You are on page 1of 1

2. Waste hunting was carried out in the old factory looking at the seven area of Muda.

This exercise established that waste was present in three main areas: production, inbound materials
and outbound products

Production

Waste
Inbound materials
Area

Outbound products

Nestle use waste hunting :-

I. To find Key areas where waste was found included excess handling, waiting
time and defects. For example, raw materials, packaging and finished goods
were handled multiple times
II. For waiting issues included blockages, idle machinery and trucks being made
to wait at loading bays
III. To revealed other areas that could be further improved. These included label
application on bottles, bottle cap application and finished bottle damage
IV. As the final area for improvement identified was that of water usage

You might also like