Professional Documents
Culture Documents
AMMONIA GAS
BY
ANDREW OFOEDU
DEPARTMENT OF CHEMICAL
ENGINEERING
OWERRI.
SEPTEMBER 2013
2
EXECUTIVE SUMMARY
TABLE OF CONTENT
Title page-----------------------------------------------------------------------i
Executive
Summary---------------------------------------------------------------------------ii
Table of
content-------------------------------------------------------------------------------iii
CHAPTER ONE
1.0 Introduction-----------------------------------------------------------1
1.3--------------------------------------------------------------------------------
Design
justification-------------------------------------------------------------------3
1.4--------------------------------------------------------------------------------
Design
Objectives---------------------------------------------------------------------4
CHAPTER TWO
2.0 Literature
review------------------------------------------------------------------------5
2.1 History of Nitric acid
production-------------------------------------------------------5
2.2 Ammonia oxidation
chemistry----------------------------------------------------------8
4
CHAPTER THREE
CHAPTER FOUR
4.0 Energy balance -------------------------------------------------------53
4.1 Conservation of energy---------------------------------------------54
4.2 Energy balance assumptions -------------------------------------56
4.3 Summary for energy balances------------------------------------56
CHAPTER FIVE
5.0 Chemical Engineering
design--------------------------------------------------------61
5.1 Process units of Nitric acid
Production--------------------------------------------61
CHAPTER SIX
6.3 Preliminary
design-----------------------------------------------------------------------68
6.4 Material
Selection-----------------------------------------------------------------------69
6.5 Design
optimization---------------------------------------------------------------------69
CHAPTER SEVEN
7.1
Objective-------------------------------------------------------------------------------
----73
CHAPTER EIGHT
8.1
Safety----------------------------------------------------------------------------------
--82
CHAPTER NINE
9.1 Overview----------------------------------------------------------------103
9.3 Cost
estimation---------------------------------------------------------------------------
106
CHAPTER TEN
10.2 Notification------------------------------------------------------------114
CHAPTER ELEVEN
11.0 Conclusion/
Recommendation----------------------------------------------------118
11.1
Conclusion-----------------------------------------------------------------------------
-118
11.2 Recommendation
-------------------------------------------------------------------119
REFERENCES----------------------------------------------------------------120
APPENDIX I
Tables and
Charts--------------------------------------------------------------------------------
123
APPENDIX II
8
Material Balance
Calculation------------------------------------------------------------------126
APPENDIX III
Energy Balance
Calculation------------------------------------------------------------------132
APPENDIX IV
Equipment Design
Calculation----------------------------------------------------------------137
APPENDIX V
Equipment Costing
Calculation---------------------------------------------------------------141
9
CHAPTER ONE
INTRODUCTION
A Nitric acid plant sited in the country producing Nitric acid made
available to the Nigerian market will not only reduce importation
of the acid but also encourage fertilizer production, create job
opportunities as well as develop the area in which it is sited.
CHAPTER TWO
14
LITERATURE REVIEW
Until the beginning of the 20th century, Nitric acid (HNO 3), also
known as aqua fortis and spirit of niter was prepared
commercially by reacting sulphuric acid with either potassium
nitrate (saltpetre) or with sodium nitrate (Chile saltpetre or nitre).
Up to four tonnes of the two ingredients were placed into large
retorts and heated over a furnace (Kirk 1996). The volatile
product vapourized and was collected for distillation. An acid of
93-95 %( wt) was produced (Gregory 1999).
These included:
Gold/palladium gauze filter pads have been added on the exit side
of the catalyst bed, inside the reactor/converter units. These
17
For the production of stronger nitric acid, tail gases are now being
treated by selective or non-selective catalytic combustion
systems. These innovative units have reduced the nitrogen oxide
emissions to below 400 ppm (Ray et al 1989).
2 N O2 (g) ⇌ N 2 O4
4.
3 N 2 O 4 + 2 H 2 O(l) → 4 HN O 3 +2 N O (g)
5.
