Professional Documents
Culture Documents
Abstract — The transmission system operators the two countries will be advantageous as it can:
TRANSELECTRICA (TEL-Romania) and EMS (Serbia) - Secure the power supply of a large consumption
have decided to increase the interconnection capacity on zone of about 1,000 MW;
the common border by building a new 400 kV transmission
line. - Increase voltage stability in the zone and implicitly,
The aim of the new 400 kV interconnection line is to reduce power and energy losses;
serve both system operators in achieving the common goal - Increase the transmission service quality, the power
– a more reliable power supply to the customers at a lower quantity that can be transferred and the safety in the
electricity price. power supply of Romania’s and Serbia’s power
In the same context, TEL has decided to upgrade the systems;
transmission line corridor in the Western part of Romania - Increment the security in the fulfillment of
from 220 kV to 400 kV voltage level, in order to facilitate import/export contracts with the European power
the evacuation of exceeding power from Portile de Fier market;
area (including hydro power plants Portile de Fier, Portile
de Fier 2, thermal power plant Halanga and future wind - Increase the possibility of using renewable energy (a
power park planned in the same area). different one from that obtained by fossils
With these goals, the authors have been prepared a combustion).
report regarding the feasibility of the project. The
objectives of the report have been: In the conditions of the future interconnection, the
- Compare from technically and economically point of upgrading of the southwestern part of Romanian power
view two candidate interconnection lines with the system is compulsory. The weak part is represented by
Serbian system. the existing 220 kV double circuit corridor from Portile
- Identify and recommend an optimal configuration for de Fier to Arad.
upgrading the transmission corridor between Arad and The map of the Project with the 220 kV OHL target
Portile de Fier, taking into account the future 400 kV
corridor and future interconnection line with Serbia is
interconnection with the Serbian system.
presented below in figure 1.
The paper presents only the most important results The analysis was structured in two phases:
obtained regarding the system study and the optimal - the power system study for selecting the optimum
solution for corridor transforming. solutions for upgrading the southwestern part of the
Romanian transmission system and for the new
Index Terms - Upgrading – Interconnection – System - 400kV interconnection line;
Configuration - Corridor – Transforming – Optimal - the conceptual study for optimal solution regarding
the upgrading of the existing 220 kV double circuit
I. INTRODUCTION corridor.
1
978-1-4577-0567-0/11/$26.00 ©2011 IEEE
- evaluate the performances of the interconnection by Based on Steady State investigations, Net Transfer
power system analysis; Capacity calculation, dynamic investigations and
- estimate costs of the various alternatives; financial evaluation the analysis performed in the study
- undertake financial analysis for the most promising has revealed that:
alternative; - the location of the new interconnection line between
- confirm financial justification and prioritization for Resita and Pancevo is the best solution and it is
the interconnection between Romania and Serbia. recommended;
- for the 220 kV transmission corridor upgrade in
Based on the results of the previous study done by Romania the conceptual Variant I is the optimal
Transelectrica and EMS two alternatives for the new solution (Variant 1 consists in a new 400kV single
400 kV interconnection have been agreed (TABLE II): circuit OHL from Arad to Portile de Fier, new
400kV substations at Calea Aradului, Sacalaz,
TABLE II Timisoara and Resita and 400/110kV step-down
ALTERNATIVES FOR NEW INTERCONNECTION 400 KV OHL transformers at Arad, Sacalaz, Timisoara and
Romanian side Serbian side Resita).
Sacalaz Novi Sad
This arrangement was tested by simulations and
Resita Pancevo found to have good static and dynamic performance for
a maximum 1000 MW transfer in both directions
between from Romania and the UCTE system.
ROMANIA
Regarding the optimal configuration for upgrading From a financial perspective, this arrangement leads
the transmission corridor between Arad and Portile de to the minimum capital expenditure for the 400 kV
Fier, various variants were retained for a preliminary transmission corridor in Western Romania and
technical evaluation, followed by an in–depth power maximizes the benefits from the increase in border
system analysis of the most promising ones. capacity by the new interconnection line.
Each of the variants can have two options,
corresponding to the interconnection line Sacalaz-Novi Also, a study about switching overvoltages for the
Sad or line Resita –Pancevo. new 400 kV axis in south-west Romanian transmission
network has been performed using the Alternative
Conclusions of System Study: Transients Program [4].
2
The results of the study reveals that, with the 400 kV downward oriented peak frame. This solution is
upgrade, the switching overvoltages values will be achieved keeping the middle crossarm and one of the
between accepted limits. The risk analysis shown an lower crossarms of the 220 kV tower geometry;
increased level of risk compared with existing situation, - delta solution, consists of replacing „hexagon” frame
but surely below a dangerous value. of the existing 220 kV tower geometry with a „delta”
tower top geometry.
