Method Statement For Insulation Works (Rev.01) PDF
Method Statement For Insulation Works (Rev.01) PDF
E mail :brauns@braunsegypt.com
Method Statement
For
Insulation Works Rev (01)
July 2020
Page 1 of 5
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
INDEX
1. INTRODUCTION 3
1.1 SCOPE OF WORK 3
2. CREW & EQUIPMENT 3
2.1 PERSONNEL 3
2.2 EQUIPMENTS 3
2.3 SAFETY REGULATION 3
2.3.1 Personal Protective Equipment (PPE) 3
2.3.2 House Keeping 3
2.3.3 Equipment Control 3
2.3.4 Fire Control 3
3. DEFINITION OF PROCESS 4
3.1 Generals 4
3.2 Materials 4
3.3 Installation of waterproofing membrane 4
3.4 Installation of cold insulation 4
3.5 Installation of water stops 5
Page 2 of 5
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
1. INTRODUCTION
1.1 Scope of Work
"Construction of Lekela Substation 220 KV" for, but not necessarily be limited to, the
2.1 Personnel
• See Attached organization chart. (Appendix A)
2.2 Equipment
• Concrete mixer machine.
• Gas Torch.
• Knife.
• Hand Tools.
• Membrane rolls and other materials will be arranged into groups at appropriate place to gain
safe and clean work place.
• Long sleeves are mandatory.
• Daily disposal of combustible material.
2.3.3 Equipment Control
• All equipment to be in good condition and inspected daily with a checklist by safety supervisor.
• Every Equipment has its portable DCP Fire Extinguisher.
2.3.4 Fire Control
• Portable DCP Fire Extinguisher equipment with required number will be available.
• Equipment to be regularly maintained and inspected.
• Hoses should be inspected daily and should have spark back arrest.
• The gas torch should have dead man stop.
Page 3 of 5
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
3. DEFINITION O F PROCESS
3.1 General
• Waterproofing system insulation will be used to prevent ground water from penetrating
within reinforcement concrete slab and controlled at the temperature and humidity to
specific levels without risk of condensation.
3.2 Materials
• All materials will be selected as per the contract.
• The contractor will submit all waterproofing system to the owner for approval.
• Membrane rolls will be stored vertically in a dry place protected from sun and weather.
3.3 Installation of Water proofing membrane
• The area of application shall be barricaded and provided with warning signs to prevent or
give warning to workers, other than those involved in this work, from moving within.
• All preparation and other installation shall be completed prior to installation of
waterproofing and all repair work for concrete have to be done and agreed by client before
start of waterproofing.
• Application shall be monitored continuously by site engineer and QA/QC engineer so that
timely inspection of hold points can be performed by client without delay.
• Bottle neck have to be performed smoothly in the perpendicular edges.
• Install one Coat of Primer Before application of waterproofing.
• Heating membrane rolls with flame torch to desired properties according to manufactured
recommendations.
• A protection layer of masonry will be performed for the transformer walls to protect the
vertical membrane.
3.4 Installation of Cold insulation
• The area of application shall be barricaded and provided with warning signs to prevent or
give warning to workers, other than those involved in this work, from moving within.
• Application shall be monitored continuously by site engineer and QA/QC engineer so that
timely inspection of hold points can be performed by client without delay.
• Application shall be one coat of Primer Prior application of cold insulation which consist of
2 coats of insulation material which is approved Siemens energy.
Page 4 of 5
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
Page 5 of 5