Reaction 1 is the overall reaction for the process. This net result is
achieved from three separate, and distinct, chemical steps. The
first is the oxidation of ammonia to nitrogen monoxide (Reaction
2). The second is the further oxidation of nitrogen monoxide to
nitrogen dioxide (Reaction 3), then nitrogen dioxide to nitrogen
tetroxide (Reaction 4). The third and final stage involves the
absorption of these nitrogen-based oxides into water to form the
nitric acid product (Reactions 5 and 6). In most commercial
19
The third step in the process involves cooling the reaction gases
below their dew point, so that a liquid phase of weak nitric acid is
formed. This step effectively promotes the state of oxidation and
dimerization (Reactions 3 and 4), and removes water from the gas
phase. This in turn increases the partial pressure of the nitrogen
peroxide component. (Chilton 1960)
3. ABSORPTION
The final step introduces the nitrogen dioxide/dimmer mixture
into an absorption process after being cooled. The mixture is
pumped into the bottom of the absorption tower, while liquid
dinitrogen tetra-oxide is added at a higher point. De-ionized
process water enters the top of the column. Both liquids flow
countercurrent to the nitrogen dioxide/dimmer gas mixture.
Oxidation takes place in the free space between the trays, while
absorption occurs on the trays. The absorption trays are usually
22
The bleacher gases are then compressed and passed through the
absorber. The absorber tail gas (distillate) is sent to an
entrainment separator for acid mist removal. Next, the tail gas is
reheated in the ammonia oxidation heat exchanger to
approximately 3920F. The final step expands the gas in the power-
recovery turbine. The thermal energy produced in this turbine can
be used to drive the compressor.
2.2.2 HIGH STRENGTH NITRIC ACID PRODUCTION
A high-strength nitric acid (98 to 99 percent concentration) can be
obtained by concentrating the weak nitric acid (30 to 70 percent
concentration) using extractive distillation. (Imai et al 1999) The
weak nitric acid cannot be concentrated by simple fractional
distillation. The distillation must be carried out in the presence of
a dehydrating agent. Concentrated sulfuric acid (typically 60
percent sulfuric acid) is most commonly used for this purpose.
The nitric acid concentration process consists of feeding strong
sulfuric acid and 55 to 65 percent nitric acid to the top of a
packed dehydrating column at approximately atmospheric
pressure. The acid mixture flow downward, countercurrent to
ascending vapors. Concentrated nitric acid leaves the top of the
column as 99 percent vapor, containing a small amount of NO 2
and oxygen (O2) resulting from dissociation of nitric acid. The
concentrated acid vapor leaves the column and goes to a
bleacher and a countercurrent condenser system to effect the
condensation of strong nitric acid and the separation of oxygen
and oxides of nitrogen (NO2) byproducts. (Ohkubo et al 1999)
24
The acid production system and storage tanks are the only
significant sources of visible emissions at most nitric acid plants.
Emissions from acid storage tanks may occur during tank filling.
The molecule is planar. Two of the N-O bonds are equivalent and
relatively short (this can be explained by theories of resonance.
The canonical forms show double bond character in these two
bonds, causing them to be shorter than typical N-O bonds.), and
the third N-O bond is elongated because the O is also attached to
a proton.
2.5 REACTIONS
Nitric acid reacts with most metals but the details depend on the
concentration of the acid and the nature of the metal. Dilute nitric
acid behaves as a typical acid in its reaction with most metals.
Magnesium, manganese and zinc liberate H2. Others give the
nitrogen oxides. (Ababio 2007)
Upon reaction with nitric acid, most metals give the corresponding
nitrates. Some metalloids and metals give the oxides, for
instance, Sn, As, Sb, Ti are oxidized into SnO2, As2O5, Sb2O5 and
TiO2 respectively.
Concentrated nitric acid oxidizes I2, P4 and S8 into HIO3, H3PO4 and
H2SO4 respectively.
2.6 USES
Nitric acid has been used in various forms as the oxidizer in liquid-
fueled rockets. These forms include red fuming nitric acid, white
fuming nitric acid, mixtures with sulfuric acid, and these forms
with HF inhibitor. IRFNA (inhibited red fuming nitric acid) was one
of 3 liquid fuel components for the BOMARC missile. (Gregory
1999)
2.6.5 WOODWORKING
2.7 SAFETY
The standard first aid treatment for acid spills on the skin is, as for
other corrosive agents, irrigation with large quantities of water.
