and long road;

4
pin; - Foundations: keep - for the 2 x ACSR 450/75 mm2 phase configuration,
- Foundations: precasted existing ones the reused parts of the OHL -towers trunks and
and casted in-situ.
foundations- do not need any reinforcements.
The most important part of the study was the
investigation of the capability of the remaining tower VI. REFERENCES
trunks and foundations to withstand the new loadings as
[1] CIGRE, Black Sea El-Net regional Meeting, 2001: H.S.
resulted for new OHL configuration. WECHSLER and others – „Aspects and results in the field of
The verification checked all towers’ and foundations increasing the power transmission capacities of the existing
types (suspension, tension, angle and dead-end) in the overhead transmission lines”
[2] HIGH VOLTAGE SYMPOSIUM, Sibiu 1995: G.
conditions of valid Romanian standards and norms. The GHEORGHITA and others – „Solutions of transforming the 220
calculations was done for same meteorological kV double circuit overhead lines into 400 kV single circuits
conditions used for the initial design of the electric lines, lines”
[3] CIGRE, Black Sea El-Net regional Meeting, 2001: C. TENCU
applied to the actual pair of wind and weight spans, and others – „Emergency restauration system for overhead
specific for each tower location. transmission lines”
Beside the existing 2 x ACSR 450/75 mm2 phase [4] I. ARDELEAN, G. VUC – „Switching Overvoltages in
Romanian S-W Transmission Network, with New 400 kV Portile
configuration, the towers and foundations were verified de Fier – Resita – Timisoara - Arad Axle”
also for a 3 x ACSR 300/69 mm2 phase configuration.

The conclusions of the verifications were as follows: VII. BIOGRAPHIES


- towers trunks and foundations have the capacity to
withstand the new loadings resulted for a 2 x ACSR
450/75 mm2 phase configuration; Daniel Marginean was born in Bucharest,
Romania, on October, 12th, 1964 and
- for a 3 x ACSR 300/69 mm2 phase configuration, the received a Diploma in Electric Power
calculations revealed loadings of the main members Engineering in 1991 from Polytechnic
of the trunks with 13% to 15% over admitted loads. University Bucharest, Romania. His
employment experience includes the
In case of main diagonals the over-loadings were
Institute of Power Studies and Design,
between 16% and 20%. Bucharest and Fichtner Engineering Ltd,
Bucharest. His special fields of interest
In these conditions, the solution with 3 x ACSR include the design of power transmission
lines. As a specialist for transmission lines,
300/69 mm2 phase configuration resulted non-economic Mr. Marginean has excellent technical capabilities related to
because of the significant reinforcements required. For transmission line routing, transmission line components like
this phase configuration many of the verified towers conductors, optical cables, insulators and supports, structural
steelwork and foundations for transmission line towers, and special
should be replaced with new towers and the benefits technical solutions PLS-Cadd abilities.
resulted from a better phase configuration do not justify
this option. Elena Mateescu was born in Bucharest,
Romania, on October, 26th, 1959 and
received a Dipoma in Electric Power
V. CONCLUSION Engineering in 1983 from Polytechnic
As resulted from the technical and financial University Bucharest, Romania. Her
employment experience includes the Institute
evaluation, the optimal solution for upgrading of Power Studies and Design, Bucharest and
transmission line corridor Resita – Timisoara – Arad is Fichtner Engineering Ltd, Bucharest. Her
the „delta” solution, consisting of replacing the existing special fields of interest include the design of
power transmission lines, electromagnetic
„hexagon” tower-top by a „delta”, 400 kV dimensioned, field effect of electric network on biological
tower-top. systems, environmental impacts and live-line maintenance methods.

Henry Silviu Wechsler was born in


The main advantages of this solution are:
Boto ani, Romania, on June, 18th, 1946 and
- costs halved compared with the costs of a new received a Diploma in Electric Power
400kV OHL; Engineering in 1970 from Polytechnic
University Bucharest, Romania.
- no land or right-of-way acquisition is necessary for
His employment experience includes the
project implementation compared with the new line Institute of Power Studies and Design,
solution, which also means minimum environmental Bucharest, Fichtner Engineering Ltd,
impact; Bucharest and Fichtner Stuttgart. His special
fields of interest include the design of power
- minimum modifications of the substations transmission lines, has excellent technical
configuration and equipments; capabilities related to transmission line components like clamps and
- better electric performances and environmental fittings, conductors, optical cables, insulators and supports, structural
impact compared with the „triangle” solution; steelwork and foundations for transmission line towers and live-line
maintenance methods.

5
Constantin Matea Constantin Matea was
born in Tomsani, Romania, on August, 19th,
1950 and received a Diploma in
Electromecanical Engineering in 1993 from
University Politehnica Bucharest, Romania.
His employment experience includes the
MEE ICMP - CELPI S.A. and Romania
National Power Grid Company
“Transelectrica”- S.A, Bucharest. His
special fields of interest include the live-line
maintenance work technologies and
different protection systems of electric network. As a Project Manager
for transmission lines Mr. Matea has excellent technical capabilities
related to transmission line components like clamps and fittings,
conductors, optical cables, insulators and supports, structural steelwork
and foundations for transmission line towers.

You might also like