III. UPGRADING TRANSMISSION LINE CORRIDOR BY While the technical advantages of a 400 kV corridor
TRANSFORMING EXISTING DOUBLE CIRCUIT LINES with new 400 kV OHL is evident (new equipments, no
need for disconnecting the link during construction
stage, etc.), some other aspects were taken in
As resulted from the power system study, a 400 kV
consideration:
connection between Portile de Fier and Arad is essential
for the efficiency of the whole project. - difficulties related to obtaining the right-of-way for
the new lines;
Solutions for setting up the 400 kV corridor: - environmental restrictions due to the presence of
National Parks and Nature Reserves in the area of
Were compared technically and economically the
the project;
following possible solutions:
- increased costs for land acquisition;
- new 400 kV single circuit OHL on existing 220 kV
- important modifications of the substations
double circuit route;
configuration and equipments;
- new 400 kV single circuit OHL on a new route;
- modifications of other existing OHL, mainly in the
- transforming existing 220 kV double circuit OHL proximity of the substation.
into a 400 kV single circuit OHL.
The main problem of the solutions with transforming
The upgrading of the existing 220 kV double circuit
existing towers is the periods when the existing 220kV
OHL by transforming into a 400 kV single circuit OHL
link is necessary to be disconnected for erection works.
has been already studied in Romania [1], [2].
For very important links, as Timisoara – Arad is, this is
not an accepted option.
Two solutions were studied and detailed until now
(see figure 2):
- better symmetry factor (defined as ratio between - OHL type: 220 kV - OHL type: 400 kV
double circuit single circuit
direct and inverse reactance);
- Length: 53.7 km: - Length: 72.8 km:
- lower corona losses, due to lower intensity of -
electric fields values at conductors surface;
Year of commissioning: - Tower-top geometry:
1974; „delta”;
- lower intensity of electric field above ground; Timi oara
– Arad - Tower-top geometry: - Phase conductors:
- reduced number of line outages because shielding „hexagon”; 2xACSR 450/75 mm2;
failure, due to the presence of two earthwires. - Phase conductor: - Earth wire: 1xOPGW +
1xACSR 450/75 mm2; 1xACS (new);
The „delta” solution has also some advantages - Earth wire: 1xOPGW; - Insulation: composite,
- Insulation: glass, cap and long road;
4
pin; - Foundations: keep - for the 2 x ACSR 450/75 mm2 phase configuration,
- Foundations: precasted existing ones the reused parts of the OHL -towers trunks and
and casted in-situ.
foundations- do not need any reinforcements.
The most important part of the study was the
investigation of the capability of the remaining tower VI. REFERENCES
trunks and foundations to withstand the new loadings as
[1] CIGRE, Black Sea El-Net regional Meeting, 2001: H.S.
resulted for new OHL configuration. WECHSLER and others – „Aspects and results in the field of
The verification checked all towers’ and foundations increasing the power transmission capacities of the existing
types (suspension, tension, angle and dead-end) in the overhead transmission lines”
[2] HIGH VOLTAGE SYMPOSIUM, Sibiu 1995: G.
conditions of valid Romanian standards and norms. The GHEORGHITA and others – „Solutions of transforming the 220
calculations was done for same meteorological kV double circuit overhead lines into 400 kV single circuits
conditions used for the initial design of the electric lines, lines”
[3] CIGRE, Black Sea El-Net regional Meeting, 2001: C. TENCU
applied to the actual pair of wind and weight spans, and others – „Emergency restauration system for overhead
specific for each tower location. transmission lines”
Beside the existing 2 x ACSR 450/75 mm2 phase [4] I. ARDELEAN, G. VUC – „Switching Overvoltages in
Romanian S-W Transmission Network, with New 400 kV Portile
configuration, the towers and foundations were verified de Fier – Resita – Timisoara - Arad Axle”
also for a 3 x ACSR 300/69 mm2 phase configuration.
5
Constantin Matea Constantin Matea was
born in Tomsani, Romania, on August, 19th,
1950 and received a Diploma in
Electromecanical Engineering in 1993 from
University Politehnica Bucharest, Romania.
His employment experience includes the
MEE ICMP - CELPI S.A. and Romania
National Power Grid Company
“Transelectrica”- S.A, Bucharest. His
special fields of interest include the live-line
maintenance work technologies and
different protection systems of electric network. As a Project Manager
for transmission lines Mr. Matea has excellent technical capabilities
related to transmission line components like clamps and fittings,
conductors, optical cables, insulators and supports, structural steelwork
and foundations for transmission line towers.