Washing is continued for at least ten to fifteen minutes to cool the
tissue surrounding the acid burn and to prevent secondary
damage. Contaminated clothing is removed immediately and the
underlying skin washed thoroughly. (Othmer et al 1981)
34
Advantages
Advantages
Disadvantages
40
Advantages
Disadvantages
(a) Siting of the control room, offices, etc., away from areas of
high accident risk, and upstream of the prevailing winds.
43
(n) Adopting a plant layout that will act to contain any fires or
explosions.
44
Some of these aims are conflicting, e.g. (i) and (iv), and
compromises are usually required when considering the plant
layout to ensure that safety and economic operation are both
preserved. The final plant layout will depend upon the measures
for energy conservation within the plant and any subsequent
modifications, and the associated piping arrangements.
The process units and ancillary buildings are laid out in such a
way to give the most economical flow of materials and personnel
around the site. Hazardous processes are located a safe distance
from other buildings. Consideration for future expansion is also
put in place. The ancillary buildings and service required on the
site include:
Administrative block
45
Laboratory
Storage for both raw materials and products
Maintenance workshop
Utilities (generator, steam boiler, transformer station)
Store for maintenance and operation supplies
Other amenities like car park, restaurant and clinic.
Emergency
Fire Station Water
Stores
Workshop
Roads
Canteen
Medical
Center
Waste Car Pack
Utilities
Incinerator
Auditorium
Offices
Roads
Sulphuric acid with 93% is mixed with the refined Chile saltpetre
as per the ratio required as per stoichiometry and sent into a
retort which is made with cast iron and the mixture is heated to
200oC with help of furnace flue gasses and coal fire. Thus at this
temperature, the following reaction is carried forward to produce
HNO3, nitric acid vapors.
All hot vapors of nitric acid are sent to cool down in water
circulated cooled silica pipes, condensed HNO3 are collected in
receiver which has material resistance to nitric acid. Uncondensed
gas which escapes from the collector is scrubbed with cooled
water in packed bed tower to collect nitric acid in dilute format.
Liquid sodium bi-sulphate is collected from the bottom outlet of
the retort.
N2 + O2 →2NO
2 NO + O 2 →2NO2
OSTWALD PROCESS
Both processes follow the basic Ostwald process for the catalytic
oxidation of ammonia. In summary, this involves an oxidation
stage whereby ammonia is reacted with air in a catalytic
50
The major difference between the two processes lies in the initial
conversion stage. The dual-pressure process employs a
conversion stage operating in the range l00-350kPa, and a reactor
temperature of about 865°C. The single-pressure process however
operates the converter at 800-1100 kPa, with a reactor
temperature closer to 940°C. ( Harvin et al 1979)
CHAPTER THREE
55
MATERIAL BALANCE
kg kg
Mass flow rate = 400000 x 1000 year = 50000 hr
Input = Output
56
There are two basic methods of material balance and they are;
From the steady state material balance equation, the flow rates of
each stream are calculated as follows.
