UPGRADATION OF KHULNA 150 MW PPP TO 225 MW CCPP PROJECT.
3114007/31/08(069) Date: | 2014.04.11
Dat 2014.03.23
351-F248C- S01-04 Rev: [0
Layout of water intake pump house
Reference PMC’s Comments
1 | GENERAL
1) The flow capacity for the water intake pump shall be 110% of raw water requirement as per contract document
vol2/3,book 3/4Section ~3 clause 3,3.15.Pl revise it taking into account the comments given for Raw Water
Balance in Drawing 351-F248C -S01-01
2) 2«100% washable stainer shall be added before the pump.
3)_The pump head is indicated as 20m. EPC has to furnish design calculations forthe pump head
EPC comments
Agree,
‘The pump take water from river directly , A take pipe. Itcan ensure the safe
‘operation of the pump. Other small Suspended solids can be removed in pre-treatment equipment,
‘The pump head will be 22m(H,0), Please see to “Design calculations for the pump head”
Conelusion:
1) Agreed.
2) Agreed, without the strainer before pump, EPC is to consider operational safety of the pumps during river water
intake.
3)_Received and to rfeview.
dadde: cept