Basis: 1hr
THE COMPRESSOR
1a 1a
Stream 1 Stream 2
58
Stream 3
THE MIXER
Stream 2 Stream 5
Stream 4
59
O2 42760 - 42760
N2 160860 - 16086
NH3 - 13500 13500
H2O - 65 65
Total 203620 13565 217185
TOTAL 217185 217185
THE COVERTER
Stream 5 Stream 7
Stream 6
O2 42760 - 11660
N2 160860 - 160860
NH3 13500 270 -
H2O 65 21060 -
NO - - 23320
HNO3 - - -
NO2 - - -
Total 217185 21330 195840
TOTAL 217185 217170
OXIDISATION VESSEL
Stream 7 Stream 8
Stream 9
Stream 8
STRIPPER Stream 10
Stream 9
Stream 3 Stream 11
COMBUSTION CHAMBER
Stream 13
Stream 10
Stream 12
PURIFICATION REACTOR
Stream 13 Stream 14
HNO CH C2
O2 N2 NH3 H2O NO NO2 CO2
3 4 H6
4972 1870 2367
1 - - - - - - - -
0 80 50
4972 1870 2367
1a - - - - - - - -
0 80 50
4427 1608 2036
2 - - - - - - - -
60 60 20
2617 3313
3 6960 - - - - - - - -
0 0
135 1356
4 - - 65 - - - - - -
00 5
4276 1608 135 2171
5 65 - -
0 60 00 80
210 2133
6 - - 270 - - - - - -
60 0
1166 1608 233 1958
7 - - - - - - -
0 60 20 40
1608 146 335 1958
8 - - - - - - -
60 0 30 50
1608 238 860 300 2242
9 - 270 670 - - -
60 30 0 00 32
1608 426 726 1769
10 4030 580 - - - -
60 0 0 90
3000 200 5000
11 - - - - - - - -
0 00 0
3737 1405 1779
12 - - - - - - - -
0 80 50
3014 267 752 86 244 3642
13 2440 - 410 - 50
40 10 0 0 80 40
3037 302 270 3642
14 2670 - 20 - 380 - -
90 30 00 60
EQUIPMENT ASSOCIATE
66
CHAPTER FOUR
ENERGY BALANCE
If a plant uses more energy than its competitor, its product could
be priced out of the market. Accountability of the energy
utilization of a process plant is necessary in every design project.
Energy exists in many forms; the basic forms are listed below:
W Q
Z1
For unit mass of material
Z2
2 2
U U
U 1 + P1 V 1 + 1 + Z 1 g+Q=U 2+ P2 V 2 + 2 + Z 2 g+W
g g
U2
In chemical processes the kinetic energy factor ( )
g and the
Potential energy factor (zg) are small and negligible and the
relation between U and PV is correlated in terms of enthalpy (H)
H = U + PV
H2 – H1 = Q – w
H 2 - H1 = Q
2. No heat is lost from the vessel and from the pipe i.e. there is
proper lagging.
THE COMPRESSOR
PROPERTIES QUANTITY/VALUE
Inlet Temperature( °C ) 20
Outlet Temperature( °C ) 155
Heat duty( KJ/hr ) 26259012
Power and Actual Shaft work, 399515.49 and
repectively.(KJ/hr and KJ) 475613.68
PROPERTIES QUANTITY/VALUE
Inlet Temperature( °C ) 350
Outlet Temperature( °C ) 200
PROPERTIES QUANTITY/VALUE
Inlet Temperature( °C ) 250
Outlet Temperature( °C ) 350
Heat Duty( KJ/hr ) 1240891.54
PROPERTIES QUANTITY/VALUE
Inlet Temperature( °C ) 50
Outlet Temperature( °C ) 54
Heat Duty( KJ/hr ) -53280.03
74
AMMONIA VAPORIZER
THE STRIPPER
CHAPTER FIVE
CHEMICAL ENGINEERING DESIGN
3. Air Compressor
4. Ammonia Vaporizer
5. Ammonia Super-heater
77
6. Reactor
7. Steam Super-heater
8. Waste-heat Boiler
9. Tail-gas Pre-heater
78
10. Cooler/Condenser
This unit condenses weak nitric acid from the gaseous mixture
and cools the remaining gases from an inlet temperature of 185°C
to 60°C. The shell and tube-type heat exchanger uses de-ionized
water as its cooling medium.
The secondary cooler takes the exit gases from the oxidation unit
at 140°C and cools them down to 65°C, a suitable temperature for
entry into the absorption column. The cooling medium is
79
13. Absorber
CHAPTER SIX
EQUIPMENT DESIGN
FOR REACTORS
The operating intensity is given for the
reactors=11296.324kg/m2/24hrs
=11296.324kg/m2/day
Shape Cylindrical
Nature Insulated
Material of Stainless Steel
Construction
Capacity 50000000kg/hr
Volume(m3) 23.8
Diameter(m) 4.6
Height(m) 13.9
CHAPTER SEVEN
PROCESS CONTROL AND INSTRUMENTATION
measured only
Flow – rate F FI FC
Level L LI LC
Pressure P PI PC
94
Temperature T TI TC
Humidity H HI HC
I- Indicator C - Controller
L- Level T - Temperature
F- Flow rate P - Pressure
H- Humidity
(Source: Sinnott, R.R 1999).
7.4 LINING, PIPING, VALVES AND PUMPS
7.4.1 VALVES
The valves used for chemical process plant can be divided into
two broad classes, depending on their primary function:
Control
Valves Used to control flow in lines.
Check
Valves
Fitted in lines of relatively high
pressure or velocity
Butterfly
Valves
7.4.2 JOINTS
There are various joints used in fig 3.0 either as flow reducers, or
to aid the carrying property of pipe. And effective transport of
fluids in the piping flow. Below is a table of the various elbows and
joints used in the P and I diagram:
96
Used in joining a
CONNECTOR line.
45o LATERAL
Used in reducing
pressure flow.
CHAPTER 8 97
8.1 SAFETY
Below
The is some
best major type are
organizations of support:
those that have come to the realization
that provision of safety is not only the right thing to do for their
I – BEAM Support to carry pipe lines
employees, it is also profitable.
H – BEAM Support above 2m
Advantages of a safe working environment
U – CHANNEL
1. Ultimately, safety leads to more profit as less money is spent
PLATES taking
TO ALIGN VALVES
care of legal bills, hospital bills, and repair of
equipment.
SHOES TO HOIST PIPE INTO PROPER ORIENTATION
2. It gives the company a good name.
3. Happy employees which increases their job performance.
COMPRESSOR
While operating the compressor, the following precautions should
be observed.
Personnel coming into the facility for the first time must be
given a proper safety orientation on the do’s and don’ts of
the company policy on safety and regular safety talks on
safety and maintenance of plant must be conducted.
Regular training of personnel on safety issues should also
take place.
Good housekeeping practice by all employees should be
encouraged.
The following words are also used in a special way, and have
the precise meanings given below:
control
More Pressure 7. Isolation valve is closed Line subject to full delivery Covered by b).
in error whilst pump pressure. IJ Perhaps worthwhile installing a
running. pressure gauge upstream of the
delivery pump.
Possible line fracture or g) Provide thermal expansion
8. Thermal expansion in flange leakage relief in the valve section.
the isolation valve section
(fire).
Less flow 9. Flange leakage or valve Decreased absorption. Covered by a),c) and d)
stub blanket but leaking Higher operating cost in
lost water
Less Temperature I0. Reaction gas Increased dissolved NOx See Table 8.6
temperature in oxidation concentrations in product
unit lower. acid.
Maintenance 11. Equipment failure, Process Stops Ensure all pipes and fittings are
flange leak, catalyst constructed of the right
changeover in reactor, etc . materials and are stress relieved.
in acid.
H i g h NOx composition 11. Improved yield from Higher tail-gas emission k) Manually increase make-
reactor. levels possible. up water Composition flow
rate.
Table 8.4. HAZOP study: Gas – Outlet stream.
Less flow 11. Leaking flange or valve Less tail gas for expansion Covered by a) and d).
stub not blanked and and release of NOx to the
leaking. environment.
12. Flooding.
Liquid Carryover 13. The entrainment device Condensation is down, Replace entrainment
ineffective. steam lines (corrosion). device.
Maintenance 14. Equipment failure, Process stops. Ensure all pipes and fittings
flange leak, catalyst are
changeover in reactor, etc . constructed of the right
materials and are stress
relieved
More temperature 6. Higher inlet temperatures Less dissolved NOx in acid Covered in Tables 8.1, 8.2 and
but higher NOx tail-gas 8.3.
emissions
More pressure 7. LCV fails shut or isolation Line subject to full surge or Covered by a)
valve close in error. delivery pressure.
Less flow 8. Leaking flange or valve stub Loss to surrounding. Covered by d) and e)
not blanked and leakage.
Less temperature 9. Lower inlet stream Higher concentrations of See Tables 8.1, 8.3 and 8.4.
temperatures or over capacity dissolved NOx in product
from cooling circuit. acid.
NOx dissolved 10. Lower steam temperature. Higher downstream See Tables 8.1,8.3 and 8.4
operating costs.
Same as 9.
maintenance 11. Equipment failure, flange Process stops Ensure all pipes and fittings are
leak, catalyst changeover i n constructed of the right
reactor, etc. materials and are stress
relieved
115
8.3.2 GOAL
Negative impact
The major negative impact of a nitric acid plant is NOx emissions
of the tail gas from the absorption tower especially during start up
and shut down before the plant stabilizes. Others include:
Positive impact
Provide skilled and unskilled job opportunities.
Make available nitric acid in the country, thereby encouraging the
production of fertilizer as it is a major chemical used in its
production.
119
Eq. 1
Eq. 3
120
Extended absorption
Extended absorption reduces NO emissions by increasing
absorption efficiency and is achieved by either installing a single
121
Chilled Absorption.
122
CHAPTER 9
ECONOMIC ANALYSIS
9.1 OVERVIEW
Therefore;
0.6
1200
cost of 1200 / day=$ 60 million ×( ) = $143.66 million
280
= ₦22.7 billion
C=capital cost.
Q=400,000tons/yr
N=13
0.615
C=14000× 13 ×( 400,000)
Rough Estimate
Cf = Fl Ce
Ce = ₦ 824.43 million
Detailed Estimate
PPC = Ce ( 1 + ∑factors )
∑factors = 3.3
2) Miscellaneous 0.24
3) Utilities Cost
Steam Negligible
Power 0.4
Total 2.04
FIXED COST
₦ Million
1) Maintenance 1.21
2) Operating Labor 7.26
3) Laboratory Cost 2.18
4) Plant Overhead 3.63
5) Insurance 387.15
6) Royalties Not applicable
Total 401.43
Total interest = p (1 + r )n
= 5.41 (1 + 0.05)2
= ₦ 5.96 billion
= ₦ 6.77 billion
= ₦ 4.2 billion
= ₦ 8.4 billion
Total income after tax (based on 2.5% tax) = ₦ (8.4 – 0.025 × 8.4)
billion
= ₦ 8.19 billion
5.41
¿ =3.81 yrs
1.42
CHAPTER TEN
134
For all separators, low low liquid level will cause the
corresponding liquid outlet SDV (Shut down Valves) to close rather
than generating an OSD (Operational Shut Down)
10.2 NOTIFICATION
Prior notification of scheduled shutdowns and scheduled start-ups
following scheduled shutdowns shall be made in a timely manner
and form. Shutdowns and start-ups must be scheduled in pairs
with scheduled dates for each. Notification of scheduled start-ups
and shutdowns is required only if an exemption from the
136
CHAPTER 11
CONCLUSION AND RECOMMENDATION
11.1 CONCLUSION
From the design procedures followed and results obtained, it can
be concluded that a plant can be set up to produce 400,000
tonnes of Nitric acid per annum from ammonia oxidation. The
excess steam generated in the process can be gathered and sold
to increase the total income to be realized from sale of products.
Also, the exhaust gases from the turbine is reduced to the lowest
minimum (<1000ppm). This is to reduce the NOx emission from
the plant which is in line with the Federal Environmental
Protection Agency (FEPA) regulations. The produced acid will be
sold mainly to fertilizer manufacturing plants and oil servicing
companies in Nigeria, and can be exported as well.
Finally, an economic evaluation of the plant showed that the rate
of return on investment is about 26.25% and the payback time is
about 3years and 7 months. Therefore the project can be said to
be economically feasible.
140
11.2 RECOMMENDATION
Additional control schemes should be put in place to ensure very
low nitrous oxide emission; this will contribute to the global
objective in reducing environmental degradation. There should be
considerations for a two stage air compression to supplement the
fluctuations in air requirement due to the anticipated increase in
the demand of nitric acid. There should be provisions for
preventive maintenance, as this will help to reduce frequent
shutdowns due to repairs. It is also anticipated that this plant will
be part of a larger chemical complex. Ammonia will be produced
by steam reforming of natural gas. The nitric acid plant will take a
portion of the ammonia product, and nitric acid and ammonia will
then be used to produce ammonium nitrate.
141
REFERENCES
Ababio, O.Y. 2005, New General Chemistry, Africana- Fep
Publishers, Sydney.
Harvin R.L, Leray D.G & Roudier L.R 1979, ‘Single pressure or
dual pressure nitric acid: an objective comparison’, Ammonia
Plant Safety, Vol. 21, pp.173-183, AIChe, New York.
143
Max, S.P, Klus, D. T. & Ronald, E.W 2003, Plant design and
economics for chemical engineers; 5th Ed., McGraw-Hill, New
York.
APPENDIX I
APPENDIX II
MATERIAL BALANCE CALCULATION
Basis: 1hour
3NO2+H2O ⇌ 2HNO3+NO
OXIDISING UNIT
2NO+O2 ⇌ 2NO2
CONVERTER
4NH3+5O2 ⇌ 4NO+6H2O
=0.64 tons O2
152
=2.29tons O2 reacted
=0.48 tons NO
APPENDIX III
ENERGY BALANCE CALCULATION
Unit 3: THE COMPRESSOR
T2
Components involved N2 an O2
Specific heat capacities;
N2 = 1.04 KJ/KgK and O2 = 0.6486 KJ/KgK
Enthalpy, H;
H1= 1.04(428 −293 ) = 140.4 KJ/Kg
=
152.484KJ/Kg
H2 = 0.973504T + 1.76 ×10 -4
T2 −1187.2T-1
=
80.79 KJ/Kg
Heat Duty of the Air Heater, Q = n ∆ H = ∑ nHOut − ∑ HIn
0.488
1163
H4 = ∫ 1.7461+1.47376× 10 -3
T – 9076.8T2
523
=
3035.09 – 1132.10 = 1902.99 KJ/ Kg
1163
= 610.38 KJ /Kg
Heat outlet, Q = 3307.5(-907.3) + (270
Q = 20579273.85 KJ/hr
Unit 9; WASTE HEAT BOILER
Inlet Temperature = 890 ° C and Outlet Temperature=
250°C
Enthalpies of the compositions
0.9454+1.315 ×10
¿
T −5897.46 T-2)
523
H1 and H3 = -4
∫¿
1163
H5 = -685.088 KJ/ Kg
Q = -15976252KJ/Kg
m= 1000Kg/hr
TSteam=410°C
H4= -50.906KJ/kg
Q = 160860(-52.909) + 1460(-50.906) + 33530(-65.5) –
160860(-52.909) + 335030(-65.5)
Q= -74322.76 KJ/Kg
¿
-74322.76 = 13565 ×2.15 ׿ TST -30)
159
TSteam= 118.48
= -102.59 KJ/Kg
H2 and H5 = 131 KJ/Kg
Q = 160860(-104.734) + 1460(-102.59) + 33530(-131)
Q=-149781.4 KJ/hr
TSteam=103°C
AMMONIA VAPORIZER
Q + ƛ =13565 × 2.15(T +33.4)
ƛ=Latent heat of Steam= 1910.3
Q=149781.4
T = 15169.14/ (13565×2.15) -33.4= -28.199°C
AMMONIA SUPERHEATER
Q= -1596252KJ/hr, ƛ=3300
Q + ƛ = 13565×2.15(T + 28.2)
T = (1596252+3300)/ (13565×2.15) -28.2
T=26.65°C
160
APPPENDIX IV
EQUIPMENT DESIGN CALCULATION
STACK GAS HEATER
74322.76/3600 =20.6452KJ/h
( 200−118.48 )−(150−30)
(200−118.48)
ln [ ]
(150−30)
81.52−120
81.52
ln
120
38.48
0.387
o
∆ T m=99.43 C
Q
A=
U ∆Tm
20.6452
0.102× 99.53
A = 2.03m 2
161
AMMONIA VAPORIZER
149781.4 KJ 149781.4
Q= ,∈ KJ / sec= =41.606 KJ /S
hr 3600
Tc ¿ =−33. 4 o C
out =¿−28.19 9o C
Tc ¿
Th¿ =208
(208+28.199)−(167.2+ 33.4)
208+28.199
ln [ ]
167.2+33.4
236.199−200.6
236.199
ln [ ]
200.6
35.599 35.599 o
= =218. 4 C
ln 1.177 0.163
U = 0.102KW/m2
Q 41.606
A= = =1.868 m2
U ∆ Tm 0.102 ×218.4
(890−410)−(250−30) 480−220
=
890−410 480
ln [ ] ln
250−30 220
∆ Tm=333.76
Q 4437.8 4437.8
A= = = =130.73 m2
U ∆ Tm 0.102 ×333.76 34.04
Q
A=
U ∆ Tm
= 41.61KJ/S
41.61
=11.83 m2
0.102×34.48
NH3 SUPERHEATER.
163
( 410−26.65)−(330−28.2) 81.55
∆ Tm= = =340.9 5o C
410−26.65 ln 1.2702
ln [ ]
330−28.2
Q = 4437.85KJ/S.
U = 0.102KW/m2
4437.85
A= =127.6 m2
0.102 ×340.95
AIR HEATER
Q = 14881486.75KJ/hr = 4133.7KJ/S.
(350−250)−(200−155) 100−45 55 55
∆ Tm= = = = =68.8 4 o C
350−250 100 ln 2.22 0.799
ln [ ] ln ( )
200−155 45
Q 4133.7
A= = =588.7 m2
U ∆ Tm 7.02
164
APPENDIX V
IN 1998
A m2 0.6
Cost ∈ A m2=cost of 500 m2 ×( )
500 m2
IN 2013
2013 index
Cost ∈2013=cost∈1998 ×( )
1998 index
AMMONIA VAPORIZER
165
A = 1.87m2
0.6
1.87
Cost ∈1998=N 1.84 million ×( ) =N 0.06 million
500
683.6
Cost ∈2013=N 0.06 million ×( )
390
N 0.11 million.
IN 1998
2 2 A m 2 0.6
Cost ∈ A m =cost of 500 m ×( )
500 m 2
IN 2013
2013 index
Cost ∈2013=cost∈1998 ×( )
1998 index
In 1998
11.8 0.6
Cost ∈ A m2=N 1.84 million ×( )
500
166
In 2013
683.6
cost of 2013=N 0.19 million × =N 0.33 million
390
AMMONIA SUPERHEATER
A = 128m2
Cost in 1998
2 128 0.6
Cost of 128 m =N 1.84 million ×( ) =N 0.8214 million
500
Cost in 2013
683.6
cost of 2013=N 0.8124 million × =N 1.424 million
390
A = 130.5m2
In 1998
2 0.6
Am
Cost ∈ A m2=cost of 500 m2 ×( 2
)
500 m
0.6
130.5
Cost of 130.5 m2=N 1.84 million ×( ) =N 0.8219 mi llion
500
683.6
cost of 2013=N 0.8219 million × =N 1.44 million
390
IN 1998
2 2 A m 2 0.6
Cost ∈ A m =cost of 500 m ×( )
500 m 2
IN 2013
2013 index
Cost ∈2013=cost∈1998 ×( )
1998 index
588.7 0.6
Cost of A m2=N 1.84 million ×( ) =N 2.1 million
500
683.6
cost of 2013=N 2.1 million × =N 3.68 million
390
1998
2.03 0.6
Cost ∈ A m2=N 1.84 million ×( ) =0.068 million
500
683.6
cost of 2013=N 0.068 million × =N 0.119 million
390
CONVERTER
680
Cost ∈2013=$ 1.457( )=$ 2.541million
390
COMPRESSOR
In 1990
cap 1
( )
Cost of eq1 = cost of eq2 cap 2
0.6
7294
×( )
Cost of eq1 = $2100 447.8
0.6
928.1
cost in 2013 = 11203.4 ( 756.3 )
=$ 13748.4
= # 2.2 million
1637.96 = $2830.56
= #447228
683.6
¿
Cost in 2013 = 1593.39( 395
= $2830.56
= N447228.00
RATIO METHOD
1200
( )
Cost of 1200tons per day =cost of 280 per day 280
0.6
=#23 billion
C = 14000 N Q0.615
= # 79.8 billion